• No results found

Fresh Start for Fresh Water Clean-up Fund

N/A
N/A
Protected

Academic year: 2021

Share "Fresh Start for Fresh Water Clean-up Fund"

Copied!
19
0
0

Loading.... (view fulltext now)

Full text

(1)

Fresh Start for Fresh Water

Clean-up Fund

Quarterly Report

Covering the period 1 January to 31 March

2015

Project Name: Wainono Restoration Project

Date: 30/04/2015

V

ERSION

:

Draft

(2)

Introduction

What is this report for?

This template has been collaboratively developed by the Ministry for the Environment and the

Clean-up Fund project teams with the aim of producing efficient and informative report templates

that work for both the project teams and the Ministry.

This quarterly report gives the opportunity to recipients of the Clean-up Fund to record and

communicate to interested parties, including the Ministry for the Environment, funding partners and

the wider public, the progress made on their project, along with any significant risks, issues and/or

health & safety matters encountered, and stakeholder engagement undertaken.

The report provides the Ministry for the Environment with information on how the delivery phase of

the project is going. The reports are a key source of information for updates to the Minister and the

Ministry’s website on the progress of projects funded through the fresh Start for Fresh Water

Clean-up Fund.

The different sections in this report serve different purposes.

The “Project Overview and key facts” section presents a snapshot of what has been happening in the

project this quarter, and is particularly useful for situations where high-level reporting is required

(e.g., strategy/ governance group meetings, preparing fact sheets for the Minister on the progress of

freshwater projects).

The rest of the report provides a more in depth understanding of the project progress. This is a

useful recording tool for the project team and any other involved parties for assessing what has

been achieved to date and what is ahead, as well as providing robust information whenever the

project comes under scrutiny.

Finally, the Declaration section provides assurance to the Ministry that the regional council

recognises its accountability for the information provided, which may be requested by interested

parties beyond the Ministry.

(3)

When your report is complete

Quarterly reports should be submitted by the dates agreed in your funding deed, unless otherwise

discussed with your Clean-up Fund Analyst.

Email the completed report to your Clean-up Fund Analyst.

Alternatively, you can post these to:

Remediation Projects Team –Clean-up Fund

Ministry for the Environment

PO Box 10362

Wellington 6143.

What happens next?

Your Clean-up Fund Analyst will assess the report to ensure that you have met the requirements for

funding as specified in your funding deed. During your Clean-up Fund Analyst’s review of the report,

further information may be requested.

(4)

1. Project Overview and key facts

Implementation of the project actions continues as we experience good ground conditions for the earthworks. The drought this year has delayed further planting work but fortunately most of the initial plantings undertaken in the previous quarter have survived. Spending is behind budget and we are unlikely to complete all of the on ground work by the end of June. However funds will be committed in contract to projects by this time. Implementation of contracted works will continue, but the rate of progress will be governed by soil conditions and farming operations as we approach wetter months.

Sediment mitigation works

Work has progressed on several properties including further work on the main stem of the Hook River. Low flows in streams has mean that we are largely working in completely dry stream beds which simplifies operations by not needing temporary diversions in most situations.

We have been required to use a chainsaw felling crew to remove vegetation ahead of the earthworks proceeding to avoid health and safety risks and damage to machinery. This has delayed some work due to contractor availability. As most of the trees to be removed are willows, the felling is particularly hazardous (willows are prone to splitting and springing under tension) and this has meant that only contractors with the appropriate qualifications, equipment and health and safety procedures could be used. Some of the work involved felling from top down requiring tree climbing qualifications and equipment. This has added costs and delays to some of the work.

The availability of suitable rock armouring material has also been an issue. Competition between contractors led to one earthworks operator not being able to source material from our usual supplier who has somewhat of a monopoly on supply in the area. It took some time to find an alternative source that was suitable material and close enough to the site. An alternative has now been found and we will have ongoing supply to avoid this being an issue in the future. The material from the new site is particularly good for some situations as it comes in large slab formations that can be split to suit the job in hand.

While contractors are becoming more familiar with the requirements of the work, the amount of time that needs to be spend on site is still significant. Often additional visits are made as land owners become more aware of the implications of the work as it occurs and request minor changes. The most publicly visible works to date commenced in this quarter and this work has generated a lot of conversation in the community and enquiries to the landowner as to what is going on. This site adjoins the main highway and the nature of the work and the heavy machinery have attracted a lot of interest. The most common comment seems to have been along the lines of “I wish I could get that done on my place mate” which is really positive to hear.

