• No results found

All PMP

N/A
N/A
Protected

Academic year: 2021

Share "All PMP"

Copied!
204
0
0

Loading.... (view fulltext now)

Full text

(1)

PROJECT MANAGEMENT FRAMEWORK

Project Management

(2)

Agenda

 Definition of a Project 

 What is Project Management 

 What is Program Management 

 What is Portfolio Management 

 Project Management Office (PMO) 

 The Triple Constraints 

 Stakeholder Management 

 Organization Structure 

 Project Life Cycle vs. Product Life Cycle 

 Quiz 

(3)

What is Project?

 A project is a temporary endeavor undertaken to create a unique product, service or result.

 Temporary means that a project has a definite start and end date.  Temporary does not necessarily mean short in duration.

 A project comes to an end when either its objectives are met or its objectives can not be met because of various reasons.

 Project work is different from operational work. Operations is doing ongoing repetitive work. For example, the work of an office receptionist can be classified as operational.

(4)

Project versus Operation

Project work is different from operational work. Operations is doing ongoing repetitive work. For example, the work of an office receptionist can be classified as operational. Both projects and operations are  carried out by people, both  require planning, both require  management, and both are  constrained by a fixed amount of  budget, resources, and  timelines. Projects require  project management, while  operations require business  process management or  operations management.  Projects and Operations will 

(5)

Project versus Operation

PROJECT

• Temporary • Output: Unique • Purpose: Attain its objective  and then terminate • Concludes when its specific  objectives have been attained

OPERATION

• Ongoing • Output: Repetitive • Purpose: Sustain the business • Adopt a new set of objectives  and the work continues

(6)

Typical Sequence of Phases in a  Project Life Cycle

INITIAL INTERMEDIATE FINAL

Charter Scope Statement Plan Baseline Progress Acceptance Approval Handover Product Idea Project Management Team Inputs Phases Project  Management  Outputs Project  Deliverable

(7)

Portfolio – Program – Project

Portfolios

Program  Strategies and priorities Progressive elaboration Program  Governance

 Disposition on request changes

 Impact from changes in others portfolios, programs or project Project Project Project Project  Performance reports  Change requests with

impact on other portfolios, programs, or projects

 Performance reports  Change requests with

impact on other portfolios, programs, or projects

(8)

What is Project Management?

 Project management is the application of knowledge, 

skills, tools, and techniques to project activities to meet 

the project requirements. 

 Project management is accomplished through the 

appropriate application and integration of the 47 project 

management processes logically grouped into the 5 

process groups. 

(9)

What is Program Management?

 A program is a group of related projects managed in a 

coordinated way to obtain benefits and control not 

available from managing them individually. 

 For a group of projects to be classified as a program, 

there must be some value add in managing them 

together as a program. If there is no value add, they 

should not be classified as a program. 

 A project may or may not be part of a program, but a 

program will always have projects. 

 Program management focuses on the project 

interdependencies and helps to determine the optimal 

approach for managing them. 

(10)

Project Management Office

 The PMO is an organization structure. It’s not a person such as a  project manager.   The PMO usually has one of the three roles mentioned below:   Providing the policies , methodologies and tools & templates for managing  projects within the organization.   Providing support and training to others in the organization on how to  manage projects.   Providing project managers for different ongoing projects in the  organization.   Some of the functions of a PMO may include:   Managing interdependencies between projects   Selecting, managing, and deploying shared or dedicated project resources   Terminating projects   Coordinating communication across projects 

(11)
(12)
(13)

Project Constraint – NOW!

 The idea is that you need to balance scope (the features that 

will go into the software, and the work needed to build 

them), time (how long it takes to build the software), and 

cost (in money or hours) in order to get your project to the 

level quality that you need. Any time your project changes, 

you'll need to know how that change affects all three 

constraints.

 The funny thing about the triple constraint is that a lot of 

project managers don't actually learn about it any more. 

Instead, it's been replaced with a wider set of project 

constraints, including (but not limited to) time, cost, scope, 

resources, quality, and risk. Jenny came up with this really 

cute graphic for it when we were working on the

(14)

Stakeholder Management

 Stakeholders are people or organizations who are 

actively involved in the project or whose interests may 

be positively or negatively affected by the performance 

or completion of the project. 

 Examples of stakeholders include project managers, 

customers, sponsors, the PMO, functional managers, 

the project team, and operations management. 

 Stakeholder management requires: 

– Identifying both internal and external stakeholders  – Determining stakeholder requirements  – Determining stakeholder expectations 

(15)

Organizational Structure

There are three types of organizational structures based on the  authority of the project manager. They include:  – Functional: The organization is grouped by areas of specialization  within different functional areas (e.g. accounting, marketing, and  engineering). Each employee typically reports to a functional  manager.  – Projectized: The organization is often grouped by organizational  units called departments. These groups either report directly to the  project manager or provide support services to the various projects.  – Matrix: This is organization is a blend of both the above types. The  three matrix forms are strong matrix, weak matrix, and balanced  matrix.  – In a strong matrix, power rests with the project manager. In a weak  matrix, power rests with the functional manager. In a balanced  matrix, the power is shared between the functional manager and  the project manager. 

