• No results found

Case Study of Long Span Structure

N/A
N/A
Protected

Academic year: 2021

Share "Case Study of Long Span Structure"

Copied!
6
0
0

Loading.... (view fulltext now)

Full text

(1)

SUBMITTED TO:

AR. SHOBHIKA

Building construction

long span structure

SUBMITTED BY:

DHARNA GARG

B. ARCH. 7 SEM.

ROLL NO. 1221009

(2)

Introduction of hall of nation

BUT ABOVE ALL, TO REFLECT SYMBOLICALLY AND TECHNOLOGICALLY, INDIA'S

INTERMEDIATE TECHNOLOGY IN THE 25TH YEAR OF ITS INDEPENDENCE.

THE DEPTH OF THE STRUCTURAL SYSTEM WAS UTILIZED AS A SUN BREAKER AND CONCEIVED OF IN TERMS OF THE TRADITIONAL 'JALI',

A GEOMETRICAL PATTERN OF PERFORATION THAT SERVES TO OBSTRUCT DIRECTS RAYS OF THE HARSH SUN WHILE PERMITTING AIR CIRCULATION.

THE MAIN PAVILION OF THE HALL OF NATIONS HAS A CLEAR SPAN OF 78 METRES AND A HEIGHT VARYING FROM THREE METRES TO 21 METRES,

THEREBY PROVIDING A VAST CAPACITY FOR ITEMS TO BE EXHIBITED, FROM

BOOKS TO BULLDOZERS.

THE PERMANENT EXHIBITION

COMPLEX IS DESIGNED TO FORM THE FOCUS OF 130 ACRES OF EXHIBITION

GROUND DESIGNED BY RAJ REWAL IN NEW DELHI.

THE DESIGN WAS EVOLVED TO MEET THE CONSTRAINTS OF TIME, AVAILABILITY OF MATERIALS AND LABOUR,

LOCATION: NEW DELHI, DELHI, INDIA

PROJECT COMPLETED: 1972

AN INTERNATIONAL TRADE

FAIR TO BE HELD AT NEW DELHI IN 1972, REQUIRED LARGE

EXHIBITION HALLS.

THE MAIN HALL IS REQUIRED TO

HAVE A FREE AND UNOBS TRUCTED SPACE

OF 670 SQ. M. WITH AN APPROPRIATE HEIGHT OF 30 M. AND WAS NAMED AS “HALL OF

(3)

SHAPE AND FORM

FOR COVERING SUH A LARGE AREA

SEVERAL OPTIONS E.G. SHELLS, FOLDED

LATES, HYPAR SHELLS WERE CONSIDERD AND

REJECTED ON THE GROUND OF ECNOMICS.

 EVENTUALLY THE SOLUTION NARROWED

DOWN TO A DOUBLE LAYERED SPACE FRAME..

THE HALL OD DIMENSIONS HAVE A BASE DIMENSION OF 73 M X73 M. WHICH REDUCED

TO ALMOST HALF AT THE ROOF.

WHILE THE INVESTIGATING THE

CONFIGURATION OF SPACE FRAME IT WAS IDENTIFIED THAT THE MOST APPRORIATE SYSTEM TO CREATE SPACE FRAME WAS THE ONE WHICH USED PYRAMID AS A BASIC ELEMENT.

STEEL AND CONCRETE WERE GIVEN

DUE CONSIDERATION AND IT WAS FOUND THAT CONCRETE WAAS THE MST ECONOMICAL MATERIAL , WITH STRUCTURAL STEEL BEING 30% MORE EXPENSIVE.THUS CONCRETE WAS THE FINAL CHOICE.

FOR CLADDING, GUNITED TRIANGULAR PLATES WERE PROVIDED WHILE ROOF

OF THE HALL WAS COVERED WITH THE PRECAST LIGHT WEIGHT CONCRETE PLANKS.

A STUDY OF THE CONFIGURATION

REVEALED TE STRUCTURE WOULD BE STABLE ONLY AFTER CONSTRUCTION HAD REACHED AT LEVEL , WHERE IT RECEIVED THE FIRST AROUND

CONTINUITY AND BEFORE THAT IT WOULD REST ON SCAFFOLDING ERECTED FROM GROUND.

DESIGN AND ANALYSIS

HOWEVER THIS RESULTED IN FIVE

DIFFERENT CONFIGURATIONS WITH INTRODUCTION OF EACH ADDITIONAL RING BEYOND LEVEL 5. THEREFORE ANALYSIS WAS CARRIED OUT FOR ALL FIVE DIFFERENT CONFIGURATION TO FIX FINAL MEMBER SIZES

(4)

THE ANALYSIS

WAS DONE ASSUMING PINNED JOINTS , AS THE MEMBER WERE SLENDER AND IT WAS BELIEVED THAT SIGNIFICAT MOMENTS WOULD NOT DEVELOPED .

