EDR Guidelines CoolTools
EDR Guidelines CoolTools
Pipe Size Optimization Tool v1.4
Pipe Size Optimization Tool v1.4
Introduction
Introduction
T
Traditionally, most designers size piping using rules of thumb, such raditionally, most designers size piping using rules of thumb, such as limiting friction rate (e.g., as limiting friction rate (e.g., 4 feet per 104 feet per 10
pipe), water velocity (e.g., 10 feet per second), or a combination of the two. These methods are expedient an pipe), water velocity (e.g., 10 feet per second), or a combination of the two. These methods are expedient an reproducible, but they seldom result in an optimum design on either a
reproducible, but they seldom result in an optimum design on either a first-cost or life-cycle first-cost or life-cycle cost basis. The opcost basis. The op
pipe size for a given design flow rate is a function of: pipe size for a given design flow rate is a function of: - Location of pipe in the
- Location of pipe in the system (whether or not it is system (whether or not it is in the critical circuit (1));in the critical circuit (1));
- First costs of installed pi
- First costs of installed pi ping;ping;
- Pump energy costs, which in turn will depend on pump and motor
- Pump energy costs, which in turn will depend on pump and motor efficiency, distribution system type (constefficiency, distribution system type (const
variable flow), annual flow profile through the system a
variable flow), annual flow profile through the system a s well as the pipe in s well as the pipe in question, type of pump control (vquestion, type of pump control (v
speed or riding pump curve), etc.; speed or riding pump curve), etc.;
- Erosion considerations (high velocities can contribute to
- Erosion considerations (high velocities can contribute to hastening of pipe wall deterioration);hastening of pipe wall deterioration);
- Noise
- Noise considerations, such as velocity limits to minimize noise caused by turbulence and the proximity of thconsiderations, such as velocity limits to minimize noise caused by turbulence and the proximity of th
noise-sensitive areas; noise-sensitive areas; - Physical constraints; and - Physical constraints; and - Budget constraints. - Budget constraints. The CoolT
The CoolTools Pipe Size Optimization ools Pipe Size Optimization TTool incorporates tool incorporates t he above design and he above design and cost factors, cost factors, allowing the designallowing the design
the lowest cost piping system design. the lowest cost piping system design.
1. The critical circuit is the circuit within the system with
1. The critical circuit is the circuit within the system with the highest pressure loss that determines pump head. This the highest pressure loss that determines pump head. This is often the longest run is often the longest run in thin th not always. The pressure loss in this
not always. The pressure loss in this circuit, and only this circuit, drives annual energy consumption.circuit, and only this circuit, drives annual energy consumption.
System Assumptions Tab
System Assumptions Tab
System
System T
Type and
ype and Average Water Temperature
Average Water Temperature
System options include chilled water, hot wa
System options include chilled water, hot wa ter, and condenser water. Choice of system type impacts tter, and condenser water. Choice of system type impacts t he anhe an
energy calculation. For chilled water, pump heat
energy calculation. For chilled water, pump heat is added to total annual energy, for is added to total annual energy, for hot water, pump heat ishot water, pump heat is
subtracted, and for condenser water,
subtracted, and for condenser water, pump heat is ignored.pump heat is ignored.
System type will also select
System type will also select a default average a default average water temperature, which will appear in the cwater temperature, which will appear in the c ell below. Defaultell below. Default
temperatures for the three system types c
temperatures for the three system types c an be adjusted on the Constants tab.an be adjusted on the Constants tab.
Is this circuit the critical circuit?
Is this circuit the critical circuit?
The T
The Tool optimizes pipe sizes for ool optimizes pipe sizes for one circuit at a time. Ione circuit at a time. I f CRITICAL is selected, the Tool will treat the circuit asf CRITICAL is selected, the Tool will treat the circuit as
critical circuit in the system, tak
critical circuit in the system, tak ing into account energy cost when determining the least expensive ing into account energy cost when determining the least expensive alternativalternativ
NON-CRITICAL is selected, the T
account for sizing. Non-critical circuits will be sized according to the
account for sizing. Non-critical circuits will be sized according to the selected noise and erosion criteria. Wheselected noise and erosion criteria. Whe
CRITICAL is selected, the Lifecycle Energy Cost output will read "-"
CRITICAL is selected, the Lifecycle Energy Cost output will read "-" because it is not because it is not possible to calculate enepossible to calculate ene
consumption from the non-critical circuit. consumption from the non-critical circuit. Note:
Note: If NON-CRITICAL is selected and noise and erosion velocity limits arIf NON-CRITICAL is selected and noise and erosion velocity limits are turned off, then the optimized pie turned off, then the optimized pi
will be the smallest
will be the smallest available pipe size.available pipe size.
System operation
System operation
Select Contstant Flow/ Constant Speed
Select Contstant Flow/ Constant Speed (CFCS), Variab(CFCS), Variable Flow/ Constant Speed le Flow/ Constant Speed (VFCS), Variabl(VFCS), Variable Flow/ Variablee Flow/ Variable
with Fixed Set Point (VFVSFSP), or Variable Flow/ Variable Speed with Reset Set Point (VFVSRSP). This selectio with Fixed Set Point (VFVSFSP), or Variable Flow/ Variable Speed with Reset Set Point (VFVSRSP). This selectio impact annual energy consumption. Variable flow selections will reduce annual
impact annual energy consumption. Variable flow selections will reduce annual energy consumption accordinenergy consumption accordin
factors specified on the Constants tab. factors specified on the Constants tab.
Hours per year of operation
Hours per year of operation
Enter total annual estimated hours of
Enter total annual estimated hours of operation.operation.
Pipe insulation thickness
Pipe insulation thickness
Select desired pipe insulation thickness or none. The
Select desired pipe insulation thickness or none. The Title 24 option will automatically select the code-requirTitle 24 option will automatically select the code-requir
insulation thickness for the
insulation thickness for the specified water temperature and pipe specified water temperature and pipe diameterdiameter..
This input is one of three that can be applied to override user inputs for individual pipe segments on the Pipi This input is one of three that can be applied to override user inputs for individual pipe segments on the Pipi
tab. Once a selection is
tab. Once a selection is made, the Apply button next to the made, the Apply button next to the input must be clicked. This will overwrite all input must be clicked. This will overwrite all inputinput
Insulation Wall Thickness column on the Piping Circuit page. After clicking Apply, further modifications to the Insulation Wall Thickness column on the Piping Circuit page. After clicking Apply, further modifications to the thickness for individual segments may be made. However, these modifications will be overwritten if
thickness for individual segments may be made. However, these modifications will be overwritten if the Applthe Appl
is clicked again. is clicked again.
