Deep Geologic Repository Project for
Low- and Intermediate-Level Waste
Proposed by Ontario Power Generation Inc.
October 29, 2013
PMD 13-P1.3I
CNSC Staff Presentation
e-Doc 4217306 (PPT) e-Doc (PDF)
Presentation Outline
• Environmental Protection Program Requirements • Environmental Protection Program – DGR Project
– Stormwater Management Pond – Groundwater Monitoring
– Baseline for surface water and aquatic biota – Noise monitoring and mitigation
• EA Follow-up Monitoring Program
• CNSC Independent Environmental Monitoring Program
Environmental Protection Program
Requirements
Environmental Protection Framework
CNSC Environmental Protection Regulatory Framework has four main components:
Regulatory Instruments Environmental Programs, Policies and Procedures in a Licence Compliance Verification Support for Decisions
5
Canadian Nuclear Safety Commission
Environmental Protection Framework:
Regulatory Instruments
• Legislation
– Nuclear Safety Control Act and Regulations – Canadian Environmental Protection Legislation • Memoranda of Understanding
– Federal (Environment Canada, Fisheries and Oceans Canada, Transport Canada)
– Provincial
• Standards and Regulatory Documents – CNSC Guidance and Regulatory Documents – Canadian Standards Association Standards
Regulatory Instruments Licensing and Environmental Programs, Policies and Procedures Compliance Verification Support for Decisions
Environmental Protection and the Nuclear
Safety and Control Act (NSCA)
• Under the NSCA, two of CNSC’s responsibilities are:
– direct protection of the environment
– regulatory responsibility for hazardous substances in addition to nuclear substances
• The NSCA contains numerous references to protection of the environment. Key obligations are to:
– prevent unreasonable risk to the environment – make adequate provision for the protection of the
environment
– take all reasonable precautions to control releases of
radioactive or hazardous substances within the site of the licensed activity and into the environment as a result of the licensed activity
7
Canadian Nuclear Safety Commission
Environmental Protection and the NSCA
• Environmental baseline characteristics of the site and the surrounding area
• Documentation of releases of nuclear substances and hazardous substances to the environment
• The proposed measures to control releases of nuclear
substances and hazardous substances into the environment
• The proposed measures to prevent or mitigate the effects…
• Information program to inform persons living in the vicinity … of anticipated effects on the environment and the health and safety of persons
• Environmental Protection Policies and Programs
• Effluent and environmental Monitoring Programs
The Regulations under the NSCA contain more specific requirements related to environmental protection
• Environmental Protection
– Release Control and Monitoring – Environmental Monitoring • Safety Analysis – Environmental Risk Assessment • Radiation Protection – Public • Management System
– Environmental Management System
• Waste Management
Environmental Protection Framework:
Programs, Policies and Procedures
Regulatory Instruments Licensing and Environmental Programs, Policies and Procedures Compliance Verification Support for Decisions
9
Canadian Nuclear Safety Commission
Environmental Protection Framework:
Compliance Verification
• Desk Top Assessments of:
– Adequacy of programs
– Annual Performance Reports • Inspections • Audits / Investigations – EMS audits – Special investigations • Independent Environmental Monitoring Program Regulatory Instruments Licensing and Environmental Programs, Policies and Procedures Compliance Verification Support for Decisions
Example – WWMF Compliance
Verification Results
• CNSC conducted an Environmental Management System Audit at WWMF in 2006
• CNSC regularly assess the WWMF’s
Environmental Protection Programs through desk top reviews
– Quarterly Operations Reports
– Annual Incinerator Emissions Reports
• CNSC Inspections do not focus specifically on Environmental Protection but sometimes look at environmental issues
11
Canadian Nuclear Safety Commission
Environmental Protection Framework:
Support for Decisions
CNSC Research and Support Programs
• Current with leading edge science and
policies
– IAEA and UNSCEAR
– Scientific and technical literature
Regulatory Instruments Licensing and Environmental Programs, Policies and Procedures Compliance Verification Support for Decisions13
