Presented by

The University of Arizona

Financial Services Office

© Copyright by the University of Arizona, Financial Services Office, 2004. This work is the intellectual property

of the author. Permission is granted for this material to be shared for non-commercial, educational purposes,

provided that this copyright statement appears on the reproduced materials and notice is given that the copying

is by permission of the author. To disseminate otherwise or to republish requires written permission from the

"Do It Yourself"

Project Portfolio Management

(2)
(3)

Here’s a snapshot of the FSO Projects website. The left-hand side of the screen lists the status of the

projects for each major phase: (1) Phase 1: Initiation and Assessment; (2) Phase 2: Business Analysis;

(3) Phase 3: Development/Beta Testing; (4) Phase 4: Pilot Testing/Deployment; (5) Phase 5: Tracking.

(4)
(5)

Phase 1: Initiation & Assessment

Preliminary Survey & Assessment Questionnaire

SECTION 1 – BUSINESS FACTORS

1.

Describe the business problem(s) that motivated you to initiate this request.

Answer

2.

Describe the current business process.

Answer

3.

Describe your vision of how the new business process would look.

Answer

4.

What would happen if the current process did not change? Will the job still get done?

Answer

5.

Scale of Customer Impact - FSO has two groups of customers: (1): internal customers (faculty,

staff, and UA administration) and external customers (students, parents, sponsors, banks,

vendors, etc.). Here we will measure how many customers (staff, faculty, students, UA

administration, banks, vendors, etc.) will be affected by the project. List all customers that will

be affected. If this project only affects FSO, list the specific units/departments.

Check only one Description

The project will not affect any customers. The project will affect one of our customers. The project will affect two of our customers. The project will affect three of our customers. The project will affect most of our customers. The project will affect all of our customers.

Notes/Comments:

6.

Operational Efficiencies (OE) - Here we will measure how much personnel time, operating

resources and/or pure $$$ this project may gain us.

One of FSO's core values is to improve

efficiencies by reducing the amount of time, money or resources it takes to do a job, so that

efforts can be directed towards providing exceptional financial services. Describe any efficiency

this project will create.

Check only one Description

(6)

The project will moderately improve operational efficiencies.

The project will significantly improve operational efficiencies.

Notes/Comments:

7.

eBusiness Match - (Optional during PSA Phase) - We want to measure how much this project

will move us toward our strategic goal of eBusiness (self-service, web-enabled processes).

Describe how this project can help us achieve this goal.

Check only one Description

The project has NO direct or indirect relationship to the achievement of eBusiness. The project has no direct relationship to eBusiness, but the project is a prerequisite system (precursor) to another system that achieves eBusiness.

The project directly achieves a portion of eBusiness. The project directly achieves eBusiness.

Notes/Comments:

8.

Enhanced Entity Relationships (EER) – (Optional during PSA Phase) – FSO has a strategic

direction of improving working relationships within FSO, the University and our community.

Relationships can be defined as creating data access or interchanges. How does solving this

business problem help enhance FSO’s working relationships?

Check only one Description

The project does not create data access or interchange between FSO and its customers and other FSO units.

The project does not create data access or interchange between FSO and its customers and other FSO units, but does improve operating efficiencies in other units (outside FSO) that bear on enhancing FSO’s reputation.

The project does not create data access or interchange between FSO and its customers and other FSO units, but does improve operating efficiencies in a key strategic area within the University.

The project provides some degree of data access or interchange between FSO and its customers and/or FSO units and moderately improves FSO’s relationship with its stakeholders.

The project provides a moderate degree of data access or interchange between FSO and its customers and/or FSO units and substantially improves FSO’s relationship with its stakeholders by providing an outstanding level of service.

The project provides a high degree of data access or interchange between FSO and its customers and/or FSO units and greatly improves FSO’s relationship with its

stakeholders by providing an unmatched level of service by other financial services in higher education.

Notes/Comments:

9.

Management Information - FSO has a goal of providing any level of management with reports

for planning, monitoring, and controlling business operations related to FSO core activities such

as managing fund receipts and disbursements and accounting of financial activities. Does this

proposal directly contribute to any level of management's need for information? If yes, please

specify what level of management and describe how this project will accomplish that goal?