Fluid speed limit for noise sensitivity?
Fluid speed limit for noise sensitivity?
If noise is a
If noise is a concern, velocities may be limited to minimize noise caused by concern, velocities may be limited to minimize noise caused by turbulence. If YES is selected andturbulence. If YES is selected and
is chosen as AUTO, then
is chosen as AUTO, then the automated pipe sizing function will not allow the automated pipe sizing function will not allow the noise velocity limit to be the noise velocity limit to be exceeexcee
YES is selected and pipe
YES is selected and pipe size is chosen manually, then a size is chosen manually, then a red-flagged cell will indicate when the maximum noired-flagged cell will indicate when the maximum noi
velocity is exceeded for a particular pipe segment. These limits
velocity is exceeded for a particular pipe segment. These limits (starting at 3 fps (starting at 3 fps for ¾" pipe for ¾" pipe and increasing liand increasing li
20 fps for 30" pipe (3) )
20 fps for 30" pipe (3) ) are given on the Constants tab and can be edited there.are given on the Constants tab and can be edited there.
Fluid speed limit for erosion control?
Fluid speed limit for erosion control?
If pipe wall erosion is
If pipe wall erosion is a concern, velocities may be limited to reduce the a concern, velocities may be limited to reduce the risk of erosion. If YES is risk of erosion. If YES is selected andselected and
is chosen as AUTO, then
is chosen as AUTO, then the automated pipe sizing function will not allow the automated pipe sizing function will not allow the erosion velocity limit to be excthe erosion velocity limit to be exc
YES is selected and pipe
YES is selected and pipe size is chosen manually, then a size is chosen manually, then a red-flagged cell will indicate when the maximium erred-flagged cell will indicate when the maximium er
velocity is exceeded. V
velocity is exceeded. Velocity limits are given on the elocity limits are given on the Constants tab. While these and similar Constants tab. While these and similar maximum velocimaximum veloci
guidelines have been around for years, they have never been
guidelines have been around for years, they have never been corroborated by researccorroborated by research. In fact, most of h. In fact, most of the rthe r
on this issue has indicated that unless there are particles or air bubbles in the water, there is little erosion of on this issue has indicated that unless there are particles or air bubbles in the water, there is little erosion of regardless of velocity, within the
regardless of velocity, within the normal velocity ranges found in normal velocity ranges found in commercial systems.commercial systems.
This input is one of three that can be applied to override user inputs for individual pipe segments on the Pipi This input is one of three that can be applied to override user inputs for individual pipe segments on the Pipi
tab. Once a selection is
tab. Once a selection is made, the Apply button next to the made, the Apply button next to the input must be clicked. This will overwrite all input must be clicked. This will overwrite all inputinput
Flow Speed Limit to Prevent Erosion? column on the Piping Circuit page. After clicking Apply, further modifica Flow Speed Limit to Prevent Erosion? column on the Piping Circuit page. After clicking Apply, further modifica this column for individual segments may be
this column for individual segments may be made. However, these modificationmade. However, these modifications will be s will be overwritten if the Apoverwritten if the Ap
button is clicked again. button is clicked again.
2. Care must be taken when sizing a n
2. Care must be taken when sizing a n on-critical circuit. Energy consumption is independent of pressure loss in a non-critical circuit as long as thon-critical circuit. Energy consumption is independent of pressure loss in a non-critical circuit as long as th pressure loss is not greater than that of
pressure loss is not greater than that of the critical circuit. If pressure loss in a non-critical circuit excethe critical circuit. If pressure loss in a non-critical circuit exceeds pressure loss in the critical circuit, theneds pressure loss in the critical circuit, then becomes the new critical circuit. Pressur
becomes the new critical circuit. Pressure loss for a e loss for a circuit can be obtained from the spreadsheet’s Tcircuit can be obtained from the spreadsheet’s Total Head (Feet) output at the bottom of otal Head (Feet) output at the bottom of thethe sheet.
sheet.
3. Wilson, George. 1988. Wilson Ihrig Associates, Oakland, Calif. Unpublished information
Piping Circuit Tab
Piping Circuit Tab
The Piping Circuit tab contains inputs for
The Piping Circuit tab contains inputs for each pipe segment and each pipe segment and system element within the piping circuit. Forsystem element within the piping circuit. For
segment, complete all yellow fields with appropriate physical data. All white fields are
segment, complete all yellow fields with appropriate physical data. All white fields are locked and may not belocked and may not be
Sheet Management
Sheet Management Functions
Functions
When starting a new pipe circuit, always clear sheet
When starting a new pipe circuit, always clear sheet and reset formulas with the Clear and Apply User Settingand reset formulas with the Clear and Apply User Setting
the top left corner of
the top left corner of the sheet. Note: This will clear ALL the sheet. Note: This will clear ALL user inputs and will apply the selections from the threuser inputs and will apply the selections from the thre
inputs (insulation thicknes
inputs (insulation thickness, erosion velocity limit, and noise velocity limit) to s, erosion velocity limit, and noise velocity limit) to all piping segments. This can noall piping segments. This can no
undone. undone.
In order to preserve the structure of the spreadsheet (formulas and conditional formatting), do not copy and p In order to preserve the structure of the spreadsheet (formulas and conditional formatting), do not copy and p or rows, and do not manually add
or rows, and do not manually add or delete rows using Excel functions. When adding or deleting piping segmeor delete rows using Excel functions. When adding or deleting piping segme
always use the Add a Row and Delete a Row buttons. Two rows is the minimum number of rows allowed. always use the Add a Row and Delete a Row buttons. Two rows is the minimum number of rows allowed. Troubleshooting: If the function buttons (Add a Row, Optimize Pipe Size, etc.) will not work, hit Esc or Return to Troubleshooting: If the function buttons (Add a Row, Optimize Pipe Size, etc.) will not work, hit Esc or Return to
editing cells. Function button
editing cells. Function buttons will not work while cs will not work while c ells are in edit mode.ells are in edit mode.
Pipe Size Selection/ Automated Sizing
Pipe Size Selection/ Automated Sizing
If automatic pipe sizing is desired for a
If automatic pipe sizing is desired for a segment, select AUTO in the pull-down menu under Select Pipe Size orsegment, select AUTO in the pull-down menu under Select Pipe Size or
Segments not containing AUTO in this
Segments not containing AUTO in this field will be field will be ignored during the optimization routine.ignored during the optimization routine.
