• No results found

Large Systems Commissioning

N/A
N/A
Protected

Academic year: 2021

Share "Large Systems Commissioning"

Copied!
34
0
0

Loading.... (view fulltext now)

Full text

(1)

Large Systems Commissioning

Large Systems Commissioning

Kirsten Zapfe, DESY

CAS Vacuum in Accelerators

Platja D`Aro, May 21, 2006

(2)

Outline

z

Introduction

z

Pump Down and Leak Check

z

Components Check

z

Bake Out

z

Interlocks/Safety

z

Cryogenic Systems

z

First Beam

z

Concluding Remarks

(3)

Introduction

z

Accelerator vacuum system

’

beam intensity

beam lifetime

beam stability

static pressure

dynamic pressure

beam pipe aperture

material

rf shielding

(4)

Introduction

Commissioning

system meets the needs and

expectations of the user

required performance accessible with

(5)

Introduction

verification of system

performance

pressure

residual gas composition

outgassing

pump down times

conditioning time

preparation for standard

operation

functionality

safety

remote operation

add equipment

(6)

Introduction

Premises for “smooth”

commissioning

proper planning

overall system design

choice of materials and

manufacturing techniques

choice of vacuum equipment

specifications

vacuum controls

availability of continuous

monitoring and data logging

quality control

design and manufacturing of

components

handling procedures

cleaning

testing

installation

(7)
(8)

Introduction

z

Large systems

z

length

z

number of components

z

complexity

Example

z

LEP

z

27 km circumference

z

~ 2700 bellows

z

~ 7000 feedthroughs

z

~ 2200 pick-up connections

z

~ 700 gauges

z

130 sector valves

z

520 roughing valves

z

1900 sputter ion pumps

z

13.000 flanged connections

TTF/FLASH

DESY

(9)

Pump Down and Leak Check

z

Proper fixture of components

z

loose/fixed points

z

bellows

z

Pressure decay

¬

first hints for leak

z

check with RGA or pressure rise method

z

Leak Check

z

gross check p < 10

-4

mbar

z

fine check p < 10

-6

mbar

z

flanged connections, ceramics, feedthroughs, windows

z

equipment

z

mobile pump station with leak detector/RGA

z

systematic work necessary

z

switch of sputter ion pumps

¬

avoid spoiling with He in case of leak

(10)

Pump Down and Leak Check

z

Conditioning of vacuum system without beam

z

activation of titanium sublimation pumps

z

activation of NEG pumps

z

Observe behavior of pressure

¬

repeat leak check if necessary

LEP

O. Gröbner

HERA

(11)

Bake Out

z

System check

z

equipment (heaters, thermocouples, cabling)

z

functionality

¬

reliable attachment of sensors

z

heating process (

Δ

T/time, …), automation

z

interlock

z

power failure

z

failure of equipment

z

pressure rise/leak

z

Cooling of critical components

z

magnets, monitors, etc.

z

During bake out

z

avoid large temperature gradients

z

check movement of components due to heating

z

observe pressure for leaks

vacuum chamber

magnet

(12)

Components Check

z

Vacuum equipment

z

correct allocation

z

components

¬

cables

¬

electronics

z

display on computer

z

functionality of pumps, gauges, valves, etc.

z

Vacuum control

z

remote operation of components

z

functionality

z

add/improve handling options

z

modify/integrate additional parameters

(13)

Components Check

z

Movable elements

(collimators, diagnostics, …)

z

correct path length

z

end switches

z

remote operation

¬

check for pressure increase during movements

z

Special equipment of experiments

z

e.g. gas inlet systems

z

Final alignment

z

be careful shifting components

under vacuum

¬

temporarily unfixed components

(14)

Interlocks/Safety Checks

z

Self safe operation of system

z

failing of equipment (pumps, gauges)

z

Vacuum interlocks

¬

closing of valves

z

pressure increase

z

failing of equipment (pumps, gauges)

z

switching off equipment

z

Fast shutters/delay lines

TTF/FLASH

prepare adequate tools for

check-out in advance

(15)