AN INDEPENDENT ANALYSIS DONE LATER CONFIRMED

THIS ASSUMPTION AS THE MOMENTS IN MEMBERS VERY SMALL.

THE SPACE FRAME WAS ANALYSED FOR

EARTHQUAKE AND WINDLOADS USING A THREE DIMENSIONAL PLAN JOINTED MODEL.MOST

IMPORTANT POINT FOR

SELECTING A MEMBER SHAPE

WAS STRENGTH AND EASE OF FABRCATION

.

SEVERAL ALTERNATIVES FOR MEMBERS SECTION

WERE CONSIDERED AND FINALLY

A RHOMBIC SECTION

WITH CHAMFERED EDGES HAVING AN AREA OF 585

SQ. CM WAS ADOPTED

THE ANALYSIS WAS REVELEAD THAT

HORIZANTALL

REFELCTIONS OF NODES NEAR CENTRAL LINES

SYMMETRY WOULD BE LARGE

.

 TO CONTAIN THERE REFLECTIONS, HORIZANTALL

DIAPHRAGMS WERE INTRODUCED BETWEEN INNER AND OUTER FACES OF THE SPACE FRQAME AT LEVEL 3,6,8.

DESIGN AND ANALYSIS

THE OBVIOUS CHOICE OF CONSTRUCTION

WAS PRECAAST CONSTRUCTION

TECHNIQUE . IT WAS VISUALLISED THAT THE

MEMBERS AND JOINT WOULD BE PRECAST SEPERATELY AND PUT TOGETHER WITH HELP OF BOLTS AND FILLED WELDING OF SHIM PLATES .

DETAILS OF SUCH PRECAST JOINT ARE

SHOWN IN FIG. UNFORTUNATELY NO CONTRACTOR CAME FORWARD TO CONTSRUCT THIS STRUCTURE USING PRECAST TECHNIQUE ,

HENCE INSITU CONCRETE WAS ADOPTED .

THE DEVELOPMENT OF INSITU JOINT WAS DIFFICULT OWING TO

CONGESTION OF

BARS AT THE JOINT ELEMENT . ON AN

AVG. , 9 MEMBERS MET AT ONE JOINT

AND EVEN WITH 4 BARS PER MEMBERS

,

(5)

DESIGN AND ANALYSIS

FINALLY A SYSTEM WAS EVOLVED WHERE

ONLY 20 BARS PASSED THROUGH THE JOINT

ELEMENT .BARS FROM LOWER 4 MEMBERS WERE LAPPED WITH 4 UPPER MEMBERS BARS THUS CATERING TO 8 MEMBERS .

THE SEQUENCE OF CONSRUCTION WAS TO

CAST STRAIGHT LENGTH OF MEMBERS FROM JOINT TO JOINT , PLACE IN POSITION PARTIALLY PREASSEMBLED FORM WORK OF THE JOINT ALONG WITH PLACED IN

POSITION SHORT LENGTH CURVED BARS .T

THESE BARS WERE WELDED WITH

STRAIGHT BARS OF MEMBERS , FORMWORK OF THEMEMBER UPTO NEXT JOIT ERECTED AND THE MEMBER AND THE JOINT

CONCRETED .

THIS SEQUENCE WAS FOLLOWED UPTO

ROOF LEVEL THE CONSTRUCTION OF

SPACEFRAME WAS TAKEN ON ALL 4 SIDES

SIMULTANEOUSLY .

THERE WOULD BE

36 BARS MEETING AT THE

JOINT

, SOME CARRYING TENSION WHILE OTHERS WERE IN COMPRESSION. IN THE PRECAST JOINT SOME ASSISTANCE WAS AVAILABLE FROM STEEL PLATES EMBEDDED IN

CONCRETE BUT IN THE INSITU JOINT THAT

(6)

Cross -section of Nehru

pavilion

plan

THE PLAN OF THESE PAVILIONS IS SQUARE WITH CHAMFERED CORNERS , PROVIDING

EIGHT ANCHORING POINTS.

THE CORNERS WERE INSPIRED BY THE TOMB OF MUGHUL EMPEROR HUMAYUN'S AND

THE TAJ MAHAL.

IN THE HALL OF NATIONS AN UNINTERRUTED VOLUME IS ACHIEVED WHERE THE HEIGHT VARIES FROM 3 M TO 30 M.

THIS PERMITS THE DISPLAY OF SUCH DIVERSE OBJECTS AS AIRCRAFT,

EARTHMOVING EQUIPMENT, TRACTORS AND CRANES.

IN THE HALL OF INDUSTRIES THE HEIGHT VARIES FROM 2.5 M TO 15 M. THE SQUARE

References

Related documents