If a fixed pipe size
If a fixed pipe size is desired for a segment, select tis desired for a segment, select t he size from the options in the pull-down menu.he size from the options in the pull-down menu.
Regardle
Regardless of pipe sizing choice ss of pipe sizing choice (AUTO or fixed size), the pipe size used in the (AUTO or fixed size), the pipe size used in the spreadshspreadsheet will be displayed ieet will be displayed i
adjacent column, under Pipe Size. adjacent column, under Pipe Size.
Segment Auto-grouping
Segment Auto-grouping
All segments must be assigned to a segment group when using the auto-size feature. If
All segments must be assigned to a segment group when using the auto-size feature. If it is desired that all seit is desired that all se
containing the same flow rate be
containing the same flow rate be grouped together and optimized to a single size, click the Auto Group buttongrouped together and optimized to a single size, click the Auto Group button
Segment Grouping heading
Segment Grouping heading. This will automatically create a group number for e. This will automatically create a group number for e ach distinct flow rate within thach distinct flow rate within th
and assign the appropriate group number to each segment. Only segments that are selected for auto-sizing w and assign the appropriate group number to each segment. Only segments that are selected for auto-sizing w assigned a group number. These group assignments may be edited manually, but
assigned a group number. These group assignments may be edited manually, but all changes will be all changes will be overwrittoverwritt
Group is clicked again. Group is clicked again.
Total system flow
Total system flow
Enter the flow rate,
Enter the flow rate, in gallons per minute, for the ein gallons per minute, for the e ntire system. Note, this is not the flow ntire system. Note, this is not the flow for the current circuifor the current circui
modeled, but for all circuits in the
modeled, but for all circuits in the system.system.
The default value for this c
The default value for this c ell is the maximum flow rate ell is the maximum flow rate of all listed pipe segments. This can of all listed pipe segments. This can be overwritten bybe overwritten by
however the formula can only be
however the formula can only be restored by clicking Clear and Apply User Settings.restored by clicking Clear and Apply User Settings.
Insulation Thickness
Insulation Thickness
If the insulation thickness has been set using the Apply button on the
If the insulation thickness has been set using the Apply button on the Settings tab (see Pipe Insulation ThicknSettings tab (see Pipe Insulation Thickn
Settings T
Settings Tab: Piping above), the insulation thickness setting for ab: Piping above), the insulation thickness setting for all segments will match all segments will match the input on the the input on the SettinSettin
Title 24 has been
Title 24 has been selected, the spreadsheet will determine the cselected, the spreadsheet will determine the c ode-requirode-required insulation thickness based on ed insulation thickness based on ww
temperature and pipe size and this thickness will be displayed in the adjacent column, under Insulation Thickn temperature and pipe size and this thickness will be displayed in the adjacent column, under Insulation Thickn fixed thickness has been selected, it will be displayed in
fixed thickness has been selected, it will be displayed in the Insulation Thickness column.the Insulation Thickness column.
Optimize Pipe Size
Optimize Pipe Size
Once pipe segment setup is complete, pipe sizes
Once pipe segment setup is complete, pipe sizes may be optimized by clicking the Auto-select Optimized Pipemay be optimized by clicking the Auto-select Optimized Pipe
button at the top left corner. The tool will iterate through pipe size options for each segment selected for auto button at the top left corner. The tool will iterate through pipe size options for each segment selected for auto until the lowest possible combination of first cost and life-cycle cost is found. Auto-sized segments with the sa until the lowest possible combination of first cost and life-cycle cost is found. Auto-sized segments with the sa segment grouping number will be treated as a single pipe size and iterated to give the group of segments the segment grouping number will be treated as a single pipe size and iterated to give the group of segments the combined cost.
combined cost.
All lifecycle parameters may be adjusted on the Settings page. Lifecycle cost is
All lifecycle parameters may be adjusted on the Settings page. Lifecycle cost is calculated annuallcalculated annually for the sysy for the sys
lifetime specified and then discounted back to the present using the specified discount rate. Energy escalation lifetime specified and then discounted back to the present using the specified discount rate. Energy escalation inflation rates may be applied to the lifecycle cost. These rates are additive: a 1.0% energy escalation rate an inflation rates may be applied to the lifecycle cost. These rates are additive: a 1.0% energy escalation rate an inflation rate will result in an annual energy rate increase of 2.8%.
inflation rate will result in an annual energy rate increase of 2.8%. Occasionally, selecte
Occasionally, selected valves are not available in the d valves are not available in the optimized pipe size. In this case, an optimized pipe size. In this case, an error message will aerror message will a
the problem valves will be tagged in red. the problem valves will be tagged in red. The
The Auto-select OptimiAuto-select Optimized Pipe Size button will grey out after optimization is completed, showing that the butzed Pipe Size button will grey out after optimization is completed, showing that the but
disabled. When a change is made
disabled. When a change is made to any of the to any of the inputs, the button will become enabled again.inputs, the button will become enabled again.
Economic Assumptions
Economic Assumptions
Life-cycle cost for the pipe segment is calculated by taking the net present value of electricity expenditures ov Life-cycle cost for the pipe segment is calculated by taking the net present value of electricity expenditures ov specified lifetime of the piping system. An inflation rate and/or an energy escalation rate can be applied to the specified lifetime of the piping system. An inflation rate and/or an energy escalation rate can be applied to the energy expenditures and a discount rate is specified to discount the expenditures back to present value. energy expenditures and a discount rate is specified to discount the expenditures back to present value.
City cost index multipliers
City cost index multipliers
Most pricing data come from RS Means Mechanical Cost Data, 2008. The location adjustment factors for mater Most pricing data come from RS Means Mechanical Cost Data, 2008. The location adjustment factors for mater labor are provided for seven California cities. Average national factors are also provided. These adjustment fac labor are provided for seven California cities. Average national factors are also provided. These adjustment fac be edited on the Constants tab. New markets may be added either by entering the new market data in the las be edited on the Constants tab. New markets may be added either by entering the new market data in the las titled "NEW MARKET" or by overwriting one of the existing markets.
titled "NEW MARKET" or by overwriting one of the existing markets.
Electricity cost/ Gas cost
Electricity cost/ Gas cost
Enter local electricit
Enter local electricity and gas prices. y and gas prices. Gas price will be used only Gas price will be used only when the HW system type when the HW system type is selectedis selected
Apply an inflation rate
Apply an inflation rate
Inflation rate and energy escalation rate, if both are used, will be applied additively. For example, an inflation r Inflation rate and energy escalation rate, if both are used, will be applied additively. For example, an inflation r 1.8% and an energy escalation rate of 1.0% will result in an overall annual energy rate increase of 2.8%. If no i 1.8% and an energy escalation rate of 1.0% will result in an overall annual energy rate increase of 2.8%. If no i rate is desired, enter 0.
rate is desired, enter 0.
