1
INTRODUCTION ... 1-2
2
HEALTH, SAFETY, ENVIRONMENT AND SECURITY ... 2-1
3
PROJECT MANAGEMENT & CONTROL... 3-1
4
PLANNING & FORECASTING ... 4-1
5
DEPOT DESIGN & ENGINEERING ... 5-2
6
HYDRANT DESIGN & ENGINEERING ... 6-1
7
GENERAL AVIATION... 7-1
8
MODULAR EQUIPMENT ... 8-1
9
OTHER FACILITIES ENGINEERING ... 9-1
10
HAZARDOUS AREA CLASSIFICATION ... 10-1
11
ELECTRICAL ... 11-2
12
CONTROL... 12-2
13
MATERIALS PROCUREMENT ... 13-1
14
CONSTRUCTION, INSPECTION AND TESTING ... 14-1
15
COMMISSIONING... 15-1
16
VEHICLES... 16-1
17
ENVIRONMENTAL... 17-2
18
DEMOLITION, ABANDONMENT & RESTORATION... 18-1
A
DEFINITIONS AND ABBREVIATIONS...A-1
B
PROJECT CONTROL CHECKLIST...B-1
A
TYPICAL STATEMENT OF REQUIREMENTS...B-1
C
TYPICAL PROJECT STRATEGY...C-2
D
PROJECT CO-ORDINATION PROCEDURE ...D-2
E
INFORMATION GATHERING CHECKLIST...E-2
F
INITIAL DESIGN STUDY... F-2
G
TYPICAL DETAILED DRAWINGS... G-2
H
SOAK TESTING ...H-1
I
MESH SCREENS FOR TANK VENTS ... I-1
J
CALCULATION OF PEAK HYDRANT FLOW RATE ... J-2
K
CALCULATION OF TANK LEVEL ...K-1
L
EXAMPLES OF CONSTRUCTION SITE REPORTING DOCUMENTS ... L-1
M
PRODUCT AND ENGINEERING DATA ... M-1
Air BP Engineering Guide 1-2 Air BP 2001
1 INTRODUCTION
1.1
PURPOSE ... 1-3
1.2
INTENDED USE OF THESE GUIDELINES ... 1-3
1.3
NATIONAL AND LOCAL REQUIREMENTS... 1-4
1.4
RELATED BP AND AIR BP PUBLICATIONS ... 1-4
1.5
AIR BP ENGINEERING STANDARDS... 1-4
1.6
EXPLANATIONS AND EXAMPLES ... 1-4
1.7
FEEDBACK AND FUTURE REVISIONS... 1-4
1.8
USE OF LANGUAGE ... 1-4
1.9
DEFINITIONS AND ABBREVIATIONS ... 1-5
1.10
UNITS ... 1-5
1.11
DISTRIBUTION... 1-5
1.12
COPYRIGHT... 1-5
Air BP Engineering Guide 1-3 Air BP 2001
1.1 PURPOSE
This
Air BP Engineering Guide
('AEG') replaces the Air BP Aviation
Engineering Practice ('AEP') last issued in 1975.
The purpose of AEG is to provide guidance on the planning, design,
construction and commissioning of safe, efficient and cost effective airfield
aviation fuel facilities for civil use.
The guidance given in AEG is based on experience gained since 1926 of
the design, construction and operation of many aviation fuel facilities
around the world. It therefore provides a sound basis for similar projects in
the future.
In general the guidance meets or exceeds the requirements for jointly
owned/operated facilities given in the Guidelines for Aviation Fuel Quality
Control and Operating Procedures for:
•
Jointly Operated Supply & Distribution Facilities
•
Joint Airport Depots
•
Joint Into-Plane Fuelling Services.
It is not intended to preclude the use of alternative designs, or construction
methods, where these can be proven to provide equivalent standards of
safety and product quality, but confirmation should be sought from Air BP
Centre Technical Branch, before such changes are implemented. This
may need to be in the form of a waiver in accordance with the procedure
given in
ADM 30
.
AEG is not intended to be directly applicable to ‘off-airport’ projects in the
supply chain, but the content may be useful when considering aviation fuel
related issues.
Key Considerations:
AEG is a guide, not a specification.
The designer is responsible for the end-product.
Queries can be referred to Air BP Centre Engineering for advice.
AEG is intended for Air BP internal use and to aid the briefing of external
consultants.
Use BP Group and Air BP standard documents whenever possible.
Feed back lessons learned.
Protect Air BP’s copyright on AEG
1.2
INTENDED USE OF THESE GUIDELINES
The engineering guidance given should be used by Air BP and authorised
third parties for feasibility studies, planning, detailed design, construction
and commissioning of new or modified aviation fuel facilities.
AEG is applicable to:
1. Airport depot installations, for the receipt, storage and supply into
aircraft (via fuel hydrants or fuellers) of both kerosene and gasoline
types of aviation fuels.
Air BP Engineering Guide 1-4 Air BP 2001
3. Aviation fuel dispensing and related vehicles (e.g. dispensers, fuellers
and pit cleaning vehicles).
Designs for new facilities or for modifications to existing facilities should
follow the guidance given here from the date of issue (or revision). At
existing facilities it may be difficult to adopt all of the recommendations, but
such improvements that are reasonably practicable should be made,
taking into account the hazards that may exist at a given site and the
feasibility of additional safety precautions.
1.3
NATIONAL AND LOCAL REQUIREMENTS
All applicable national and local (including aviation authorities) statutory
requirements and/or standards must be complied with and in the case of
any conflict with the guidance given in this document the most stringent
requirement shall be applied subject to fitness-for-purpose considerations.
In cases of any doubt, further guidance should be sought from Air BP
Centre Technical Branch.
1.4
RELATED BP AND AIR BP PUBLICATIONS
The hierarchy of documentation and other publications into which AEG fits
is shown on the Air BP Documentation Map, Get latest one from Albert B
in PDF format.