(7)

Check only one Description

The project is unrelated to management information support of core activities. The project is unrelated to mid-level management's need for information but does provide information on functions that directly support core activities in FSO. (Mid-level mgt. includes fund accountants, FSO supervisors, and department heads/business managers.)

The project is related to mid-level management's need for information of core activities. (See description of mid-level management above.)

The project is essential to providing upper-level management information support of FSO core activities. (Upper-level mgt. includes FSO executive team, UA executive level, and UA vice presidents, deans, and directors.)

Notes/Comments:

10.

Legislative/Standard Policy Implementation/Critical Service Element (LSPI/CSE) – FSO must

prioritize projects that are required by policy or legislation. Here we measure how much

legislative, standard policy, or critical service element this project has. Describe how much this

project implements a policy change or has an impact on other projects that implement a policy

change.

Check only one Description

The project has no relationship to the implementation of any type of legislation, policy, or any identifiable critical service element.

The project is a prerequisite system to another system that will help reduce the future risk of disrupting FSO-related service or activity.

The project is a prerequisite system to another system that will help implement a legislative or standard policy.

The project has an identifiable critical service element in which, if implemented, will help reduce the future risk of disrupting FSO-related service or activity.

The project has an identifiable critical service element in which, if implemented, will help reduce the present risk of disrupting FSO-related service or activity.

The project will help implement a legislative or standard policy.

(8)

SECTION 2 – TECHNICAL FACTORS

11. Strategic IS Architecture – Strategically we are moving to the web as our IS Architecture, some projects

must still be done in the mainframe environment so a NO answer is fine here. Is this project doable as a

web application (Check one)?

Check only one Description

The proposed project is unrelated to the e-business architecture.

The proposed project is a part of the e-business architecture, but not well-defined.

The proposed project is a part of the e-business architecture; it is not a prerequisite to other e-business projects, nor is it closely linked to other prerequisite projects.

The proposed project is an integral part of the e-business architecture, and is one that is to be implemented first; it is a prerequisite project to other e-business projects.

Notes/Comments:

12. Definitional Certainty – Here we want to measure how well-defined the business requirements and the

project specifications are. (Check one below, add notes if you like). This affects the confidence levels for

the time answers on #15.

Check only one Description

Business requirements unknown. Specifications unknown. Area may be quite complex. Changes may be ongoing, but the key here is unknown requirements.

Business requirements not firm. Specifications not firm. Area is quite complex. Changes are almost certain, even during the project period.

Business requirements moderately firm. Specifications moderately firm. Investigated area is straightforward. Changes are almost certain almost immediately.

Business requirements moderately firm. Specifications moderately firm. Investigated area is straightforward. Reasonable probability of nonroutine changes.

Business requirements moderately firm. Specifications moderately firm. Investigated area is straightforward. Low probability of nonroutine changes.

Business requirements moderately firm. Specifications moderately firm. Investigated area is straightforward. High probability of no changes.

(9)

13. Technical Certainty - Here we want to measure how extensive the skill requirements are and how

technologically equipped we are for tackling this project. We will measure 4 areas:

a.

Skills required are available in the technology domain.

b.

Dependency on specific hardware not now available

c.

Dependency on software capabilities not now available

d.

Dependency on application software development

a) Skills required in the technology domain: (Check one)

Check only one Description

Extensive (new) skills required for staff and management. Extensive (new) skills required for staff, some for management. Some new skills required for staff, extensive for management. Some new skills required for staff and management.

Some new skills for staff, none for management.

No new skills for staff, management. Both have experience.

Notes/Comments:

b) Dependency on specific hardware not now available: (Check one)

Check only one Description

Key requirements are not now available in MIS configuration. Some key features are not tested or implemented.

Hardware exists, but not utilized yet within organization. Hardware exists and has been tested, but not operationally. Hardware is in use, but this is a different application. Hardware is in use in similar application

Notes/Comments:

c) Dependency on software capabilities not now available: (Check one)

Check only one Description

Significant advance in state of the art is required.

Features not now supported are needed, and moderate advance in local state of the art is required.