Apply an energy escalation rate
Apply an energy escalation rate
Inflation rate and energy escalation rate, if both are used will be applied additively. For example, an inflation r Inflation rate and energy escalation rate, if both are used will be applied additively. For example, an inflation r 1.8% and an energy escalation rate of 1.0% will result in an overall annual energy rate increase of 2.8%. If no 1.8% and an energy escalation rate of 1.0% will result in an overall annual energy rate increase of 2.8%. If no escalation rate is desired, enter 0.
escalation rate is desired, enter 0.
Discount rate
Discount rate
This rate is used to discount the annual electricity expenditures over the projected lifetime of the system back This rate is used to discount the annual electricity expenditures over the projected lifetime of the system back
present. If an inflation rate is applied (see above), then this should be
present. If an inflation rate is applied (see above), then this should be the nominal discount rate. If an inflationthe nominal discount rate. If an inflation
not applied, then this should be the real discount rate. not applied, then this should be the real discount rate.
Enter the projected lifetime of the system. Input must be less than or equal to 40 years.
Constants Tab
The Constants tab contains all physical and cost parameters for the piping components and system. Notes at t each column indicate data source. All fields may be edited.
Additional Information
If you have any questions or want to report a bug, please contact: Molly McGuire, Mechanical Engineer
Taylor Engineering 510-749-9135
DISCLAIMER
This pipe sizing applet was prepared for Pacific Gas and Electric Company by Taylor Enginee Architectural Energy Corporation and funded by California utility customers under the auspi the California Public Utilities Commission. Neither Pacific Gas and Electric Company nor an employees and agents:
1. Makes any written or oral warranty, expressed or implied, regarding this report, includi not limited to those concerning merchantability or fitness for a particular purpose.
2. Assumes any legal liability or responsibility for the accuracy, completeness, or usefuln any information, apparatus, product, process, method, or policy contained herein.
3. Represents that use of the report would not infringe any privately owned rights,includin not limited to, patents, trademarks or copyrights.
0 feet of timum nt or riable e pipe to r to find e system, but ual the e. If ost into
NON-gy e size Speed n will g to the d g Circuit s in the insulation button pipe size ded. If se nearly to pipe size eded. If sion y esearch piping g Circuit s in the ions to ply total that iping Circuit
each dited. button at e Settings be aste cells nts, finish AUTO. the gments below the e system ill be en if Auto being the user, ss under gs tab. If ter ess. If a
Size sizing me lowest tem and/or a 1.8% ppear and ton is er the annual ials and tors can row, ate of inflation te of energy to the rate is
he top of ing and es of of its g, but ss of , but
Project Name
My Project
System Name
CHW
System Parameters
System
type
CHW
Average
Water
temperature
50
°F
System
operation
VFVSFSP
Hours
per
year
of
operation
2000 hours
Pipe insulation thickness (in inches)
Title 24
(must click
Fluid speed limit for noise sensitivity?
ON
(must click
Fluid speed limit for erosion control?
ON
(must click
Default
safety
factor:
greater
of
5
%
"Apply" for change to take effect)
"Apply" for change to take effect)
"Apply" for change to take effect)
Economic Assumptions
City cost index multipliers
Market
Oakland,
CA
Materials
110.2
Labor
127.3
Contractor mark-up
HVAC
25%
General
3%
Current
year
2010
Means Mechanical Cost Data year
2008
Average annual first cost escalation
9.5%
Taxes
8%
Electricity
cost
0.15 $/kWh
Gas cost (used only for HW system type)
1.00 $/therm
Inflation
rate
0.0%
Energy
escalation
rate
1.0%
Discount
rate
5.0%
Inputs Outputs Total system flow 0 GPM CRITICAL
NumberofValves SegmentHeadVelocity BHP TotalPower FirstCost AnnlEnergyCosts Pipe Segment Description GPMInches Inches Inches Feet90º 45º
S t r ai gh t B r an
c h PsiFeet Feet psi Gal HP kW kWhtherms MaterialsTaxes Labor Total 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 AUTO6 ONNOONNOTitle 24 1 #DIV/0! #DIV/0! 0.0 - #DIV/0! #DIV/0!0.00 #DIV/0! 0.00 $- $- $- $- $- #DIV/0! #DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0! $- $- $
AUTO6 ONNOONNOTitle 24 1 #DIV/0! #DIV/0! 0.0 - #DIV/0! #DIV/0!0.00 #DIV/0! 0.00 $- $- $- $- $- #DIV/0! #DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0! $- $- $ Totals #DIV/0! #DIV/0! - #DIV/0! without Safety Factor #DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0!#DIV/0! #DIV/0!
+#DIV/0! Safety factor #DIV/0! with Safety Factor
OutputSummary: #DIV/0!
Total Head (Feet) #DIV/0! Total Head w S.F. (Feet) #DIV/0! Total Cost #DIV/0!
Lifecycle Energy Cost #DIV/0! First Cost #DIV/0! Scalar Ratio #DIV/0! Notes: Enter user notes here. Add or delete a row above current cursor position SegmentGroupingFlowrate
Select Pipe Size or "AUTO"PipeSize
Flow Speed Limit to Prevent Noise? Flow Speed Limit to Prevent Erosion? Desired Insulation Wall ThicknessInsulationThickness
Straight Pipe Lengthof ElbowsNumber
Tees with flow through: Control Valve ∆P Other: Chiller/ Boiler/ Coil/ HX/ etc. Water volume
in pipe Energy Cnsmpper Year LifecycleCost Lifecycle + First Cost Too
fast? Toofast?