Water quality monitoring

Monitoring has continued throughout the Hook catchment but many of the sites have been dry so samples cannot be taken. Of note is that project staff and members of the public observed mass fish deaths in the lagoon itself where numerous flounder were seen floating on the surface or washed up on the shore. This has been observed before, and is most likely to be due to low oxygen levels in the lagoon being exacerbated by high water temperatures and reduction inflows due to the drought. Shallow water bodies are prone to these occurrences but they are likely to be more frequent and more severe where the water quality is poor as with Wainono. The fish mortality seems to have been a short term event as the observations have not persisted.

Canterbury Mudfish

The protection of a significant new population of Canterbury mudfish is imminent as negotiations with the landowner near completion. This previously undetected population was found in the course of our farm surveys and was prioritised for protection due to the abundance of mudfish found across a range of age classes. As the landowner is converting from deer farming to beef in the near future, fencing costs are much reduced from initial scenarios and should enable the project to be more affordable for the landowner and the project. As the site is in the upper reaches of a stable tributary it has the potential to seed new populations down stream of replenish existing ones.

(5)

Farm Environment Plans

The template that has been used for our farm environment plans continues to evolve and has had further changes made to reflect suggestions made by an assessment panel made up of Regional Council specialists and industry representatives. The Hook catchment steering group has also promoted changes that make the template more readable and streamlined. Environment Canterbury Land Management Advisors and project staff continue to work on these plans with individual farmers and the process is being well received.

Engineering Work for the Hook Delta Wetlands

Engineering work has yet to be completed for sediment trap works in the Hook delta wetlands. The surveying work completed last quarter did not provide sufficient elevation data for part of the site and further work is needed. This coupled with the engineer being called to give expert witness evidence for an environment court case will further delay the completion of this work. We are proceeding with preliminary site work but cannot progress the consenting process until engineering work is completed. Community

We have been developing signage and interpretation material in consultation with Waihao Rūnanga, the Waimate District Council, Ministry for Primary Industries and the Department of Conservation. This will pull together not only the physical communication material but also the messages they present. A landscape architect has been engaged to design the structures that will hold the material and these will be built with recycled hardwood timbers from the old Waihao box and Bradshaw’s bridge. Using these materials will visually brand the sites as part of the restoration project and will also provide a useful cultural heritage link with the history of water management around the lagoon. As part of the project we were pursuing the use of phone apps that provide locally triggered content that can be linked to the interpretation media on site however it has been decided not to go further with this until the technology and its potential are better embedded.

(6)

2. Milestone Table

Please provide information on the progress of milestones for the past quarter. As per the Annual Plan, please identify:

the milestones scheduled to be progressed this quarter;

the activities or interventions scheduled to be undertaken this quarter towards achieving the milestone and their scheduled completion date;

the activities status and any new forecasted completion date if the activities are on-going/delayed;

the progress (in summary) of the activities scheduled this quarter, including tangible achievements.

Scheduled Milestone

Scheduled Activities

Scheduled

completion

date for

activities

Activities Status:

complete

or

or

on-going/delayed

new completion date

Progress summary on activities

(incl. tangible achievements)

1. Develop and maintain project support and relationships with stakeholders.

 Integrate Land Water Regional Planning (LWRP) planning implications.  Catchment group establishment and maintenance  Re-measure perception survey Ongoing Ongoing June 2015 On track On track Delayed, completion date now June 30 2015.

 Our Farm Environment Template has been reviewed and now meets the requirements of the LWRP  Sub-regional plan produced and

now published for submissions  Catchment steering group

performing well as a conduit for project implementation and planning process information

 Perception survey delayed to allow for the result to reflect further work in the last quarter

2. Complete investigations to inform management

decisions.

 Complete fish habitat assessment and management planning

 Complete fish passage remediation actions December 2014 Nov 2015 Delayed, expect completion June 2015. Delayed. Expect completion December 2015

 Field work and data assessment completed. Report has been significantly delayed due to family health issues being experienced by our consultant Leanne O’Brien  A number of remediation actions

have been completed in the course of the sediment control activities

(7)

Date revised in line planning delays identified. We are undertaking contingency planning with the Working Waters Trust to ensure that this work can be completed post June 30th

4. Survey farms using modified Riparian

Management Classification (RMC) assessment protocol.

 Undertake surveys January 2015 Delayed, expect completion March 2015

 Desk top and on ground surveys continue. Some work is prioritised by the knock on effect from one property to the next, e.g. improving flow paths on an upstream property will affect the downstream neighbour 5. Undertake sediment

control implementation.

