• No results found

Infrastructure costs

N/A
N/A
Protected

Academic year: 2021

Share "Infrastructure costs"

Copied!
14
0
0

Loading.... (view fulltext now)

Full text

(1)

HEATCO Workshop

Infrastructure costs

Thomas Odgaard

Karsten Sten Pedersen

(2)

Infrastructure costs

Issues of infrastructure costs

y Capital costs for the infrastructure project

y Residual value y Optimism bias y Running costs:

– Costs for maintenance, operation and administration – Changes in infrastructure costs on existing network

(3)

Capital costs for the infrastructure

project

Definition

y Construction costs, including materials, labour, energy, preparation, professional fees and contingencies

y Planning costs, including design cost, planning authority

resources and other costs incurred after the decision to go ahead

y Land and property costs, including the value of the land needed for the scheme (and any associated properties), compensation payment necessary under national laws and the related

transactions and legal costs

y Disruption costs, i.e. the disruption to existing users to be

estimated using the same values of time as are used for travel time savings arising from the scheme.

(4)

Capital costs for the infrastructure

project

Two general principles

y Costs should be attributed to the project year in which the resources become unavailable to alternative uses

y It is necessary to distinguish between

– Costs incurred before and after the decision whether to go ahead with the project or not

– Retrievable and non-retrievable costs

More details on how to treat each of the four elements are given in the text

(5)

Residual value (I)

Background

y An item which captures net benefits beyond the formal evaluation period

y The residual value is often of relatively little importance

Recommendation

y Pragmatic approach (2 elements)

– Fixed lifetime of the infrastructure (or its sub-components) – Linear depreciation profile

(6)

Residual value (II)

Lifetimes by mode and group of components (example: road)

If lifetimes outside these ranges are used, it has to be explicitly stated why such an approach is taken

Group of components Min Main Max

Base course 30 45 60 Wearing course 10 20 30 Environmental installations 10 20 30 Drainage 50 75 100 Retaining walls 50 75 100 Bridges 50 75 100 Tunnels 50 75 100

(7)

Optimism bias (I)

Tendency to underestimate construction costs

y Cost escalation occurs in almost nine out of ten projects

y Actual costs on average are 28% higher than estimated/forecast

costs

(8)

Optimism bias (II)

Ideas to reduce uncertainty/cures to optimism-bias

Guidelines Process Organisation of risk/

uncertainty

Benchmark projects Independent reviews Change incentive structure

Use reference class

forecasting Engage stakeholders etc. Make forecasters share financial responsibility Make all information

publicly available Make go-ahead contingent on private risk capital

Make sure guidelines are applied consistently

across member states

In PPPs, make size of subsidy dependent on accuracy of forecasts

(9)

Optimism bias (III)

Recommendation

y Make side-analysis, where optimism-bias uplifts are applied

y If feasible -> Continue appraisal y If not feasible

1. Benchmark cost estimates to realised costs of similar projects 2. Justify why cost estimates are lower

3. Revise construction cost estimate

Why 'only' side analysis?

y Complex issue

(10)

Optimism bias (IV)

(11)

Optimism bias (V)

Applicable uplifts Category Uplift Roads 22% Fixed links 43% Rail 34% Building projects 25% IT projects 100%

(12)

Running costs (I)

Two elements

y Costs for maintenance, operation and administration

y Changes in infrastructure costs on existing network

Complex task to give recommendations, as the countries have different

y Standards of infrastructure, composition of traffic, maintenance

practice, approaches to cost accounting, climate and topographical conditions, etc.

(13)

Running costs (II)

Recommendation

y First best

– Use national default values (check applicability) – Available for road in 50% of countries

(14)

Running costs (III)

y Second best (2 steps)

1. Distinction between fixed and variable costs

y National accounts/statistics

y General classification of cost categories into "fixed" and "variable"

2. Allocation of variable costs to cost drivers

– Two simplifying assumptions

– The marginal costs per vehicle can be approximated by the average variable costs

– Average variable costs/marginal costs are constant (and not for instance increasing with traffic

– Allocation factors:

– Weight dependent (ESA) – Non-weight dependent (vkm)

References

Related documents

1) Informing the students properly in the campus and at the university level and describing the advantages of internet evaluation by authorities responsible for evaluating

significance. Methods employed to engage the Keweenaw community are also presented in this chapter. A grassroots outreach strategy focused on education and interpretative programs

As a result, the main argument of the study is that a contextual interpretation of the SOM, using Jesus’ authoritative reinterpretation as hermeneutical key, clarifies the

A point was made by several delegates to the October 2013 course and by some LSS staff that the recent changes in format and delivery of PEAT 1 and PEAT 2 3 , with concentration on

However, if findings cannot be ascribed to normal variation of BPE and there is a question about whether observed enhancement could be transient and related to the hormonal status

If the agency requests memory above the standard, the Commonwealth will be responsible for the full cost of the replacement memory, installation charges, maintenance costs in

Start Free Trial Cancel Anytime... Trusted by over 1 million members. Try Scribd FREE for 30 days to access over 125 million titles without ads