• No results found

A Model to Develop and Use Risk Contingency Reserve

N/A
N/A
Protected

Academic year: 2021

Share "A Model to Develop and Use Risk Contingency Reserve"

Copied!
18
0
0

Loading.... (view fulltext now)

Full text

(1)

A Model to Develop and Use Risk

Contingency Reserve

NK Shrivastava, PMP, RMP, ACP, CSM, SPC

CEO/Consultant/Agile Coach - RefineM

www.RefineM.com

Agenda

1. Your Expectations from this Presentation

2. Introduction – Myself

3. Model to Develop and Use Risk Contingency Reserve

a. Background/Overview of Risk Management

b. What is a Contingency Reserve?

c. Using Expected Monetary Value to calculate Contingency Reserve

d. Communicating the Contingency Reserve

e. Using the Contingency Reserve

f. Limitations of the Model

(2)

www.RefineM.com

Session Objectives

1. Learn a very simple way to calculate contingency reserve using Expected Monetary Value

2. Learn ways to communicate the contingency reserve to stakeholders

3. Understand how to use the contingency reserve to respond to risks as they are realized

www.RefineM.com

Your Expectations

What are your expectations from this

presentation?

(3)

www.RefineM.com

NK Shrivastava

,

PMP, RMP, ACP, CSM, SPC

 CEO/Consultant since Dec 2011

 Agile Coaching/Adoption

 Project Management/ Process Improvement Consulting and Training

 Project Management Toolkits (for PMs, Executives and Agile Practitioners)

Helping organizations turn their project management capability

into a competitive advantage

My professional journey b/f RefineM  20+ years of Successful Project Leadership

 Led 100s of projects of all sizes, successfully

 Recovered many projects, saved millions of $

 Implemented numerous process improvements

 Coached/mentored 100s of PMs, and some executives

 Board Member – SWMO PMI Chapter (2008-2014)

A Model to Develop and Use Risk

Contingency Reserve

Overview of Risk Management

What is a Contingency Reserve?

Using Expected Monetary Value

(EMV) to calculate contingency reserve

Communicating Contingency Reserve

(4)

www.RefineM.com

What is a Project Risk?

Project risk is an

uncertain event

or condition

that, if it occurs, has a positive or a negative effect

on a project's objectives.

- From PMI's Practice Standard for Project Risk Management – Chapter 2 , Page 9

What is a Project Risk?

www.RefineM.com

Risks Vs Issues

Risks Issues

• A future event

• It has not occurred yet but there are chances that it may occur – there is uncertainty

• The probability of occurrence can range from 0 to 1 but it is neither 0 or 1 (greater than 0 but less than 1)

• The language to describe a risk uses future tense

• A response plan is needed in case risk event occurred • Risk Register is used for risks

• An event of past or present • It has already occurred or

occurring right now, there is no doubt whether it’ll happen or not – no uncertainty

• Probability is 1 since it already occurred

• The language to describe an issue uses present to past tense • Need a resolution plan with

action items to resolve an issue • Issue log is used for issues

(5)

www.RefineM.com

Risk Management Processes

Identify Risks

Perform Qualitative Risk Analysis Perform Quantitative Risk

Analysis

Monitor and Control Risks Plan Risk Responses

Adapted from PMI’s Practice Standard for Project Risk Management

Plan Risk Management

www.RefineM.com

Risk Management Processes

Plan Risk Management

Identify Risks

Perform Qualitative Risk Analysis Perform Quantitative Risk

Analysis

Monitor and Control Risks Plan Risk Responses

Risk Mgmt Plan

•Tailored Process •Risk Thresholds •Roles/Responsibilities •Risk Register Template

(6)

www.RefineM.com

Risk Management Processes

Plan Risk Management

Identify Risks

Perform Qualitative Risk Analysis Perform Quantitative Risk

Analysis

Monitor and Control Risks Plan Risk Responses

Risk Register

•List of risks •Risk Owners

Adapted from PMI’s Practice Standard for Project Risk Management

www.RefineM.com

Risk Management Processes

Plan Risk Management

Identify Risks

Perform Qualitative Risk Analysis

Perform Quantitative Risk Analysis

Monitor and Control Risks Plan Risk Responses

Updated Risk Register

•Probability & Impact •Root Causes •Prioritized List of Risks •Watch List

(7)

www.RefineM.com

Risk Management Processes

Plan Risk Management

Identify Risks

Perform Qualitative Risk Analysis

Perform Quantitative Risk Analysis

Monitor and Control Risks Plan Risk Responses

Updated Risk Register

•Numerical models •Sensitivity analysis

(Monte Carlo Simulation)

•Re-prioritized list

Adapted from PMI’s Practice Standard for Project Risk Management

www.RefineM.com

Risk Management Processes

Plan Risk Management

Identify Risks

Perform Qualitative Risk Analysis Perform Quantitative Risk

Analysis

Monitor and Control Risks

Plan Risk Responses

Updated Risk Register

•Strategies/Responses •Actions/Action Owners •Contingency Reserves

(8)

www.RefineM.com

Risk Management Processes

Plan Risk Management

Identify Risks

Perform Qualitative Risk Analysis Perform Quantitative Risk

Analysis

Monitor & Control Risks

Plan Risk Responses

Updated Risk Register

•Variance Analysis •Risk Audit

•Trends in risk exposure

Adapted from PMI’s Practice Standard for Project Risk Management

www.RefineM.com

Time or cost set aside to manage identifiedrisks

Contingency Reserve covers “known unknowns”

Management Reserve covers “unknown unknowns”

Contingency Reserve

Contingency Reserve is a CRITICAL part of Risk Management

(9)

www.RefineM.com

How It Is Used

Communicating risks

Responding to risks

Making project outcome more predictable

www.RefineM.com

How to Develop

What is needed?

