• No results found

J. & W. LOWRY LIMITED. This case study has been prepared for J & W Lowry Limited By Thomas Elliott Foster

N/A
N/A
Protected

Academic year: 2021

Share "J. & W. LOWRY LIMITED. This case study has been prepared for J & W Lowry Limited By Thomas Elliott Foster"

Copied!
33
0
0

Loading.... (view fulltext now)

Full text

(1)

J. & W. LOWRY LIMITED

This case study has been

prepared for

J & W Lowry Limited

By Thomas Elliott Foster

(2)

Table of Contents

1.1.Brief ... 2

2.1.Introduction ... 3

Charles, J (2004). ... 3

2.2.Foundation types Covered in this Report ... 3

2.3.Considered factors affecting the foundations ... 4

2.4.Foundation ... 4

2.5.Elements requiring foundations ... 4

2.6.Information required before designing foundations ... 5

3.1.Assumptions/Belief of ground type/condition ... 6

Charles, J (2004). ... 6

3.3.After the nature of the ground has been ascertained a risk register should be completed to identify; ... 6

3.4.A remedial strategy should then be formed subject to; ... 6

4.1.Report 1 – Shallow foundation ... 7

4.2.Strip Foundation (see appendix 1 & 2 for detail) (trench foundations are very similar to strip foundations, differing mainly in thickness of foundation) ... 7

4.3.Pad foundations (see Appendix 3) ... 9

4.4.Raft foundations (see appendix 4) ... 11

5.1.Report 2 – Deep Foundations ... 13

5.2.Friction/Driven piles/Displacement piles (see appendix 5) ... 13

5.3.End-bearing piles/Bored piles/Replacement piles (see appendix 6) ... 14

6.1.Decision matrix (showing the value you each foundation through a rating system of 1-5 in which 1 – poor and 5 – ideal) ... 16

7.1.Conclusion ... 16

Reference ... 17

(3)

A client has identified a city centre, brownfield site (with possible obstructions within the ground) that is surrounded by buildings and has bedrock 8m below ground level. The site is to accommodate a five storey office building that is to house 250 staff.

The client requires a technical report that will enable them to understand the suitability of various substructures. Where appropriate the report shall identify relevant guidance, legislation and sustainability considerations relating to the proposed building.

The report will:

1) Illustrate various foundation types (excluding piles) that may be used to support a building. Investigate and analyse the advantages and disadvantages of these various systems including the way in which they transmit the loads to the ground. Suggest when it may be appropriate to use each of the foundation types.

2) Illustrate various types of pile foundation that may be used to support a building. Investigate and analyse the advantages and disadvantages of these various systems including the way in which they transmit the loads to the ground. Suggest when it may be appropriate to use each of the pile types.

(4)

Foundations are primarily required to support building construction but on brownfield sites they can also act as a barrier to contaminants. The performance of foundation materials can be adversely affected by contaminants

Charles, J (2004).

2.2. Foundation types Covered in this Report

a. Shallow foundations a.i. Strip foundations a.ii. Pad foundations a.iii. Raft foundation b. Deep foundations

b.i. Pile foundations

b.i.1. Friction/Driven piles/Displacement piles

b.i.2. End-bearing piles/Bored piles/Replacement piles

2.3. Considered factors affecting the foundations

a. Live Loads

b. Dead Load (5 storey building) c. Wind Load

d. Earthquake e. Uplift

f. Structural Member Forces

g. Horizontal Pressures below Grade

(5)

2.4. Foundation

a. Must transfer the combined load to the required load bearing stratum, while coping

with

i. The grounds settlement characteristics ii. Possible ground heave

iii. The impact of creep on the foundation b. Should be technically and economically feasible

2.5. Elements requiring foundations

a. External walls b. Separating walls c. Chimney breasts d. Piers

e. Internal loadbearing or masonry walls f. Sleeper walls

g.

2.6. Information required before designing foundations

a. site and ground appraisals b. dwelling design

c. site layout d. site levels

(6)

f. trees

g. frost susceptible soils

3.1. Assumptions/Belief of ground type/condition

3.2. A brownfield site can have many hazards, these need to be identified so remedies can be

taken to eliminate/limit their impact on the building and its’ users. Most sites have a Land Condition Record (LCR) which should provide a record of the nature of any contamination and the previous used of the land. Along with the LCR it is recommended to consult a specialist in land contamination (SILC). The chart below illustrates the recommended steps to take from initial assessment to complete construction.

(7)

Charles, J (2004).