Some new features are required in operating software; some complex interfaces between software may be required.

Some new interfaces between software are required, and complex programming may be required.

Standard software is used, but complex programming is required. Standard software, or straightforward or no programming required.

(10)

d) Dependency on application software development: (Check one)

Check only one Description

No package or current in-house software exists. Complex design and programming are required, even if contracted outside.

No package or current in-house software exists. Complex design and programming are required, with moderate difficulty.

Software is available commercially but the complexity is high, or software will be developed in-house and the difficulty is moderate.

Programs are available commercially with moderate modifications, or programs available in-house with extensive modifications, or software will be developed in-house with minimal design complexity but moderate programming complexity.

Programs are available commercially with minimal modifications, or programs available in-house with moderate modifications, or software will be developed in-house with minimal complexity.

Programs exist with minimal modifications required.

Notes/Comments:

14. IS Infrastructure Risk Management - Here we are measuring the impact of this project to existing

computer service delivery and additional investment from the FSO ITS unit, not included in the direct

project cost.

Check only one Description

Substantial change in elements of computer service delivery is required, in multiple areas. Considerable up-front investment in staff, software, hardware, and management is necessary to accommodate the project. This investment is not included in the direct project cost, but represents IS facilities investment to create the needed environment for the project.

Moderate change in elements of computer service delivery is required, in multiple areas. Moderate to high up-front investment in staff, software, hardware, and management is necessary to accommodate the project. This investment is not included in the direct project cost, but represents IS facilities investment to create the needed environment for the project.

Moderate changes in several elements of the computer service delivery system are required. Some up-front investment is necessary to accommodate this project. Some later investment for subsequent integration of this project into the mainstream of the IS environment may be necessary.

Small changes in several elements of the computer service delivery system are required. Some up-front investment is necessary to accommodate this project. Some later investment for subsequent integration of this project into the mainstream of the IS environment may be necessary.

Change in one element of the computer service delivery system is required for this project. The associated up-front investment other than direct project costs is relatively small.

The system uses existing services and facilities. No investment in IS prerequisite facilities (e.g., database management) is required; no up-front costs that are not directly a part of the project itself are anticipated.

(11)

SECTION III – TIME FACTOR

15. If you had nothing else to do, how many work hours would it take to do this? How many people would

it take? Break this down into project subcomponents if possible and. Measure each subcomponent -

high, medium, low and then a confidence percentage.

Project Sub-component

(Will vary by project – you

define the subcomponents)

Size

In Your Estimate

Confidence

In your Estimate

†

Big - Months

†

Medium-Large - > 2 Weeks

†

Medium – 5 – 10 Working Days

†

Small - 3-5 Working Days

†

Quick - 2 Days or Less

†

100%

†

90%

†

75%

†

50%

†

25%

†

Big - Months

†

Medium-Large - > 2 Weeks

†

Medium – 5 – 10 Working Days

†

Small - 3-5 Working Days

†

Quick - 2 Days or Less

†

100%

†

90%

†

75%

†

50%

†

25%

†

Big - Months

†

Medium-Large - > 2 Weeks

†

Medium – 5–10 Working Days

†

Small - 3-5 Working Days

†

Quick - 2 Days or Less

†

100%

†

90%

†

75%

†

50%

†

25%

†

Big - Months

†

Medium-Large - > 2 Weeks

†

Medium – 5–10 Working Days

†

Small - 3-5 Working Days

†

Quick - 2 Days or Less

†

100%

†

90%

†

75%

†

50%

†

25%

†

Big - Months

†

Medium-Large - > 2 Weeks

†

Medium – 5–10 Working Days

†

Small - 3-5 Working Days

†

Quick - 2 Days or Less

†

100%

†

90%

†

75%

†

50%

†

25%

†

Big - Months

†

Medium-Large - > 2 Weeks

†

Medium – 5–10 Working Days

†

Small - 3-5 Working Days

†

Quick - 2 Days or Less

†

100%

†

90%

†

75%

†

50%

†

25%

Notes/Comments:

(12)
(13)
(14)
(15)
(16)
(17)
(18)
(19)

Sample TAB – PSA Prioritization Scorecard

References