Canadian Nuclear Safety Commission
Stormwater Management Pond: Design
Stormwater Management Pond:
Design Criteria
• The stormwater management pond and its outlet structure is designed to:
– Ensure that peak flows during construction for various storm events do not exceed current peak flows in the existing site ditch leading to Lake Huron
– Safely convey the peak outflow rate associated with a 24-hour 100-year storm event
– Provide 24 hours of sediment settling time from stormwater runoff associated with 25 mm of rainfall in 6 hours
– Ensure that the average annual Total Suspended Solids concentration in the effluent does not exceed 40 mg/L
15
Canadian Nuclear Safety Commission
Stormwater Management Pond:
Inflow Sources
• Surface runoff from
the site
• Onsite precipitation
• Runoff from
temporary waste rock
pile
• Runoff from
permanent waste
rock pile
• Pumping from shafts
and underground
Waste Water Management:
Source Reduction and Treatment
• Source reduction techniques
– Ammonia reduced by best blasting techniques
– Saline groundwater treated with an evaporator
• Treatment
– Monitoring of pond water before discharge will determine the treatment technique
chosen
– Options prior to discharge include aeration and reverse osmosis
17
Canadian Nuclear Safety Commission
Stormwater Management Pond: Discharge
• Discharge criteria are essentially provincial and
national water quality guidelines
• Compliance with the discharge criteria meets
section 36(3) of the
Fisheries Act
• CNSC and Environment Canada staff
recommend acute and chronic toxicity testing
before discharge (
Undertaking #47
)
• These tests will provide further assurance of
compliance with 36(3) of the
Fisheries Act
Stormwater Management Pond:
Impacts on Wetlands and Groundwater
21
Canadian Nuclear Safety Commission
Shallow to Intermediate Groundwater
Monitoring Network
Intermediate and Deep Groundwater
Monitoring Network
23
Canadian Nuclear Safety Commission
CNSC Staff’s Assessment of OPG’s
Groundwater Monitoring Network
• Information sufficient for Environmental Assessment and Licensing decisions
• Additional information to be collected if project proceeds:
– design an adequate groundwater monitoring well network that includes upgradient wells
– assess the migration of a tritium plume and its interaction with proposed shafts
– propose a contingency plan should the tritium plume reach the shaft before shaft collars are installed
Baseline for Surface Water and
Aquatic Biota
25
Canadian Nuclear Safety Commission
Baseline - Surface Water and Sediment
Quality
• Baseline information sufficient for Environmental Assessment and Licensing decisions
• Additional information being collected if project proceeds
– Additional baseline surface water and
sediment quality data at Un-named drainage ditch and MacPherson Bay
• CNSC staff recommend that OPG collect additional baseline sediment and water quality (CNSC
Residual Effects on Water Quantity and
Flow
• Residual effects on water quantity and flow of the DGR Project
– 31% flow reduction (or 2.5 L/s) in the North Railway Ditch
due to drainage diversion to the SWMP
– 114% flow increase (or 12.2 L/s) in the un-named drainage
ditch emptying into MacPherson Bay during site preparation and construction
– 61% flow increase (or 9.2 L/s) in the un-named drainage
ditch emptying into MacPherson Bay during operation phase
• CNSC staff recommend that OPG verify EA
predictions on flow reduction in North Railway Ditch and Stream C (CNSC Recommendation #8)
27
Canadian Nuclear Safety Commission
Aquatic Biota – Baseline
• Baseline data for the aquatic environment included recent field study results and
referenced existing data sources from the Bruce Nuclear site
• Additional quantitative fish and fish community baseline data, including lake whitefish in Lake Huron, were provided in response to Panel Information Requests
Aquatic Biota – Effects
• No measurable changes to VECs in Stream C were predicted
• No measurable changes to VECs in Lake Huron and embayments were predicted as effluent
discharge meeting regulatory discharge criteria • The residual adverse effects on fish habitat loss
(< 1.6%) in the South Railway Ditch and disturbance of burrowing crayfish habitat
(0.01%) are determined not significant as the affected area is localized
29
Canadian Nuclear Safety Commission