3.3. After the nature of the ground has been ascertained a risk register should be completed to

identify;

a. Hazards

b. The nature and degree of risk resulting from the hazards c. A planned response

(8)

e. The nature and degree of residual risk and with whom it lies

f.

3.4. A remedial strategy should then be formed subject to; a. Technical adequacy

b. Cost

c. Environmental effects d. Perception

NHBC (2011)

Note: Advice and guidance on foundations have been given solely based on the clients’

information given in the brief (1.0). Should any information change the advised foundation type should be re-analysed as it may not be suitable.

4.1. Report 1 – Shallow foundation

Illustrate various foundation types (excluding piles) that may be used to support a building. Investigate and analyse the advantages and disadvantages of these various systems including the

(9)

way in which they transmit the loads to the ground. Suggest when it may be appropriate to use each of the foundation types.

4.2. Strip Foundation (see appendix 1 & 2 for detail) (trench foundations are very

similar to strip foundations, differing mainly in thickness of foundation)

a. Required for:

i. External walls ii. Separating walls iii. Chimney breasts

iv. Piers

v. Internal loadbearing walls

b. Dimensions are 150mm -500mm thick depending of bearing stratum (refer to

appendix 2 for more information)

c. Material

i. Cast in-situ concrete (OPC or SRPC) ii. pre-cast concrete (OPC or SRPC)

d. Concrete shall be of a mix design which is suitable for the intended use, items to be

taken into account include:

i. strength to safely transmit loads

ii. durability against chemical or frost action e. Normal depth of 1m

f. Not recommended for soils with low bearing capacity and should be laid at a depth

(10)

g. Except where strip footing sit on bedrock, foundations should be taken to a minimum

of 450mm below ground

h. Reinforcement can be added

i. When taking the foundations to the required depth the water table may have to be

taken into consideration

j. Brownfield site ground maybe hazardous therefore the foundation should be designed

by an engineer

i. Designed in accordance with 1. BS EN 1991-1-1 2. BS EN 1991-1-3 3. BS EN 1991-1-4 4. BS 648.

5. BS 8500-1

6. BRE Special Digest 1

RIBA (2010), NHBC (2011), Hodgkinson, A (1986) Strip Foundations

Advantages Disadvantages When Required

Shallow foundations, therefore little excavation needed.

Economically cheap due to the narrow, shallow design.

Little to no impact on

Limited load carrying ability due to foundation depths and design, therefore only suited to small/medium

developments. Not ideal for framed

In ground of medium to good bearing stratum, on domestic scale developments,

underneath loadbearing walls, separating walls, chimneys, piers and internal loadbearing walls.

(11)

neighbouring properties. Sulphate Resisting Portland Cement (SRPC) can be used in place of Ordinary Portland Cement (OPC) to cope with sulphur attack from soils.

construction.

Weak against uplift forces, wind forces and earthquake forces.

Weak in stratum of loose sand or gravel.

To carry light loads

Riley et al.(2009)

The continuous narrow trenches excavated for the Strip foundations are suited to continuous load bearing walls as opposed to point loads. Not intended to support building higher than 3/4 storeys. The narrow trenches would need to be taken to a depth where the foundation could transfer the load to suitable stratum, at depth the excavated trenches would require supports to prevent caving in. Working space needed of 600mm (under building regulations) for health and safety would need to be provided for workers to carry out work, the sided of the excavated working space trenches requiring support. Once all required work has been carried out the working space trenches would have to be backfilled.

4.3. Pad foundations (see Appendix 3)

a. An alternative to strip foundations for framed structures b. Required for:

i. External walls

ii. Separating (party) walls iii. Chimney breasts

(12)

v. Internal loadbearing or masonry walls vi. Sleeper walls

c. Material

i. Cast in-situ concrete (OPC or SRPC) ii. Reinforcement

d. Thickness designed to transmit the load at a 45° angle through the Pad to minimise

tensile stresses on the soffit of the foundation

e. Transmit the load to the bearing strata through individual foundations

f. Concrete shall be of a mix design which is suitable for the intended use, items to be

taken into account include:

i. strength to safely transmit loads

ii. durability against chemical or frost action

g. Reinforcement can be added to carry the tensile stresses and required loads h. Shear reinforcement can be added to avoid punching failure

i. Not recommended for soils with low bearing capacity and should be laid at a depth

where the foundation can transfer the required load to good bearing strata

j. Brownfield site ground maybe hazardous therefore the foundation should be designed

by an engineer

i. Designed in accordance with; 1. BS 648

(13)

3. BS EN 1997-1 4. BS EN 1992 5. BS 10175

NHBC(2011), RIBA (2010), Hodgkinson, A (1986) Pad Foundations

Advantages Disadvantages When Required

Shallow foundation Requires little excavation. Can be designed to accommodate tight sites. Economic due to control of foundation size.

