• No results found

dist-cord(r)

N/A
N/A
Protected

Academic year: 2021

Share "dist-cord(r)"

Copied!
12
0
0

Loading.... (view fulltext now)

Full text

(1)

Co-ordination of over current relays in distribution system

(Prepared by: N.Shahul Hameed B.E, SE/P&C(Retired),TNEB)

The single line diagram of the network considered for relay calculation shown in fig 1

Fig 1 The fault MVA of each component

For the system (1) MVA = 2600 = 2600 MVA 1

For the 10MVA transformer (2), MVA = 10 = 92.57 MVA 0.108

For the line (3) MVA = 332 = 111 MVA

15.75 x 0.625

For the 5MVA transformer (4), MVA = 5 = 77 MVA 0 .065 110KV VVVV V KKKV 2600MVA D E 8 7 110/33KV 10MVA Z% = 10.8 5 6 C B A 4 3 2 1 2.5MVA 2.5MVA 33/11KV 5MVA Z% = 6.5 Dy1 15.7KM J0.625 Ώ/km Yy0 33KV 33KV 11KV

(2)

Fault level of Bus D = 2600 MVA Fault level of Bus C = 1 = 89.28 MVA 1 + 1 .

2600 92.59

Fault level of Bus B = 1 = 49.48 MVA 1 + 1 + 1 .

2600 92.59 111

Fault level of Bus A = 1 = 49.48 MVA 1 + 1 + 1 + 1 . 2600 92.59 111 77 Fig 2 1 2 3 4 2600MVA (Source) 92.59MVA AA 111MVA 77MVA 30.12 MVA 49.48 MVA 89.28 MVA 2600 MVA D C B A

(3)

ISCA = 30.12 = 1.581 KA √3 x 11 ISCB = 49.48 = 0.8657 KA √3 x 33 ISCC = 89.28 = 1.564 KA √3 x 33 ISCD = 2600 = 13.647 KA √3 x 110 SELECTION FOR CT RATIO

:-The CT ratio is selected using the higher of the following two currents.

i) the nominal current

ii) the maximum short circuit current for which no saturation is

occurred (0.05 x Isc)

Relay 1 &2 : Inom 1 = Inom 2 = Pnom 1

√3 x V1

= 2.5 x106 .

√3 x 11 x 103

= 131.22 A (referred to 11KV)

Relay 3 : Inom 3 = Pnom 3

√3 x V3

= 5 x106 .

√3 x 11 x 103

= 262.44 A (referred to 11KV)

(4)

Relay 4 : Inom 4 = Pnom 4

√3 x V4

= 5 x106 .

√3 x 33 x 103

= 87.48 A (referred to 33KV) Relay 5 &6 : Inom 5 = Inom 6 = 87.48 A (referred to 33KV)

Relay 7 : Inom 7 = Pnom 7

√3 x V7

= 10 x106 .

√3 x 33 x 103

= 174.96 A (referred to 33KV) Relay 8 : Inom 8 = Pnom 8

√3 x V8

= 10 x106 .

√3 x 110 x 103

= 52.49 A (referred to 110KV)

The short circuit current, nominal load current and CT ratio inline with the criteria for selection of CTs are tabulated in the table below :

Relay No P

nom Isc 0.05 x Isc Inom CT Ratio

MVA A A A 1 & 2 2.5 1581.21 79.06 131.22 150/5 3 5 1581.21 79.06 262.44 300/5 4 5 866.37 43.32 87.48 100/5 5 5 1564.42 78.22 87.48 100/5 6 5 1564.42 78.22 87.48 100/5 7 10 1564.42 78.22 174.96 200/5 8 10 13646.41 682.32 52.49 700/5

(5)

SETTING OF INSTANTANEOUS UNITS OF OVER CURRENT RELAYS :-The setting of instantaneous units for various system elements such as line between sub- stations, distribution lines and transformers are adopted as per following criteria.

Lines between sub-stations :-

The setting of instantaneous units is carried out by taking at least 125% of the maximum fault level at the next station. The procedure must be started from the farthest sub-station, and continued by moving back towards the source. When the characteristic of two relays cross at a particular system fault level, thus making it difficult to obtain correct co-ordination, it is necessary to set the instantaneous unit at the sub-station that is farthest away from the source to such a value that the relay operates for slightly lower level of current. 25% margin avoids overlapping the downstream instantaneous unit.