Interlocks/Safety Checks

z

Beam interlocks

z

linear accelerator

¬

stop beam production

z

storage rings

¬

dump beam

z

Different modes of beam operation

z

injection

z

user beam lines

z

Interlocks connected to other systems

z

diagnostics

z

experiments

(16)

Cryogenic Systems

z

Superconducting magnets

z

beam pipe partially surrounded by liquid helium

e.g. Tevatron, HERA, RHIC, LHC

(17)

Cryogenic Systems

z

Superconducting accelerating structures (cavities)

z

cavities = beam pipe surrounded by liquid helium

e.g. Tristan, LEP, CEBAF, TTF/FLASH, XFEL, …

beam vacuum system (2K)

coupler vacuum system (RT) insulating vacuum system

TTF, XFEL

(18)

Cold Beam Vacuum Systems

z

Leak check of final connections

z

flanges, in-situ welds

z

no leak check under cold conditions possible

z

extreme care necessary, e.g. integral leak check

Beam lines movable

Plug-in module

Beam lines fixed Cold bore

Cooling tubes Beam screen

Cooling tube exit pieces

(19)

Cold Beam Vacuum Systems

z

Pressure before cool down

z

permanent pumps (e.g. sputter ion pumps)

z

HERA: p ~ 10

-6

mbar

z

no active pumping after pump down

(20)

Cold Beam Vacuum Systems

z

Cool down

z

beam pipe = cryo pump

¬

pressure drop

z

Measure integral leak rate and wall coverage

z

release of gas during warm up measured with RGA

HERA

RT

¬

4.5 K

(21)

Insulating Vacuum Systems

z

Segmentation

z

distance of vacuum barriers has increased with time

z

HERA

¬

20 m

z

RHIC

¬

500 m

z

LHC

¬

200 m

¬

larger distance = increased complexity for commissioning

L H C AR C : CR Y O G E N IC A N D IN S U L A T IO N VA C U U M BA S E L IN E D E S IG N

A B A B A B A B A B A C D A B A B A B A B A B A B A

Insulatio n V acu um sectorization:

M agnet vacuum barriers Jum per vacuum barriers Cryogenic line vacuum barriers

C old-m ass sectorization:

Bus-bar plugs Safety relief valves C ooldow n and fill valves

QR L vacuum jacket

M agnet vacuum vessel

(22)

TTF/XFEL

z

Pump down

z

equipment

z

start with large roughing pumps

z

sufficient mobile pump stations necessary

z

initial pump down dominated by large amounts of water

from super insulating foils

z

be prepared for frequent maintenance of roughing pumps

z

eventually flushing with N

2

Insulating Vacuum Systems

(23)

Insulating Vacuum Systems

Example

10 days

first pump down takes a long time

RHIC

D. Hseuh et al

.

(24)

Insulating Vacuum Systems

z

Leak check of air leaks

z

equipment

¬

sufficient granularity important

z

leak detectors at mobile pump stations and/or directly attached to tank

¬

base pressure usually not sufficient for RGA

z

gauges

z

He background in tunnel may be significant

z

leaks from cryogenic He supply lines

z

no exhaust line for roughing pumps

¬

HD as alternative to He as tracer gas

z

dead time could be significant

z

large leaks are not exceptional

z

at high pressure small leaks are not detectable

z

needs to repair large leaks first

(25)

Insulating Vacuum Systems

z

Leak check of air leaks (cont’d)

z

O-rings

z

permeation determines detection limit for leaks

z

permeation takes time

¬

might simulate leak due to delay

in signal

dead time 10 s He at t=0

(26)

Insulating Vacuum Systems

z

Leak check of process lines

z

equipment

z

same as for leak check of insulating vacuum

¬

leak detectors/gauges

z

sufficient He compression in case of He leaks necessary

z

with insulating vacuum pumped down

z

pump out process lines

¬

background level

z

pressurize one line after the other

e.g. HERA: 15 bar He

(27)

Insulating Vacuum Systems

z

Leak check of process lines (cont.)

z

leak location

z

often not easy to find

¬

sufficient diagnosis mandatory

¬

profile of He signal

z

vent insulating vacuum, open sliding sleeves,

check welds, etc.