1.5
AIR BP ENGINEERING STANDARDS
References are made in AEG to detailed Air BP Engineering
Specifications and Standard Drawings. A list of
Air BP Engineering
Specifications
is also available on the Intranet. Details of Standard
Drawings are available from Air BP Centre Technical Branch.
Copies of specifications and drawings are available either by downloads
from the Intranet or from Air BP Centre Technical Branch.
1.6 EXPLANATIONS
AND
EXAMPLES
As far as possible, explanation for the reasoning, the background and/or
examples are included in the text to help in the interpretation and
application of the guidance given. Some sections of AEG including this
introduction start with a list of “Key Considerations” to aid the designer.
1.7 FEEDBACK
AND
FUTURE
REVISIONS
The value of AEG to its users will be significantly enhanced by
participation in its improvement and updating. For this reason, users are
encouraged to inform Colin Robson (
[email protected]
), the Engineering
Team Leader, or the Section Owner (whose email address appears at the
end of each section) with their comments in all aspects of its application.
1.8
USE OF LANGUAGE
In this document, the words 'will', 'may', 'should', 'shall', and 'must', when
used in the context of actions by BP or others, have specific meanings as
follows:
'Will' is used normally in connection with an action by BP (or authorised
third party) rather than by a contractor or supplier.
'May' is used where alternatives are equally acceptable.
'Should' is used where a provision is preferred.
'Shall' is used where a provision is mandatory.
Air BP Engineering Guide 1-5 Air BP 2001
1.9 DEFINITIONS
AND
ABBREVIATIONS
Refer to Appendix A for a list the definitions and abbreviations used in the
AEG.
1.10 UNITS
SI metric units are used throughout these pages, with the imperial
equivalents given in brackets. The use of SI units is encouraged in all
cases, even where local practice differs.
1.11 DISTRIBUTION
AEG should be made available to all Air BP staff and authorised third
parties engaged in the design and construction of aviation fuelling
facilities. Copies (or appropriate extracts) should also be issued to any
BP Group staff who are engaged by Air BP in the design or construction of
aviation fuelling facilities.
It is intended that these pages will contain the most up-to-date copy of
AEG. Paper copies, preferably limited to extracts, can be issued to those
persons without access to the Intranet.
1.12 COPYRIGHT
Attention is drawn to the copyright notice at the front of this document.
The issue of AEG to external consultants and contractors should be strictly
controlled and all copies or extracts from AEG (and associated Air BP
Specifications or Standard Drawings) should be returned on completion of
the project.
Air BP Engineering Guide 2-1 Air BP 2001
2
HEALTH, SAFETY, ENVIRONMENT AND SECURITY
2.1
INTRODUCTION...2-2
2.1.1
Group Policy ...2-2
2.1.2
Aim 2-2
2.1.3
HSE Expectations/Capital Value Process...2-2
2.2
PRINCIPLES...2-2
2.2.1
BATNEEC 2-2
2.3
HSES MANAGEMENT ...2-2
2.4
SECURITY 2-3
2.5
APPLICATION OF HSES STANDARDS TO AIR BP FUEL FACILITY
DESIGN AND CONSTRUCTION ...2-3
2.5.1
Design Safety...2-3
2.5.2
Construction Safety ...2-3
2.5.3
Environmental Considerations...2-3
2.5.4
Legislation 2-3
2.5.5
Site Investigations ...2-4
2.5.6
Noise Control ...2-4
2.5.7
Environmental Monitoring...2-4
2.5.8
Vapour Emissions ...2-4
2.5.9
Emergency Spill Containment / Clean Up...2-4
2.6
CONSIDERATIONS ...2-1
2.6.1
Element 1 – Leadership and Accountability...2-1
2.6.2
Risk Assessment and Management ...2-3
2.6.3
People, Training and Behaviours ...2-5
2.6.4
Working With Contractors and Others ...2-7
2.6.5
Facilities Design and Construction ...2-9
Air BP Engineering Guide 2-2 Air BP 2001
2.1 INTRODUCTION
2.1.1 Group
Policy
BP Group HSE Policy (March 1999) makes a commitment to Health Safety
and Environment performance and states three simple goals:
•
No accidents
•
No harm to people
•
No damage to the environment
Air BP endorses the principles set out in the BP Group commitment to
Health Safety and Environment performance and the BP Group Security
Policy.
2.1.2 Aim
The aim of this section is to highlight the HSE issues that can be
influenced by the engineer in order to allow engineers to minimise risks by
good planning, design and project management.
This section uses the Thirteen Elements of BP’s HSE Management
System Framework to ensure all issues are covered and to make it simple
for the engineer to cross reference with the Group’s HSE Expectations.
2.1.3
HSE Expectations/Capital Value Process
There is significant overlap between these two tools. Before reading this
section you should be familiar with the Capital Value Process (CVP) and
its terminology.
2.2 PRINCIPLES
2.2.1 BATNEEC
B – Best
A – Available
T – Technology
N – Not
E – Entailing
E – Excessive
C - Cost
2.3 HSES
MANAGEMENT
Within Air BP, HSES management is viewed as a significant tool in
ensuring that our business is run efficiently. The objectives are
appropriate standards of employee welfare, ensuring our licence to
operate and meeting Society's expectations. HSES management is
important from the outset when a new facility is considered; from the initial
site visit, through design, procurement, construction and commissioning to
the eventual operation, all aspects of HSES need to be carefully
considered.
Many HSES topics will be noted throughout AEG and the associated
Specifications. These range from the methodologies adopted to maintain
the aviation products on specification to consideration of the Health and
Safety aspects associated with the operation of the facilities and protection
of the environment from damage.
Air BP Engineering Guide 2-3 Air BP 2001
From acquisition or design, through to abandonment or divestiture the
HSES risks associated with Air BP facilities, equipment and operations,
should be assessed and managed. Air BP’s aim is to address HSES
concerns throughout the entire life of the facilities and operations.
2.4 SECURITY
Appropriate provisions need to be made to ensure the security of each
operation. An overall security plan should be developed for each site
taking due accounts of all existing airport security arrangements where
appropriate.