(16)

Project Life Cycle vs Product Life Cycle

 A typical product lifecycle starts with the conception of the  product and goes until its withdrawal from the market or when it  becomes obsolete.   A product can require or spawn many projects over its life. For  example, a project during the product conception phase could be  “Determine customer’s need” and a project during the product  maturity phase could be ”Do competitor analysis”.   A project has its own lifecycle. The lifecycle depends upon the  control needs of the performing organization or the organization’s  preference defined in their project execution methodology.  For example, typically in the IT industry, the project lifecycle can  be “Requirement Analysis ‐ High Level Design ‐ Detailed Design ‐ Coding ‐ Testing ‐ Installation ‐ Hand over to Operation”. 

(17)
(18)

PROJECT MANAGEMENT PROCESSES

Project Management

(19)

Agenda

 Project Life Cycle vs Project Management Process.  The Five Project Management Process Groups.

 Process Groups, Knowledge Areas and Project Management  process Mapping 

(20)

Project Life Cycle Vs Project Management Process 

 Project life cycle – “What to do to get the work done” 

 Project management process – “What to do to manage 

the project” 

 Project management processes are grouped in 5 

categories: 

– Initiating Process Group  – Planning Process Group  – Executing Process Group  – Monitoring & Control Process Group  – Closing Process Group 

(21)

Project Management Process Groups 

Initiating  Processes Closing Processes Planning  Processes Executing Processes Enter Phase Close Phase Monitoring and Controlling Processes

(22)

5 Process Groups

Project Management Process Groups 

Initiating Planning Executing Controlling Closing

9 Knowledge Areas

47 Project Management Processes

(23)

Process Iteration Groups

Planning  Processes Group Initiating Processes Group Level of  Process Interaction T i m e Start Finish Executing Processes Group Monitoring Processes Group Closing Processes Group

(24)
(25)

Initiating Process Group

The Initiating process group, as its name  implies, occurs at the beginning of the  project and at the beginning of each  project phase for large projects.  Initiating acknowledges that a project, or  the next project phase, should begin.  This process group grants the approval  to commit the organization’s resources  to working on the project or phase and  authorizes the project manager to begin  working on the project. The outputs of  the Initiating process group, including  the project charter and identification of  the stakeholders, become inputs into the  Planning process group.

(26)
(27)

Planning Process Group

The Planning process is the process 

group of formulating and revising project  goals and objectives and creating the  project management plan that will be  used to achieve the goals the project  was undertaken to address. The Planning  process group also involves determining  alternative courses of action and  selecting from among the best of those  to produce the project’s goals. This  process group is where the project  requirements are fleshed out and  stakeholders are identified.

(28)

Planning Process Group

Activity during planning process  Refine requirements to make it more specific   Define Project deliverables and work required to complete them   Get Stakeholder approval on scope   Select Project Team   Break down work into smaller manageable pieces (WBS)   Develop the project schedule   Determine project quality standards   Determine Project Team’s Roles & Responsibilities   Complete risk identification, analysis and risk response planning   Determine what needs to be purchased   Determine how to execute and control the project 

(29)

Executing Process Group

The Executing process group involves  putting the project management plan  into action. This process group involves  coordinating people and resources,  managing stakeholder expectations, as  well as integrating and performing the  activities of the project in accordance  with the project management plan.  The Executing process group will utilize  the most project time and resources,  and as a result, costs are usually highest during the Executing processes.

(30)

Activities during Executing

 Manage Stakeholder’s satisfaction

 Complete work packages

 Implement Quality Assurance

 Produce project reports

 Remove project bottlenecks

 Organize team building activities

 Organize training for team members

 Conduct project progress meeting

 Implement approved change, corrective action ,

preventive action and defect repair

(31)

Monitoring & Controlling Process Group

The Monitoring and Controlling process  group is where project performance  measurements are taken and analyzed  to determine whether the project is  staying true to the project plan. The Monitoring and Controlling Process  Group consists of those processes  required to track, review, and  orchestrate the progress and  performance of the project; identify any  areas in which changes to the plan are  required; and initiate the corresponding  changes.

(32)

Activities during Controlling

 Measure against the performances baseline

 Determine variance and take appropriate action

 Recommended changes, preventive and corrective 

action

 Facilitate conflict resolution

 Identify root causes of problems

 Obtain formal acceptance for deliverables

 Administer contract with seller

 Control changes

 Conduct status review meeting

(33)

Closing Process Group

The Closing process group is probably  the most often skipped process group in  project management. Closing brings a  formal, orderly end to the activities of a  project phase or to the project itself. The Closing Process Group consists of  those processes performed to conclude  all activities across all Project  Management Process Groups to formally  complete the project, phase, or  contractual obligations.

(34)

Activities during Closing

 Confirm all Project requirements are met 

 Obtain formal signoff from customer 

 Make Payment to all parties and update cost records 

 Complete Contract closure 

 Update lesson learnt database 

 Measure Customer Satisfaction 

 Handover Project deliverables to Operations team 

 etc

(35)

Closing Process Group

 Confirm all project requirement are met 

 Obtain formal signoff from customer

 Make payment to all parties and update cost records

 Complete agreement closure

 Update lesson learnt database

 Measure customer satisfaction

 Handover project deliverables to user/operation team

 Etc

(36)

Recapitulation 

Initiating Process Executing Process Initiating Process Approved corrective  & preventive action  or change request   requires re‐planning Integrated Change  Control results in  hanged Project  Management Plan  Business  Need Monitoring &  control process Closing Process

(37)

PROJECT MANAGEMENT

(38)

What is Project Integration Management

 Project integration management involves unification, 

consolidation, articulation and integrative actions that 

are crucial for successfully completing the project. 

 Project integration management is high level work that 

involves the project manager managing 

interdependencies among the other knowledge areas. 

