DESIGN OF AN EXTENDED AERATION TREATMENT PLANT
2300
P.E.
CADANGAN PEMBANGUNAN BERCAMPUR DI ATAS TANAH KERAJAAN
SELUAS 30.0EKAR, MUKIM PEDAH, DAERAH JERANTUT, PAHANG DARUL MAKMUR
UNTUK TETUAN DOYENVEST (M) SDN BHD
BASIC DATA:
This is an outline design to produce 10:20 BOD5:SS effluent.
Population, PE = 2300 P.E
Dry Weather Flow, DWF = 0.225
Suspended Solid, SS = 300mg/l
BOD5, BOD = 250mg/l
Influent Ammonia NH3-N = 30mg/l
Effluent BOD5, EBOD = 10mg/l
Effluent SS ESS = 20mg/l
Effluent Ammonia ENH3-N = 10mg/l
LOADING
a. Hydraulic flow, Qavg = PE * DWF
= 517.50
b. Peak Flow, Qpeak = Peak Factor * Qavg
-0.11
Peak Flow Factor Pff = 4.7(P)
= 4.29
Therefore, Qpeak = Pff x Qavg
= 2219.31
= 1.54
c. Suspended Solids Loading Rate = Qavg * SS
= 155.25 kg/d
d. BOD5 Loading Rate = Qavg * BOD
= 129.38 kg/d
e. NH3-N Loading Rate = Qavg * NH3-N
15.53 kg/d m3/c/d
m3/d
m3/d m3/min
PRIMARY BAR SCREEN DESIGN
Design Population, PE 2300
Design Flow, Qavg 517.50 0.0060 l/s
Peaking Factor, PF 4.29
Peak Flow, Qpeak 2219.31 25.81 l/s
Guidelines : Quantity of screenings = 30 m3 screening / 10^6 m3 wastewater
Number of Channels = 1
Number of Back-up Channel = 1
Qavg = 517.50
Quantity of Screenings = Qavg x 30 / 1000000
= 0.0155
Provide storage for 7 days
Quantity of Screenings = 7 x Quantity of Screenings per day
= 0.109
Number of Storage Units = 1
Quantity per Unit = 0.109
Dimension of screenings trough
L = 0.50m
W = 0.30m
D = 0.30m
Volume = 0.045 > 0.109 error
Screen Design
Guidelines: Max flow through velocity at Qpeak Vmax = 1.0 m/ses Guidelines: Min approach velocity at Qpeak Vmin = 0.3 m/sec
Bar Size Bs = 10mm
Clear Opening Co = 25mm
Efficiency Coefficient Eff = Clear Opening
Clear Opening + Bar size
= 0.71
Clear area through each screen at Qpe AQpeak = Qpeak Vmax x 24 x 60 x 60
= 0.026
Total cross sectional area of channel AC = AQpeak Eff
= 0.036
Assume, Depth of Flow at Qpeak D = 0.050m
.
Required Width of Clear Opening @ Q Wclr = AC / D
= 0.72 m Number of Openings No = Wclr x 1000 Co = 29 m3/day m3/day m3/day m3/day m3 m3 m3 m3 m2 m2
Number of Bars Nbars = No - 1
= 28
Gross Width of Screen Wch = Wclr + (Nbars x Bs / 1000)
= 1.00 m
Set Wch = 0.50m
Check velocities
Qpeak = 2219.31 0.02569 m3/sec
Velocity of approach Vapp = Qpeak / (Wch x D)
= 1.03 m/sec > = 0.30 m/sec ok
Velocity through screen Vscr = Qpeak / (Wclr x D)
= 0.71 m/sec < = 1.00 m/sec ok
Hydraulic Profile Through Screen
Headloss Through Clean Screen
Formula: HLc = .0729 (V^2 - v^2)
where HLc = ? Clean screen max headloss (m)
V = 0.71 Velocity through screen (m/s) v = 1.03 Approach velocity (m/s)
Therefore HLc = -0.04 m
Elevation of Channel Invert = 76.75m Upstream Water Elevation = 76.76 m Downstream Water Elevation = 76.80 m Headloss Through Half Clogged Screen
Assume velocity through screen is doubled
Formula: HLc = .0729 (V^2 - v^2)
where HLc = ? Clogged screen max headloss (m)
V = 1.429 Velocity through screen (m/s) v = 1.03 Approach velocity (m/s)
Therefore HLc = 0.07 m
Elevation of Channel Invert = 76.75 m Upstream Water Elevation = 76.87 m Downstream Water Elevation = 76.80 m
PUMP SUMP DESIGN
Influent at Qpeak Influent = 2219.31 25.69 l/s