Reference should be made to the BP Group Security Policy.
2.5
APPLICATION OF HSES STANDARDS TO AIR BP FUEL
FACILITY DESIGN AND CONSTRUCTION
Specific application of HSES Standards to Air BP fuel facility design and
construction are incorporated in the appropriate sections of AEG and
associated Air BP Engineering Standards. However, some general points
are noted in the following sections.
2.5.1 Design
Safety
All facilities and equipment should be designed, so as to be safe in
operation and to minimise risks to personnel, our customers and the
surrounding public when properly used. For aviation fuel facilities this
includes the design aspects that ensure the quality of the product.
The design process should consider HSES aspects through the
construction, commissioning and projected life of the facility.
2.5.2 Construction
Safety
Construction safety covers all aspects of the physical building and
commissioning of a facility so as to ensure this work is carried out in a safe
manner. This involves the selection of contractors, control and monitoring
of the site work and maintaining appropriate standards of safety at all
times. The Client and Contractor(s) responsibility for safety needs to be
clearly defined in the project documentation.
GEN 5 provides a detailed guide to Construction Health and Safety.
Special considerations also apply when undertaking work on existing
facilities and guidance on this aspect is given in GEN 10.
Further guidance on the qualification of contractors is given in GEN 15.
2.5.3 Environmental
Considerations
When considering both design safety and construction safety, any adverse
physical effects on the environment should be minimised both in the short
term (during construction) and in the longer term (during the operational
life and decommissioning of the facility).
The aim in the design stage is to reduce the impact of Air BP’s activities on
the environment at all our facilities and throughout our operations. This
should include the minimisation of waste through prevention, recycling or
re-use. From the outset, consideration should be given to the means of
disposal of all waste in accordance with local legislation.
2.5.4 Legislation
Legal responsibilities and duties relating to safety in design and
Air BP Engineering Guide 2-4 Air BP 2001
BP operates, these should be understood and adhered to. In the event of
conflict with Air BP practices, procedures, standards or specifications,
guidance should be sought from Air BP Technical Centre.
2.5.5 Site
Investigations
Before the acquisition of any new site or taking over an existing site a
detailed site investigation shall be carried out to determine if there is any
pre-existing soil or groundwater contamination. The records of such
investigations shall be agreed and filed with local authorities where
possible. Reference should be made to the BP Oil Guidelines on the
Evaluation of Acquisitions and Disposals (click on the link and follow the
"Learning Lessons (Post Project Appraisal)" and then "Green
Booklets"options)
2.5.6 Noise
Control
Local legislative requirements shall be adhered to and due consideration
given to Air BP’s own staff, contracted staff and neighbouring third parties.
2.5.7 Environmental
Monitoring
All sites should include at least two appropriately located wells and routine
sampling procedures to monitor for product loss into the soil or
groundwater (possibly from adjacent facilities).
2.5.8 Vapour
Emissions
Local legislative requirements shall be adhered to.
2.5.9
Emergency Spill Containment / Clean Up
Appropriate emergency spill containment and clean-up procedures and
associated equipment and services need to be prepared and in place
during construction and commissioning phases. National legislation shall
be complied with and a comprehensive philosophy developed suitable for
a given site.
AEG Issue 1 2-1 Air BP 2001
2.6 CONSIDERATIONS
2.6.1
Element 1 – Leadership and Accountability
EXPECTATION ENGINEERING
CONSIDERATIONS
Leaders model positive HSE behaviours by
personal example both on and off the job, and
reinforce and reward positive behaviours.
•
The Engineer should set an example to all involved in the project; contractors,
site staff and anyone involved in the project.
•
Issue copies of the BP HSE Expectations to Contractors.
Leaders engage in clear, two-way
communication with employees, contractors
and others on HSE issues
•
Ensure all involved in the project (both internal and external) are aware of the
methods of communication.
•
Encourage regular HSE reporting. This is best done in the form of a one page
weekly report that asks for project progress, near miss and other HSE
information. These reports should be circulated to the assets HSE coordinator
and possibly the projects SPA (see Appendix ?? for an example). The reports
are useful when reviewing the project in the Execute Stage.
•
If you are not based on the site during the works make contact daily.
Leaders integrate the HSE Expectations into
business planning and decision-making
processes, ensuring that documented systems
are in place to deliver these Expectations.
•
The relevant HSE Expectations shall be considered alongside the CVP when
planning any engineering projects. If the CVP is followed then this should
happen.
Leaders establish clear HSE goals and
objectives, roles and responsibilities,
performance measures and allocate competent
resources and, where necessary, specialist
expertise.
•
Appoint key personnel early on in the project. If necessary bring in specialists
such as site supervisors.
AEG Issue 1 2-2 Air BP 2001
EXPECTATION ENGINEERING
CONSIDERATIONS
HSE mgt systems are developed, documented,
implemented and supported throughout the
organisation. These address health, safety,
technical integrity, environmental, security,
product and operational risks in accordance
with the appropriate expectations.
•
Insist that all tender applications are accompanied by a detailed HSE plan that
shows how the contractor manages HSE issues.
•
Provide support to contractors who are new to the BP HSE Expectations.
•
Register project on Air BP Engineering Project Database.
Leaders' HSE performance is assessed against
their annual objectives, based on feedback
from line management, peers and others in the
Business Unit.
•
N/A
Leaders integrate Group HSE targets into their
business activities. (These include, for
example, external verifications, climate change,
sustainable development, biodiversity and
emissions reduction.
•
N/A
Leaders promote the sharing of HSE lessons
learned inside and outside their Business Unit.
•
Communicate “lesson learnt” on projects to colleagues, persons working on
similar projects and relevant networks (e.g. AGNES).
AEG Issue 1 2-3 Air BP 2001
2.6.2
Risk Assessment and Management
EXPECTATION ENGINEERING
CONSIDERATIONS
Leaders put into place and promote the
use of processes to identify hazards
associated with BP's activities, assess
risks, control the hazards and manage
the risks to acceptable levels.