(39)

Key Role of the PM, Team and Sponsor

 The key role of the project manager is to perform 

integration. 

 The key role of the project team is to concentrate on 

completing the project activities. 

 The key role of the project sponsor is to protect the 

project team from unnecessary changes and loss of 

resources. 

(40)

Origins of Projects

Why a new project ? 

A project may originate as a result of one or more of the 

following categories of reasons:

Business/legal requirementsMarket OpportunitiesProblems/IssuesEcological impactSocial needs

(41)

Project Selection Method

 Benefit Measurement Methods

– Scoring Models  – Economic Models  – Benefit contribution

 Constrained Optimization Methods

– Linear – Nonlinear – Dynamic – Integer – Multiple objective programming

 Expert Judgment

(42)
(43)

Project Integration Management Processes 

Project Integration Management Process  Time Develop Project Charter  Initiating Process Develop Management Plan Planning Process Direct and Manage Project Execution Execution Process  Monitor and Control Project work Monitoring and Control Process

Perform Integrated Change Control Monitoring and Control Process

(44)

Develop Project Charter

Develop Project Charter is the process of developing a document  that formally authorizes the existence of a project and provides the  project manager with the authority to apply organizational resources  to project activities. Input  Project statement of  work  Business case  Agreement  Enterprise  environmental factor  Organizational process  assets

Tools and Techniques

 Expert judgment

 Facilitation techniques

Output

(45)

Develop Project Management Plan

Develop Project Management Plan is the process of defining,  preparing and coordinating all subsidiary plans and integrating them  into a comprehensive project management plan.  Input  Project charter  Output from others  process  Enterprise  environmental factor  Organizational process  assets

Tools and Techniques

 Expert judgment

 Facilitation techniques

Output

 Project management  plan

(46)

Direct and Manage Project Work

Direct and Manage Project Work is the process of leading and  performing the work defined in the project management plan and  implementing approved changes to achieve the project’s objectives Input  Project management  plan   Approved change  requests  Enterprise  environmental factor  Organizational process  assets

Tools and Techniques

 Expert judgment  Project management  information system  Meetings Output  Deliverables  Work performance data  Change requests  Project management  plan updates  Project document  updates

(47)

Monitor and control Project Work

Direct and Manage Project Work is the process of leading and  performing the work defined in the project management plan and  implementing approved changes to achieve the project’s objectives Input  Project management  plan   Schedule forecast   Cost forecast  Validated changes  Work performance  information   Enterprise  environmental factor  Organizational process  assets

Tools and Techniques

 Expert judgment  Analytical techniques  Project management  information system  Meetings Output  Change request  Work performance  reports  Project management  plan updates  Project document  updates

(48)

Perform Integrated Change Control

Perform Integrated Change Control is the process of reviewing all  change requests; approving changes and managing changes to  deliverables, organizational process assets, project documents, and  the project management plan; and communicating their disposition.  Input  Project management  plan   Change request  Work performance  report   Enterprise  environmental factor  Organizational process  assets

Tools and Techniques

 Expert judgment  Meetings  Change control tools Output  Approved change  requests  Change log  Project management  plan updates  Project document  updates

(49)

Close Project or Phase

Close Project or Phase is the process of finalizing all activities across  all of the Project Management Process Groups to formally complete  the project or phase. Input  Project management  plan   Accepted deliverables  Organizational process  assets

Tools and Techniques

 Expert judgment  Analytical techniques  Meeting Output  Final product, service,  or result transition   Organizational process  assets updates

(50)

What is Project Charter

 Formally authorizes the existence of the project 

 Provides authority to the project manager to spend 

money and other corporate resources 

 Defines the high level project requirements 

 It is issued by the project sponsor 

 It is broad enough not to require any changes during 

project execution 

(51)

Develop Project Management Plan

 Developing the project management plan is the process of documenting the actions necessary to define, prepare, integrate and coordinate all the subsidiary plans. It also contains all of the performance measurement baselines.

 Examples of subsidiary plans include the Cost Management Plan, Time Management Plan, Human Resource Management Plan, Quality Management Plan, and Risk Management Plan.

 The Project management plan defines how the project is to be executed, monitored & controlled, and closed.

Inputs to Develop Project Management Plan

 Project charter 

 Output from planning process group   Enterprise environmental factors 

(52)

Terms

Work Authorization System   A system for authorizing work or notifying team members (or  contractors) that they may begin work on a project work package or  activity  Corrective Action   Any action taken to bring actual or expected future project performance  in line with the relevant baseline in the project management plan.  Preventive Action   While corrective action involves implementing actions to deal with  actual or future deviations from the performance baselines, preventive  actions focus on reducing the probability of negative consequences  associated with project risks.  Change Control System   A system for formally collecting documented procedures, paperwork,  and authorized changes 

(53)

Direct and Manage Project Execution

Direct and manage project execution is the process of performing  the work defined in the project management plan to achieve the  project objectives  Project Management  Plan Direct and Manage  Project Execution Approved Corrective or  Preventive Actions or  Changes New Changes Project Deliverables Work Performance  Information Implement Corrective  and  Preventive actions and  approved changes

(54)

Monitor and Control Project Work

 Monitor & control project work is the process of tracking,  reviewing and regulating the progress to meet the performance  objective(s) defined in the project management plan.   The results of monitoring & control are recommended changes to  the project as well as recommended corrective actions,  preventive actions, and defect repair actions.  Inputs to Monitor and Control Project work  Project management plan  Work Performance information  Enterprise environmental factors 

(55)

Perform Integrated Change Control

 Perform integrated change control process is the process of reviewing all  change requests, approving & managing changes to the project 

deliverables, organizational process assets, project documents and the  project management plan. 