C i r c ui t S e t t er S i l en t C h e c k S wi n g C h e c k B al l or B u t t er f l y W y e- S t r ai n er S u c t i on D i f f u s er owF l L i m i t i n g Feet/
sec therms /hr Contractor Markup O tim
Grey cells indicate components or elements that do not exist; values are set to
Pink cells indicate extrapolations for data points that were unavailable
Red
Red font indicates updated pricing values
Flow Parameters
K VALUES COPPER
SIZE
ELLS
TEES
90
45
Straight
Branch
1/2
0.47
0.25
0.29
1.1
3/4
0.45
0.24
0.28
1.05
1
0.43
0.22
0.26
1
1
1/4
0.41
0.22
0.25
0.95
1
1/2
0.4
0.21
0.23
0.9
2
0.38
0.2
0.2
0.84
2
1/2
0.35
0.19
0.18
0.79
3
0.34
0.18
0.17
0.76
4
0.31
0.18
0.15
0.7
K VALUES STEEL
SIZE
ELLS
TEES
90
45
Straight
BRANCH
1
0.43
0.22
0.26
1
1
1/4
0.41
0.22
0.25
0.95
1
1/2
0.4
0.21
0.23
0.9
2
0.38
0.2
0.2
0.84
2
1/2
0.35
0.19
0.18
0.79
3
0.34
0.18
0.17
0.76
4
0.31
0.18
0.15
0.7
5
0.3
0.17
0.13
0.66
6
0.29
0.17
0.12
0.62
8
0.27
0.17
0.1
0.58
10
0.25
0.16
0.09
0.53
12
0.24
0.16
0.09
0.5
14
0.23
0.15
0.08
0.5
16
0.23
0.15
0.08
0.47
T-cubed
18
0.22
0.14
0.07
0.44
6400020
0.22
0.14
0.07
0.42
12500024
0.21
0.13
0.06
0.41
34300026
0.21
0.13
0.06
0.4
72900030
0.2
0.12
0.05
0.39
1331000 2197000Property at
T=
c (Btu/lb
m-°F)
u (ft3/lb
m)
3375000 4913000 6859000 9528128
Piping Component Pricing
column for
1
2
3
4
5
6
7
Use copper piping for sizes less than or equal to:
2 1/2 inches
Copper pipe pricing (type L)
piping
90
ell
45
ell
Size
Mat ($/LF)
Inst ($/LF) Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
1/2
$2.26
$4.61
$0.92
$18.70
$1.67
$18.70
3/4
$3.51
$4.92
$2.04
$19.65
$2.93
$19.65
1
$5.10
$5.50
$5.00
$23.50
$7.35
$23.50
1 1/4
$7.05
$6.45
$7.60
$25.00
$10.45
$25.00
1 1/2
$9.05
$7.20
$11.80
$28.50
$12.60
$28.50
2
$14.05
$8.90
$21.50
$34.00
$21.00
$34.00
2 1/2
$21.50
$10.85
$45.50
$51.50
$45.00
$51.50
3
$29.50
$12.00
$60.50
$61.00
$66.50
$51.50
4
$50.00
$17.25
$156.00
$74.50
$142.00
$74.50
5
$107.00
$19.80
$650.00
$112.00
$550.00
$112.00
6
$149.00
$26.00
$865.00
$116.00
$865.00
$116.00
8
$208.00
$29.00 $3,200.00
$131.00
$2,950.00
$131.00
Steel pipe pricing
piping
90
ell
45
ell
Size
Mat ($/LF)
Inst ($/LF) Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
1/2
$2.18
$5.95
$27.00
$45.51
$37.50
$45.51
3/4
$2.58
$6.10
$27.00
$45.51
$37.50
$45.51
1
$3.70
$7.85
$13.10
$45.51
$13.45
$45.51
1 1/4
$4.93
$8.67
$13.10
$52.01
$13.45
$52.01
1 1/2
$5.65
$9.59
$13.10
$55.42
$13.45
$55.82
2
$7.40
$11.92
$14.10
$73.10
$13.45
$73.10
2 1/2
$9.80
$15.49
$16.95
$91.00
$15.70
$91.00
3
$12.50
$16.96
$21.00
$104.00
$16.95
$104.00
4
$16.50
$19.72
$34.00
$146.25
$30.00
$146.25
5
$24.00
$22.76
$71.00
$182.05
$46.00
$182.05
6
$30.00
$30.56
$74.00
$220.25
$60.00
$220.25
8
$47.00
$37.94
$140.00
$294.00
$100.00
$279.15
10
$60.00
$45.84
$282.00
$368.70
$200.00
$368.70
12
$75.00
$57.96
$420.00
$442.50
$282.00
$442.50
14
$85.00
$73.24
$430.00
$553.00
$380.00
$553.00
16
$114.00
$84.82
$790.00
$732.50
$670.00
$732.50
18
$120.00
$100.10 $1,050.00
$880.00
$955.00
$880.00
20
$146.00
$122.25 $1,500.00
$959.00
$990.00
$959.00
24
$186.00
$138.00 $2,000.00
$1,080.00
$1,500.00
$1,048.50
26
$345.00
$146.50 $2,500.00
$1,200.00
$1,650.00
$1,291.00
30
$375.00
$183.35 $3,000.00
$1,350.00
$1,825.00
$2,450.00
Insulation Pricing: Materials
Insul.
Thicknes
1/2
1
1
1/2
2
Pipe size
2
3
4
5
3/8
$0.73
$0.86
$1.58
$2.55
1/2
$0.73
$0.89
$1.67
$2.60
3/4
$0.83
$0.97
$1.68
$2.68
1
$0.86
$1.04
$1.80
$2.86
1 1/4
$0.91
$1.12
$1.96
$3.02
1 1/2
$1.05
$1.21
$2.05
$3.14
2
$1.12
$1.31
$2.26
$3.32
2 1/2
$1.17
$1.49
$2.42
$3.57
3
$1.32
$1.59
$2.54
$3.79
4
$1.55
$2.11
$2.88
$4.42
5
$1.77
$2.38
$3.23
$5.05
6
$2.00
$2.52
$3.41
$5.20
8
$2.45
$4.12
$4.78
$6.35
10
$2.90
$4.37
$5.15
$7.60
12
$3.35
$4.76
$5.85
$8.50
14
$3.81
$5.50
$6.70
$10.55
16
$4.26
$7.00
$8.75
$11.60
18
$4.71
$7.75
$9.85
$12.95
20
$5.16
$8.65
$10.05
$14.65
24
$6.06
$10.55
$12.30
$15.75
26
$6.51
$10.92
$12.80
$17.35
30
$7.42
$12.52
$14.58
$19.69
Noise/Erosion Sensitivity
Noise Sensitivity
Noise sensitivity eqn
Pipe OD
Pipe ID
Max fps
Max V for size: 3
1/2
0.55
2.54
Max V for size: 10
3/4
0.79
3.06
1
1.03
3.49
log(fps) =m* log(Pipe OD)
1
1/4
1.27
3.88
m
0.5
1
1/2
1.51
4.24
b
0.54
2
1.99
4.87
2
1/2
2.47
5.44
fps = 10^0.5379*10^(0.50
3
3.07
6.07
4
4.03
6.96
5
5.05
7.80
6
6.07
8.55
8
7.98
9.82
10
10.02
11.01
12
12.00
12.06
14
13.25
12.67
16
15.25
13.60
18
17.25
14.47
20
19.25
15.30
24
23.25
16.82
26
25.25
17.54
30
29.25
18.88
System and Location Defaults
Default Water Temperatures
CHW
50 °F
HW
160 °F
CW
80 °F
Variable Flow/Variable Speed Diversity Factor
CFCS
VFCS
VFVSFSP VFVSRSP
1
0.6
0.3
0.2
CFCS
Contstant Flow/ Constant Speed
VFCS
Variable Flow/ Constant Speed
VFVSFSP
Variable Flow/ Variable Speed with Fixed Set Point
VFVSRSP
Variable Flow/ Variable Speed with Reset Set Point
Market Lookup
Materials
Labor
Oakland, CA
110.2
127.3
Los Angeles, C
103.3
115.1
Fresno, CA
103.9
112.3
San Francisco,
112.4
137.5
San Jose, CA
107
130.4
Riverside, CA
102.1
112.5
Sacramento, C
106
113.6
Average Nation
100
100
ADD MARKET
Efficiencies
Pump
Current value, based on input system gpm
GPM
Pump
55%
Greater than
Efficiency
0.00
55%
60.00
58%
100.00
66%
Pump Efficiency eqn
500.00
70%
1000.00
72%
eff = m * ln(gpm) + b
1500.00
73%
m
5.870E-02
2000.00
75%
b
37%
2500.00
76%
3000.00
76%
3500.00
77%
4000.00
78%
4500.00
78%
5000.00
79%
5500.00
Motor (premium)
Current value, based on calculated HP
HP
Motor
#DIV/0!