•
Encourage HSE awareness by unannounced site visits and ASAs.
•
Develop site audit checklist and use it!
•
Insist on Method Statements and accompanying risk assessments for all activities.
•
Use Air BP Spec GEN 10 to communicate Expectations.
Potential hazards and risks to
personnel, facilities, the public,
customers and the environment are
assessed for existing operations,
products, business developments,
acquisitions, modifications, new
projects, closures, divestments and
decommissioning.
•
Provide contractors with information on all known hazards on the site.
•
Carry out Project Loss Control Reviews (PLCR) as often as you see necessary and at least
when specified in the CVP.
Assessed risks are addressed by levels
of management appropriate to the
nature and magnitude of the risk.
Decisions are clearly documented and
resulting actions implemented through
local procedures.
•
Follow the CVP.
•
Do not ignore financial risks.
Risk assessments and risk
management / control measures are
referenced in project approval
documentation.
•
Ensure all Risk Assessments and Method Statements are checked and filed in the project
Health & Safety file.
AEG Issue 1 2-4 Air BP 2001
EXPECTATION ENGINEERING
CONSIDERATIONS
specified intervals and as changes are
planned.
AEG Issue 1 2-5 Air BP 2001
2.6.3
People, Training and Behaviours
EXPECTATION
ENGINEERING CONSIDERATIONS
Employees and contractors practice,
encourage, and reinforce safe,
healthy and environmentally sound
behaviours.
•
All Air BP staff involved in the project shall set an example to all contractors.
•
Insist on weekly reports. Stop work if HSE standards or procedures are violated.
HSE roles, responsibilities and
accountabilities are developed and
used to define individual
performance targets. These are
documented, and feedback on
personal performance is provided.
•
Ensure all involved in the project (both internal and external) are aware of the HSE
Expectations.
•
Make performance targets and penalties clear in the tender/contract documentation.
Recruitment, selection and
placement process ensure that
personnel are qualified, competent,
and physically and mentally fit for
their assigned tasks.
•
Insist on contractors’ certificates of competency, qualifications, health and insurance
certificates.
BP’s workforce has the required
skills and training to competently
perform their tasks in a healthy, safe,
and environmentally sound manner.
Training is evaluated to determine its
effectiveness.
•
Ensure all Air BP staff on the project are trained in the relevant skills.
•
Carry out inspections and ASAs.
With employees’ involvement,
physical, chemical, biological,
•
Plan for the worst case (e.g. asbestos, equipment that has been used with Avgas – lead) and
mitigate risks with control measures.
AEG Issue 1 2-6 Air BP 2001
EXPECTATION
ENGINEERING CONSIDERATIONS
ergonomic and psychological health
hazards are identified and the risks
managed in the workplace.
mitigate risks with control measures.
•
Seek expert advice (from Head Office) if unsure.
Each worksite has access to an
appropriate level of medical support
and to resource/facilities that
promote health and wellness
•
Provide facilities, as required ensuring any use of existing site facilities does not have a
detrimental effect on local staff.
•
Monitor working hours of Air BP staff and contractors (weekly report).
A programme is in place to ensure
that drugs or alcohol do not impair
the performance of our workforce
and others on our premises.
•
Inform contractors of site policies.
New or transferred employees,
contractors and other visiting
personnel undergo appropriate site
orientation/induction training that
covers HSE rules and emergency
procedures.
•
Ensure principle contractor and permit issuing authority has a suitable site induction training
package. The regular site induction is almost certain not suitable.
•
Consider increasing visitor restrictions to the site. Have a “by appointment only” policy to
avoid visitors impacting site safety and project productivity.
AEG Issue 1 2-7 Air BP 2001
2.6.4
Working With Contractors and Others
EXPECTATION
ENGINEERING CONSIDERATIONS
Pre-qualification and retention criteria are
established for work performed by
contractors, suppliers and others,
including a system for assuring their
compliance.
•
Assess contractors before committing to a contract against the Group HSE
Expectations. See Appendix ?? for an example questionnaire.
•
Are internal audits undertaken?
Hazards and risks associated with
contractor and procurement activities in
our businesses are identified, managed
and communicated.
•
Provide contractors with information on all known hazards on the site.
•
Ensure all risk assessments are recorded in the Health & Safety file and
communicated to affected parties.
•
Carry out Project Loss Control Reviews (PLCR) as often as you see necessary
and at least when specified in the CVP.
Interfaces between BP and suppliers of
services and products are identified and
effectively managed.
•
Ensure a clear contract is in place. Use BP Legal for more complex projects.
Contact Head Office for a suitable example of a contract.
Clear deliverables and performance
standards are agreed to and systems are
put in place to assure HSE and technical
compliance.
•
Break projects into manageable sections to allow simple quantification.
•
Set clear standards in the project specification (part of the contract).
•
Provide relevant Air BP Specifications and guideline.
•
Reference relevant National and IP Standards to be followed.
AEG Issue 1 2-8 Air BP 2001
EXPECTATION
ENGINEERING CONSIDERATIONS
where possible, verified as meeting
national / international health, safety and
environmental standards.
indirectly) complies with Air BP Specifications, National and Industry Standards.
Joint venture and alliance partners have
HSE management systems that are
aligned with those of BP’s, meet legal
compliance requirements and satisfy the
Group's Expectations and targets.
AEG Issue 1 2-9 Air BP 2001
2.6.5
Facilities Design and Construction
EXPECTATION
ENGINEERING CONSIDERATIONS
Baseline technical, environmental and health data are collected
before the development of any new operation, facility or major
modification.
•
Consider commissioning an (baseline) environmental audit
of the site especially if it is a new location or a
decommissioning.
•
Topographical and geo-technical surveys are invaluable if
the ground make-up is not known or unreliable.
Facilities are designed and constructed using technology, which
balances commercial risks and financial benefits to manage
technical risk and minimise or eliminate emissions, discharges,
impacts on biodiversity and other environmental impacts.
•
Ensure all practices follow Air BP specifications and
procedures.