 Process of making changes

– Evaluate impact – Create option – Get internal buy‐in – Get customer buy‐in

 Change Control Board

Inputs to Develop Project Management Plan  Project management plan  Work performance information  Change request  Enterprise environmental factors   Organization process assets 

(56)

Corrective Action and Integrated Change Control

Measure Look for  alternatives and  make  recommendation  Corrective Action  Process Is there any  variance? Corrective Action  Process Is corrective  action  required? Submit  recommended  action to change  control board to  approve or reject  the change If approved,  update project  management  plan Manage project as  per the new plan If rejected look  for alternative  or accept the  Impact Submit  recommended  action to change  control board to 

(57)

Close project or phase

 Close project or phase is the process of finalizing all activities  across all the project management process groups to formally  complete the project or phase.   A project must be formally closed.   The project should always be closed no matter if it was  completed, stopped, or terminated.  Inputs to Close Project or Phase  Project management plan  Accepted deliverables  Organization process assets 

(58)

PROJECT MANAGEMENT

(59)

Agenda

 What is Project Scope Management.  Product scope vs project scope.  The key terms in Project Management Scope.  The Project Scope Management Knowledge Area.  Collect requirement  Define scope  Create WBS  Verify scope  Control scope

 Quiz

(60)

What is Project Scope Management

 Project scope management includes the processes 

required to ensure the project includes the all the work 

required and only the works required to complete the 

project successfully.

 Managing the project scope is primarily concern with 

defining and controlling what should be included in the 

Project.

(61)

What is Project Scope Management (cont’d)

 The key activities that happen as a part of project scope 

management .

– Constantly checking to make sure that all the work is being  completed  – Not letting people randomly add to the project scope  – Preventing gold plating ‐ doing more than is required on the  project 

(62)

Product Scope vs Project Scope

 Product Scope: The features and functions that 

characterize a product, service, or result. 

 Project Scope: The work that needs to be accomplished 

to deliver a product, service, or result with the specified 

features and functions.

 Project scope management deals with managing both 

the product scope, as well as the project scope. 

(63)

The Key Terms in Project Scope Management

WBS: Work Breakdown Structure 

 The WBS breaks the project scope into smaller and more 

manageable pieces called work packages. 

 Each level of the WBS is a smaller piece of the level above. 

 Work not in the WBS is not considered part of the project. 

WBS Dictionary: 

 Since work can not be defined in detail in the WBS, a WBS 

dictionary is created to define the WBS work packages. 

 It contains a description of the WBS, the person responsible, 

the schedule, etc. 

(64)

Project Scope Management Processes 

Project Scope Management Process  Time Plan Scope Management Planning Process Collect Requirement Planning Process Define Scope Planning Process Create WBS Planning Process Verify Scope Monitoring and Control Process Control Scope Monitoring and Control Process

(65)

Plan Scope Management

Plan Scope Management is the process of creating a scope  management plan that documents how the project scope will be  defined, validated, and controlled. Input  Project management  plan  Project charter  Enterprise  environmental factor  Organizational process  assets

Tools and Techniques

 Expert judgment  Meeting Output  Scope management  plan  Requirement  management plan

(66)

Collect Requirement

Collect requirements is the process of defining and documenting  stakeholders’ needs to meet the project objectives Input  Scope management  plan  Requirement  management plan   Stakeholder  management plan   Project charter  Stakeholder register

Tools and Techniques

 Interview  Focus groups  Facilitated workshops   Group creativity  techniques   Group decision making  techniques  Questionnaire & surveys  Observations  Prototyping  Benchmarking  Context diagram Output  Requirements  documentation  Requirements  traceability matrix 

(67)

Define Scope

Define scope is the process of developing a detailed description of  the project and product Input  Scope management  plan  Project charter  Requirements  documentation  Organizational process  asset

Tools and Techniques

 Expert judgment   Product analysis   Alternatives  identification  Facilitated workshops  Output  Project scope statement  Project document  updates

(68)

Create WBS

Create WBS is the process of subdividing project deliverables and  project work into smaller, more manageable components. Input  Scope management  plan  Project scope statement  Requirements  documentation  Enterprise  environmental factor  Organizational process  assets

Tools and Techniques

 Decomposition  Expert judgment Output  Scope baseline  Project document  updates

(69)

Validate Scope

Validate scope is the process of formalizing acceptance of the  completed project deliverables. Input  Project management  plan  Requirements  documentation  Requirement  traceability matrix  Validated deliverables  Work performance data

Tools and Techniques

 Inspection  Group decision making  techniques Output  Accepted deliverables  Change request  Work performance  information  Project document  updates

(70)

Control Scope

Control scope is the process of monitoring the status of the project  and product and managing changes to the scope baseline. Input  Project management  plan  Requirements  documentation  Requirement  traceability matrix  Work performance data  Organizational process  assets

Tools and Techniques

 Variance analysis Output  Work performance  information  Change request  Project management  plan updates  Project document  updates  Organizational process  assets updates

(71)
(72)

PROJECT MANAGEMENT

(73)

Agenda

 What is Project Time Management.  What is a Project Schedule.  The key terms in Project Time Management.  The Project Time Management Processes.  Define Activities  Sequence Activities  Estimate Activity Resources  Estimate Activity Duration  Develop Schedule  Control Schedule

(74)

What is Project Time Management

 Project scope management includes the processes 

required to manage timely completion of the project.

