Estimate as per APWD (Bldg.) SoR for the Year 2013-14
Mark APWD Nos. Length (M) Width(M) Height(M) Quantity Rate Amount Remarks
(Rs.) (Rs.)
1 1.1 Earthwork in excavation for foundation trenches of walls A A Upto a depth of 2 M below the existing ground level
a a In ordinary soil Unit: CuM
Foundation 8 2.1 2.1 2.1 74.09
74.09
Rs.108.82
8062.47 Basement 2 2.1.1 Plain cement concrete works with coarse aggregatea a
1:3:6 Unit: CuM
Foundation 8 2.1 2.1 0.1 3.53
1:4:8 3.53
###
15153.80 BasementTie Beam 1 1 49.32 0.1 4.93
###
19180.71 Basement3 2.1.3 Damp proof course
1 49.32 0.115 5.67
Rs. 181.99
1031.88 Basement4 2.2.1 A Providing and laying RCC works in proportion 1:1.5:3 i i In sub-structure upto plinth level
Foundation, footing, column with base , tie and plinth
a b d CuM
Foundation 8 2.1 2.1 0.15 5.29
8 0.45 0.45 0.45 8.30
Stair beam 1 1.7 0.25 0.9 0.38
Column to Tie beam top
8 0.45 0.3 1.5 1.62
Tie beam 1 49.32 0.45 0.3 6.66
Col. to plinth top 8 0.45 0.3 0.6 0.65
22.90
###
138857.59 BasementB ii In super-structure from plinth level to 1st floor level b. Column, pillar, post
Column 8 0.3 0.45 2.4 2.59
###
16398.48 Basement 2.2.3 8 0.3 0.45 3.1 3.35###
22236.13 u/gr 8 0.3 0.45 3 3.24###
22498.04 1st flr 8 0.3 0.45 3 3.24###
23490.10 2nd flr Beam 1 49.32 0.45 0.3 6.66###
42167.52 Basement 1 49.32 0.45 0.3 6.66###
44206.75 u/gr 1 49.32 0.45 0.3 6.66###
46245.97 1st flr 1 49.32 0.45 0.3 6.66###
48285.20 2nd flr Lintel 1 49.32 0.125 0.2 1.23###
7787.70 Basement 1 49.32 0.125 0.2 1.23###
8164.31 u/gr 1 49.32 0.125 0.2 1.23###
8540.92 1st flr 1 49.32 0.125 0.2 1.23###
8917.54 2nd flrRoof Slab 1 16.86 19.5 0.12 39.45
###
249776.10 Basement1 16.86 19.5 0.12 39.45
###
261855.29 u/gr 1 16.86 19.5 0.12 39.45###
273934.49 1st flr 1 16.86 19.5 0.12 39.45###
286013.68 2nd flr Staircase 1 12.76 1.7 0.15 3.25###
20577.25 Basement 1 4 2.8 0.15 1.68###
10636.85 Basement 20 1 0.0225 1.7 0.77###
4875.22 Basement 1 1 1 1 5.70###
37834.61 u/gr 1 1 1 1 5.70###
39579.89 1st flr 1 1 1 1 5.70###
41325.17 2nd flrSupporting post 2 0.2 0.2 2.4 0.19
###
1202.98 Basement2 0.2 0.2 3 0.24
###
1666.52 1st flrMark APWD Nos. Length (M) Width(M) Height(M) Quantity Rate Amount
2 0.2 0.2 3 0.24
###
1740.01 2nd flrStair post 2 0.3 0.3 2.4 0.43
###
2722.53 Basement2 0.3 0.3 3.1 0.56
###
3717.08 u/gr2 0.3 0.3 3 0.54
###
3749.67 1st flr2 0.3 0.3 3 0.54
###
3915.02 2nd flr5 18.1.1 Supplying, fitting and fixing in position reinforcement bars
b TMT bars Unit: Qtl.