 Stock exclusion fencing  Riparian planting  Stream bank battering  Construction of sediment

traps and detention bunds

June 2015 On-going/delayed  4.5 kilometres of stream battering completed this quarter

 11 sediment traps completed this quarter

 10 detention bunds completed  Major gravel removal and bed

modification completed in the main stem of the Hook River

 No fencing completed this quarter  No planting completed this quarter

(8)

3. Evaluation of Significant Risks

Please provide details on significant project risks updated for this quarter and how they are managed. Rate the risk (low, moderate, severe) based on the

probability of the risk occurring and the severity of impact on the project.

A significant risk is an event or a situation that

may occur

and impact on the completion of the project or cause the project to fail.

Risk

Date raised

Consequence

Rating

Strategy to

mitigate

Status

Outcomes/comments

Changes in

landowner

support for

project due to

sub-regional

planning

implications

Dec 2013

Reduced success in

accessing farms and

negotiating funding

agreements and

contributions

Moderate

Improve understanding of

implications

Develop communication

responses

Open

While this is still a potential issue, we

have not experienced any access issues

due to this process. There is tension

and caution present in some

discussions however. As the

sub-regional plan is now published for

submission and its implications will be

made clearer, this risk may still have a

bearing on project outcomes.

Extensive areas

of exposed soil

during project

works

October 2014

Sediment discharge

during rain events

Moderate

Sow in grass as soon as

earthworks completed.

Stagger work across

several months

Open

Grass strike has improved with recent

rain fall and we continue to sow works

as soon practicable after completion. A

new seed mix using plantain and

cocksfoot is being tried as this will

provided faster cover growth in cooler

months. Land owners are expressing

concern about the risk of continuing

works into the traditionally wetter

months. We are aware of this risk and

it may mean that we suspend work in

areas where this risk would have the

greatest consequence.

Reduced dairy

pay-out

prediction

October 2014

More difficult

negotiating

environment for

Moderate

Remain aware of issue

facing landowners and

communicate accordingly

Open

We continue to see reduced pay outs

and predictions for the dairy sector

and this has a knock on to cropping

(9)

causing greater

spending caution

agreements and

contributions

and dairy support operations. We have

yet to encounter changes in landowner

intentions or support due to this risk.

4. Evaluation of Significant Issues

Please provide details on significant project issues updated for this quarter and how they are managed. Rate the issue (low, moderate, severe) based on the

severity of impact on the project.

A significant issue is an event or a situation that

has occurred

and could or has impacted on the completion of the project or cause the project to fail.

Issue

Date raised

Consequence

Rating

Strategy to

mitigate

Status

Outcomes/comments

Engineering

work repeatedly

delayed (See

budget

underspend

comments for

further detail)

Implementation

works

significantly

behind budget

schedule,

activities may

30/04/2015

03/04/2015

Not completing

works in the

project

timeframe

Not completing

works in the

project

timeframe

High

High

We have proceeded with site

preparation work that does not need

prior engineering work or consents but

are otherwise unable to mitigate for

this. This work is an integral part of the

project in that it will manage one of the

most significant sediment pathways to

the lagoon.

We will continue to progress work

quickly as possible and as water levels

and soil conditions permit.

Open

Open

To be discussed with MfE.

(10)

need to be

suspended if

water levels and

soil conditions

prevent

earthworks.

(11)

5. Health and Safety

Do your systems meet requirements of Health & Safety Act?

Yes

No

Please describe any new hazard that is

not covered in your health & safety management plan

and/or serious health and safety issue(e.g. boat capsized and

volunteer nearly drown) that have occurred this quarter; their impact (real or potential); their mitigation, if any; significant amendments to your health

&safety management plan; and any comments you think are relevant.

Hazard/issue identified

Impact

Mitigation

significant amendments to the

health &safety plan

Comments

No new hazards

identified for this

quarter

(12)

6. Change Register

Please provide information on significant change requests. What changes occurred to the Annual Plan this quarter? Have they been approved and

implemented? Who were they approved by and when? Was the Ministry for the Environment consulted?

A ‘significant change’ is defined as any change that will result in an aggregate increase or decrease in cost of $50,000 or greater to the relevant project costs

as originally set out in the project work programme or annual plan, or in changes to the key outcomes of the programme.