 Project time management is primarily concerned with 

developing realistic project schedule change to the 

schedule.

 Schedule management plan: this plan define how 

schedule contingencies will be reported and assessed. 

(75)

The Key Activities

 Identifying the list of project activities 

 Estimating the time and resources required to complete 

each of the identified activities 

 Sequencing the activities to occur one after the other in 

a logical manner. 

(76)

What is the project schedule?

 A schedule wherein activities are assigned a duration 

and sequenced in a logical order. 

 The project schedule defines the start and end dates of 

the project and the project activities. 

 Scheduling software is usually used to develop the 

project schedule. 

 Microsoft Project is the most popular tool used for 

project schedule development. 

 Many people confuse a project schedule with the 

project management plan. The project management 

plan is comprehensive and includes the project 

(77)
(78)

Estimation 

One time Estimate: When estimating use only one time estimate per activity. For  example, the person doing the estimating says that the activity would take 2  weeks. In real life, people make their best guess and just double the estimate to  take care of any uncertainties. Adding this extra time is called “padding”. This  techniques should only be used for high level estimates. Analogous Estimating: This estimating is based on previous projects (or activities).  The last 5 similar projects took 6 months, so this one should also take 6 months. Parametric Estimating: This uses a mathematical model to calculate projected  times for an activity based on historical records from previous projects and other  information.

(79)

Project Time Management Processes 

Project Time Management Process  Time Plan Schedule Management Planning Process Define Activities Planning Process Sequence Activity Planning Process Estimate Activity Resource Planning Process Estimate Activity Duration Planning Process Develop Schedule Planning Process Control Schedule Monitoring and Control Process

(80)

Plan Schedule Management

Plan Schedule Management is the process of establishing the  policies, procedures, and documentation for planning, developing,  managing, executing, and controlling the project schedule. Input  Project management  plan  Project charter  Enterprise  environmental factor  Organizational process  assets 

Tools and Techniques

 Expert Judgment  Analytical techniques  Meeting Output  Schedule management  plan

(81)

Define Activities

Define activities is the process of identifying the specific actions to  be performed to produce the project deliverables.  Input  Schedule management  plan  Scope baseline  Enterprise  environmental factor  Organizational process  assets 

Tools and Techniques

 Decomposition  Expert judgment  Rolling wave planning Output  Activity list  Activity attribute  Milestone list

(82)

Sequence Activity

Sequence activities is the process of identifying and documenting  relationships (dependencies) among the project activities.  Input  Schedule management  plan   Activity list   Activity attributes  Milestone List   Project scope statement   Enterprise  environmental factor  Organizational process  assets 

Tools and Techniques

 Precedence  Diagramming Method  (PDM)   Dependency  determination   Leads and lags Output  Project schedule  network diagram  Project document  updates

(83)

Estimate Activity Resource 

Estimate activity resources is the process of estimating the type and  quantities of material, people, equipment or supplies required to  perform each activity. Input  Schedule management  plan   Activity list   Activity attributes  Resource calendars  Risk Register  Activity cost estimates  Enterprise environment  factor  Organizational process  assets 

Tools and Techniques

 Expert judgment  Alternative analysis  Published estimating  data  Bottom‐up estimation  Project management  software  Output  Activity resources  requirements  Resources breakdown  structure  Project document  update

(84)

Estimate Activity Duration

Estimate activity durations is the process of approximating the  number of work periods needed to complete individual activities  with estimated resources.  Input  Schedule management plan   Activity list   Activity attributes  Activity resources  requirement  Resources calendars  Risk register  Resource breakdown  Structure  Project scope statement   Enterprise environment  factors

Tools and Techniques

 Expert judgment  Analogous estimating  Parametric estimating  Three point estimate  Group decision‐making  techniques  Reserve analysis Output  Activity duration  estimate  Project document  updates

(85)

Develop Schedule

Develop schedule is the process of analyzing activity sequences,  durations, resource requirements and schedule constraints to create  the project schedule. Input  Schedule management plan  Activity list   Activity attributes  Project schedule network  diagrams  Activity resource requirement  Resource calendars  Activity duration estimate  Project scope statement  Risk register  Project staff assignment  Resources breakdown structure  Enterprise environmental  factors  Organizational process asset

Tools and Techniques

 Schedule network  analysis  Critical path method  Critical chain method  Resource leveling  What‐if scenario  analysis  Applying leads and lags  Schedule compression  Scheduling tools Output  Schedule baseline   Project schedule  Schedule data  Project calendars  Project management  plan updates  Project document  update

(86)

Control Schedule

Control schedule is the process of monitoring the status of the  project to update project progress and manage changes to the  schedule baseline Input  Project management  plan  Project schedule  Work performance data  Project calendars  Schedule data  Organization process  assets

Tools and Techniques

 Performance review   Project  management  software  Resources optimization  techniques  Modeling techniques  Leads and lags  Schedule compression  Scheduling techniques Output  Work performance  information  Schedule forecasts  Change request  Project management  plan updates  Project document  updates  Organization process  assets updates

(87)

Schedule Network Analysis Techniques

Schedule Network Analysis is a technique that generates

the project schedule. This technique includes:

 PERT

 Critical Path Method

 What‐if scenario analysis

 Schedule compression

 Critical chain method

(88)
(89)

PERT (Three Point Estimate)

Expected duration= (P+4M+O)/6 

Standard deviation of an activity= (P‐O)/6 

Variance of an activity = [(P‐O)/6]^2 

P= Pessimistic estimate 

M= Most likely estimate 

O= Optimistic estimate 

(90)

PERT

If A, B, C and D are the only sequential activities in the project, what  is the project duration?   The Answer is 179 with a standard deviation of 10.4, so the  minimum project duration is 168.6 and maximum duration is  189.4   The Project standard deviation is calculated by adding all activity 

Activity O M P PERT SD Var Range

A 20 30 40 30 3.33 11.08 30,+/‐3.33

B 40 60 90 61.6 8.33 69.38 61.6,+/‐8.33

C 35 50 60 49.1 4.16 17.30 49.1,+/‐4.16

D 25 40 45 38.3 3.33 11.08 38.3+/‐3.33

(91)

Critical Path Method

 Critical Path: 

The longest duration path through a network 

diagram and determines the shortest time to complete the 

project. 