Greater than
Efficiency
0.00
89.5%
5.00
91.0%
10.00
92.4%
15.00
92.4%
20.00
93.6%
30.00
94.1%
40.00
94.1%
60.00
95.0%
75.00
95.4%
100.00
95.4%
125.00
95.8%
150.00
95.8%
200.00
95.8%
Chiller
0.60 kW/ton
Boiler
75%
VS
Drive
97%
999999999
VALVES
SIZE
Cv
Circuit Setter
Silent Check
Ball
Butterfly
Wye-Strainer
1/2
1.7
6.86
4.8
5
999999999
#VALUE!
3/4
2.7
16.3
14.3
12
999999999
#VALUE!
1
5.8
30
24
22
999999999
#VALUE!
1
1/4
11
49
43
35
999999999
#VALUE!
1
1/2
20
72
60
52
999999999
#VALUE!
2
40
130
102
95
166
72
2
1/2
62
110
221
999999999
247
111
3
110
155
327
999999999
340
164
4
220
278
605
999999999
660
285
5
420
431
975
999999999
1080
410
6
650
625
1440
999999999
1613
597
8
875
1115
2670
999999999
3759
1000
10
1200
1770
4300
999999999
5300
1800
12
2250
2500
6350
999999999
7969
2800
14
999999999
3400
8600
999999999
11917
#VALUE!
16
999999999
4400
11400
999999999
16383
#VALUE!
18
999999999
5600
14700
999999999
21705
#VALUE!
20
999999999
6900
18100
999999999
27908
#VALUE!
24
999999999
10000
26800
999999999
43116
#VALUE!
26
999999999
15400
31000
999999999
60922
#VALUE!
30
999999999
22400
42000
999999999
86375
#VALUE!
1.01
1
1.01
0.02
0.02
0.02
T-squared
Temperature
Viscosity
1600 40 1.66E-05 2500 50 1.41E-05 4900 70 1.06E-05 8100 90 8.26E-06 12100 110 6.67E-06 16900 130 5.58E-06
Swing
Check
32
°F77
°F212
°F22500 150 4.76E-06
28900 170 4.13E-06
36100 190 3.62E-06
44944 212 3.19E-06
8
9
10
11
12
13
14
tee
Circuit
Setter
Silent
Check
Swing
Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
$1.56
$28.50
$40.00
$17.15
$93.77
$17.15
$23.50
$3.75
$31.00
$44.00
$18.85
$148.16
$18.85
$30.00
$11.60
$37.50
$54.00
$21.00
$260.00
$26.50
$42.00
$16.70
$41.50
$78.00
$25.00
$271.00
$31.00
$54.50
$25.50
$46.50
$91.00
$31.50
$325.00
$34.00
$72.00
$40.00
$53.50
$130.00
$37.50
$440.00
$41.50
$109.00
$95.00
$84.00
$370.00
$45.00
$495.00
$74.50
$258.00
$124.00
$96.00
$562.00
$170.00
$550.00
$84.00
$345.00
$299.00
$135.00
$867.00
$226.00
$810.00
$135.00
$1,100.00
$980.00
$168.00
$1,308.00
$205.18
$1,050.00
$174.00
$1,400.00
$1,325.00
$174.00
$1,763.00
$251.56
$1,375.00
$209.00
$1,700.00
$5,150.00
$209.00
$3,313.00
$344.31
$2,225.00
$232.00
$2,800.00
tee
Circuit
Setter
Silent
Check
Swing
Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
$68.00
$73.10
$40.00
$17.15
$93.77
$17.15
$280.14
$68.00
$73.10
$44.00
$18.85
$148.16
$18.85
$335.79
$34.50
$73.10
$54.00
$21.00
$340.00
$26.50
$510.00
$42.00
$80.75
$78.00
$25.00
$375.00
$31.00
$447.07
$42.00
$91.00
$91.00
$31.50
$410.00
$34.00
$502.71
$34.00
$121.35
$130.00
$37.50
$495.00
$41.50
$645.00
$46.50
$146.25
$370.00
$45.00
$595.00
$74.50
$745.00
$51.50
$182.05
$562.00
$170.00
$695.00
$84.00
$745.00
$72.50
$242.70
$867.00
$226.00
$945.00
$135.00
$1,100.00
$120.00
$291.50
$1,308.00
$205.18
$1,175.00
$174.00
$1,400.00
$124.00
$368.70
$1,763.00
$251.56
$1,525.00
$209.00
$1,700.00
$219.00
$442.50
$3,313.00
$344.31
$2,225.00
$232.00
$2,800.00
$435.00
$553.00
$4,650.00
$437.07
$3,125.00
$261.00
$4,150.00
$605.00
$690.00
$10,133.00
$529.83
$4,825.00
$350.00
$5,900.00
$985.00
$848.00
999999999
999999999
$7,300.00
$455.00
$8,525.00
$1,200.00
$1,106.00
999999999
999999999
$10,200.00
$600.00
$8,550.00
$1,875.00
$1,370.00
999999999
999999999
$10,700.00
$695.00
$10,400.00
$2,900.00
$1,475.00
999999999
999999999
$13,387.50
$820.00
$12,946.91
$3,750.00
$1,580.00
999999999
999999999
$17,492.50
$1,056.00
$19,700.00
$4,125.00
$2,002.00
999999999
999999999
$19,545.00
$1,174.00
$27,280.03
$4,550.00
$3,662.00
999999999
999999999
$23,650.00
$1,410.00
$41,213.61
Insulation Pricing: Installation
Insul.