•
Ensure Air BP and/or the relevant Competent Authority
approves all equipment used.
•
“Design out” HSE risks as much as possible.
•
Apply BATNEEC to all designs and technology with the aim
of minimising impact on the environment.
•
Consider design innovations.
•
Consider commissioning and operation when designing;
involve operators in the design.
Project management systems and procedures addressing technical
integrity and HSE accountabilities are documented and well
understood. Design, procurement and construction standards are
formally approved by the designated technical/engineering
authority. Formal design review, verification and validation studies
are carried out based on risk assessment.
•
Use CVP.
•
Carry out PLCR.
•
Apply all appropriate construction regulations e.g. CDM in
the UK).
•
Apply for planning permission and other necessary
permissions/consents (e.g. consent to discharge).
AEG Issue 1 2-10 Air BP 2001
EXPECTATION
ENGINEERING CONSIDERATIONS
Operational, maintenance and HSE expertise are integrated early in
the project/design stage. Experience from previous projects and
current operations is applied.
•
Appoint key personnel early on in the project. If necessary
bring in specialists such as site supervisors.
•
Seek advice from asset HSE advisors.
•
Consult discipline experts.
•
Involve operations and maintenance staff in design and
PLCRs.
Potential hazards are identified and HSE risks assessed using
appropriate risk assessment tools (e.g. quantified risk assessments,
HAZOPS, and HSE reviews) at specific stages of a project from
concept through to start-up, and risks are mitigated through risk
management techniques.
•
Insist that all tender applications are accompanied by a
detailed HSE plan that shows how the contractor manages
HSE issues.
•
Provide support to contractors who are new to the BP HSE
Expectations.
•
Provide Risk Assessment assistance to contractors.
•
Carry out HAZOPs for all changes.
•
Check all relevant site visit reports for required and/or
suggested changes/modifications.
Deviations from design standards are identified and managed at an
appropriate level, with the reasons documented and retained.
•
Specify in contract that all deviations from the construction
drawings & specification are to be authorised by the project
engineer.
•
Carry out PLCR and risk assessment(s) if changes are
significant.
•
Ensure construction drawings/specifications are amended
so that accurate as built drawings can be produced.
AEG Issue 1 2-11 Air BP 2001
EXPECTATION
ENGINEERING CONSIDERATIONS
Local regulatory requirements are met or exceeded. Where these
are absent or inadequate, standards are set that protect people and
the environment.
•
Planning permission.
•
Building warrant.
•
Consent to discharge.
Quality assurance and inspection systems are in place to ensure
that facilities meet design and procurement specifications and that
construction is in accordance with approved standards.
•
Arrange a GEN 500 inspection on completion of new site.
•
Documented pre-start up reviews are carried out for all newly
installed or modified equipment to confirm that construction is in
accordance with design, all required verification testing is complete
and acceptable, and all recommendations/deviations are closed
and approved by the designated technical authority.
•
Carry out “close-out” PLCR.
•
Document commissioning procedure.
•
Obtain necessary Competent Authority
completion/compliance documentation (e.g. building
certificate for buildings).
No. EXPECTATION
ENGINEERING
CONSIDERATIONS
Post-start up reviews are carried out for all newly installed or
modified equipment to confirm that construction is in accordance
with design, all required verification testing is complete and
acceptable, and all recommendations/deviations are closed and
approved by the designated technical authority.
•
The operate stage of the CVP.
•
Amend construction drawings so that as built drawings can
be produced.
•
Do not close contracts until all “snags” have been resolved.
Applicable regulatory requirements are met or exceeded and
operational/technical/mechanical integrity is maintained by use of
clearly defined and documented operational maintenance
•
Follow local CA guidelines.
AEG Issue 1 2-12 Air BP 2001
No. EXPECTATION
ENGINEERING
CONSIDERATIONS
clearly defined and documented operational, maintenance,
inspection and corrosion control systems.
maintenance schedule.
•
Provide all relevant technical documentation to site and/or
Maintenance engineer Manager.
•
Recommend inspection programmes.
Key operating parameters are established and regularly monitored.
The workforce understands their roles and responsibilities to
maintain operations within these parameters.
•
Ensure operating procedures are drawn up.
Clearly defined start-up, operating, maintenance and shutdown
procedures are in place with designated authorities identified (e.g.
permit to work, hand-over, equipment and process isolation, etc.)
•
Ensure operating procedures are drawn up.
Equipment that has been out of service for maintenance or
modification is subject to documented inspection and testing prior to
use.
•
Get all “recycled” equipment is reconditioned/overhauled
before reuse.
Reliability and availability of protective systems are maintained by
appropriate testing and maintenance programmes, including
management of temporary disarming or deactivation.
•
Ensure all safety equipment is added to the planned
maintenance system.
•
Write procedures for emergency equipment override.
Risks introduced by simultaneous operations are assessed and
managed.
•
Carry out risk assessments in the design phase in order to
mitigate risks.
HSE impacts associated with waste, emissions, noise, biodiversity
and energy use are monitored and minimised.
•
Consider in design phase.
•
Operating procedures should be written so as to minimise
impact.
Comprehensive waste management programmes are in place to
ensure that wastes are minimised re used recycled or properly
•
AEG Issue 1 2-13 Air BP 2001
No. EXPECTATION
ENGINEERING
CONSIDERATIONS
ensure that wastes are minimised, re-used, recycled, or properly
disposed of.
•
Provide suitable equipment to assist recycling and, if
necessary, disposal of materials.
Decommissioning, remediation and restoration plans are
established using risk-based studies for end of life equipment/
facilities.
•
Consider in Select stage of CVP.
A quality assurance programme exists to ensure that equipment
replacement or modification maintains operations integrity.
•
Planned maintenance.
The health, safety, security, environmental, technical and other
impacts of temporary and permanent changes are formally
assessed, managed, documented and approved.
•
Covered by PLCR process..
Changes in legal and regulatory requirements, technical codes, and
knowledge of health and environmental effects, are tracked and
appropriate changes implemented.
•
Ensure you are applying up to date Standards and codes to
the design.
