Document Management

Implementation

Milestones with Timescales

(2)

Document Control

Organisation Sandwell MBC

Title Document Management Implementation - Milestones with Timescales

Author Binda Rana, Business Systems Development Manager (Children’s)

Filename H:\ems\officepro2000sp3\Binda Rana\ICS\ICS Phase 9 - Document Management\Document Management -

Milestones with Timescales V1.0.doc

Owner Binda Rana, Business Systems Development Manager (Children’s)

Subject Document Management

Protective Marking None

Review date N/A

Revision History

Revision Date Editor Previous

Version Description of Revision

14/07/2011 Binda Rana 1.0 New sections for project leads and signatures

Document Distribution:

(3)

Contents

Background 4

Overview of Key Stages of Document Management 5

Stage 1 – Case File Audit 6

Stage 2 – Develop Case File Structure/Recording Policy 7

Stage 3 - Define Business Requirements 8

Stage 4 - Technical Configuration 9

Stage 5 – Back Scanning 10

(4)

Background

The implementation of an electronic document management system has been identified as a key priority for Children’s Services.

This document supports the Project Initiation Document (PID) and provides details of the key milestones and provisional timescales for implementation.

The actions and milestones will be monitored through The Child’s File Strategic Board. Kulbant McLaughlin, The Child’s File Strategic Lead will be responsible for updating Helen Smith, Service Director for Children’s & Families, social work line management of progress, risks and any

dependencies.

Project Leads

Kulbant McLaughlin – The Child’s File Strategic Lead Martin Parsons – Business Information Systems Manager

Signatures

Signature: ……… Date: ………..

Helen Smith, Service Director, Children & Families

Signature: ……… Date: ………..

(5)

Overview of Key Stages of Document Management

Stage 1 Case File Audit

Stage 2 Develop Case File Structure/Recording Policy Stage 3 Define Business Requirements Stage 4 Technical Configuration Stage 5 Back Scanning Stage 6 Training & Roll Out

Overview: To audit a representative set of

case files to assess their current status and identify if there

are common structures/standards.

Overview: To develop the new

case file structure including procedures/guidance

for contents.

Overview: To define the business

requirements for the electronic document system. For example storage requirements,

number of scanners, number of users, user

roles, systems set up etc.

Overview: To configure a separate Children’s

document system. This includes all

software and hardware installation.

Overview: To back scan existing

case files in accordance with back

scanning guidance.

Overview: Roll out system to users so that they use

a real-time LIVE document management. Approach to roll out needs to be agreed. Possible options are

big bang or phased approach. Timescales: July – August 2011 Timescales: September 2011 Timescales: October 2011 Timescales: November - December 2011 Timescales: January 2012 Timescales: January 2012

(6)

Stage 1 – Case File Audit

Overview

To audit a representative set of case files to assess their current status and identify if there are common structures/standards Key People Involved

Project Officer Practice Lead

Administration Manager

Business Systems Development Manager Team Manager

Dependencies

Provision of Case Files from Children’s & Families Timescales

July – August 2011 Outcomes

Representative sample of case files from all services

Identification of the current structures and contents of case files Details of the size of case files

(7)

Stage 2 – Develop Case File Structure/Recording Policy

Overview

To develop the new case file structure including procedures/guidance for contents. Key People Involved

Project Officer Practice Lead

Administration Manager

Business Systems Development Manager Team Manager

Legal Incl. DPA Social Workers Dependencies

Stage 1 – Case File Audit Timescales

September 2011 Outcomes

(8)

Stage 3 - Define Business Requirements

Overview

To define the business requirements for the electronic document system. For example storage requirements, number of scanners, number of users, user roles, systems set up etc.

Key People Involved Project Officer

Practice Lead

Administration Manager

Business Systems Development Manager Social Care Systems Team

Systems Supplier Transform Sandwell Timescales

October 2011 Dependencies

Stage 2 – Develop Case File Structure/Recording Policy Outcomes

Identification of Electronic Storage Requirements Hardware Requirements - Scanners

Systems Configuration – Document Stores, Document Types Users Requirement – Number of Users, Access Levels

Criteria for Back Scanning Developed including Additional Resources Required Business Processes for Using Document Management

(9)

Stage 4 - Technical Configuration

Overview

To configure a separate Children’s document system. This includes all software and hardware installation. Key People Involved

Practice Lead

Administration Manager

Business Systems Development Manager Social Care Systems Team

Systems Supplier Transform Sandwell Dependencies

Stage 3 - Define Business Requirements Timescales

November - December 2011 Outcomes

Electronic Storage Available

Hardware Available – Scanners Purchased and Installed

Systems Configuration Configured – Document Stores and Document Types Set Up User Set Up Completed – Users and Access Levels Set Up

(10)

Stage 5 – Back Scanning

Overview

To back scan existing case files in accordance with back scanning guidance.

Key People Involved Project Officer

Practice Lead

Administration Manager

Business Systems Development Manager Social Care Systems Team

Back Scanners Dependencies

Stage 4 - Technical Configuration Timescales

January 2012 Outcomes

Back Scanning Files are Prepared in Accordance with Case File Structure/Recording Policy Files agreed to be back scanned are scanned

(11)

Stage 6 – Training & Roll Out

Overview

Roll out system to users so that they use a real-time LIVE document management.

Approach to roll out needs to be agreed. Possible options are big bang or phased approach. Key People Involved

Project Officer Practice Lead

Administration Manager

Business Systems Development Manager Trainer

Social Care Systems Team Transform Sandwell

All Children’s Services Staff Dependencies

Stage 4 - Technical Configuration Timescales

January 2012 Outcomes

All Children & Families Staff are trained to use the system

References