• No results found

Preparing the Work Area

N/A
N/A
Protected

Academic year: 2021

Share "Preparing the Work Area"

Copied!
90
0
0

Loading.... (view fulltext now)

Full text

(1)

Preparing the Work Area

(2)

Work Area Preparation

¾ Objectives of Work Area Prep

¾ Sequence and Methods for Prep

¾ Engineering Controls:

¾ Negative Pressure Requirements, Equipment

and Set-up

(3)

Purpose of Area Prep

¾ To protect the people outside the work area from asbestos exposure

¾ To protect the building surfaces and fixtures from asbestos contamination and water damage

¾ To confine the airborne asbestos within

the work area

(4)

Work Area Prep

¾Improper prepping will result in

• Damage to surfaces; wall, floors, fixtures etc.

• Additional expense and work to the contractor

• Delays that will affect the entire job timeline

• Possibly contaminating the area outside of

the work area

(5)

Work Area Prep

¾ Guidance for prepping

z Specifications

z “Specs” are not a guideline…they are part of a contract. They have to be followed

z Consultant

z May make recommendations to assist in meeting the specs

z Regulations

z Federal, State and City regulations have

particular sections that affect work area prep

z More experienced persons

z An experienced Supervisor makes prep work go

much easier

(6)

Materials

¾ Polyethylene (poly)–6 mil (Fire retardant for NYSDOL)

¾ Duct tape

¾ Spray adhesive

¾ Furring strips or wood blocks

¾ Tools

¾ OSHA DANGER SIGNS

(7)

Prep Materials

The Basics:

6 mil poly Duct tape, heavy duty, 4-6” wide Spray glue OSHA

required

danger signs

(8)

Prep Materials

Reinforced 10 mil poly for high durability

(9)

WORK AREA

PREPARATION STEPS

The following is a guideline listing the order of the required components of work area

preparation. The regulation requirements may only be modified after filing for and receiving a variance for each change.

NYCDEP and NYSDOL require that the

worker Decon unit be constructed first and

have it fully functional prior to preparing the

work area.

(10)

WORK AREA

PREPARATION STEPS

1.- “Notice Of Asbestos Abatement” Sign (Building Occupant Notice)

2.- Vacate Work Area and Restrict Entry 3.- Post Warning Signs

4.- Build Worker and Waste Decons

5.- Shutdown and lock out of electric power

6.- Shut Down the Heating, Ventilation, and Air-

Conditioning System (HVAC)

(11)

WORK AREA

PREPARATION STEPS

7.- Moveable and Fixed Objects 8.- Pre-Cleaning the Work Area

9.- Critical Barriers and Isolation Barriers 10.- Engineering Controls - Setting up the

Negative Air System

11.- Elevator Shutdown or Isolation

12.- Plasticizing Floors, Walls & Ceilings

of the Work Area

(12)

“Notice Of Asbestos Abatement” Sign (Building Occupant Notice)

The Notice of Asbestos Abatement sign must be posted 10 calendar days prior to commencement of work on any asbestos project in NYS and 7 days in NYC.

According to the state regulations, this

sign must be posted on the floor or floors where the actual project is to be

conducted.

(13)

Vacate Work Area and Restrict Entry

Occupants and non-certified personnel must be removed from the work area

before any work area preparation activities

can take place and shall remain vacated

until satisfactory clearance air sampling

(14)

Post Warning Signs

Asbestos warning signs, required as per current OSHA regulations shall be posted to restrict access to the

regulated abatement work area.

During abatement activities, signs are posted at locations such that persons may take the necessary protective

measures to avoid potential exposure.

(15)

Warning Signs

Danger signs are to be placed at all

entrances and exits to and from the work area

It is an OSHA requirement that signs are to be in the language that workers and

building occupants can comprehend.

(16)

Warning Signs

(17)

Warning Signs

(18)

Protecting The Public

Poly and wood

structures are erected to prevent the movement of people and

contaminated air

(19)

Protecting The Public

Lockable physical barriers in public areas are a must

Asbestos danger sign

on door to

actual work

area not the

exterior door

(20)

Build Worker and Waste Decons

The worker (personal) decon must be installed or constructed prior to preparatory activity in the work area or before disturbing ACM. The

waste decon must be installed or constructed before beginning

abatement activities

(21)

Electricity Preparation

Shutdown and lock out of all existing power to fixtures, lights, machinery and outlets

within the enclosure.

