Capital Projects Report. December 18, 2018

N/A
N/A
Protected

Academic year: 2021

Share "Capital Projects Report. December 18, 2018"

Copied!
14
0
0

Loading.... (view fulltext now)

Full text

(1)
(2)

Capital Plan Progress Highlights

The construction for Sci-High is ahead of schedule with major demolition of

the existing building complete and pile driving almost complete.

McMain Envelope Repair phase one thru three have been completed, with

the exterior repair and painting proceeding on schedule. Subsequent

phases are anticipated to reduce in duration with project completion in the

3

rd

quarter of 2019.

Hynes ES envelope repair was awarded with a notice to proceed on

12/17/18.

Ben Franklin phase II is scheduled to begin on 1/2/19.

(3)

DBE Participation (Committed)

Project

Contract Value

Current DBE

Participation Value

% of DBE

Participation

# DBE Vendors

Ben Franklin Elementary School –

Refurbishment: Phase 1

$ 1,980,000

$ 700,000

35.35%

1

McMain High School – Building

Envelope

$ 3,540,000

$956,300

27.01%

6

New Orleans Charter Science and

Math High School – New

Construction

$ 27,496,000

$8,993,875

32.71%

15

Douglass Gymnasium - Renovation

$ 490,000

$ 174,000

35.51%

5

Mahalia Jackson Child Center –

Reconfiguration – Phase 1

$ 150,000

$68,400

45.6%

2

Mahalia Jackson Child Center –

Reconfiguration – Phase 2

$ 113,372

$80,532

71%

2

Rosenwald Response Action

$1,296,772

$336,720

34.97%

3

Hynes Elementary Exterior

Envelope

$ 422,500

$ 165,000

39.05%

3

(4)

Funding Overview

4

Eligible/Approved/Reimbursed To Date (thru 8/2018)

$ 311,091,445.98

Eligible Expenditures/Reimbursement Submissions Under

Review

$ 2,811,886.62

Follow-Up on Eligible Executed Work and Execution of Remaining

Eligible Work (Includes contents to be purchased for the new Karr

HS and the new New Orleans Charter Science and Math High

School)

$ 61,063,709.38

(5)

Project Summary

Project

Current

Budget

Construction

Complete

Ben Franklin Elementary School – Refurbishment:

Phase 1

$ 7,665,367

(pending Board

approval)

December 2018

Ben Franklin Elementary School – Refurbishment:

Phase 2

July 2019

Hynes Elementary School – Envelope Repair

$ 423,000

February 2019

Karr High School – New Construction

$ 49,549,591

July 2020

McMain High School – Building Envelope

$ 5,148,000

August 2019

New Orleans Charter Science and Math High School

(6)

6

Ben Franklin Elementary School – Refurbishment Phase 1

Project Information

Owner: Orleans Parish School Board Project Status: Construction

Funding Source: Bonds

Architect: NY Associates, Inc.

Contractor: Construction Masters, Inc.

Scope of Work

Refurbishment of existing elementary school

Asbestos & lead paint abatement, window refurbishment Brick repair & refurbishment

Interior demolition as needed for structural investigation & inspection

Project Status

Abatement complete, window refurbishment 99% complete. Brick repair & lintel repair are ongoing.

Budget/Cost Information Phases 1 & 2

Current Budget Projected Costs Projected Over/Under

$ 7,665,367 (pending Board approval)

$ 7,665,367 $ 0

Schedule Status

Task Planned Adjusted Actual

Design April 2014 --- May 2017 Procurement March 2015 --- September 2017 Construction

Complete

December 2018

---DBE Participation (Committed)

Contract Value Current DBE Participation Value

% of DBE Participation

# of DBE Vendors

(7)

Ben Franklin Elementary School – Refurbishment Phase 2

Project Information

Owner: Orleans Parish School Board Project Status: Procurement

Funding Source: Bonds

Architect: NY Associates, Inc. Contractor: TBD

Scope of Work

Refurbishment of existing elementary school

Site work, ADA compliance, ceiling replacement, new elevator Floor repairs, update HVAC, sprinkler system & fire alarm

Project Status

Project bid in November 2018. Board approval in 12/2018. Notice to Proceed will be given 1/2/2019.

Budget/Cost Information Phases 1 & 2

Current Budget Projected Costs Projected Over/Under

$ 7,665,367 (pending Board approval)

$ 7,665,367 $ 0

Schedule Status

Task Planned Adjusted Actual

Design October 2018 --- ---Procurement November 2018 --- ---Construction

Complete

July 2019 ---

---DBE Participation (Committed)

Contract Value Current DBE Participation Value

% of DBE Participation

# of DBE Vendors

(8)

8

Hynes Elementary School – Exterior Envelope Repair

Project Information

Owner: Orleans Parish School Board Project Status: Construction

Funding Source: FEMA/Capital Projects Architect: SCNZ

Contractor:

---Scope of Work

Repair of building envelope due to water infiltration

Project Status

Board approved contract at November Board Meeting. Notice to Proceed was given 12/17/2018.