Distribution

lines:-Since the distribution lines are the end of the system any one of the following criteria may be adopted.

i) 50% of the maximum fault current at the point of connection of the CT supplying relay.

ii) Between six and ten times of the maximum load current. Transformer

units:-The instantaneous units of over current relays on the primary side of the transformer should be set between 125 and 150% of the short circuit current at the bus bar on the secondary side, referred to the primary side. If the instantaneous units of the transformer secondary and feeder relays are subjected to same short circuit level then the transformer secondary instantaneous over current unit needs to be overridden to avoid loss of co-ordination.

CALCULATION OF INSTANTANEOUS SETTING: Relays 1 & 2

Iinst = 0.5 x Isc = 0.5 x1581.21 = 790.6 A (Primary)

ie = 790.6 x 5/150 = 26.35A (Secondary)

Set the relay at 27A secondary amps equivalent to 810A primary amps. Relay 3

The instantaneous unit is overridden to avoid the possibility of loss of co- ordination.

Relay 4

The setting is based on 125% of the short circuit current that exists at the busbar on the low voltage side of the transformer, referred to the high voltage side.

(6)

Iinst = 1.25 x1581.21 x (11/33) = 658.84 A primary amps

ie =658.84 x(5/100) = 32.94A secondary amps Set 33 amps equivalent to 660 primary amps

Relay 5

The setting is calculated on the basis of 125% of the current for the maximum fault level that exists at the next downstream substation.

Iinst = 1.25 x 866.37 = 1082.96 A primary amps

ie = 1082.96 x (5/100) = 54.15A secondary amps Set 55 amps equivalent to 1100 primary amps.

Relay 6

Iinst = 1000 A primary amps

ie = 50A secondary amps Relay7

The instantaneous unit is overridden to avoid the possibility of loss of co- ordination.

Relay 8

The setting is calculated on the basis of 125% of the current for the maximum fault level that exists at the next downstream substation referred to the high voltage side

Iinst = 1.25 x 1564.42 x (33/110) = 586.66 A primary amps

ie = 586.66 x (5/700) = 4.19A secondary amps

Set at 6 secondary amps (the minimum setting) equivalent to 840 primary amps. PICK-UP SETTING:

The pick-up setting or plug setting is determined by the following expression. Pickup setting = OLF x Inom

CTR OLF = over load factor, CTR = CT ratio

The overload factor(OLF) recommended for various circuits are given below. For phase fault relays:

For motor 1.05 For lines, generator, and transformers 1.25 to 1.5

(7)

For distribution feeders under emergency condition 2 For earth fault relays:

For lines, generator, and transformers 0.2 For transmission lines 0.1 For distribution feeders 0.3 Calculation of pick-up settings:

PU = OLF x Inom

CTR

Relay 1 &2 PU 1,2 =1.5 x 131.22 x (5/150) =6.56; set at 7 Relay 3 PU 3 =1.5 x 262.44 x (5/300) =6.56; set at 7 Relay 4 PU 4 =1.5 x 87.48 x (5/100) =6.56; set at 7 Relay 5 PU 5 =1.5 x 87.48 x (5/100) =6.56; set at 7 Relay 6 PU 6 =1.5 x 87.48 x (5/100) =6.56; set at 7 Relay 7 PU 7 =1.5 x 174.96 x (5/200) =6.56; set at 7 Relay 8 PU 8 =1.5 x152.49 x (5/700) =0.56; set at 1 TIME MULTIPLIER SETTING :

The criteria procedure for calculating the time multiplier setting (TMS) to obtain appropriate protection and co-ordination for the system are given below.

1) determine the required operating time t1 of the relay farthest away from the

source by choosing the lower time multiplier setting and considering the fault level for which the instantaneous unit of this relay picks up. This may be higher if it is necessary to co-ordinate with devices installed downstream. eg. Fuses or reclosers and condition like cold load pick-up.

2) determine the required operating time of the relay associated with the next upstream breaker t2a = t1 + tmargin. Use the same fault level that used to

determine t1 of the relay associated with the previous breaker for this

calculation also.

3) For the same fault current as in 1 above and knowing t2a and pick-up value for

relay 2, calculate time multiplier setting of the relay 2.