Effects of change on the workforce/organization, including training
requirements, are assessed and managed.
•
Local staff will require training on new equipment. Does
the project result in more/less staff?
The impact on product quality of changes in manufacturing
processes is assessed, associated hazards are evaluated and risks
are controlled.
•
N/A
The original scope and duration of temporary changes are not
exceeded without review and approval.
•
A waiver from the local fuels quality advisor should cover
all changes affecting fuel quality.
AEG Issue 1 2-14 Air BP 2001
No. EXPECTATION
ENGINEERING
CONSIDERATIONS
A system is in place to securely manage drawings, design data and
other documentation, including definition of responsibilities for
maintaining this information.
•
Set up a filing system in the Appraise stage.
•
Ensure the H&S file is kept up to date and reviewed
frequently.
Applicable regulations, permits, codes, standards and practices are
identified. The resultant operating requirements are documented
and communicated to the workforce.
•
Identify all relevant standards and codes early on and if
necessary include them in tender documentation.
Pertinent records are maintained, available and retained as
necessary. Obsolete documentation is identified and removed from
circulation.
•
Ensure drawings are kept up to date and revisions
maintained.
Scope and format of technical documentation will be agreed for
each facility and will form part of the design input for new facilities
and modifications.
•
Follow CVP and Air BP specification ADM 1 (documents) &
ADM 20 (drawings).
Employee health, medical and occupational exposure records are
maintained with appropriate confidentiality and retained as
necessary.
•
N/A
Assessments are conducted for new products prior to marketing or
distribution, to identify health, safety and environmental hazards
and risks associated with normal use and foreseeable misuse.
•
Only use approved equipment.
Periodic reassessments are conducted for all manufactured and
re-branded products and intermediate streams. This includes a review
of adverse effects reported or experienced by those handling these
products.
•
N/A
New uses or markets for existing products are evaluated to ensure
that health; safety and environmental hazards and risks are
identified and addressed.
AEG Issue 1 2-15 Air BP 2001
No. EXPECTATION
ENGINEERING
CONSIDERATIONS
Records of assessment, background information and conclusions
are kept up-to-date throughout the product’s life and retained as
appropriate.
•
N/A
Up-to-date information on health, safety and environmental hazards
and risks relating to the use, storage, handling, transport and
disposal of our products is available to the workforce, customers
and others. Material Safety Data Sheets (MSDS), labels and other
information are developed and issued to handlers and users in
accordance with legislative and customer requirements, and as
information changes.
•
Provide contractors will all necessary MSDS and COSHH
assessment forms.
A system exists to collect and review adverse effects reported or
experienced by those handling our products. Causes for concern
are identified and actions are taken.
•
N/A
An effective recall system exists for products where a defect could
give rise to health, safety or environmental hazards.
•
N/A
A system is in place to respond on a 24-hour basis to emergency
requests for product health, safety and environmental information.
•
A contact list should be generated, circulated and
maintained. The local emergency contact (in the Air BP
Emergency Contact Directory) should be made aware of
the project.
Open and proactive communications are established and
maintained with employees, contractors, regulatory agencies, public
organizations and communities regarding the HSE aspects of our
business.
•
Consult the relevant Competent Authorities regarding the
project design and possible impacts.
•
Ensure all consents are got before work commences (e.g.
planning permission, consent to discharge).
BP recognizes and responds to government and community HSE
related expectations and concerns about our operations and our
AEG Issue 1 2-16 Air BP 2001
No. EXPECTATION
ENGINEERING
CONSIDERATIONS
related expectations and concerns about our operations and our
products.
HSE impacts of new business development on local communities
are openly assessed, communicated, and integrated into the
business case.
•
PLCR
HSE impacts of any divestment or decommissioning on existing
operations, neighbours or local community (originally identified
during the new business development stage) are reviewed,
communicated and managed.
•
Keep neighbours (e.g. Airport Authority) informed of
developments and changes.
Major business operations periodically issue an externally verified
statement relating to HSE performance and programmes.
•
Provide the local HSE advisor with the necessary
information to publish an informed bulletin.
Emergency management plans are based on the risks that
potentially impact the business. These plans are documented,
accessible, clearly communicated and align to the BP Group’s
emergency management system.
•
Equipment, facilities and personnel needed for emergency
response are identified, tested and available.
•
Personnel are trained and understand emergency plans, their roles
and responsibilities, and the use of crisis management tools and
resources.
AEG Issue 1 2-17 Air BP 2001
No. EXPECTATION
ENGINEERING
CONSIDERATIONS
Drills and exercises are conducted to assess and improve
emergency response/crisis management capabilities, including
liaison with and involvement of external organizations.
•
Periodic updates of plans and training are used to incorporate
lessons learned from previous incidents and exercises.
•
All health, safety, technical integrity, security and environmental
incidents, including near misses, are openly reported, investigated,
analysed and documented.
•
Major incidents are investigated by a multi-function/level team with
participation and leadership from outside the business unit.
•
Incident investigations, including identification of root causes and
preventive actions, are documented and closed-out.
•
Information gathered from incident investigations is analysed to
AEG Issue 1 2-18 Air BP 2001
No. EXPECTATION
ENGINEERING
CONSIDERATIONS
Lessons learned from investigations are shared across BP and
personnel take appropriate action upon receipt of such information.
•
Mutual sharing of lessons learned and good practice is encouraged
within the wider energy and chemical industry.
•
HSE performance indicators (both inputs and outcomes) are
established, communicated and understood throughout the
organization.
•
The workforce is actively involved in periodic self-assessments of
the effectiveness of processes and procedures to meet the HSE
Expectations.
•
HSE performance indicators are regularly used to determine when
and what management system changes are necessary. When
changes occur in one HSE Element the impact on the entire
management system is evaluated.
•
A system exists to continually improve HSE behaviours through
observation, recording, and coaching.
•
A documented, risk-based audit programme exists to periodically
AEG Issue 1 2-19 Air BP 2001
No. EXPECTATION
ENGINEERING
CONSIDERATIONS
the effectiveness of the Business Unit management system(s).