Influent at Qavg Influent = 517.50 5.99 l/s
Dimension of pump station L = 1.80m
W = 1.50m
Depth between start and stop D = 0.65m
Chamfer volume v = 1/2 x ( 2.05 x 0.2 x 0.4 )
= 0.072
Therefore effective volume to fill /drain
V = L x W x D - v
= 1.68
Pumping rate @ Qpeak P = 26.00l/s >= 25.69 l/s ok
Pump cycle time at Qavg
Guideline: 6 min, 15 max @ Qavg
Volume required for pump sump, V = T x q
4
Assume number of start / stop = 15 times per hr (required 6 - 15 start/hour)
where V = ? Required Volume (m3)
T = 4.0 Cycle Time (minute)
q = 26.00 Pumping Rate (L/sec)
= 1.56 Pumping Rate (m3/min)
Therefore, V = 1.56 1.68 ok
Pump Headloss Calculations
VALVES & FITTINGS K QUANTITY DISCHARGE
VALUE TOTAL
EXIT 1.00 1 1.00
CHECK VALVE 2.50 1 2.50
GATE VALVE 0.20 1 0.20
TEE THRU SIDE 1.80 1 1.80
ELBOW - 90 DEG 0.30 6 1.80
SUM OF K's FOR FITTINGS 7.30
PIPE DIAMETER 0.20 m
PUMPING RATE 26.00 L/sec
V = VELOCITY 0.83 m/sec
F = TOTAL FITTING HEAD LOSS 0.25 m
= (K x V2 / 2g)
L = LINEAR METER OF STRAIGHT PIPE 8.00 m
C = HAZEN-WILLIAMS ROUGHNESS COEFFICIENT 100.00
P = HEAD LOSS USING HAZEN-WILLIAMS EQATION 0.05 m
TOTAL LOSS = F + P 0.30 m
S = STATIC HEAD LOSS (Worst Case Scenerio) 79.60 - 76.00 m 3.45
TOTAL DYNAMIC HEAD 3.75 m
m3/day or m3/day or
m3
m3
Size pump for 26.00 L/sec @ 3.75 m TDH
The submersible pump selected is as
follows:-Make = TSURUMI Model = 100B42.2 Capacity = 18.20 L/sec Total Head = 6.20 m Power = 2.20kW Discharge Size = 100 mm
No. of Units = 2(1 duty; 1 standby)
CHANNEL INVERT EL 76.75
0.0 m
HIGH LEVEL ALARM EL 76.75
0.15 m
STANDBY PUMP CUT IN EL 76.60
0.15 m
DUTY PUMP CUT IN EL 76.45
0.65 m
ALL PUMPS CUT OFF EL 75.80
0.4 m
INVERT ELEVATION EL 75.40
Pump cycle time at Qpeak
Guideline: 6 min, 15 max @ Qavg
Time to fill sump = V
Qpeak
= 1.09 min
Time to empty sump = V
Qpump - Qpeak
= -3.75 min
Cycle time base on actual operating point = 60 min per hour Time fill + Time empty min per cycle
= -22.6 cycle per hour 6 - 15 cycle / hr error
Determine Size of Force Main
Guideline: 1 - 2.5m/s velocity in pipe
Required size of raw sewage pipe = =
= 0.115 m
= 100 mm > 115 mm error
Actual velocity in selected pipe = Qpump / cross section area of pipe
2.32 m/s < 2.5 m/s ok
[ 4 x Qraw / (2.5 m/s x 3.14] 1/2 [ 4 x 0.0182 / (2.5 m/s x 3.14] 1/2
Determine Total Dynamic Head ( TDH )
TDH =
Where ; = Static head (m) …………A
= Losses through the pipe ( Hazen - William Formula ) …………B
= Losses through fittings …………C
A = 79.60 - 76.00m
= 3.45 m
B Hazen - William Formula
= 6.82 1.85 x L
C
Where ; V = Velocity m/sec
V = Q / A = 11.50 L/sec = 0.83 m/sec C = Coefficient of roughnes = 100.00 L = Length of pipe, m = 8.00 m D = Diameter of pipe, m = 0.20 m = 0.050 m
C Losses through fittings
= KV²
2g
Where ; K = Head loss coefficeint 7.30
V = Velocity m/sec 0.83
G = Gravity, m/s² 9.81
= 0.25 m
Therefore ,
Total Dynamic Head ( TDH ) =
= 3.76 m
To plot chart for the System Curve & Pump Curve from the above
equitition:-Q (L/s) V (m/s) hst (m) hf (m) hm (m) TDH (m) 0 0.00 3.45 0.000 0.000 3.45 16.0 3.33 0.11 3.45 0.001 0.004 3.46 14.0 6.67 0.21 3.45 0.004 0.017 3.47 12.6 10.00 0.32 3.45 0.009 0.038 3.50 10.8 13.33 0.42 3.45 0.015 0.067 3.53 9.0 16.67 0.53 3.45 0.022 0.105 3.58 7.0 20.00 0.64 3.45 0.031 0.151 3.63 5.2 23.00 0.73 3.45 0.040 0.199 3.69 3