Description of Change

Reason

Impact

Comment

Approval date

Approved by

MfE consulted

(13)

7. Evaluation of Financials

Project Tasks

Total from

Annual

Plan

3rd 1/4

Planned

Target

3rd 1/4

Actual

2nd 1/4

Variance

3rd 1/4

Variance

4th 1/4

Planned

target

4th 1/4

Total

Comment

1. Community integration via

catchment groups and

sub-regional planning

$10,899 $3,132 $3,799 $1,132 ($667) $3,899 $3,232

Slightly over budget. Additional hours required to modify Farm Environment Plan template after panel review

2. Complete investigations to

inform management

decisions

$20,000 $20,000 $3,842 ($2,671) $16,158 $0 $16,158

Fish passage remediation to date has been completed simultaneously with sediment control (pitched culvert repair, scour pool barriers) and costs cannot be meaningfully separated.

Final recommendation report from consultant still pending.

3. Establish baseline

monitoring for indicator

species and habitats

$39,000 $11,000 $11,998 ($96) ($998) $8,000 $7,002 Slightly over budget with additional staff hours used for eel monitoring.

4. Farm surveys to identify

and prioritise actions

$6,000 $2,000 $2,181 $3,888 ($181) $0 $0

Slightly over budget, Re-survey of site due to implications of upstream works that change stream capacity affecting downstream property.

5. Sediment control

implementation

$1,116,000 $325,000 $135,875 ($201) $189,125 $401,000 $590,125

This output is significantly behind budget.

*See explanatory comments below

(14)

Explanatory comments for budget underspend

An accumulation of factors has led to a significant underspend for the main implementation outputs of this project.

 Severe drought conditions from November through to April have meant that no riparian planting works have been undertaken since September. While most of the species for planting are quite hardy, the total lack of soil moisture would have meant very high failure rates. Irrigation of the planting sites is not practicable.

 Hook delta sediment control ($80,000 phased for 3rd quarter) works have been repeatedly delayed due to consultant availability. We cannot proceed with consents or operations for this work until the engineering work is completed. The consultant chosen for this work is a specialist in the area of river morphology and sediment management and has many years of local experience with this type of work. Despite the delays, for this reason and the fact that the work had commenced, we did not want to change service providers. He is currently involved as an expert witness for ongoing Environment Court hearings and the demands and timing of this are largely out of his control. The preliminary engineering work has been completed and drawings pending, however consent timeframes and river conditions will dictate progress on this work.

 Large scale drainage realignment and wetland enhancement work was planned for lake margin areas recently acquired by the Waimate District Council. However the gazettal and title transfer of this land was stalled on a technicality by the previous landowner due to ongoing grievance with the Council, effectively suspending the land parcels in an undetermined legal state. The land was procured as part of a legal settlement when the land owner was prosecuted under the RMA. This has prevented legal access to the site so none of the proposed work site has commenced. This land provides opportunities to treat priority drainage tributaries that cannot otherwise be managed so the option of doing alternative works with the funds proposed for this site has not been pursued. We have been informed that full title transfer has now occurred, so can now begin this work.

 Availability of suitable rock armouring material has delayed work at some sites at the head of the south branch of the Hook River. Commercial competition between earthmoving contractors has limited the supply of this material as one operator has control of the main quarries that are within economic transport distance of the project. As some land owners have preferences for the contractors they use, and these operators could not source the material from the usual supplier, there were delays in finding a suitable alternative. Such a supply has now been found and work has progressed at these sites. This issue had not been anticipated as the level of controlling interests in the supply were not known.

 In general terms the implementation work is slower to deliver than anticipated. The time that needs to be spent with landowners and contractors on site for work that is underway, prevents the required planning, administration and liaison occurring for the next body of work to be progressed. As works proceed on site, often landowners only then discover implications of the work that needs to be addressed. These have all been relatively minor adjustments to things like fence lines, tree removal and gravel deposition but none the less require a site visit, land owner and contractor

management time.

 The implications of farming operations has also caused delays in the surveying and implementation work for some properties. Some of the issue is that the land owners are unavailable to meet to go over proposals, but at other times it has been access limitations due to stock or cropping activities.

(15)

8. Evaluation of Communication and Engagement

Provide information on your communication and engagement mechanisms. How do you keep stakeholders informed? How often do you need to engage with

them to keep them informed? How easy was it to keep them informed? What positive/negative feedback have you received from them?

Stakeholder

Engagement mechanism

Frequency

What’s covered

Stakeholders Feedback

Comments

Waihao

Rūnanga

Catchment group

meetings

Rūnanga meetings

Direct contact with

individuals

Sub-regional

planning processes

Monthly

All issues,

cultural focus

but more

broadly involved

also.