The Business Unit, in co-operation with the audit team, plans
audits, which are objective and systematic. These are documented
and conducted using expertise from inside and outside the unit.
•
Findings from learning processes (e.g. audits, incident
investigations, near misses, HAZOPS, etc.) are prioritised, tracked
and used to systematically improve the HSE management system.
•
The Business Unit leadership team reviews the management
system to ensure it is continually delivering consistent, desired
performance. Based on the review, new risk-based targets are
considered and established wherever necessary.
•
Business Units report HSE performance data, as part of the
Group’s HSE Reporting Requirements.
•
A process is in place whereby assurance is regularly provided to
the Group Chief Executive demonstrating effective implementation
of the BP HSE Policy and Expectations. Annual self-assessments
against these Expectations are carried out by each Business Unit,
along with external audits at least every three years.
AEG Issue 1 3-1 Air BP 2001
3
PROJECT MANAGEMENT & CONTROL
3.1
GENERAL...3-2
3.2
BP GROUP TOOLS ...3-2
3.3
STATEMENT OF REQUIREMENTS ...3-4
3.4
PROJECT STRATEGY ...3-4
3.5
CONTRACTS...3-5
3.5.1
Contract Strategy ...3-5
3.5.2
Forms of Contract ...3-5
3.6
PROJECT CO-ORDINATION...3-6
3.7
COST ESTIMATES ...3-6
3.8
PROJECT LOSS CONTROL REVIEW PROCEDURE & RISK
ASSESSMENT...3-6
3.9
VALUE ENGINEERING ...3-7
3.10
QUALITY ASSURANCE AND CONTROL ...3-7
3.11
PROJECT DOCUMENTATION ...3-8
3.12
POST-PROJECT APPRAISALS...3-9
AEG Issue 1 3-2 Air BP 2001
3.1 GENERAL
In this section, guidance is given on the management and control of
projects.
What is a “project” ?
A project is any situation that involves change – usually new works or
modifications to existing facilities but can be non-physical e.g. a
reorganisation or system implementation.
The first step in a successful project is to recognise that a change is taking
place !
Key Considerations:
Recognise the change and manage it.
Use BP Group tools e.g. CVP
Identify the client and key players.
Define the opportunity / problem.
Consider all the solutions and pros v. cons.
Consider HSE issues from the start.
Key decisions are at the front end (most influence).
Cost of a change increases as a project proceeds.
Consider all the risks and effect on the project’s payback.
Develop a project strategy
Use standard documents whenever possible.
Do Loss Control Reviews at key stages.
Review and feed back lessons learned (technical and commercial).
3.2
BP GROUP TOOLS
Reference should be made to The BP Group ‘
Getting HSE Right’
Expectations Document, Section 5 - Facilities Design and Construction
and the
BP Group Project Management Guidelines
available on the
Intranet.
Air BP projects of estimated value > $5M must follow the
BP Group Capital Value Process.
Air BP projects of estimated value < $5M but > $1M must follow the
Air BP Simplified Capital Value Process.
AEG Issue 1 3-3 Air BP 2001
Air BP projects of estimated value < $1M should follow the principles of the
Air BP Simplified Capital Value Process.
The Capital Value Process is to ensure that a project is aligned with the
business strategy and is implemented efficiently. 'Front End Loading' is
the term used to apply resources at an early stage where the influence is
greatest and the most value can be extracted. Air BP Engineers are
encouraged to participate in the Appraise and Select stages to ensure
that the right technical solution is chosen.
It is important from the outset of any project to be fully aware of the factors
that impact on its successful implementation. These include not only the
technical design and detailed specifications, but also legal, tax, local
regulations, and other factors that could enhance or detract from the
project adding value to Air BP's operation and which should all be
considered in the preparation of a sound commercial case. The principles
of how a project is to be managed and controlled from initial concept to
construction and commissioning also need to be carefully considered at an
early stage.
In order to highlight the phases of a typical project and the general order in
which things should be done, a Project Control Checklist has been
produced and is given in Appendix B. (add link)
Key points to note are:
•
It is important to clearly identify the Client, Single Point Accountability
and Gatekeeper at the start of any project.
•
It is essential to understand the project's commercial objective and a
preliminary Finance Memorandum should be prepared at an early
stage to help understand the cost, schedule and operability drivers
together with HSE implications.
AEG Issue 1 3-4 Air BP 2001
•
A written Statement of Requirements (SoR) should be prepared at an
early stage and formally agreed with the Client. (see below)
•
A comprehensive data gathering exercise is often necessary, with site
visit(s), in order to prepare initial designs and layouts, size facilities
and make first order cost estimates. During this phase, many factors
other than those of a purely technical nature need to be considered
which could have a significant impact on the project, both upside and
downside.
•
The client needs to be able to make a business decision on the
strength of the case(s) presented, which will often need to be prepared
with their co-operation to develop the full commercial position. The
use of risk modelling to analyse the sensitivities of the case(s) to
variations in assumptions should be considered.
Lessons from similar past and current projects should be carefully
considered.
3.3
STATEMENT OF REQUIREMENTS
A Statement of Requirements (SoR) is an unambiguous definition of the
services and/or facilities required by the Client. This may include several
options yet to be evaluated, but it should be as precise and
comprehensive as possible to ensure that all parties involved know what is
to be delivered.
The SoR should be prepared and agreed with the Client before any
significant work commences on the project. Any subsequent change or
deviation from the agreed SoR, whether at the request of the Client or
through the design/construction process, should be noted in a revision to
the SoR, clearly identifying the reason(s) for the change.
A description of the contents for a typical SoR is given in Appendix C.
3.4 PROJECT
STRATEGY
To have the best chance of completing a project safely, to specification, on
time and within budget a clear and coherent project strategy should be
defined at an early stage.
This should identify how the project is to be managed, the responsibilities
and interfaces for all parties concerned with the project, the resources
required, a cost estimate, project programme, quality assurance and
control procedures, the contract and purchasing strategy, cost controls,
loss control review procedures and how these should be managed.