Reinforcement for tension and shear can be added.

Concrete mix can use SRPC in place of OPC

Foundation size can be a very large to cope with high point loads.

Limited foundation suitability to point loads of framed buildings. Separate foundations make this design weak against differential settlement that may affect the building.

Deep excavations for foundations would require support to prevent caving in. Weak against uplift forces, wind forces and earthquake forces.

Ideal foundation for point loads from framed

buildings when bearing capacity of ground is suitable a shallow depths.

Riley et al.(2009)

Pad foundations are suited to a framed construction however the ground type described in the brief and the heavy load of the 5 story building would require this usually shallow foundation to be taken deeper to better bearing stratum, thus eliminating the economic advantage of this

(14)

foundation. The foundation size would have to be enlarged to cope with the high point loads. Additional costs occur for supporting the excavations to prevent cave-ins. As the site is a brownfield site SRPC my need to be introduced thus increasing the material cost.

Hodgkinson, A (1986)

4.4. Raft foundations (see appendix 4)

a. Used in ground with very low bearing capacity or where excessive variations in

ground conditions would cause unacceptable differential settlements

(15)

i. External walls ii. Separating walls iii. Chimney breasts

iv. Piers

v. Internal loadbearing walls vi. Sleeper walls

c. Recommended when Strip or Pad foundations occupy more than 50% of the floor

area

d. Requires reinforcement to carry the tensile, load Steel reinforcing fabric should

comply with BS 4483

e. Suitable for projects where there is a shallow water table f. Material

i. Cast in-situ concrete (OPC or SRPC)

g. Approved Document C4 requires the minimum quality of the concrete to be at least

mix ST2 of BS 5328-1

h. Concrete shall be of a mix design which is suitable for the intended use, items to be

taken into account include:

i. strength to safely transmit loads

ii. durability against chemical or frost action

i. Brownfield site ground maybe hazardous therefore the foundation should be designed

by and engineer

(16)

1. BS 648 2. BS EN 1991 3. BS EN 1997-1 4. BS EN 1992 5. BS 10175 NHBC(2011), RIBA (2010). Raft Foundations

Advantages Disadvantages When Required

Financially cheap due to the combined use of the foundation as the floor.

Shallow depth of foundation means little excavation. Can cope with poor/mixed ground conditions.

Weak when supporting point loads, specific treatment required.

Susceptible to edge erosion.

Lightweight structures on poor ground with low bearing capacity.

Used in areas with mixed bearing capacity usually filled ground.

Riley et al.(2009), Hodgkinson, A (1986)

Raft foundations are ideal foundation choice to support light weight buildings (3/4 stories high). The design provides an economical advantage that is the dual use of the raft as the ground floor concrete slab. The foundation is suited to traditional buildings in grounds of poor/mixed bearing stratum. The raft provides very good protection against differential ground settlement,

earthquakes and heave due to the design. The raft would traditionally not suit a famed building. The raft can be designed to accommodate framed structures however they were not intended to cope with high point loads. The concrete mix can have SRPC added to help resist chemical attack.

(17)

5.1. Report 2 – Deep Foundations

Illustrate various types of pile foundation that may be used to support a building. Investigate and analyse the advantages and disadvantages of these various systems including the way in which they transmit the loads to the ground. Suggest when it may be appropriate to use each of the pile types.

5.2. Friction/Driven piles/Displacement piles (see appendix 5)

a. Are piles driven into the ground, they derive their bearing capacity from skin friction

and/or adhesion

b. Required for;

b.i. External walls b.ii. Separating walls b.iii. Chimney breasts

b.iv. Piers

b.v. Internal loadbearing or masonry walls b.vi. Sleeper walls

c. Suited to loose and moisture bearing granular soils d. Material

d.i. Reinforced concrete d.ii. Prestressed concrete d.iii. Steel

(18)

e. Unsuited to ground containing boulders or obstacles

f. Brownfield site ground maybe hazardous therefore the foundation should be designed

by and engineer

f.i. designed in accordance with; f.i.1. BS 648

f.i.2. BS EN 1991 f.i.3. BS EN 1997-1 f.i.4. BS EN 1992 f.i.5. BS 10175

g. May be accompanied by a reinforced ring beam or pile caps to provide stability

against forces and help transfer loads NHBC(2011), RIBA (2010), Biddle et al.(2002)

Friction/Driven piles/Displacement piles

Advantages Disadvantages When Required

Can transfer load in variable ground conditions.