 Float (Slack): 

Total Float (Slack): The amount of time an activity can be delayed  without delaying the project end date or an intermediary milestone.  – Free Float (Slack): The amount of time an activity can be delayed  without delaying the early start date of its successor(s).  – Project Float (slack): The amount of time a project can be delayed  without delaying the externally imposed project completion date  required by the customer or previously committed by the project  manager. 

(92)

How to Calculate Float?

ES LS EF LF F L O A T Backward Pass Forward Pass ES : Early Start LS : Late Start EF : Early Finish LF : Late Finish

Float = LS – ES

or 

(93)

Critical Path Example

Activity Duration Activity 1 3 Activity 2 3 Activity 3 6 Activity 4 8 Activity 5 4 0 0 3 3 Activity 1 Float=0 3 3 6 6 Activity 2 Float=0 Start 6 6 14 14 Activity 4 Float=0 14 14 18 18 Activity 5 Float=0 3 8 9 14 Activity 3 Float=5 End Path Duration Start, 1, 2, 4, 5, End 18

(94)

Develop Schedule

Fast Tracking Crashing:

Increasing resources on critical path  activities while making cost and  schedule tradeoffs to determine  how to obtain the greatest amount  of schedule compression for the  least incremental cost while  maintaining project scope.   Schedule Compression: Schedule compression is done during project planning  to see if the desired completion date can be met and what will have to change  to meet that date.   Two techniques:  – Fast Tracking  – Crashing  A B C A B

(95)

Schedule Compression Example

 To suppress the project duration by 1 day. Which activity 

would you crash? 

 The answer is Activity A, as it has the minimum crash cost 

Activity Original  Duration Crash  Duration Time Saving Original  Cost Crash Cost Extra  Cost Crash  Cost per  Day A 10 8 2 10,000 12,000 2,000 1,000 B 14 10 4 14,000 24,000 10,000 2,500 C 5 4 1 15,000 17,000 2,000 2,000 D 9 7 2 12,000 18,000 6,000 3,000

(96)

Impact of Schedule Compression

Option  General Impact to the Project  Fast Track  Adds risks  Increases management time for the project manager  Crash  Adds costs  Increases management time for the project manager  Reduce Scope  Saves time and cost  Increases customer dissatisfaction  Cut Quality Saves cost and Resources  Increases risks Resource reallocation Does not add cost or increase risks

(97)

Other Schedule Network Analysis Techniques

 What‐if Scenario Analysis: In this method the following question  is asked to produce a realistic schedule:  What if a particular  scenario changed on the project, would that produce a shorter  schedule?   Monte Carlo Analysis: This method of estimating cost or duration  uses a computer to simulate the outcomes of a project making  use of input values selected at random from probability  distributions.   Resource Leveling: Resource leveling is used to produce a  resource limited schedule. It results in a more even spread of the  workload of resources used on the project.   Critical Chain Method: This is another technique used to develop  the project schedule. It takes into account both the activity and  resource dependencies. We will not go into detail of this  technique, just remember that this technique exists.

(98)

Control Schedule

Control schedule is the process of monitoring the status of the project to update project progress and manage changes to the schedule baseline.

Input

 Project management plan  Project schedule

 Work performance information  Organization process assets 

Tools and Techniques

 Performance reviews   Variance analysis   Project management software  Resource leveling   What‐if scenario   Adjusting leads and lags   Schedule compression   Schedule tool  Output  Work performance measurements  Organizational process assets   Change requests 

(99)

PROJECT MANAGEMENT

(100)

Agenda

 Process Flow Diagram  What is Project Cost Management.  Difference between Cost Estimating and Cost Budgeting   Control Account   The Project Cost Management Processes.  Estimate Cost  Determine Budget  Control Schedule  Earn value management  Project selection method

(101)

What is Project Cost Management

 Project cost management includes the processes involved in  estimating, budgeting, and controlling costs so that the project  can be completed within the approved budget.   Cost Management Plan: This plan contains details like how to go  about planning the project cost and how to effectively manage  and control the project to the cost baseline and manage cost  variance.   The cost management plan is a part of the project management  plan.   The techniques for estimating the cost involved in performing  each of the project activities are the same as estimating the time  required.   Expert judgment, analogous estimating, bottom up estimating  and reserve analysis are some of the techniques used in cost  management. 

(102)

What is a Control Account

 In larger projects, its is difficult to do cost management 

at each individual activity level and hence costs are 

managed at a higher level. 

 It is done at a level higher than the work package. 

Remember, the project is broken into a WBS. The WBS is 

further broken down into work packages and work 

packages are finally broken into activities (WBS 

Dictionary). 