4) Determine the operating time t2b of relay 2, but now using the fault level just before the operation of its instantaneous unit.

5) Continue with the sequence, starting from the second stage. Time discrimination margin :

A discrimination margin between two successive time characteristic of the order of 0.2 to 0.4s should be typically used.

The operating time of the relay can be obtained from the operating characteristic on log-log paper or from the mathematical formula given below.

(8)

t = kβ + L (I/Is)α - 1

Where I = fault current, Is = pick-up setting.

K = time multiplier setting, L a constant t = relay operating time in sec

The consants α, β and L of relays of various standard charactricstic are given below.

Curve description standard α β L

Moderately inverse IEEE 0.02 0.0515 0.114

Very inverse IEEE 2 19.16 0.491

Extremely inverse IEEE 2 28.2 0.1217

inverse CO8 2 5.95 0.18

Short time inverse CO2 0.02 0.0239 0.0169

Standard inverse IEC 0.02 0.14 0

Very inverse IEC 1 13.5 0

Extremely inverse IEC 2 80 0

Long time inverse IEC 1 120 0

By knowing the PSM and operating time the equation can be solved for TMS CALCULATION OF TIME MULTIPLIER SETTIG :

Characteristic used - IEC very inverse time

Constants used for operating time of inverse characteristic is β = 13.5, α = 1, and L = 0

Substituting the constants in the characteristic reduces to t = k x 13.5 + 0

(I/Is)1 - 1

k x 13.5 PSM - 1

For relays associated with breakers 1 & 2 choose the smaller multiplier setting and calculate the operating time.

Relays 1 & 2

Choose time multiplier setting k = 0.05 PSM = Iinst.sec x (1/PU1,2)

(9)

= 27 x (1/7) = 3.857 times

t1 = 0.05 x 13.5

3.857 - 1

= 0.236 sec or say 0.24 sec Relay 3

The relay backs up relay 1 and 2 Use a grading margin of 0.4sec

There fore the required operating time is t3a = 0.24+0.4 = 0.64

PSM is based on 810 primary amps associated the instantaneous setting of relays 1 & 2 So PSM3a = 810 x(1/CTR3) x (1/PU3)

= 810 x (5/300) x(1/7) = 1.928 times k = (PSM – 1) x t3a

13.5

= (1.928 – 1) x 0.64 = 0.04 Or say0.05 (minimum setting) 13.5

Since in this case the instantaneous unit is overridden the short circuit current is used and multiplied by the factor 0.86 in order to cover the delta-star transformer arrangement.

So PSM3b = 0.86 x IscA x (1/CTR) x (1/PU3)

= 0.86 x 1581.21 x (5/300) x (1/7) = 3.238 times

With time multiplier setting 0.05 and PSM3b of 3.238 the operating time of the relay

t3b = 0.05 x 13.5 = 0.3sec

3.238 - 1 Relay 4

The relay 4 backs up relay 3 Use a grading margin of 0.4sec

Hence the required operating time is t4a = 0.3+0.4 = 0.7

PSM4a is based on 1581.21 primary amps of the CT associated with relay 3

So PSM4a = 1581.21 x (11/33) x (5/100) x (1/7)

(10)

With PSM4a = 3.764 and backup time of 0.7

k = (3.764 – 1) x 0.7 = 0.14 13.5

It is now necessary to calculate the operating time of relay 4 just before the operation of the instantaneous unit.

PSM4b = Iinst.prim4 x (1/CTR4) x (1/PU4)

= 660 x (5/100) x (1/7) = 4.714 times

With time multiplier setting 0.14 and PSM4b 4.714

t4b = 0.14 x 13.5 = 0.51sec

4.714 - 1 Relay 5

The relay 5 backs up relay 4 Use a grading margin of 0.4sec

Hence the required operating time is t5a = 0.51+0.4 = 0.91

PSM5a is based on 660 primary amps of the CT associated with relay 4

So PSM5a = 660 x (5/100) x (1/7)

= 4.714 times

With PSM5a = 4.714 and backup time of 0.91

k = (4.714 – 1) x 0.91 = 0.25 13.5

It is now necessary to calculate the operating time of relay 5 just before the operation of the instantaneous unit.