¬

pressurized with sniffer

¬

pressurized with vacuum tight fixtures

locating and repairing He leaks

-difficult and time consuming effort

(28)

Insulating Vacuum Systems

z

Cool down

z

check for movement of components due to

shrinkage of materials

z

pressure drop

z

10

-3

mbar required before cool down

z

10

-6

mbar required for routine operation

¬

remove part of mobile pump stations

z

check for condensation/freezing of water

z

thermal bridges

z

monitoring of He signal

z

leaks from process lines

¬

locate after warm up

¬

cold leaks

HERA

4.5 K

(29)

Insulating Vacuum Systems

z

Leaks which can not be localized or repaired

z

He leaks

z

inside magnets, cavities, …

¬

add pump stations at insulating vacuum

z

air leaks

z

flanges on insulating tanks, …

¬

glue, rubber mastic …

HERA

4.5 K

(30)

Insulating Vacuum Systems

z

Observe also beam vacuum

z

during leak check of process lines

z

during cool down

¬

direct leaks from (liquid) He

at sc. cavities/ sc. Magnets

¬

leaks against insulating vacuum

¬

combined leaks:

process lines

¬

insulating vacuum

¬

beam vacuum

z

less critical if leak against insulating vacuum

z

not so nice

¬

He leaking into beam vacuum

¬

supply sufficient pumping speed for He

e.g. sputter ion pump with enhanced He pumping speed

e.g. charcoal (RHIC)

(31)

First Beam

z

First passage of beam …

… possible reasons if the beam does not pass

z

closed valves

z

obstacles, e.g. rf fingers

z

z

proper functioning of magnets, etc.

z

Check heating of components

z

proper rf-shielding

(32)

First Beam

z

Beam life time

z

Beam-gas effects

z

Pressure behavior

z

thermal heating

z

photon-induced desorption

z

Conditioning of vacuum with beam

z

cleaning of surface

¬

beam scrubbing

LEP

O. Gröbner
(33)

Concluding Remarks

z

Sufficient time for systems tests necessary

z

installation of vacuum system is one of the final steps of accelerator installation

z

time slot often reduced due to delays of preceding steps

z

pump down can not really be speed up

Commissioning

(final) proof of correct

layout

design

manufacturing and

installation

proper planning of commissioning

=

(34)

References

Related documents

As most consumers involved in the questionnaire survey are aware of the positive effects of drinking milk and dairy products and are trying to keep their consumption in

Stimulating the enthusiasm of young volunteers for environmental protection, 1000 Environment-Friendly Youth Ambassador Action Program encourages and supports their active

In this simple experiment, we will be creating our own battery with the use of citrus fruits, with a power that is strong enough to make a small bulb light up.. Later on, we

Price level (t-1) is the lagged value of the PPP factor (from OECD); DNEER(t-1) is the lagged value of the rate of appreciation of the nominal effective exchange rate (from

Public Health Informatics Innovation and Dissemination through the Beacon Communities.. Saira Haque, PhD, MHSA Diana Danoff, MA

In an article in Business Officer, Duin and others (2002) describe three basic organizational approaches to distance learning: adding bolt-on programs and new services to

The results from a survey of 30 practitioners showed that project scope management, project time management and project cost management are the three most important skills for

In the relatively more sustainable narratives,s, e.g., SSP1 and SSP5, climate policy does not bring large further reductions in air pollution; but in cases of more heterogeneous