Lake Whitefish Monitoring at the Bruce
Nuclear Site
• Monitoring Programs in place at the Bruce
Nuclear site address the following areas:
– Population Structure & Thermal Stress
– Population Modelling & Intake Entrainment – Egg Survival Threshold Criteria
– Bruce A Refurbishment EA Follow-up Monitoring
Aquatic Biota – Whitefish Results
Results:
• Impingement 9-year average of 135 lake whitefish but declining last five years reflecting lake-wide trends
• Spawning habitat mapped and multi-year adult spawner surveys showed lowest relative habitat use at
MacPherson Bay
Ongoing and Planned :
• Lake whitefish population spatial extent (genetics, diet, tagging)
• Effects of thermal plume on whitefish eggs
• Impingement and entrainment, analysis of winter
spawning habitat temperatures and biological data from adult spawners
31
Canadian Nuclear Safety Commission
Aquatic Biota – Bruce Nuclear Site
Comprehensive Monitoring
• Offsite radiological Environmental Monitoring in human exposure pathways
• Fish Monitoring Programs record catches for all fish species (impingement, entrainment, angler harvest, scientific gill netting)
• Updated Bruce A and B Environmental Risk Assessment investigates all stressors
• Long-term monitoring of status of local indicator cold-water and warm-water species since
Aquatic Biota – Interactions with Ontario
Ministry of Natural Resources
• Bruce Nuclear Site Sportfishing survey
design and analysis
• Lake whitefish fin clip monitoring at
reference sites
• Attend annual meetings whitefish research
and EA follow-up
Noise
• Residual Socio-Economic Effect
– Reduced enjoyment of private property at Baie de Doré
– In-design mitigation planned
• Follow-up Monitoring Program
– Confirm predictions and mitigation measures
• CNSC relies on expertise from Health
Canada
– No recommendations from Federal Government beyond what OPG has
EA Follow-up
Monitoring Program
(EA FUMP)
Initial Scope of OPG’s EA Follow-up
Monitoring Program
• A follow-up program is mandatory under the
Canadian Environmental Assessment Act
(CEAA)
• Preliminary Follow-up Monitoring Program
plan was provided in the EIS
• Developed in accordance with CSA
standards, CNSC regulatory standards and
guides
37
Canadian Nuclear Safety Commission
EA Follow-up Monitoring - Activities
• An EA follow-up monitoring activity is used to
verify a specific prediction or conclusion of the
EIS
• The monitoring activity:
– has a finite duration
– monitors or measures a specific effect or lack of effect
• The activity is to be discontinued:
– when the prediction has been confirmed – at the end of a pre-determined period
Baseline Studies
• Baseline studies:
– provide a benchmark to test project effects – determine the need for additional
pre-construction or pre-operational monitoring
• Baseline data must be obtained prior to
construction
• Further baseline data may be required if
background data is found inadequate
39
Canadian Nuclear Safety Commission
Development and Implementation of a
Follow-up Monitoring Program
Review/Revise the Preliminary EA FUMP
Develop preliminary sampling plan consistent
with CSA Standards
Review EA FUMP with FAs and other regulatory bodies
Review EA FUMP with stakeholders
Accept EA FUMP
Report on EA FUMP, as required
Develop detailed sampling plan consistent with CSA
Example – Development and Implementation
of a Follow-up Monitoring Program (cont’d)
Step 1: Review/Revise the Preliminary
EA FUMP
• OPG in consultation with CNSC
• Table 12.2-1 of the EIS outlines the proposed
monitoring by project phase, objective, frequency and location
• CNSC staff recommended additional follow-up program elements in PMD 13-P1.3
• OPG will be required to update the initial table with any recommendations made by the Panel, if the project is approved
41
Canadian Nuclear Safety Commission
Example – Development and Implementation
of a Follow-up Monitoring Program (cont’d)
Step 2: Develop preliminary sampling plans
consistent with CSA Standards
• To be conducted by OPG
• CSA standards provide the overall guidance for design and implementation of monitoring
programs
• Detailed design will be determined once program is accepted (number and specific location of
EA FUMP Step 2 Example –
Atmospheric Environment
• CNSC Recommendation #14: CNSC staff recommend that OPG monitor NOx (nitrogen oxides) and
particulates as part of the EA FUMP to confirm predictions of the EIS