The asbestos abatement contractor shall

provide temporary power and lighting to the regulated abatement work area, This

temporary power shall be protected by a

ground fault circuit interrupter (GFCI)

(22)

Temporary Electrical Power

All circuits must be GFCI protected

(23)

Shut Down the Heating,

Ventilation, and Air-Conditioning System (HVAC)

The HVAC system which services the proposed work area must be shut down or isolated to

prevent asbestos fibers from escaping into other areas of the building.

All vents and air ducts within the work area must

be covered and sealed with two layers of 6-mil

polyethylene and duct tape. These "isolation

barriers" must remain in place until final air

clearance testing .

(24)

Moveable and Fixed Objects

Moveable objects such as furniture, pictures and other items have to be removed from the work area prior to abatement.

Fixed objects and other items which are to remain within the regulated abatement work area shall be pre-cleaned using HEPA-filtered vacuum

equipment and/or wet cleaning methods. Such

objects and items shall be covered with two layers

of at least 6-mil fire retardant plastic sheeting and

sealed airtight with duct tape.

(25)

Furniture & Equipment

(26)

Furniture & Equipment

These types of items may not always be contaminated but if they are they

need to be cleaned with HEPA vacuum before moving and storage

(27)

Pre-Cleaning the Work Area

The regulated abatement Work Area are cleaned using HEPA filtered vacuum

equipment or wet cleaning methods or both. Methods that raise dust, such as sweeping or vacuuming with non HEPA- filtered equipment shall be prohibited.

ACM/PACM shall not be disturbed during

pre-cleaning.

(28)

HEPA

Vacuum Wet Wipe

(29)

Critical Barriers and Isolation Barriers

“Isolation Barriers” as per ICR 56 are temporary hard-wall barriers to complete the containment enclosure and establish the asbestos project

regulated abatement Work Area. Constructed of conventional 2” x 3” (minimum) stud framing, 16”

on center maximum, plywood or oriented strand

board (OSB) sheathing material of at least 3/8

inch (NYS) or ½ inch (NYC) thickness shall be

fastened to the work area side of the barrier

partition.

(30)

Isolation Barriers

Isolation Barrier Cont’d:

Sealing of Isolation Barriers: The edges of the isolation barrier partition shall be sealed at the

floor, ceiling, walls and fixtures using caulk or fire- retardant expandable foam to form an airtight

seal.

Plasticizing Isolation Barriers. The regulated

abatement work area side of the isolation barrier

partition shall be covered with two (2) layers of, at

least, six (6) mil fire-retardant plastic sheeting with

staggered joints and sealed airtight.

(31)

Critical Barriers

The construction of critical barriers to seal off all openings and penetrations to the

regulated abatement work area including, but not limited to operable windows,

skylights, doorways, ducts, corridors (which shall not be used for passage), HVAC

system , diffusers, grills, seams and any

other penetrations to surfaces within the

work area.

(32)

Critical Barriers

Critical barriers are constructed using two independent layers of at least 6-mil fire-retardant plastic sheeting with each layer sealed separately with duct tape.

Caulk and fire-retardant expandable foam may be used to seal small

openings or penetrations.

(33)

Critical Barriers and Isolation Barriers

Critical Barriers and Isolation Barriers When properly placed will make a room “airtight”.

All critical barriers and isolation barriers must be left in place

until the completion of the

project.

(34)

Critical Barriers

(35)

Critical Barriers

(36)

Critical Barriers

(37)

Engineering Controls

The main function of an asbestos

professional is to abate the asbestos in such a manner as to prevent fibers from becoming airborne. To achieve this, a

variety of engineering controls are used to help reduce the amount of fibers

generated in the asbestos abatement

process.

(38)

Engineering Controls

The engineering controls help a contractor to perform the job more effectively and

reduce the hazard in the work area.

Wetting the Asbestos: The EPA, OSHA,

NYS and NYC all law require that asbestos be adequately wetted and sufficient time

be allowed for penetration to occur prior to

abatement.

(39)

Engineering Controls

To wet the asbestos, a contractor will

use Amended Water. Amended water is water that has a surfactant added to it.

Amended water makes wetting and

penetrating the asbestos containing

material more effective.

(40)

Engineering Controls

Negative Air Filtration:

The use of Negative Air Filtration in

conjunction with the other engineering

controls will remove asbestos fibers

from the abatement area.

(41)

AIR FILTRATION DEVICES

One of the most important pieces of

equipment used in the asbestos removal process is the negative air ventilation unit.

These units are known by several

different names including Micro-Trap™, Red Barron™, Hog™, negative air

machine (NAM), negative air pressure

unit (NAPU), negative air unit (NAU), and

air filtration device (AFD).