Thickne
1/2
1
1
1/2
2
Pipe size
2
3
4
5
3/8
$2.49
$2.60
$2.70
$2.83
1/2
$2.48
$2.59
$2.70
$2.82
Temp is less t
3/4
$2.59
$2.70
$2.82
$2.96
0
1
$2.70
$2.82
$2.96
$3.10
40
1 1/4
$2.82
$2.96
$3.10
$3.27
60
1 1/2
$2.82
$2.96
$3.10
$3.27
105
2
$2.96
$3.10
$3.27
$3.45
140
2 1/2
$3.10
$3.27
$3.45
$3.65
200
3
$3.27
$3.45
$3.65
$3.88
250
4
$3.56
$4.14
$4.43
$4.78
350
5
$3.86
$4.43
$4.78
$5.15
6
$4.16
$5.15
$5.65
$6.20
8
$4.75
$6.20
$6.90
$7.75
10
$5.34
$6.90
$7.75
$8.85
12
$5.94
$7.75
$8.30
$9.55
14
$6.53
$7.75
$8.85
$10.35
16
$7.12
$8.85
$9.55
$11.30
18
$7.71
$8.85
$10.35
$12.40
20
$8.31
$10.35
$11.30
$13.80
24
$9.49
$10.35
$12.40
$15.50
26
$10.09
$10.09
$13.95
$17.04
30
$11.27
$11.27
$15.68
$19.27
Erosion Max Velocity
6 fps
Hours/yr opeMax v [fps]
11 fps
0
15
2000
14
+ b
3000
13
4000
12
6000
10
4*log(Pipe ID))
2 3 4 5 6 7 $-$500.00 $1,000.00 $1,500.00 $2,000.00 $2,500.00 $3,000.00 $3,500.00 -$1,000.00 $2,000.00 $3,000.00 $4,000.00 $5,000.00 $6,000.00 $7,000.00
0 2 4 6 8 0 5 10 15 $-$500.00 $1,000.00 $1,500.00 $2,000.00 $2,500.00 $3,000.00 $3,500.00 $4,000.00
PIPE INNER DIAMETERS
dP (feet)
O.D "
I.D. "
999999999
7.4
1/2
0.55
0.62
999999999
7.4
3/4
0.79
0.82
999999999
7.4
1
1.03
1.05
999999999
7.4
1
1/4
1.27
1.38
999999999
7.4
1
1/2
1.51
1.61
55
7.4
2
1.99
2.07
90
7.4
2
1/2
2.47
2.47
110
7.4
3
2.95
3.07
200
7.4
4
3.91
4.03
350
7.4
5
4.88
5.05
520
7.4
6
5.85
6.07
760
7.4
8
7.73
7.98
1000
7.4
10
9.63
10.02
999999999
7.4
12
11.57
12
999999999
7.4
14
13.25
999999999
7.4
16
15.25
999999999
7.4
18
17.25
999999999
7.4
20
19.25
999999999
7.4
24
23.25
999999999 999999999
26
25.25
999999999 999999999
30
29.25
Roughness
0 0Suction
Diffuser
Flow
Limiting
Valve
Type L
COPPER
SCH 40 or
STD WT
STEEL
15
16
17
18
19
20
21
22
heck
Ball
Butterfly
Wye-Strainer
Suction
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
$15.55
$10.30
$17.00 999999999
999999999
$19.20
$18.85 999999999
$18.70
$16.95
$18.70 999999999
999999999
$21.50
$19.85 999999999
$19.65
$21.50
$19.65 999999999
999999999
$23.00
$22.00 999999999
$25.00
$32.50
$25.00 999999999
999999999
$51.50
$25.00 999999999
$28.50
$42.50
$28.50 999999999
999999999
$365.00
$34.50 999999999
$34.00
$51.50
$34.00
$227.00
$26.50
$440.00
$47.00
$250.00
$45.00
$172.00
$41.50
$228.00
$74.50
$650.00
$136.00
$279.00
$51.50
$261.00
$46.50
$240.00
$84.00
$805.00
$151.00
$279.00
$224.00
999999999 999999999
$271.00
$135.00
$1,225.00
$226.00
$550.00
$287.00
999999999 999999999
$335.00
$209.00
$1,225.00
$310.00
$725.00
$350.00
999999999 999999999
$375.00
$209.00
$2,325.00
$350.00
$755.00
$420.00
999999999 999999999
$485.00
$232.00
$2,550.00
$405.00
$1,025.00
heck
Ball
Butterfly
Wye-Strainer
Suction
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
Mat ($/ea)
$17.15
$62.50
$38.46
999999999
999999999
$7.75
$18.85 999999999
$18.85
$83.00
$38.46
999999999
999999999
$9.45
$21.00 999999999
$37.50
$103.00
$48.74 999999999
999999999
$12.90
$23.50 999999999
$25.00
$138.00
$55.82
999999999
999999999
$17.20
$25.00 999999999
$31.50
$180.00
$66.10
999999999
999999999
$101.00
$34.50 999999999
$46.50
$255.00
$85.60
$227.00
$26.50
$106.00
$47.00
$250.00
$135.00 999999999 999999999
$228.00
$74.50
$128.00
$136.00
$279.00
$149.00 999999999 999999999
$240.00
$84.00
$142.00
$151.00
$279.00
$224.00 999999999 999999999
$271.00
$135.00
$181.00
$226.00
$550.00
$287.00
999999999 999999999
$335.00
$209.00
$283.00
$310.00
$725.00
$350.00 999999999 999999999
$375.00
$209.00
$283.00
$350.00
$755.00
$420.00 999999999 999999999
$485.00
$232.00
$580.00
$420.00
$1,025.00
$475.00 999999999 999999999
$620.00
$261.00
$1,100.00
$530.00
$2,475.00
$615.00 999999999 999999999
$925.00
$350.00
$1,675.00
$620.00 $3,475.00
$805.00
999999999 999999999
$1,225.00
$455.00
$3,075.00
$810.00 $5,075.00
$1,050.00
999999999 999999999
$1,600.00
$600.00
$4,350.00
$1,050.00 999999999