Monitoring
activity Monitor air quality
Objective Confirm predictions, mitigation and effect
Criteria EIS maximum predictions
Frequency
Continuous monitoring, log hourly averaged recordings, Data will be downloaded quarterly
Duration Site preparation and construction phase
43
Canadian Nuclear Safety Commission
Example – Development and Implementation
of a Follow-up Monitoring Program (cont’d)
Step 3: Review EA FUMP with federal
authorities and other regulatory bodies
• To be conducted by CNSC
• CNSC will coordinate with the federal and provincial authorities
• A federal authority may assist in the design of a follow-up program and the review of the data obtained
Example – Development and Implementation
of a Follow-up Monitoring Program (cont’d)
Step 4: Review EA FUMP with identified
stakeholders
• To be conducted by CNSC
• Appropriate stakeholders to be identified based on past CNSC practice
• Consultation could include:
– receiving comments through the CNSC website and direct mail outs
– holding technical meetings with interested parties
45
Canadian Nuclear Safety Commission
Example – Development and Implementation
of a Follow-up Monitoring Program (cont’d)
Step 5: Accept EA FUMP
• To be conducted by CNSC • As per Licence Condition 1.2
– Documents that require acceptance by CNSC staff
Example – Development and Implementation
of a Follow-up Monitoring Program (cont’d)
Step 6: Develop detailed sampling plans
consistent with CSA Standards
• To be conducted by OPG • Elements to be considered:
– Objectives
– Information required to meet the objectives – Spatial and temporal boundaries
– Method and frequency of data collection
– Performance or acceptance criteria to be used – Implementation plan
47
Canadian Nuclear Safety Commission
Example – Development and Implementation
of a Follow-up Program (cont’d)
Step 7: Report on EA FUMP, as required
• To be conducted by OPG
• EA follow-up reports to be submitted annually to CNSC
• Additional mitigation measures may be required if results of follow-up monitoring are not within EA predictions
Summary
• Licence requirement for EA Follow-up
Monitoring Program
• Review and acceptance by CNSC staff
required before licensed activities begin
– Federal, provincial and stakeholder
involvement in the review process
Independent Environmental
Monitoring Program
Overview and Objectives
• In 2012, CNSC initiated an Independent Environmental Monitoring Program (IEMP) • The objectives of the IEMP are to:
– assess the level of risk on the health and safety of humans and the environment from contaminants and physical stressors of concern
– independently verify licensee’s environmental performance
– post the environmental data on the CNSC Web site
• These objectives will be achieved independently of licensees’ EA monitoring programs
51
Canadian Nuclear Safety Commission
CNSC IEMP Development Process
• Developed based on guidance found in CSA standard N288.4-10
• US EPA Guidance on Systematic Planning Using
Data Quality Objectives Process will be used to
develop performance and acceptance criteria • Individual sampling plans for each facility were
designed based on:
– licensees approved Environmental Monitoring Programs
– Environmental Risk Assessments
– licensee environmental performance – issues of public concern
Systematic Planning Process for the
Development of the IEMP
Each sampling plan is being developed using a
systematic planning process:
1. Describe study objectives
2. Identify information required to meet objectives 3. Define boundaries of the IEMP and
site-specific sampling plans
4. Develop data collection and analytical approaches 5. Specify performance / acceptance criteria
53
Canadian Nuclear Safety Commission
Stakeholder Involvement
• To date, CNSC staff have not had direct
involvement with stakeholders in developing
sampling plans
• Consideration of parameters that have been
brought up during public hearings have been
taken into account
• CNSC staff will hold meetings with communities
to identify public concerns to incorporate the
Example - 2013 Bruce Power Sampling
Campaign
• Samples of air, soil, grass,
surface water, local
produce, milk, fish, and meat were obtained
• Sample locations included
publically accessible areas such as beaches and
parks. Both near field and reference sites were
considered
• Laboratory analysis will
measure tritium,
Carbon-14, radioactive iodine, gross gamma and gross beta