Good feedback,

well engaged

with project

Ongoing conversations with

regard to project activities and

implications of Hunter Downs

irrigation scheme

Recent engagement regarding

Waihao Rūnanga application to

the Te Mana o Te Wai fund

Landowners

One on one

Hook catchment

group meetings

Sub-regional

planning process

As required

Monthly

As required by

process

Operational

detail

Planning issues

Generally good,

farmers pleased to

be involved and

keen to see the

work done, caution

about their

contributions

Positive comments

about how the

work is turning out

Concerns

expressed about

the functioning of

the Waihao Box

lagoon level

Land are provided for carpark

will require designation as road

reserve to fall within Waimate

District Council maintenance

funding. This has been

successfully negotiated with

the land owner.

Hook Catchment steering

group is proving to be a good

forum for getting better

communication going beyond

the project activities and we

are getting insights into how to

make some of our

organisation’s processes more

effective and easier for land

owners to navigate

This is not part of the Wainono

project but has implications for

project outcomes. These

concerns will be forwarded to

Environment Canterbury’s

(16)

management

structure

River Engineering Section

DOC

Zone Committee

meetings

Arranged ongoing

meetings and

operational

communications

Monthly

As required

Broader context

and summary

updates

Operational

issues

DOC are keen to

get more involved

with the Wainono

Lagoon Restoration

Project now that

their new

organisational

structure, staff

roles and funding

environment are

embedded

Positive meeting held in March

with DOC Partnerships and

operational staff

Collaborations underway with

weed control, signage and

communications work

Waimate

District

Council

Via District Planner

Zone Committee

meetings/reps

As required

Monthly

Operational

issues

Broader context

and summary

updates

Good feedback on

completed works

WDC providing materials and

site agreements for public

access areas

WDC lake margin lands now

gazetted and agreed that work

can proceed

General

public

Zone Committee

meetings/reps

Monthly

Broader context

and summary

updates

General support

continues with

Newsletter to be produced in

January with website update

9. Lessons Learned

What key lessons have you learned while implementing the project over the last quarter? Please provide a context to the lesson learned (what event or

situation triggered the lesson learned), the mitigation undertaken if any, the impact the event or situation had on the project. Finally, state what you might

do differently or keep doing in the future as a result

(17)

30/04/2015 Staff time

Complexity of work

means large amount

of contact time

required with

contractors and

landowners once

work proceeds

Delays in

progressing

outputs

n/a

The main learning is being

more conservative with

regard to expenditure

estimates and allowing

greater time for contractor

management.

While the time on site is often

relatively short, when combined

with travel time additional site

visits impact significantly on

time available to forward other

work.

(18)
(19)

Declaration

As a duly authorised representative of the organisation:

I declare that to the best of my knowledge, the information contained in all sections of this quarterly

report, or supplied by us in support of our quarterly report, is complete, true and correct.

I declare that I have the authority to sign this quarterly report and to provide this information.

I understand that information presented to the Minister for the Environment and Ministry for the

Environment is subject to disclosure under the Official Information Act 1982.

Name

Kennedy Lange

Position

Project Manager

Signature

by typing your name in

the space provided you

are electronically signing

this quarterly report.

References

Related documents

If your brewer has not been used for several weeks or more, it is necessary to start up the machine by using the Service T DISC, and rinse the water tank with fresh, clean water..

APPROACH-IS consortium: Luis Alday, Héctor Maisuls, Betina Vega (Córdoba, Argentina, Hospital de Niños); Samuel Menahem, Sarah Eaton, Ruth Larion, Qi Feng Wang

disorder was also found to significantly mediate the relationship between socioeconomic status and cigarettes smoked per week such that lower socioeconomic status individuals reported

Despite his theoretical act of nuancing, Rozik is unable to delink theatre from ritual. He traces the roots of theatre to “innate imagistic thinking” and ritual to

Represents the change in projected revenues from applications for admission to the unit and from tuition and registration fees of students, net of the change in central financial

GEOLOGICAL STRENGTH INDEX The strength of a jointed rock mass depends on the properties of the intact rock pieces and also upon the freedom of these pieces to slide

Frail sen- iors had not been seen as citizens with equal social rights (see Health Canada, Division of Aging and Seniors, 2001; Morgan and Sam, 2002; UN, 2002a,b) and the

Many mineral processing operations rely on the movement of solids in fluids, especially liquids. Por example, one common process is gravity separation of minerals in water. It