i TATA/SAIL
22.90 0.01 78.5 17.98
###
108362.22 all floors6 3.1.1
3.1.1.1 Providing form work Unit: Sq.M.
Foundation. Footing, bases of col., pile cap, raft Using 25mm thick plank
ii Foundation PCC 8 2.1 0.1 4 6.72
Foundation RCC 8 2.1 0.2 4 13.44
Col. To tie beam top
8 0.45 1.69 4 24.34
Col. tie top to plinth
8 0.45 0.25 4 3.60
48.10
Rs.252.24
12132.74 Basement3.1.1.3 (Rs.) (Rs.)
Col., pillar, post
a. 8 0.45 11.5 4 165.60
2 1 11.5 4 92.00
257.60
Rs.364.01
93768.98 all floors 3.1.1.4 Sides and soffits of beama For depth not exceeding 1M ii Using 25mm thick plank
Beam 1 49.32 0.4 3 59.18 Lintels 1 49.32 0.15 3 22.19 81.37
Rs.202.44
16472.54 all floors staircase 1 12.76 0.3 2 7.66 1 12.76 1.7 1 21.69 20 1.7 1 0.15 5.10 2 1 4 2.8 22.40 2 2 4 0.15 2.40 2 2 2.8 0.15 1.68 60.93Rs.496.80
30270.02 all floors 3.1.1.5 Flat surface such as soffits of suspende floora Floor etc. upto 200mm in thickness ii Using 25mm thick plank
Roof slab 1 16.86 19.5 1 328.77
328.77
Rs.429.93
141348.09 all floors 7 4.1.4 Brickwork in cement mortar with 1st class bricksb In proportio 1:4 Unit: Cu.m
Building
1 49.32 0.75 0.23 8.51
8.51
###
49875.92 Basement8 4.1.8 112mm thick 1st class brick nogged wall in cement mortar
1 49.32 11.5 1 567.18
Mark APWD Nos. Length (M) Width(M) Height(M) Quantity Rate Amount
Less
-8 2.1 1.07 -17.98 D1
-21 2 1.6 -67.20 W1
-21 2 0.45 -18.90 V1
463.10
Rs. 653.01
302408.93 all floors 9 26.1.3 Pre construction anti - termite treatment by applying in the entire levelled area after plinth fillingUnit: Sq.m
1 70.47 77.09 5432.53 Basement
10 26.1.4 Pre construction anti - termite treatment by applying in the junction of walls, column with the floor Unit: Sq.m
a 49.35
Rs. 168.27
8304.12 Basement11 4.1.1 Providing brick soling in foundation etc
a Brick flat soling Unit: Sq.m
1 15.66 4.5 1 70.47
-9.8 -9.80
60.67
Rs. 368.71
22369.64 Basement12 1.3 Earth/sand filling in plinth
C. With river sand or silt Unit: CuM
1 15.66 4.5 0.3 21.14
1 0.25 0.25 9.8 -0.61
20.53
Rs.345.61
7095.37 Basement 13 2.1.2 (b) PCC floor base. 50mm thick Unit: Sq.m1 15.66 4.5 1 70.47
-9.80
60.67
Rs. 253.28
15366.50 Basement 14 6.2.2 15 mm thick Cement plaster in single coat on A.)rough side of single or half brick wall for interior(a). In cement mortar 1:6 Unit: Sq.m
463.10
Rs. 127.87
59216.60 all floorsB) On fiar side 463.1
Rs. 126.34
58508.05 all floors15 13.2.2 c) Applying one coat of distemper primer of approved brand and manufacture on wall surfac
Unit: Sq.m
463.10
Rs.35.17
16287.23 all floors16 6.2.1 (b) 10mm cement plaster on wall/concrete Unit: Sq.m
3 15 2.5 0.25 28.13
1 160.24 2 1 98.12
126.25
Rs. 116.85
14752.31 all floors 17 9.1.2 Providing wood work in frame (chowk aths) of doors, windows, clerestory windows(b). With 1st class timber (Hollock/ Sundi) Unit: Cu.m
32 0.1 0.075 6.34 1.52 D1
21 0.1 0.075 7.2 1.13 W1
21 0.1 0.075 4.9 0.77 V1
3.42
###
264961.08 all floors 18 13.6.4 (a) Applying priming coat over new wood based surfaces up to 100mm in girth/widthUnit: Sq.m
297.50
Rs.3.95
1175.13 all floors19 5.1.10 cement plaster skirting Unit: Sq.m
a In proportion 1:3 12.33
Rs.230.44
2841.33 all floorsUnit: Sq.m
Mark APWD Nos. Length (M) Width(M) Height(M) Quantity Rate Amount
Staircase: 1 60 0.6 1.8 64.80
Floor 1 1 45 1 45.00
Landing 1 4 1.2 2.4 11.52
121.32
###
229424.61 all floors21 9.9.3 (b) (i) wooden panelled door Unit: Sq.m
3 1 1.95 1 5.85
5.85
###
21880.99 all floors 9.9.7(b) (i) Providing, fitting and fixing fully glazed window with sash bars1 7 2 1.3 18.20
###
35808.86 all floors22 13.3.2 Providing two coats of acrylic water based wall putty Unit: Sq.m
wall 463.10
ceiling 241.88
704.98
Rs.52.10
36729.46 all floors13.2.3 A cement primer Unit: Sq.m
1 1 1 463.1 463.10
Rs.40.66
18829.65 all floors23 15.2.1 Door and window fittings Unit: Nos.
a.1. sliding door bolt 10.00
Rs. 272.17
2721.70 all floorsb.1. tower bolt 20.00
Rs. 140.90
2818.00 all floorsb.ii 20.00
Rs. 121.86
2437.20 all floorsd.v 40.00
Rs. 60.27
2410.80 all floorse.ii 40.00
Rs. 77.75
3110.00 all floorsc.i 44.00
Rs. 36.49
1605.56 all floors24 16.1.2. b. Glass fitting Unit: Sq.m
1 21 1.2 1.3 32.76
Rs.562.01
18411.45 all floors25 18.4.1. Providing and fixing in position collapsible M.S. shutters Unit: Sq.m
1 3.00 2.4 7.2 4245.50 30567.60 basement
26 6.2/iv. Septic tank 25 user 1 22227.60 22227.60 for all floors
Total = 3387939.69
So, Cost of Civil Works = 3387939.69
Services
27 Internal Water Supply works(5% of the cost of civil works) 169396.98 for all floors 28 Internal electrification(5% of the cost of civil works) 169396.98 for all floors
Grand Total = 3726733.65
A. Basement construction cost with foundation & footings = 1151471.09
B. Upper Ground Floor construction cost = 841569.17
C. 1st floor construction cost = 858111.09
D. 2nd floor construction cost = 875582.31
Grand Total = 3726733.66
Say, Rs. 37,27,000.00
(Rupees Thirty Seven Lakh Twenty Seven Thousand) only
Prepared by,