Can transfer loads to deep bearing stratum

Suitable to tight sites.

Problematic when dimensional stability of the ground is an issue.

Problematic when there is demolition debris or boulders in the ground.

Sites with poor ground conditions.

Soils that have low bearing capacity but offer good friction forces. Bearing stratum is deep

(19)

Made off site and quality maintained due to factory production.

There is no evidence that Steel piles are susceptible to corrosion by the action of sulphur reducing bacteria (<0.03mm corrosion per annum).

No excavation required. No need to support excavated holes.

Suited to framed construction.

Noisy installation method can cause environmental impact Vibration can affect neighboring properties

Can cause ground heave

below the surface.

Harrison et al.(2012), Riley et al.(2009), Biddle et al.(2002), Technical Committee B/517 (2009)

Friction Pile foundations are uniformly distributed columns driven into the ground via the repeated dropping of a weight onto the head of the pile, to reach the required depth and transmit the required building loads to good bearing stratum. Pile foundations would normally be used when ground conditions are not suitable to economically support reason for traditional

foundations. Friction piles cope well with live loads, dead loads, wind loads, earthquakes and uplift. They can cause problems such as heave. The piles are compatible with framed buildings and designed to carry loads of light to heavy weight structures. Steel piles have a very high resistance to sulphur attack or SRPC can be added to concrete mixes. Piles are ideal for

brownfield sites that may have had previous buildings on the site. Reinforcement can be added to cope with the horizontal forces. There is an economic advantage not excavating material.

(20)

5.3. End-bearing piles/Bored piles/Replacement piles (see appendix 6) a. Holes bored into the ground and filled with concrete

b. Required for;

b.i. External walls b.ii. Separating walls b.iii. Chimney breasts

b.iv. Piers

b.v. Internal loadbearing or masonry walls b.vi. Sleeper walls

c. The pile transmits the load through the pile to the bearing strata which the pile is in

contact with

d. Suited to poor/mixed ground e. Material

e.i. In-situ concrete (OPC or SRPC) e.ii. Reinforced

f. Brownfield site ground maybe hazardous therefore the foundation should be designed

by and engineer

f.i. Designed in accordance with; f.i.1. BS 648

f.i.2. BS EN 1991 f.i.3. BS EN 1997-1

(21)

f.i.4. BS EN 1992 f.i.5. BS 10175

g. May be accompanied by a reinforced ring beam or pile caps to provide stability

against forces and help transfer loads from the building to good bearing stratum NHBC(2011), RIBA (2010), Biddle et al.(2002), Hodgkinson, A (1986)

Large diameter bored piles

Advantages Disadvantages When Required

Can transmit heavy loads. Larger diameter of piles mean less piles needed.

No need to support bore hole as concrete replaces the void created.

Almost vibration free. Almost noise free.

Not susceptible to boulders or debris below ground.

Can transfer loads to deep bearing stratum on tight sites.

Require reasonably good soil content to avoid bore hole collapsing.

Large plant needed to excavate earth.

Heavy buildings with large loads.

When there is a risk of damage to surrounding buildings through vibration. Bearing stratum is deep below the surface.

Riley et al.(2009), Biddle et al.(2002), Technical Committee B/517 (2009)

End-bearing piles are suited to sites where there is a requirement to transfer large loads to a bearing stratum that is too deep for other foundations. The boring process eliminates the noise

(22)

and vibration factor. Bored pile diameters range from 450mm to 1200mm so fewer piles would be needed if larger piles were used. Piles can be combined with pile caps or a ring beam to increase stability to the structure. Suited to framed structures and ideal for dealing with point loads and they are very strong in compression. Reinforcement can be added to cope with the horizontal forces. SRPC can be added to the concrete mix to combat the sulphate chemicals in soils. Piles are ideal for brownfield sites.

