• No results found

5.0 Reference: Application, Volume I, Chapter 5, Heritage Contract

N/A
N/A
Protected

Academic year: 2021

Share "5.0 Reference: Application, Volume I, Chapter 5, Heritage Contract"

Copied!
7
0
0

Loading.... (view fulltext now)

Full text

(1)

5.0 Reference: Application, Volume I, Chapter 5, Heritage Contract

1.5.30 Page 5-27: Provide a comprehensive explanation of the application of the Equipment Health Rating process to transformers and generators and provide examples of the output and how it has been used.

RESPONSE:

Equipment Health Rating (EHR) is an objective, repeatable equipment health evaluation system. EHR enables comparison of the health of BC Hydro generation assets. EHR has been developed to evaluate the following types of equipment: generators, exciters, turbines, governors, unit circuit breakers, unit transformers and coatings. Evaluation of the health criteria and test and inspection data is completed by a team of asset specialists.

The EHR system uses test and inspection data and other information to determine the condition or health of assets. The result is a technical evaluation of the asset resulting in a letter grade; Good, Fair, Poor, Unsatisfactory (G,F,P,U), as follows:

Good no noticeable deterioration/defects;

Fair some deterioration/defects exist (function not affected);

Poor serious deterioration/defects exist in at least some portions

of the asset (function affected); and

Unsatisfactory extensive deterioration/defects (no longer functions as

required).

In addition, the EHR process includes a "technical prescription" which is BC Hydro's asset specialists' recommendations on what needs to be done to restore the asset to “Good” condition, including a cost estimate and time period in which the work should be completed. This identifies future expenditures.

The technical prescription details the following:

• What? the intervention recommendation (e.g. replacement);

• When? the intervention timing (e.g. 2 to 5 years);

• Cost? a budget estimate of the intervention cost;

• How Long? an estimate of the time required to implement the intervention; and

(2)

The EHR results, along with economic, environmental and social risks are used to assess and prioritize investments. The Latent Risk Matrix shown below is used as a tool for investment prioritization.

(3)
(4)

The following examples illustrate the application of EHR for:

GM Shrum unit transformers; and

Mica generators.

Example 1. GM Shrum Unit Transformers

The EHR for assessing the condition of transformers includes the following criteria, and test and inspection data:

1. Age

2. Condition Index Tests and Inspections

Gas in Oil Analysis

Winding Insulation Megger Reading

Winding Doble Power Factor Reading

Furan Analysis

Moisture Content.

Bushing Doble Power Factor Test.

Insulating Oil kV Breakdown

Insulating Oil Power Factor (100 deg C)

Insulating Oil Interfacial Tension

Insulating Oil Moisture Content.

Tank Surface Defects and Leaks

3. Known Problems

The results for GM Shrum T1 B-Phase Unit Transformer are as follows:

1. Age

The transformer is approximately 35 years old.

2. Condition Index Tests and Inspections

The Gas in Oil Analysis indicates that the transformer paper insulation is overheating leading to premature failure.

The Bushing Doble Power Factor Test indicates that the high voltage C1 bushing power factor is high indicating that insulation has deteriorated reducing the overall transformer performance.

The Furan Analysis indicates that the paper insulation is ageing.

The Moisture Content tests were not conclusive, indicating uncertainty with this particular test.

(5)

3. Known Problems

This transformer suffers from a severe known problem of low voltage lead overheating.

As a result, the most significant health measures indicated that the transformer is in "Unsatisfactory" condition and the technical prescription included a recommendation to replace the transformer. Replacement of the GM Shrum unit transformers rated "Unsatisfactory" is in progress.

Example 2. Mica Generators

The Equipment Health Rating for assessing the condition of generators includes the following criteria, and test and inspection data:

1. Forced Outages

2. Condition Index Tests and Inspections

Stator Winding Insulation Resistance and Polarization Index Test

Stator Winding High-Voltage Direct-Current Step Test

Stator Winding Partial Discharge Test

Rotor Winding Insulation Resistance and Polarization Index Test

Rotor Pole Drop Test

Stator Winding, Core and Support Inspection

Rotor Winding, Core and Support Inspection 3. Trends of Condition Index Tests and Inspections 4. Age compared to industry life expectancy

5. Design

6. Spare Parts Availability 7. Technical Support 8. Safety

(6)

The results for Mica Unit 4 Generator are as follows:

1. Forced Outages

Mica Unit 4 has suffered four significant forced outages primarily due to core related problems. In particular, moving laminations cut into the stator winding insulation causing failures. On a number of occasions similar problems were discovered during inspections and were repaired prior to a failure occurring.

2. Condition Index Tests and Inspections

Stator Winding High-Voltage Direct-Current Step Test results identify

weaknesses in the stator winding insulation system. The winding insulation system has failed during tests because of weakness caused by moving laminations.

Stator Winding Partial Discharge tests show that the stator winding

continues to age at a faster than normal rate.

Rotor tests show that the rotor is considered to be in acceptable and

expected condition for its age and operation.

Inspection of the stator core studs since commissioning has revealed

core waves and lamination movement. A core stud was found to be broken during a routine maintenance inspection. Subsequent tests devised by Powertech Labs have identified and quantified core stud cracking. The stud cracking is a considered to be a significant problem and is caused by fatigue.

Unit G4 also has a particular problem with the lower stator core

laminations migrating radially inward cutting into the winding insulation.

4. Age

The generator was commissioned in 1977.

5. Design

Stator core waves, lamination movement, and stud cracking are directly related to the generator design. This was verified by the Mica Stator Advisory Board Report dated 04 Dec 2003.

As a result, the most significant health measures indicated that the generator is in "Unsatisfactory" condition and the technical prescription included a recommendation to replace the generator stator.

(7)

The replacement of Mica Unit 4 Stator is listed in Chapter 11, Page 12, Table 11-4. Note that the reference in the table is incorrectly labelled as “Mica Units 1 to 4 Stator Replacement” instead of “Mica Unit 4 Stator Replacement”.

References

Related documents

2) that Britain - London particularly - occupied a special place in any negotiations / confrontations that took place on the religious question. After all, back in Japan, the British

Note: If you receive a call from someone claiming to be from First Trust Merchant Services or an engineer asking you to manually key in card details into a Terminal, please contact

ره لاس ه رد سرادم و هاگشناد اه ي يمسر دنليات ماجنا يم يگ .در نيا مسارم زا لاس 4951 زا هديا يقاب هدنام كي ملعم سپ زا گرم ( هب مان Canbe ) ب ه ناونع

Stubb’s observations of Queequeg and Pip in “The Doubloon” additionally raise questions of interpretation directly linked to Ishmael and Ahab, and so I will begin by

(1) When applying our method to Haskell source code that contains a single type error; Do we show improvement in locating the errors compared to the Glasgow Haskell Compiler.. The

But instructional leadership and social justice leadership dimension were selected based on the perceived relevance to the context of this study in Trinidad and Tobago, where

· National Pension Fund Association, Overview of Japanese Individual Defined Contribution Plan (http://www.npfa.or.jp/401K/status/). · Ministry of Economy, Trade and Industry,

Maximum possible Java heap sizes The “correct” Java heap size. Fixed heap