$805.00 999999999 999999999
$2,075.00
$695.00
$5,564.89
$1,073.37
999999999
$1,102.50 999999999 999999999
$2,550.00
$1,050.00
$7,139.48
$1,197.08
999999999
$1,400.00 999999999 999999999
$3,575.00
$1,400.00 $10,877.33
$1,444.48
999999999
$1,375.30 999999999 999999999
$4,256.58
$1,634.54 $13,040.59 $1,568.18 999999999
$1,589.62 999999999 999999999
$5,705.58
$2,186.43 $17,955.78 $1,815.58 999999999
Insulation
thickness
per
T24
Motor
and
VF
Pipe diameter is less than: (in inches)
HP
Greater than
0
1
2
4
6
8
0.00
2
3
4
5
6
7
1/12
1
1
1
1/2
1
1/2
1
1/2
1
1/2
1/8
1/2
1/2
1/2
1
1
1
1/6
0
0
0
0
0
0
1/4
1
1
1
1
1
1/2
1
1/2
1/3
1
1/2
1
1/2
1
1/2
1
1/2
1
1/2
1
1/2
1/2
1
1/2
1
1/2
1
1/2
2
2
3
1/2
3/4
2
2
2
1/2
2
1/2
3
1/2
3
1/2
1.00
2
1/2
2
1/2
2
1/2
3
3
1/2
3
1/2
1.50
2.00
3.00
5.00
7.50
15.00
20.00
25.00
40.00
50.00
75.00
100.00
150.00
200.00
$500.00 $1,000.00 $1,500.00 $2,000.00 $2,500.00 $3,000.00 $3,500.00 $4,000.00 $4,500.00 $5,000.00 Column U $ $ $ $ $1 $18 9 10 11 Column M Column O 0 5 10 15 20 25 30 $-$200.00 $400.00 $600.00 $800.00 $1,000.00 $1,200.00 $1,400.00 $1,600.00 Column T 0 2 4 6 8 10 12 14 16 18 -0 5 10 15 20 25 30 $-$500.00 $1,000.00 $1,500.00 $2,000.00 $2,500.00 $3,000.00 $3,500.00 $4,000.00 Column S
10 12 14
20 25 30
Column S Column S
Threshold for fully turbulent rough flow
Re3
Re2
2.70E+01
9.00E+00
3.00E+00
20
8.57E-01
9.03E-01
9.50E-01
66.67
4.75E+05
6.08E+03
7.80E+01
500
8.52E+07
1.94E+05
4.40E+02
2500
9.26E+09
4.41E+06
2.10E+03
10000
9.73E+10
2.12E+07
4.60E+03
2.00E+04
inches
Reynolds
Number*
10-4
Relative
Roughness,
D/E
23
24
25
iffuser
Flow Limiting Valve
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
999999999
$120.98
$17.15
999999999
$131.12
$18.85
999999999
$142.72
$21.00
999999999
$263.70
$25.00
999999999
$263.70
$31.50
$63.00
$394.10
$37.50
$104.00
$587.54
$45.00
$104.00
$587.54
$170.00
$194.00
$1,514.78
$226.00
$278.00
$1,514.78
$205.18
$320.00
$1,514.78
$251.56
$390.00
$2,338.04
$344.31
iffuser
Flow Limiting Valve
Inst ($/ea)
Mat ($/ea)
Inst ($/ea)
999999999
$120.98
$17.15
999999999
$131.12
$18.85
999999999
$142.72
$21.00
999999999
$263.70
$25.00
999999999
$263.70
$31.50
$63.00
$394.10
$37.50
$104.00
$587.54
$45.00
$104.00
$587.54
$170.00
$194.00
$1,514.78
$226.00
$278.00
$1,514.78
$205.18
$320.00
$1,514.78
$251.56
$390.00
$2,338.04
$344.31
$440.00
$2,654.16
$437.07
$585.00
$3,401.69
$529.83
$705.00
$4,445.58
$626.98
999999999
$6,191.38
$719.65
999999999
$8,922.05
$812.33
999999999
$11,209.68
$905.00
999999999
$13,497.32
$1,090.35
999999999
999999999
999999999
999999999
999999999
999999999
D drive cost
Motor and VF
Pump
VFD
HP
Materials
Installation
Total
Materials
Installation
Total
$272
$112
$384
$829
$355
$1,184
$455
$112
$567
$829
$355
$1,184
1/12
$555
$135
$690
$829
$355
$1,184
1/8
$705
$135
$840
$829
$355
$1,184
1/6
$980
$168
$1,148
$829
$355
$1,184
1/4
$1,025
$168
$1,193
$829
$355
$1,184
1/3
$1,175
$168
$1,343
$829
$355
$1,184
1/2
$1,700
$168
$1,868
$868
$355
$1,223
3/4
$1,550
$224
$1,774
$1,466
$355
$1,821
1.00
$1,825
$224
$2,049
$1,466
$355
$1,821
1.50
$1,900
$292
$2,192
$1,525
$455
$1,980
2.00
$2,350
$375
$2,725
$1,675
$455
$2,130
3.00
$2,925
$395
$3,320
$1,975
$545
$2,520
5.00
$5,800
$515
$6,315
$1,975
$545
$2,520
7.50
$7,025
$655
$7,680
$3,375
$820
$4,195
15.00
$7,250
$680
$7,930
$3,925
$1,100
$5,025
20.00
$9,475
$870
$10,345
$4,775
$1,100
$5,875
25.00
$11,900
$1,000
$12,900
$7,650
$1,375
$9,025
40.00
$16,200
$1,250
$17,450
$8,375
$1,600
$9,975
50.00
$18,000
$1,475
$19,475
$11,700
$1,800
$13,500
75.00
$22,300
$1,650
$23,950
$12,900
$1,800
$14,700
100.00
$33,100
$2,150
$35,250
$20,500
$2,125
$22,625
150.00
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
200.00
11 1/2 12 12 1/2 13 13 1/2 14 14 1/2 15 15 1/2 16 16 1/2 $-2,000.00 4,000.00 6,000.00 8,000.00 0,000.00 2,000.00 f(x) = 1343.75x - 11370.83