(42)

AIR FILTRATION DEVICES

Both City and State regulations require the negative air

ventilation units become

operational after critical barriers and isolation barriers are

installed.

(43)

Negative Air Machines (NAM)

¾ Provide ventilation in the work area by drawing air from outside

¾ Help prevent fibers from escaping by lowering the pressure inside the work area (Creates Negative Pressure)

¾ Continually filters fibers out of the air

(44)

Types Of Negative Air Machines

¾ Machines are rated by how much air is drawn through the unit in a minute-CFM

• 2,000 CFM typical rating

• HEPA vacuums – 85 to 200 CFM

(45)

Negative Air Machines

Typical 2000 CFM machine

4000 CFM unit

(46)

Negative Air Machines

There are 3 filters:

½” pre-filter (coarse)

2” secondary filter (fine)

~12” HEPA filter

If the coarse pre-filter and fine secondary filter are changed often the HEPA lasts longer before

becoming clogged with dust

The HEPA filter is typically

rated in “running hours”

(47)

Negative Air Machines

OSHA, NYSDOL & NYCDEP require a minimum of 4 air changes per hour.

NAM’s are exhausted to the outside of the building

This will require windows or other openings

that can be sealed

(48)

NAM Exhaust

Plywood and aluminum duct stock make a good template in the window frame (or other openings, HVAC opening etc.)

If in an office-type building, the windows are often permanently mounted and

may have to be removed by a specialty

contractor.

(49)

Negative Air Machines

(50)

Negative Air Machines

(51)

Negative Air Machines

(52)

Negative Air Machines

NAM ’s

NAM exha ust

(53)

Negative Pressure

OSHA, NYSDOL & NYCDEP

regulations require a minimum negative pressure of -0.02 column inches of

water

Proof of maintaining negative pressure as evidenced by manometric

measurements (negative pressure

recorder)

(54)

Negative Pressure Recorder

(55)

Negative Pressure Recorder

The plastic tube is

inserted through the poly;

the device measures the pressure differential

between the work area

and the area outside of

the work area

(56)

Negative Pressure Recorder

Many of these devices have strip chart

capabilities that can print out readings at desired

time intervals; hourly, daily etc. NYSDOL requires a recording device for

proving that negative pressure is properly maintained to other

employers and the public.

(57)

Negative Pressure

(58)

Negative Pressure

Constructing an “airtight” work area in conjunction with operating the negative air machines creates a negative

pressure environment. If the work area

were totally airtight, a vacuum would be

created. However an abatement area

has openings, which allow outside air to

rush into the work area because of the

draw from the negative air unit.

(59)

Negative Pressure

The negative pressure environment has

to be maintained to such a degree that

should there be a rip or tear (breech) in

the barriers, outside air would rush into

the work area. This keeps the asbestos

fibers inside the work area and protects

building occupants

(60)

Negative Pressure

Since the work area should be “airtight”, air is only allowed to enter the work area through the Decons and makeup air vents. Air flows through from the openings and then to the

negative air units in the work area. The units should be strategically placed throughout the work area as far from the Decons as possible.

This allows the air to pass through every part

of the work area

(61)

Negative Air Machines

Decon

Load Out

Make up Air

Neg Air Machines

NAM’s should be placed in a variety of locations in the work area so that the air moves through the area providing

proper ventilation and helps keep fibers levels controlled

(62)

Negative Pressure

Once abatement has begun, the units must run continuously to maintain negative

pressure until the job is completed, 24 hours a day, seven days a week. Since airborne asbestos fibers are microscopic in size and tend to remain in suspension for a long time, the negative air units must be kept

operational throughout the entire abatement,

cleaning and final clearance processes.

(63)

Negative Pressure

Continuous operation of the units during the final clean-up and clearance process allows the units to remove the suspended asbestos fibers from

the air. This is very important to a contractor who must rely on air sampling results to determine if the fiber concentration is in compliance for re-

occupancy. In addition, continuous operation of

the units will ensure that there is no leakage of

contaminated air outside the enclosure should

the fiber levels be unusually high.

(64)

Plasticing the Work Area

(65)

Preparation of the Work Area

The proper preparation of the work area prior to asbestos abatement is key to

keeping these fibers contained in a specific space.

Some jobs will require far more preparation

detail than others.

(66)

Plasticizing Floors, Walls &

Ceilings of the Work Area

NYSDOL: All floor, wall and ceiling

surfaces shall be covered with two layers of, at minimum, 6-mil fire-retardant plastic sheeting. Plastic sheeting is not required to be placed on any surface where

abatement of ACM will be performed.