It is important to ensure that the Project Manager and project team have
the relevant knowledge and experience. To ensure consistency the
Project Manager should ideally be appointed prior to the preparation of the
project strategy and not changed for the duration of the project.
Reference should be made to a Project Co-ordination Procedure for more
details of the inter-relationships, responsibilities and limits of authority.
AEG Issue 1 3-5 Air BP 2001
It is important to make sure that timescales are realistic. Tight timescales
and compressed schedules are likely to force Project Management
compromises that will invariably be costly.
A description of the contents for a typical Project Strategy is given in
Appendix D.
3.5 CONTRACTS
In general terms a Contract awarded to a contractor for work associated
with a project includes:
•
A Contract Agreement (signed by both parties)
•
Conditions of Contract (including the responsibilities of both parties,
programme dates to be met and the method and timing of payments)
•
A Technical Specification (for the work or services)
•
Co-ordination Procedures.
3.5.1 Contract
Strategy
A Contract Strategy should be evolved early in the life of the project as
part of the overall project strategy. It should give the number and types of
contract that will result in the optimum allocation of resources and
risks/responsibilities between BP, contractor(s) and the Client in order to
achieve project completion to programme, budget and operability targets.
Before implementation, the contract strategy must be endorsed by the
appropriate BP Contract Committee prior to any authorisation required
from the Client (or Partners).
3.5.2
Forms of Contract
There are three principal types of contract:
(a) Lump (fixed) Sum Contracts
These are favoured where clear definition of the scope of work is possible
and the risks and liabilities are clearly identified so that prospective
contractors can estimate the time and effort and costs involved. It is
essential to allow sufficient time for the preparation of the scope of work
before such lump sum bids are sought, as bids against a poorly defined
scope of work will typically need to be revised upwards.
(b) Measured Contracts
These use Bills of Materials (or Quantities) that are detailed listings of
each element of construction work against which prospective contractors
can quote unit cost rates. Final cost is agreed based on actual
measurement of the work completed, and the Bills and measurement of
work are usually prepared and administered by independent Quantity
Surveyors. If the scope against which the Bill is prepared is not varied, a
measured contract will effectively become a fixed (lump sum) contract.
(c) Reimbursable Contracts
These do not require a high degree of definition of the scope of work but
need to be put together carefully so that the expenditure can be properly
controlled. Such contracts can include incentives e.g. risk / reward
payments based on outturn measures which could include for example -
cost, programme, safety, operating performance of the new asset.
AEG Issue 1 3-6 Air BP 2001
All these forms of contract can include an element of design. The design
responsibilities, risks and liabilities should be clearly defined. Where a
project can be adequately defined at the start, it is generally preferable to
place work on a Lump Sum or Measured basis because this means
payment is for the contractor's actual output rather than for the time taken.
The contractor therefore has an incentive to be as efficient as possible.
3.6 PROJECT
CO-ORDINATION
A Project Co-ordination procedure should be prepared to clearly identify
the inter-relationships between all of the parties involved in a project, the
responsibilities and limits of authority. This generally covers four
categories of work, which may need to be detailed as the project
proceeds: (i) Initial Design / Specification, (ii) Contractor(s) (iii)
Construction and (iv) Commissioning
Local regulations applicable to Construction, Design and Management
shall be taken into consideration to ensure that all parties involved
understand their health and safety responsibilities.
A description of the contents for a typical project Co-ordination Procedure
is given in Appendix E (add link).
3.7 COST
ESTIMATES
Reliable cost estimates are essential. An underestimate may lead to a
non-viable project, and an overestimate could result in rejection of a sound
investment. The accuracy of an estimate is directly related to the level of
technical definition - this should improve as the project develops and the
financial case should be checked regularly testing the upside and
downside cost estimate limits. Consideration should be given to the use
of probabilistic techniques to determine the estimate accuracy or range of
probable costs.
3.8
PROJECT LOSS CONTROL REVIEW PROCEDURE & RISK
ASSESSMENT
Loss control reviews of all projects will be carried out to ensure that the
facilities are designed and constructed in the best interests of BP and in
accordance with national legislative requirements, BP group policies and
accepted good engineering and construction practices, so as to minimise
the potential for loss.
Losses include those arising from misconceived objectives, safety, design
and environmental aspects as well as construction, commissioning and
operational practices. Reviews shall be conducted for all new projects,
major facility extensions and modifications.
It is important that the opportunity to review the commercial viability of a
project and its impact on surrounding activities is taken at appropriate Loss
Control Reviews.
AEG Issue 1 3-7 Air BP 2001
Guidance on the type of review and the procedure to be adopted is given
in
GEN 40
.
An essential consideration during this process is Risk Assessment – you
must understand the risks to the project. This is done in three stages:
FIGURE 3-1RISK MANAGEMENT PROCESS
The objective is to move from the RED situation where risks are not fully
understood to the GREEN situation where risks are being managed.
Firstly risks are identified and can be logged in a Risk Register. The risks
are then evaluated in terms of probability and likely consequences.
Finally, a decision can then be made on each risk:
ACCEPT and do nothing
MITIGATE the risk by design and/or operational practices
ELIMINATE the risk e.g. don’t do something, do it differently or insure
3.9 VALUE
ENGINEERING
There is often scope for capital cost savings by means of a cost reduction
exercise. Ideally this should be done at the design stage, considering the
full cost of technically acceptable alternatives where they exist. However,
a review of areas of potential cost saving should be undertaken as part of
the Loss Control Review process, described above.
The BP Capital Value Process includes a toolbox of
Value Improving
Practices
.
3.10 QUALITY
ASSURANCE
AND
CONTROL
It is important to ensure that project implementation fully meets all of the
standards specified and adequate records demonstrate that this so. This
is achieved by following a pre-established, methodical, procedural
approach to all project work by all people - project, contractor and
suppliers - involved with all stages of the project.
AEG Issue 1 3-8 Air BP 2001