• No results found

Project Vice-Presidency

N/A
N/A
Protected

Academic year: 2021

Share "Project Vice-Presidency"

Copied!
14
0
0

Loading.... (view fulltext now)

Full text

(1)

Codelco Investment Plan

Codelco Investment Plan

2012

Project Vice-Presidency

(2)

CODELCO INVESTMENTS 2011

Investment Projects (*)

est e t

ojects ( )

US$ 1.835 Bn

US$

835

Mine development expenses costs

US$ 670 M

Project contribute to business

US$ 40 M

TOTAL CODELCO 2011

US$ 2.545 Bn

(*)

Project Portfolio

( )

Project Portfolio

managed by VP

US$ 1.022 Bn

(3)

VP INVESTMENT PLAN 2011 ACHIEVEMENTS

Completed Projects

p

j

(US$ M currency 2011)

(

y

)

MH

 

EARLY

 

WORKS

 

150

RÍO

 

BLANCO

 

DIVERSION

 

TUNNEL

160

WATER FLOW REGULARISATION (ANDINA)

95

With these projects, operations received assets totalling US$ 405 M

WATER

 

FLOW

 

REGULARISATION

 

(ANDINA)

95

 

(4)

VP INVESTMENT PLAN 2011 ACHIEVEMENTS

Progress at Key Projects

Progress at Key Projects

Ministro Hales Project

j

Stage: Investment Implementation

April: Started world’s largest

p

g

pre-stripping

p

pp g

operation.

p

August: Completed early works.

August: Awarded first civil engineering contract.

Chuquicamata Underground Mine Project

Stage: Feasibility+ Early works implementation

Progress on feasibility stage.

August: Early works approved by Board.

October: Positive recommendation by Cochilco – Mideplan on early

y

p

y

works and start-up operations.

(5)

VP INVESTMENT PLAN 2011 ACHIEVEMENTS

Progress at Key Projects

Progress at Key Projects

Andina Expansion 244 Project

p

j

Stage: Feasibility

Progress on early works of projects. Acid Water Treatment (TADA)

and Node 3.,00.

August: Surface rights agreements for concentrator plant and other

facilities.

New Mine Level Project – El Teniente

St

I

t

t I

l

t ti

Stage: Investment Implementation

March: Environmental Impact Assessment (EIA) approval.

J l

I

t

t i

l

t ti

t

d b th B

d

July: Investment implementation stage approved by the Board.

Progress on early works (Confluence platforms).

(6)

VP INVESTMENT PLAN 2011 ACHIEVEMENTS

Progress at Key Projects

Progress at Key Projects

RT Sulphide Mine - Phase II Project

Stage: Feasibility

Stage: Feasibility

August: Started Prefeasibility Stage.

Decision to double mineral treatment capacity at concentrator plant,

S

O

p

y

p

that will use desalinated seawater.

December: End of Prefeasibility Stage.

San Antonio Oxides Project

Stage: Feasibility

J l

St t d F

ibilit St

July: Started Feasibility Stage.

September: Base project Environmental Impact Statement approval.

Metallurgical studies to double project production capacity.

Drilling campaign to define primary sulphides at this deposit

(7)

VP INVESTMENT PLAN 2011 ACHIEVEMENTS

Safety Indicators

Total Frequency Rate

:

1.53

Total Severity Rate

:

40

Total Man-Hours

:

11 787 421

Total Man-Hours

:

11,787,421

Employment

Average 2011

:

6,029 employees

(8)

CODELCO ESTIMATED CAPITAL EXPENDITURE

FOR 2012

FOR 2012

I

t

t P

j

t (*)

US$ 3 572 B

Investment Projects (*)

US$ 3.572 Bn

Mine development

& contribution to joint-ventures

US$ 756 M

& contribution to joint-ventures US$ 756 M

TOTAL CODELCO 2012

US$ 4.328 Bn

(*) P

j

t P

tf li

(*) Project Portfolio

managed by VP

US$ 2.273 Bn

Note: Values express in nominal currency

Note: Values express in nominal currency.