NHBC(2011), Hodgkinson, A (1986)

6.1. Decision matrix (showing the value you each foundation through a rating system of 1-5

in which 1 – poor and 5 – ideal) Information/requirement s known Strip Foundation (weighting) Pad Foundation (weighting) Raft Foundation (weighting) Driven Pile Foundation (weighting) Bored Pile Foundation (weighting) Bed rock 8m below

ground

1 1 5 5 5

five storey office building

2 2 3 5 5

brownfield site 3 3 2 5 3

city centre 4 4 4 2 4

possible obstructions within the ground

5 5 5 3 5

Total 15 15 19 20 22

7.1. Conclusion

After analysing the various foundations and processing them into the decision matrix, Bored pile foundations appear to be the most suitable, however there is very little information known at this stage and it would be possible to use raft, driven piles or bored piles on such a project. Strip and

(23)

pad foundation would not be suitable sue to land, size of building and loads the foundations would have to cope with. Raft foundation although used mainly for light weight structures could be designed to cope with greater loads. The building design is not known and it would be

suggested if this building would be a framed building then it would be best not to use raft foundation as its design is traditionally weak in supporting point loads, the raft would cope with the land and deep bearing stratum issue. Driven piles appear to be a better option according to the decision matrix as they are designed to cope with heavier loads. Driven piles are ideal for tight sites as they require no excavation, there would be an economical benefit to this too. The driven pile foundations are not perfect, they are unsuitable for use in ground with boulders or debris below ground, which the pile may hit and be pushed off course, in this case it would be a cost to, have the pile removed and relocated, or excavate the boulder/debris, and drive the pile again. The decision matrix shows bored piles have come out as the favourite choice, the reason for this is its ability to cope with the loads specified for the building. They can reach the depths of the bedrock, the reduced vibration and noise in comparison to the driven pile are to the advantage of the bored piles, this is a city centre site and therefore likely to have neighbouring buildings, which with driven piles may be subject to heave or settlement displacement. With bored piles the client would have less chance of falling foul to disturbing the neighbouring properties. More information at this stage is required in order to properly select the right foundation such as the LCR. Based on the information provided either of the pile foundation types would be suitable.

Reference

Biddle,A.,Yandzio,E (2002). Specifiers’ Guide to Steel Piling. Berkshire: The Steel Construction Institute. 1-46.

(24)

Chudley, R., Greeno, R (2010). Building Construction Handbook, Incorperating Current building & Construction Regulations. 8th ed. Oxford: BSIElsevier Ltd. p206-319.

European committee for standardisation (2007). Precast concrete products — Foundation piles. Brussels: BSI. 1-44.

Harrison,H.,Trotman,P (2012). Foundations,basements and external work. London: BRE Building elements. 1-249.

Hodgkinson, A (1986). Foundation Design. London: Architectural Press Ltd. p15-81.

NHBC (2011). NHBC Standards: Land Quality - Managing Ground Conditions Chapter 4. 1. 4th ed. England: National house building council. 1-16.

RIBA (2010). StructuresApproved Document A. London: NBS. p1-45.

RIBA (2010). Fire Safety Approved Document B, Volume 2: Buildings Other Than Dwelling Houses. London: NBS. p1-150.

RIBA (2010). Site Preparation and Resistance to Contaminants and MoistureApproved Document C. London: NBS. p1-40.

RIBA (2010). Toxic Substances Approved Document D. London: NBS. p1-5.

Riley,M.,Cotgrave,A (2009). Construction technology 2:Industrial and commercial building. 2nd ed. England: Palgrave. 109.

Technical Committee B/517 (2003). Concrete — Complementary British Standard to BS EN 206-1 — Part 1: Method of specifying and guidance for the specifier. London: BSI. p1-40. Technical Committee B/517 (2009). Code of practice for noise and vibration control on construction and open sites – Part 2: Vibration. 3rd ed. London: BSI. p1-90.

Technical Committee B/517 (2011). Structural design of low-rise buildings Part 1: Code of practice for stability, site investigation, foundations, precast concrete floors and ground floor slabs for housing. 3rd ed. London: BSI. p1-58.

(25)

Image taken from: NHBC(2011)

(26)

Image taken from: http://www.google.co.uk/imgres? imgurl=http://www.thebeamlockcompany.co.uk/images/Beamlock-Foundations.jpg&imgrefurl=http://www.thebeamlockcompany.co.uk/technical.html&h=602&w= 566&sz=94&tbnid=1QOdwPHCDx63HM:&tbnh=90&tbnw=85&prev=/search%3Fq%3Dpad %2Bfoundations%2Bdetails%26tbm%3Disch%26tbo %3Du&zoom=1&q=pad+foundations+details&usg=__-kM0aIizEOTaO- c3ub9h3ytAV8g=&docid=WT-fGBMNXwOLKM&hl=en&sa=X&ei=J_C7UJGEDsWg0QXxlIGoDA&ved=0CC4Q9QEwAA &dur=0

(27)