Budget/Cost Information Phases 1 & 2

Current Budget Projected Costs Projected Over/Under

$ 422,500 $ 422,500 $0

Schedule Status

Task Planned Adjusted Actual

Design February 2018 August 2018 August 2018 Procurement October 2018 --- ---Construction

Complete

February 2019 ---

---DBE Participation (Committed)

Contract Value Current DBE Participation Value

% of DBE Participation

# of DBE Vendors

(9)

McMain High School – Building Envelope

Project Information

Owner: Orleans Parish School Board Project Status: Construction

Funding Source: FEMA

Architect: Concordia, LLC Contractor: Tuna Construction

Scope of Work

Refurbishment of building envelope (excluding roof)

Including but not limited to windows, doors, stucco, and painting

Project Status

Phases 1 – 3 are complete. Exterior repair and painting ongoing.

Budget/Cost Information Phases 1 & 2

Current Budget Projected Costs Projected Over/Under

$ 5,148,000 $ 4,635,866 ($ 512,134)

Schedule Status

Task Planned Adjusted Actual

Design March 2018 --- March 2018 Procurement May 2018 June 2018 June 2018 Construction August 2019

DBE Participation (Committed)

Contract Value Current DBE Participation Value

% of DBE Participation

# of DBE Vendors

(10)

10

New Orleans Charter Science & Mathematics High School –

New Construction

Project Information

Owner: Orleans Parish School Board Project Status: Construction

Funding Source: FEMA/Bonds/Capital Projects Architect: Verges Rome

Contractor: McDonnel Group

Scope of Work

Demolition of Wicker Elementary School Construction of a new high school

Project Status

Groundbreaking was held on 11/7/2018. Major demolition is complete. Test piles are almost complete.

Budget/Cost Information Phases 1 & 2

Current Budget Projected Costs Projected Over/Under

$ 36,137,138 $ 33,884,511 ($ 2,252,627)

Schedule Status

Task Planned Adjusted Actual

Design April 2018 --- April 2018 Procurement May 2018 August 2018 August 2018 Construction December 2020

---Move-In April 2021

---DBE Participation (Committed)

Contract Value Current DBE Participation Value

% of DBE Participation

# of DBE Vendors

(11)

Karr High School – New Construction

Project Information

Owner: Orleans Parish School Board Project Status: Construction

Funding Source: FEMA

Architect: Trapolin Peer Architects, APC

Contractor: Core Construction Services, LLC - CMAR

Scope of Work

Construction of new high school – Construction Manager at Risk

Project Status

Grade beam and slab pours are underway. Steel deliveries are underway and structural steel and decking are being set. Framing contractor is scheduled to mobilize during November.

Budget/Cost Information Phases 1 & 2

Transferred Projected Costs Projected Over/Under

$ 49,782,165 $ 48,773,696 ($1,008,469)

Schedule Status

Task Planned Adjusted Actual

Design November 2017 March 2018 March 2018 Procurement January 2018 March 2018 March 2018 Construction July 2020 ---

(12)

---12

RSD: Booker T. Washington - New

Project Information

Project Control: Recovery School District Project Status: Construction

Funding Source: FEMA

Architect: Hewitt Washington & Associates

Contractor: Core Construction Services, LLC - CMAR

Scope of Work

Construction of a New High School Restoration of existing Auditorium

Project Status

Installation of interior finishes is underway. Casework is being installed. Installation of storm-water retention structure is in progress. Installation of brick on facades of the Auditorium building is beginning.

Budget/Cost Information Phases 1 & 2

Current Budget Projected Costs Projected Over/Under

$70,329,905 $67,380,498 ($2,949,407)

Schedule Status

Task Planned Adjusted Actual

Design --- --- December 2017 Procurement --- ---

---Construction January 2019 May 2019

(13)

---RSD: Cohen High School - New

Project Information

Project Control: Recovery School District Project Status: Design

Funding Source: FEMA

Architect: HMS Architects Contractor: TBD

Scope of Work

Construction of a New 110,000 square foot high school. Once the Charter has moved into the new building, the current building will be demolished.

Project Status

Educational Specification development and review with New Orleans College Prep staff is underway.

Budget/Cost Information Phases 1 & 2

Current Budget Projected Costs Projected Over/Under

$32,664,263 $30,244,688 ($2,419,575)

Schedule Status

Task Planned Adjusted Actual

Design August 2019 --- ---Procurement --- --- ---Construction October 2021 ---

(14)

---14

RSD Capital Project Summary

Planning/Design:

CTE High School, CMAR

New Cohen High School, CMAR

Behrman Elementary

Lafayette Elementary

Construction:

New Karr High School, CMAR

Booker T. Washington High School, CMAR

First Year of Occupancy:

John McDonogh High School Renovation, CMAR

Harriet Tubman Elementary School Renovation

Thurgood Marshall Elementary

Refurbishment

Fisk Howard Exterior Envelope Repairs

McDonogh #28 Flooring

McDonogh #32 Refurbishment

Harriet Tubman School Cottage

Schaumburg Elementary Roof Repairs

Village de-l’Est & Sarah T. Reed HVAC and Fencing