PSM5b = Iinst.prim5 x (1/CTR5) x (1/PU5)

= 1100 x (5/100) x (1/7) = 7.857 times

With time multiplier setting 0.25 and PSM5b 7.857

t5b = 0.25 x 13.5 = 0.492sec

7.857 - 1 Relay 6

(11)

Time multiplier setting = 0.3 (assume slightly higher setting than relay 5 for clarity of problem)

Relay 7

Relay 7 backs up relay 5 & 6 and should be coordinated with the slower of these two relays.

Relay 5 has an instantaneous setting of 1100primary amps and relay 6 has an instantaneous setting of 1000 primary amps. Therefore the operating of both the relays should be calculated for 1000 primary amps current.

Relay 5; PSM5 = 1000 x (5/100) x 1/7) = 7.14 times

With PSM = 7.14 and time dial setting 0.25 t5 = 0.25 x 13.5 = 0.55sec

7.14 - 1

Relay 6; PSM6 = 1000 x (5/100) x 1/7) = 7.14 times

With PSM = 7.14 and time dial setting 0.3 t6 = 0.3 x 13.5 = 0.66sec

7.14 - 1 The slower relay is relay 6

Therefore, in order to be slower than relay 6, the back up time of relay 7 should be t7a = 0.66+0.4 = 1.06 sec

PSM7a is based on the 1000 primary amps of the CT associated with relay 6

So, PSM7a = Iinst.prim7 x (1/CTR7) x (1/PU7)

= 1000 x (5/200) x (1/7) = 3.57 times

With PSM7a =3.57 and backup time of 1.06 sec

k = (3.57 – 1) x 10.6 = 0.2 13.5

As the instantaneous unit is overridden, the multiplier PSM7b is calculated using

the current for a short circuit on busbar C So, PSM7b = Isc x (1/CTR7) x (1/PU7)

(12)

= 1564.42 x (5/200) x (1/7) = 5.5 times

With time multiplier setting 0.2 and PSM7b 5.5

T7b = 0.2 x 13.5 = 0.6sec

5.5 - 1 Relay 8

The relay 8 backs up relay 7 Use a grading margin of 0.4sec

Hence the required operating time is t8a = 0.6+0.4 = 1.0 sec

PSM8a is based on 1564.42, the short circuit current of busbar C referred to 110 KV bus,

since the instantaneous unit of relay 7 is overridden.

So PSM8a = 1564.42 x (33/110) x (5/700) x (1/1)

= 3.35 times

With PSM8a = 3.35 and backup time t8a = 1

k = (3.35 – 1) x 1 = 0.17 13.5

Table 2

Summery of setting

Relay no CT Ratio pickup Time dial Instantaneous setting

primary secondary 1 & 2 130/5 7 0.05 810 27 3 300/5 7 0.05 overridden 4 100/5 7 0.14 600 33 5 100/5 7 0.25 1100 55 6 100/5 7 0.3 1000 50 7 200/5 7 0.2 overridden 8 700/5 1 0.17 840 6

Ref:- Protection of Electricity Distribution Networks By Juan Gers and Edward Holmes IEEE Power and Energy Series

References

Related documents

Incline through downtown fond du lac bike easements east peoria riverfront park is flat and a trail will let you to the trail will link the village of.. Lots of the fon du lac

Fadugba will seek intervention of IATA in issues including: the harmful impact of the EU blacklist on the global reputation of the African airline industry; unilateral

Μελιτζάνες Τσακώνικες με φέτα Υλικά για 1 ταψί φούρνου 1 ½ κιλό Τσακώνικες μελιτζάνες ελαιόλαδο για το τηγάνισμα 3 νεροπότηρα ψιλοκομμένη φρέσκια

4.1 The Select Committee is asked to consider the proposed development of the Customer Service Function, the recommended service delivery option and the investment required8. It

Voor de proactieve component zullen de lidstaten, veel meer dan voorheen, gebruik kunnen maken van de gegevens over een groot aantal stoffen die de industrie aanlevert bij

How Many Breeding Females are Needed to Produce 40 Male Homozygotes per Week Using a Heterozygous Female x Heterozygous Male Breeding Scheme With 15% Non-Productive Breeders.

• Follow up with your employer each reporting period to ensure your hours are reported on a regular basis?. • Discuss your progress with