(67)

Plasticizing Floors, Walls &

Ceilings of the Work Area

The DEP requires the poly be placed on the floor and walls only. The other

requirements are similar to the State

except that the floor poly extends up the wall 6 inches in NYC. Also, NYCDEP requires seams between adjacent

layers be a distance of at least 6 inches

(68)

Plasticizing Floors, Walls &

Ceilings of the Work Area

The floor shall be plasticized first, and its plastic sheeting shall extend up the walls a distance of at least twelve (12) inches on all sides.

The walls shall then be plasticized by

applying plastic sheeting from the ceiling to the floor, overlapping the floor sheeting by at least 12 inches.

The ceiling shall then be plasticized,

overlapping the walls by at least 12 inches,

to form a secure airtight seam.

(69)

Plasticizing Floors, Walls &

Ceilings of the Work Area

This process shall be repeated for the second layer of plastic sheeting for the floor, walls and ceiling.

All seams within a layer shall be

separated by a distance of at least six feet and sealed airtight with duct tape.

All seams between layers shall be

staggered at least two feet.

(70)

Wall & Floor Poly

Wall

Floor

Poly

(71)

Wall Poly

Ca rdb oa rd pie ce s he lp h old

up po ly

Prep is below trim to minimize

damage

(72)

Floor Prep

(73)

Floor Prep

(74)

Finished Prep

(75)

Finished Prep

(76)

Emergency Exit

¾ Work area must have at least one

emergency exit

(77)

REMOVAL

(78)

REMOVAL

EPA, OSHA, New York State and New York City require that any asbestos removed must be kept wet during the removal and when it is bagged. Two advantages to the use of wet methods for removing asbestos

materials include a reduction in airborne

fiber concentrations, which are generated

during removal, and a reduction in the effort

required removing the material.

(79)

REMOVAL

Wet removal is based on the ability of water to lower the potential for the

asbestos-containing material to release airborne asbestos fibers and increase the settling rate of fibers that are

released. Airborne fiber concentrations

may be reduced significantly by using

wet removal techniques rather than dry.

(80)

REMOVAL

At this point of the abatement project, the work area has been sealed off with at least two layers of 6-mil polyethylene on the floors and two layers of 6-mil polyethylene on the

walls. The decontamination unit and negative air filtration units are in place, and the

scaffolding, ladders, various sizes of short-

and long-handled scrapers and other removal

equipment have been brought into the work

area.

(81)

REMOVAL

The first step in the removal process is

to thoroughly wet the ACM with a low-

pressure mist of amended water. Then

the material will be continuously wetted

while being removed.

(82)

REMOVAL

Gross removal: Is when most of the material is abated. Some of the workers will use

scrappers to remove the material, while others will be involved with keeping the

material wet and packaging the debris into

the appropriate container.

(83)

REMOVAL

ACM, on detachment from the substrate, shall be directly bagged or dropped into a flexible catch basin and subsequently bagged or containerized. (Title 15, Chapter 1 uses the word “promptly”).

According to ICR-56, cleanup of accumulations of loose debris/waste material shall be

performed whenever enough loose debris/waste

material has been removed to fill a single leak-

tight container.

(84)

CLEANING PROCESS

Once all the ACM has been removed and no gross debris is observed, the cleaning process starts. Typically a combination of brushing and wet wiping is used to

remove the remaining residue. Wet rags and High efficiency particulate air

(HEPA) vacuum cleaners are also useful

for removing "hard-to-get-to" residue.

(85)

FINAL CLEANING

Any cleaning of the work area is to be accomplished by wet wiping and/or

HEPA filtered vacuuming. The

contractor will choose the appropriate method based on the surface to be

cleaned.

(86)

FINAL CLEANING

All surfaces inside the Work Area are included in the cleaning, including the

Decon(s), floors, walls, and the surfaces

where asbestos has been abated.

(87)

DAILY CLEANING

NYC VS NYS

The following requirements will be required on all large and small projects:

1. Cleanup of accumulations of loose debris/waste material shall be performed whenever there is

enough to fill a single leak-tight container appropriate for the type of ACM being removed. Cleanup of all remaining waste shall be performed at least once prior to close of each workshift.

2. Non-metal shovels allowed.

3. Accumulations of dust or debris shall be cleaned off all surfaces on a daily basis using HEPA-vacuum or wet-cleaning methods or both.

4. Decontamination system enclosures shall be HEPA-vacuumed or wet-cleaned or both at the end of each workshift.

5. The regulated abatement work area, holding area, waste trailer and hardtop dumpster areas must be kept free of uncontainerized asbestos waste/debris at all times.