 Risk Register

 Quantitative Analysis Technique

(10)

www.RefineM.com

Expected Monetary Value

Expected Monetary Value (EMV) of a Risk

Probability x Impact

 Probability of the risk occurring (percentage)

 Impact, if the risk occurred (time or cost measure)

www.RefineM.com

There is a 70 percent chance that computers needed for the project team will not be available on time, causing a delay of 5 days.

What is the EMV for this Risk? EMV (probability x impact)

= 0.7 x 5 days = 3.5 days

(11)

www.RefineM.com

There is a 50 percent chance that a critical piece of equipment will fail during the project and will cost $10,000 to replace.

What is the EMV of this Risk? EMV (probability x impact)

= 0.5 x $10000 =$5,000

EMV Example #2

www.RefineM.com

Schedule baseline = Estimated finish date + contingency reserve (time/schedule aspect)

 Example: Estimated Finish date is in 10 weeks, with contingency reserve of 4 weeks. What is the schedule baseline?

 Schedule Baseline is 14 weeks.

“No Later Than” date

(12)

www.RefineM.com

Cost baseline = Estimated costs + contingency reserve

 Example: Project budget is $1,000,000, contingency reserve is $250,000. What is the cost baseline?

 Cost baseline is $1,250,000.

“Not to Exceed” budget

Communicating Cost

www.RefineM.com

(13)

www.RefineM.com

When risk occurs:

 Actual impact is added to cost/schedule

 Estimated budget/schedule is updated

 Contingency reserve decreases

 Baseline is NOT updated

If risk does not occur, contingency not spent Project finishes before time, under budget

Using the Reserve

www.RefineM.com

(14)

www.RefineM.com

Risks With EMV

www.RefineM.com

Magnitude Over Time

79.75 108.95 108.95 80.45 42.95 39.25 33.75 27.75 22 17.35 8.65 3.85 3.85 11 13 13 12 12 12 12 11 10 10 9 5 5

Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10-1 Aug-10-2 Sep-10 Oct-10 Nov-10 Dec-10 Risk Magnitude # of Risks

(15)

www.RefineM.com

Risk Duration

www.RefineM.com

Charting Estimates

Show periodic expenditure for each risk that occurs

 Monthwise or otherwise

For each risk:

 Remaining contingency reserve goes down

 Cost / Schedule Estimate goes up

(16)

www.RefineM.com

Estimates Over Time

www.RefineM.com

This Model is NOT as useful when:

 Only few risks have been identified

 All risks have high probability

Either of these could produce erroneous results

(17)

www.RefineM.com

Too Few Risks

If risks are too few, “insurance pool” not large enough

 Need to find more risks

 Consider a Risk Breakdown Structure (RBS)

www.RefineM.com

Too High Probability

Look into strategies other than risk contingency reserve

 Avoid

 Mitigate

 Transfer

(18)

www.RefineM.com

Summary

Contingency reserve is:

 Critical in risk management

 Included in baselines (schedule and cost)

 An effective communication tool for risks

 A way to make project outcomes more predictable

Start using Contingency Reserve today!

EMV is a simple way to get started

www.RefineM.com

__________________________________________________________________

NK Shrivastava,MBA, PMP, RMP, ACP, CSM, SPC CEO/Consultant, RefineM

Nixa, MO 65714, USA

[email protected], www.refinem.com

http://www.linkedin.com/in/nkshrivastava @justrightpm

References

Related documents

• Administrative role to record all issues and decisions • Analyzes incident reports for trending issues • Assists coordinator in providing roll-up reporting

The primary objective of this research was not necessarily to “fix” or remedy specific leadership issues or capability gaps. Instead, this research described why leadership

The article argues, however, that this conception of autonomy ought to be confined to the specific legal and policy context of investment agreements between Member States of

sent study was to analyze the effect of successful reperfu- sion on functional outcome, mortality and sICH in patients presenting with ASPECTS 0–5 who were included in the

In the past few years, large risk transfer transactions have occurred resulting in an acute awareness to risk transfer without the usual complete plan termination event. As more plan

CES-D: Center for Epidemiologic Studies Depression Scale; CISS: Coping Inventory for Stressful Situations; EQ-5D: EuroQol-5D; HR-QoL: Health-related quality of life; IPA: Impact

A standardized marking system employed during and after the search of a structure for potential victims used in conjunction with the Structure and Hazards marking system.

A virtual doubling of the growth rate in Securitas Direct, from about 10,000 to almost 20,000 new alarms sold, is proof of the force that follows from a sharper focus. The