(103)

Project Cost Management Processes 

Project Cost Management Process  Time

Cost Management Plan Planning Process

Estimate Cost Planning Process

Determine Budget Planning Process

(104)

Plan Cost Management

Plan Cost Management is the process that establishes the policies,  procedures, and documentation for planning, managing, expending,  and controlling project costs. Input  Project management  plan  Project charter  Enterprise  environmental factors  Organization process  assets 

Tools and Techniques

 Expert judgment   Analytical techniques  Meetings

Output

(105)

Estimate Cost

Estimating cost is the process of developing an approximation of the  monetary resources needed to complete project activities. Cost estimates  are a prediction that is based on the information known at a given point in  time.  Input  Cost management plan  Human resource plan   Scope baseline  Project schedule  Risk register   Enterprise  environmental factors  Organization process  assets 

Tools and Techniques

 Expert judgment   Analogous estimating   Parametric estimating   Bottom up estimating   Three point estimates   Reserve analysis  Cost of quality  Project management  software   Vendor bid analysis   Group decision‐making  techniques  Output  Activity cost estimates   Basis of estimates   Project document  updates 

(106)

Determine Budget

 Determining the budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.

 The cost baseline includes all authorized budgets but excludes management Input  Cost management plan  Scope baseline   Activity cost estimates   Basis of estimates   Project schedule   Resource calendars   Risk register  Agreements  Organizational process  assets 

Tools and Techniques

 Cost aggregation   Reserve analysis   Expert judgment   Historical relationships   Funding limit  reconciliation  Output  Cost baseline   Project funding  requirements   Project document  updates 

(107)

Control Cost

Controlling cost is the process of monitoring the status of the project to  update the project budget and manage changes to the cost baseline. Any  increase to the authorized budget can only be approved through the  perform integrated change control process.  Input  Project management  plan   Project funding  requirements   Work performance data  Organizational process  assets

Tools and Techniques

 Earned value  management  Forecasting   To‐complete  performance index  Performance reviews   Project management  software   Reserve analysis Output  Work performance  information  Cost forecasts   Change requests  Project management  plan updates   Project management  plan updates   Organizational process  assets updates

(108)

Earn Value Management Techniques

The earned value management technique is a method to measure project  performance against the project baselines. It results from an earned value  analysis indicating potential deviation of the project from the cost and/or  schedule baselines. 

Acronym Term Explanation

PV Planned Value Estimated value of the work to be done 

EV Earn Value Estimated value of the work actually 

accomplished

AC Actual Cost Actual cost incurred in work accomplished 

BAC Budget at Completion The Budgeted amount for the total work 

EAC Estimate at Completion The current estimate for the total project cost

ETC Estimate to Complete From this point, how much more the project 

(109)

Earn Value Management Formula

Acronym Formula Explanation

Cost Variant (CV) EV‐AC Negative is over budget, positive is 

under budget.

Schedule Variant (SV) EV‐PV Negative is behind schedule, positive is 

ahead of schedule.

Cost Performance Index (CPI) EV/AC We are getting $___worth of work out 

of every $1 spent. Schedule Performance Index  (SPI) EV/PV We are progressing at $___ percent of  the rate originally planned.  Estimate at Completion (EAC)  BAC/CPI  How much do we expect the Project to  cost 

Estimate to complete (ETC)  EAC‐AC  How much more the Project would 

cost. 

(110)

EVM Problem Example

 Contract: To build 10 tanks in 12 months

Construction Budget :  10 tanks @ $ 1000 = $  10.000Construction period : 12 months

 Condition after 5 months:

Planned Value (PV) : $ 3.600 (from S‐curve)Actual Cost (AC) : $ 3.700 (from finance)Earn Value (EV) : $ 2.500 (from site actual)

(111)
(112)

EVM Problem Example

 Cost Variant (CV) : EV‐AC = 2.5 – 3.7 = ‐ 1.2  Schedule Variant (SV) : EV – PV = 2.5 – 3.6 = ‐ 1.1  Cost Perform. Index (CPI) : (EV)/(AC) = 2.5/3.7 = 0.676  Schedule Performance Index : (EV)/(AC) = 2.5/3.7 = 0.676

(113)

PROJECT MANAGEMENT

(114)

Agenda

 What is Quality.  What is Quality Management?  Cost of Quality  The Project Quality Management Knowledge Process.  Plan Quality  Perform Quality Assurance  Perform Quality Control  Basic tools of Quality

(115)

Quality???

 Quality is defined as “conformance to requirement and 

fitness for use”. 

 So, if all the project requirements are met and the 

resulting product/service is usable then quality has been 

met. 

 Quality is the responsibility of each and everyone in the 

organization. 

 The project manager is responsible for project quality, 

 While senior management is responsible for quality of 

the whole organization. 

(116)

Dimension of Quality

Crosby’s  “Conformance  to  Specification” Juran’s “Fitness  for Use” Deming’s  “Customer  Satisfaction” Ishikawa’s  “Continuous  Improvement” Quality

(117)

What is Project Quality Management 

 Quality management includes creating and following 

policies and procedures that meet the project’s defined 

quality needs. 

 The aim of quality management is to ensure that the 

specified approach to quality is implemented on the 

project. 