(9)

CHALLENGES TO VP INVESTMENT PLAN 2012

P

j

t Vi

P

id

h

t

tf li

th t

Project Vice-Presidency has to manage a portfolio that

includes approximately 30 studies and projects, totalling US$

2.273 billion, that will have a positive impact on all Codelco

divisions.

Implement projects within deadline, budget and quality

p

p

j

g

q

y

standard,

and,

particularly,

prevent

serious

accidents

occurring.

Complex scenario: Simultaneous projects at Codelco and

in the mining industry; high demand for professionals,

engineering services and supplies; increase in project costs

engineering, services and supplies; increase in project costs

and risk of unexpected events

(10)

CHALLENGES TO VP INVESTMENT PLAN 2012

MINISTRO HALES

Total Investment 2012

US$ 1.145 Bn

Total Investment 2012

US$ 1.145 Bn

Start all Construction Contracts

1Q 2012

CHUQUICAMATA UNDERGROUND MINE

Total Investment 2012

US$ 234 M

Total Investment 2012

US$ 234 M

Complete Basic Engineering

4Q 2012

(11)

CHALLENGES TO VP INVESTMENT PLAN 2012

ANDINA EXPANSION 244

T t l I

t

t 2012

US$ 86 M

Total Investment 2012 US$ 86 M

•API (Investment Project Approval) issued End of 2012

NEW MINE LEVEL– EL TENIENTE

Total Investment 2012 US$ 399 M

Complete Emergency Ramp

2Q 2012

(12)

CHALLENGES TO VP INVESTMENT PLAN 2012

RT SULPHIDE MINE - PHASE II

T t l I

t

t 2012

US$ 73 M

Total Investment 2012

US$ 73 M

Development of Feasibility Stage

2012

SAN ANTONIO OXIDES

Total Investment 2012

US$ 57 M

Start of Investment Implementation Stage 3Q 2012

(13)

BUSINESS & DEVELOPMENT PLAN 2012

Copper Output (

Thousands of Mtf.)

close ENMS Close RT Oxides Close Chuqui Open Close Salvador Oxides

Sur Open Pit

San Quetena NEW MINE ANDINA 244 MH San Antonio RT Phase II LEVEL CHUQUI UNDER

(14)

CODELCO’S OUTPUT EVOLUTION

(Thousands of Mtf )

(Thousands of Mtf.)

History

Projection

With

Projects

Without

Projects

Note:

Includes Codelco’s 49% stake in El Abra.

Projection Source:

2011: Budget 2012: Triennial Plan proposed to Ministry of Finance and Ministry of Mining.

2020: Business & Development Plan (PND) 2011 & Non Development Plan (PSD) 2011 and SCM El Abra

2020: Business & Development Plan (PND) 2011 & Non-Development Plan (PSD) 2011, and SCM El Abra.

References

Related documents

Pollen (gametophytic) selection for resistance to aflatoxin in corn can greatly facilitate recurrent selection and screening of germplasm for resistance at a much less cost

Comparing the power consumption of the processor core itself to the power consumed by the local instruction and data memory, it can be seen that nearly 80% of the total power is

Great Ocean Road Tours Yarra Valley Tour Phillip Island Tour Grampians Tour. Book any 2 tours

Romberg and Hass define the pre-series logistics as an "already series process close department with the tasks to ensure the technical quality of components from

From recent workshop discussions in the Ministry of Education, Sport, Arts and Culture and Ministry of Higher and Tertiary Education (2014) on inclusive education,

This study seeks to introduce the software approach towards the development of a model that can be adopted especially in other polytechnics and higher institutions in

 The maximum penetration of 3.64 mm, minimum weld width of 3.76 mm, as well as angular distortion of 0.76°, is obtained at optimized parameters of current 140 A, welding speed

Ao contrário do que ocorre no discurso de Anfion na peça de Eurípides, não mais a vida intelec- tual, a música e o prazer estão conectados; Cálicles, se ainda defende