Appendix 3

Image taken from: http://www.google.co.uk/imgres?

imgurl=http://www.thebeamlockcompany.co.uk/images/Beamlock-Foundations.jpg&imgrefurl=http://www.thebeamlockcompany.co.uk/technical.html&h=602&w= 566&sz=94&tbnid=1QOdwPHCDx63HM:&tbnh=90&tbnw=85&prev=/search%3Fq%3Dpad %2Bfoundations%2Bdetails%26tbm%3Disch%26tbo %3Du&zoom=1&q=pad+foundations+details&usg=__-kM0aIizEOTaO- c3ub9h3ytAV8g=&docid=WT-fGBMNXwOLKM&hl=en&sa=X&ei=J_C7UJGEDsWg0QXxlIGoDA&ved=0CC4Q9QEwAA &dur=0

(28)

Appendix 4

Image taken from: http://www.google.co.uk/imgres?

imgurl=http://www.thebeamlockcompany.co.uk/images/Beamlock-Foundations.jpg&imgrefurl=http://www.thebeamlockcompany.co.uk/technical.html&h=602&w= 566&sz=94&tbnid=1QOdwPHCDx63HM:&tbnh=90&tbnw=85&prev=/search%3Fq%3Dpad %2Bfoundations%2Bdetails%26tbm%3Disch%26tbo %3Du&zoom=1&q=pad+foundations+details&usg=__-kM0aIizEOTaO- c3ub9h3ytAV8g=&docid=WT-fGBMNXwOLKM&hl=en&sa=X&ei=J_C7UJGEDsWg0QXxlIGoDA&ved=0CC4Q9QEwAA &dur=0

(29)

Appendix 5

Image taken from: http://www.google.co.uk/imgres?

q=friction+driven+piles&um=1&hl=en&sa=N&tbo=d&biw=1366&bih=648&tbm=isch&tbnid=l k5DNHOkKOqPNM:&imgrefurl=http://www.substruck.ie/our-services/foundation- repair/piling&docid=qzfj53dH8b7PKM&imgurl=http://www.substruck.ie/wp-content/themes/substruck/pictures/frictionpile.jpg&w=604&h=367&ei=duq7UKjLBu7M0AWar4 HQCw&zoom=1&iact=hc&vpx=1035&vpy=375&dur=1369&hovh=175&hovw=288&tx=109& ty=121&sig=104003884147091334153&page=1&tbnh=131&tbnw=216&start=0&ndsp=25&ve d=1t:429,r:24,s:0,i:160 Appendix 6

(30)

Image taken from: http://www.google.co.uk/imgres? q=friction+driven+piles&um=1&hl=en&sa=N&tbo=d&biw=1366&bih=648&tbm=isch&tbnid=l k5DNHOkKOqPNM:&imgrefurl=http://www.substruck.ie/our-services/foundation- repair/piling&docid=qzfj53dH8b7PKM&imgurl=http://www.substruck.ie/wp-content/themes/substruck/pictures/frictionpile.jpg&w=604&h=367&ei=duq7UKjLBu7M0AWar4 HQCw&zoom=1&iact=hc&vpx=1035&vpy=375&dur=1369&hovh=175&hovw=288&tx=109& ty=121&sig=104003884147091334153&page=1&tbnh=131&tbnw=216&start=0&ndsp=25&ve d=1t:429,r:24,s:0,i:160 Appendix 7

(31)

Image taken from: NHBC(2011)

(32)

Image taken from: NHBC(2011)

(33)

References

Related documents

Section 7 of the National Voter Registration Act (NVRA) of 1993 requires that each state provide the opportunity to register to vote with every application for public assistance

However, overall a positive correlation between symptoms and viral load was observed for virus challenge trials of transgenic lines generated from A-MM4, C-MM6 and C-MM8

Often, the offer to “carry” to a higher rank isn’t enough for some women. For Jeanist, above, and many other male members in the League community, they offer “skins,” small

The measurements led to recording a total of 759 specimens (originating from 17 families in 30 genera and 74 species) as trace element hyperaccumulators, including 28

Multiple qualitative studies found students expressing negative attitudes to reading when AR implementation included letter grade penalties for failing to read and limited time to

Bakiyev was not popularly elected, and thus his legitimacy was shaky. As the opposition leader at the time of the coup he could claim popular support, but this soon ran out. His focus

Target(s)  Timeframe Resource  Deployment  Status Document Link 3 1  Growing Transit  Communities [PSRC]  2013  Puget Sound Regional  Council (PSRC)