Objectives
• Confirm sub-surface geological and
geotechnical conditions
• Verify and complete the details of the
DGR design
• Support DGR Safety Case
57
Canadian Nuclear Safety Commission
Verification Activities and Timing
• OPG proposed geoscientific verification activities: – Geological Characterization – EDZ characterization – Excavation response – In situ stress measurement – Geochemical and microbiological characterization – Sealing material demonstration
Verification Activity – Geological
Characterization
• Geological Characterization (geological mapping and geophysics)
– Verify stratigraphy and geological structures – Characterize the rock mass
– Provide a permanent record of rock structure and quality
– Optimize the ground support
59
Canadian Nuclear Safety Commission
Verification Activity – EDZ Characterization
• Objectives:
– Characterize and verify the extent and evolution of the EDZ – Obtain some
geomechanical
properties of the EDZ – Characterize EDZ
permeability
• Phase: construction, operation, and
decommissioning
Proposed borehole configuration for EDZ characterization
Verification Activity – Excavation Response
and Up-scaling Geomechanical Testing
• Objectives:
– Monitor rock response to the excavation of the shaft and lateral
openings to confirm their stability
– Confirm DGR
excavation design – Verify the rock mass
properties
– Confirm shaft liner design and optimize ground support
• Phase: construction
Deformation array in shaft
61
Canadian Nuclear Safety Commission
Verification Activity – In-situ Stress
Measurement
• In situ stress measurement by overcoring and under-excavation tests to: – Verify estimates of the in situ stresses – Verify the design ofthe repository level openings – Inform layout modification • Phase: construction
Under-excavation test Overcoring measurement
Verification Activity – Geochemical and
Microbiological Characterization
• Purpose:
– Verify the geochemical characteristics and ages of mineral infill
– Verify the geochemical characteristics of groundwater
– Verify estimated rock matrix diffusion coefficients – Verify multiphase flow and transport properties and
mechanisms
– Characterize microbial activity and its influence on DGR performance
63
Canadian Nuclear Safety Commission
Verification Activity – Seal Performance
• Sealing material
demonstration, in support of the safety case
– Demonstrate long term hydraulic, structural and chemical performance of the sealing materials – Study seal interaction
and compatibility with the rock mass and its EDZ
• Phase: construction and operation and beyond if necessary
CNSC Review of the Proposed
Geoscientific Verification Plan (GVP)
• OPG has adequately planned the verification activities needed to achieve the objective of the GVP
• The verification activities would address or reduce uncertainties associated with geoscientific aspects of the DGR and the DGR safety case
• The plan does not contain the details of all verification activities with respect to contents, methods, equipments, schedule, and procedures
• A detailed geoscientific verification program would be developed and submitted to CNSC for review and
acceptance if the project is approved
• CNSC has made several recommendations that are related to the verification activities
65
Canadian Nuclear Safety Commission
DGR Safety Case Update
• During the DGR Construction Phase
– Results from the GVP will be compared with the conditions in the bounding scenarios of the safety assessment
– Where the results are less conservative, the effect on safety will be assessed
– Where the effect is significant, the DGR safety case will be updated
• For an Operating Licence for the DGR
– The DGR safety case will be updated with the results from the GVP collected during construction
– DGR safety case will be updated at each operating licence renewal or when there is a proposed change to the licence that affects the safety case
CNSC Compliance Verification Program
• If the DGR is licensed to proceed, CNSC staff will as part of the compliance verification program:
– verify the acceptability of the technical program for implementing the GVP
– monitor the licensee’s implementation of the GVP through the construction phase
– verify that the repository level design adequately take into account the GVP results
– assess the GVP results and verify that they are within the bounds of the safety case