NYSDOL Code Rule-56

The following requirements shall be followed on all large asbestos projects:

1. Visible accumulation of waste must be bagged whenever there is enough to fill a bag or at the end of each shift whichever shall occur first.

2. Non-metal shovels and/or HEPA vacuums (i.e. dust pans, squeegees etc.) allowed.

3. Accumulations of dust cleaned daily.

4. Waste decon shall be cleaned twice after the removal of waste. When worker decon is used for waste, shower shall be cleaned with a detergent prior to wet-cleaning of decon.

5. Worker decon cleaned, as appropriate, after each shift change and meal break.

6. Excessive water accumulation or flooding shall require work to stop until water is collected.

NYCDEP Title 15, Chapter 1

(88)

FINAL CLEANUP PROCEDURES

NYC VS NYS

1. First Cleaning. All surfaces are wet-cleaned using rags, mops and sponges.

2. Apply a thin coat of a lockdown encapsulant to all surfaces except abated surface or surfaces.

3. Conduct appropriate waiting/settling, or drying time (see table on next page).

4. Remove the cleaned, exposed top layer of plastic sheeting. Barriers and Decons remain in place.

5. Second Cleaning. All objects and surfaces cleaned using HEPA vacuums and then wet cleaned.

6. Conduct appropriate waiting/settling, or drying time Remove remaining bottom layer of poly. Barriers remain in place.

7. Third Cleaning. All objects and surfaces cleaned using HEPA vacuums and then wet cleaned. All equipment (except NAU’s) and tools shall be removed and properly decontaminated.

8. Conduct appropriate waiting/settling, or drying time 9. Visual inspections conducted by both the asbestos

abatement contractor’s supervisor and a project monitor.

10. Maintain air filtration for at least four air changes per hour.

11. Begin aggressive/final clearance sampling.

1. First cleaning. All surfaces are HEPA vacuumed first and then wet cleaned.

2. Remove the cleaned layer of poly sheeting. Barriers and Decons remain in place.

3. Wait 12 hours.

4. Second Cleaning. All surfaces HEPA vacuumed and wet cleaned again.

5. Remove remaining layer of poly. Barriers and Decons remain in place.

6. Wait 4 hours.

7. Third Cleaning. Wet clean and/or HEPA vacuum all surfaces. All equipment (except NAU’s) and tools shall be removed and properly decontaminated.

8. Conduct final visual inspection.

9. Encapsulate all abated surfaces.

10. Wait until at least 1 hour after the area is dry from the 3rdcleaning and no visible pools of water or

condensation remain.

11. Air filtration must be at least two air changes per hour at this point.

12. Begin aggressive/final clearance sampling.

NYSDOL Code Rule-56

NYCDEP Title 15, Chapter 1

(89)

VISUAL INSPECTION

Prior to the final clearance sampling, a visual inspection will be performed by the third party consulting company.

The project monitor visual inspection for

completeness of abatement and completeness of cleanup shall be performed as per the

provisions of the current ASTM International

Standard E1368 “Standard Practice for Visual

Inspection of Asbestos Abatement Projects”.

(90)

VISUAL INSPECTION

The aggressive clearance sampling will start ONLY once the visual inspection is completed and it has been determined that the scope of abatement work for

the asbestos project was accomplished,

and no visible asbestos debris/residue,

pools of liquid or condensation remain

inside the work area.

References

Related documents

Seven cars on sale in 2013 are considered: the Ford Fiesta (diesel), the VW Polo (gasoline), the Fiat Punto Evo (bi-fuel - CNG), the Natural Power Alfa Romeo Mito (bi-fuel -

These studies showed that the radio properties of clusters on the Mpc scale have a bimodal behaviour, either they host radio halos, whose radio powers increase with the X-ray

H1: SMEs representing individual clusters (based on the use of marketing communication tools and their intended use) in terms of selected attributes (enterprise size,

7/8/2020 1.8 Review updated drafts to Statements and Schedules and prepare comments to global notes and financial statement presentation. Allison (A&M) re: NEGG letters of credit

In order to evaluate the impact of basic socio economic factors on retention of employees of telecom sector in Pakistan, interviews were carried out with middle and high level

In the previous Section, it was shown that the SCI serviceability limits result in a design for the Reference Frame which is heavier than that obtained using serviceability

The effect can be done with a borrowed deck, and a borrowed set of keys (making The effect can be done with a borrowed deck, and a borrowed set of keys (making sure they have a

Future research agendas may also include the investigation of influence of different types of symbiotic and commensal networking on a SME’s internationalization, including