 The three aspects to quality management are: 

– Quality planning – Quality assurance – Quality control

(118)

Quality Planning vs QA vs QC

Quality 

Planning 

Quality 

Assurance

Quality Control

Determine a plan for quality Determine if the project is  complying with the  organizational (as well as  project) policies and  procedures. Measure specific project  result (product/deliverables) against standard. A major task is preparation  of the quality management plan. A major task is conducting  regular project audits Result of the audit are  corrective and preventive  A major activity is to inspect  and verify the project’s  product, defect repair, and  measuring whether the  quality indicators are 

(119)

Standard and Specification

 Technical Specification: Document that prescribe technical  requirements to be fulfilled by a product, process or service ISO  (1991)   Specification: A document intended primarily for use in  procurement, which clearly and accurately describes the essential  technical requirements for items, materials, or services including  the procedures by which it will be determined that the  requirements have been met. DOD‐STD‐480A   Standard: Document, established by consensus and approved by  a recognized body, that provides, for common and repeated use,  rules, guidelines or characteristics for activities or their results,  aimed at achievement of optimum degree of order in a given  context. ISO (1991) 

(120)

Cost of Quality

 Cost of quality includes all costs incurred over the life of the product by  investing in preventing nonconformance to requirements and ensuring  that the product conforms to requirements (rework).  Cost of Conformance  Quality training  Inspection  Testing This is cost spent during the project  execution to avoid failures

Cost of Non Conformance

 Rework  Scrap  Warranty cost This  is cost spent during and after  project execution caused by  failures

(121)

Project Quality Management Processes 

Project Scope Management Process  Time

Plan Quality Management Planning Process

Perform Quality Assurance Execution Process

(122)

Plan Quality Management

Plan Quality Management is the process of identifying quality  requirements and/or standards for the project and its deliverables,  and documenting how the project will demonstrate compliance with  relevant quality requirements. Input  Project management  plan  Stakeholder register  Risk register   Requirement  documentation   Enterprise  environmental factors  Organizational process  assets

Tools and Techniques

 Cost benefit analysis  Cost of quality  7 basic quality tools  Benchmarking  Design of experiments  Statistical sampling  Additional quality  planning tools  Meeting Output  Quality management  plan  Process improvement  plan  Quality metrics  Quality checklist  Project document  updates

(123)

Perform Quality Assurance

Perform Quality Assurance is the process of auditing the quality  requirements and the results from quality control measurements to  ensure that appropriate quality standards and operational  definitions are used. Input  Quality management  plan  Process improvement  plan  Quality metrics  Quality control  measurement   Project documents

Tools and Techniques

 Quality management  and control tools  Quality Audits  Process Analysis Output  Change request   Project management  plan updates  Project document  updates  Organizational process  assets updates

(124)

Control Quality

Control quality is the process of monitoring and recording results  activities to assess performance and recommend necessary changes.  Input  Project management  plan  Quality metrics  Quality checklist  Work performance data  Approved change  request  Deliverables  Organizational process  assets

Tools and Techniques

 7 quality tools   Statistical sampling  Inspection  Approve change  requests review  Output  Quality control  measurements  Validated changes  Verified deliverables  Work performance  information  Project management  plan updates  Project document  updates

(125)

Ishikawa’s Seven Quality Tools 

 Control charts 

 Cause and effect diagram 

 Flowcharting 

 Histogram 

 Pareto chart 

 Run chart 

 Scatter diagram 

(126)

Control Charts: 

 Control charts graphically 

help you to determine if 

the process is within 

acceptable limits. 

 A control chart can be 

used to monitor project 

performance figures such 

as cost or schedule 

variance. 

(127)
(128)

Flowcharting 

 Flowchart shows how a process or system flows from 

beginning to end and how the elements interrelate. 

 Graphically represent the process and helps analyze 

how the problems occur. 

 Used to identify redundancies and bottlenecks. 

(129)

Pareto Chart 

 Also called 80/20 rule. 

 Helps focus attention 

on the most critical 

issues. 

 Prioritizes potential 

causes of the problem. 

 Helps identify the 

critical few from the 

uncritical many. 

(130)

Histogram 

 It is a vertical bar chart showing how often a particular 

variable occurred. 

 The height of each column represents the relative 

frequency of the variable. 

(131)

Run Chart 

 Used to identify a pattern of variation. 

 Used to identify a trend. 

(132)

Scatter Diagram

(133)

PROJECT MANAGEMENT

(134)

Agenda

 What is Human Resource Management.  Project Sponsor  Functional Manager vs Project Manager  The Project Human Resource Management Knowledge Process.  Develop Human Resource Plan  Acquire Project Team  Develop Project Team  Manage Project Team  Conflict Management  Power of Project Manager

References

Related documents

Full time N/A Postgraduate Programme in Counselling Psychology University of East London (formerly Polytechnic of East London / North East London Polytechnic). 2004

Favor you leave and sample policy employees use their job application for absence may take family and produce emails waste company it discusses email etiquette Deviation from

In this case we compare the solution time of pure branch and bound with the solution time for branch and cut using two rules to select the seed of the DCC: most fractional and

Stakeholder engagement should be part of the stakeholder management process, aiming to interact with and involve stakeholders of a specific project of the organization.. They could

in this respect, Periñán- Pascual & Arcas-Túnez (2010a) described seven ontological commitments to which the FunGramKB ontology is subject, i.e. ontology

Change Management Top Management Support Stakeholder Management Harmonized Processes Right people in the project Enough time to change Clear IT strategy.. How often is

Hybrid Cloud Agent Emctl Dispatcher On-premise EM OMS 12.1.0.5 Hybrid Cloud Gateway HTTPS HTTPS TMClient over HTTPS.. Hybrid Cloud Agent to On-Premise

A simple way to perform this kind of analysis would be to partition the parameter space (see Table 3) in a number of subsets along the date coordinate, and run