* refer to Chart attached
hst + hf + hm
hst
hf
hm
Thus, static head of pump, hst
hf V
D1.167
1000 x 3.142 x 0.10 2 / 4
Thus, losses through the pipe, hf
hm
hm
hst + hf + hm
Pump head (m)
0
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
0.00
5.00
10.00
15.00
20.00
INFLUENT RAW SEWAGE PUMP
(TSURUMI MODEL 100 B42.2)
Flowrate, Q (L/sec)
H
ea
d
(m
)
System Curve
Pump Curve
Pump Operating Point
18.2L/sec @ 5.5 m TDH
FINE SCREEN DESIGN
ParametersPopulation PE = 2,300
Peak Flow Qpeak = 2219.31
= 0.03
Design Flow Qavg = 517.50
= 0.01
Guidelines: Max flow through velocity at Qpeak Vmax = 1.00m/sec Guidelines: Min approach velocity at Qpeak Vmin = 1.00m/sec
Set Elevation of Datum Hd = 0.00m
Design
Bar Size Bs = 10.00mm
Clear Opening Co = 12.00mm
Efficiency Coefficient Eff = Clear Opening
Clear Opening + Bar size
= 0.55
Clear area through each screen at Qpeak, AQpeak = Qpeak Vmax
= 0.0257
Total cross sectional area of channel required = AQpeak Eff
= 0.05
Assume Depth of Flow D = 0.055m - - - 1
Width of Clear Openings Wclr = AQpeak / D
= 0.47 m
Number of Openings No = Wclr x 1000
Co
= 39
Number of Bars Nbars = No - 1
= 38
Width of Frame Wfr = 0.10m
Gross Width of Screen W = Wclr + Wfr + (Nbars x Bs / 1000)
= 0.95 m
Set width of screen W = 0.50m
Determine Width of Downstream Throat
Total Peak Flow, Qpeak = 1.71 B (H^1.5)
Qpeak = 0.026 m3/s
Set depth of flow H = 0.055 m from - - 1
Determine width of throat B = ? m
Therefore B = Qpeak / 1.71 / (H^1.5)
= 1.16 m
= Throat width of grit chamber m3/day m3/sec m3/day m3/sec m2 m2
Energy equation between upstream and downstream of clean screen Velocity at Qpeak through clear openings of screen, Vs
Vs = Qpeak
Wclr x d1
= 0.65 m/sec
Headloss through clean screen hLs = (Vs^2 - v1^2) / 2g x 1/0.7
= 0.0039 m
X2 E2 + d2 + (v2^2 /2g) =
X3 = E3 + d3 + (v3^2 /2g) + hLs
X2 = X3
Where,
E2 = 0.000m Height above datum
Trial and Error d1 = 0.09m Upstream Depth
v1 = 0.60 m/sec Upstream Velocity
E3 = 0.000m Height above datum
d2 = 0.055 m Downstream Depth @ Qpeak
v2 = 0.93 m/sec Channel Velocity
Therefore, X2 = 0.10
X3 = 0.10 ok
0.000 Elevation of Channel Invert = 79.00m Upstream Water Elevation = 79.09 m Downstream Water Elevation = 79.06 m
Energy equation between upstream and downstream of 50% clogged screen
Headloss through clogged screen hLcs = (Vcs^2 - v2^2) / 2g x 1/0.7
Velocity through clogged screen Vcs = Qpeak
(Assume 50% clogging) Wclr x 0.5 x Upstream Depth d"
= 0.92 m/sec hLcs = 0.05 Therefore, X2 =E2 + d" + (v"^2 /2g) X3 = E3 + d3 + (v3^2 /2g) + hLcs X2 = X3 Where,
E2 = 0.00m Height above datum
Trial and Error d" = 0.120m Upstream Depth
v" = 0.43 m/sec Upstream Velocity
E3 = 0.00m Height above datum
d3 = 0.055 m Downstream Depth @ Qpeak
v3 = 0.93 m/sec Channel Velocity
Check:
X2 = 0.13
X3 = 0.15 ok
-0.018 Elevation of Channel Invert = 79.00 m Upstream Water Elevation = 79.12 m Downstream Water Elevation = 79.06 m
DESIGN OF A CONSTANT VELOCITY GRIT CHANNEL
Guidelines = 0.2 m/s flow through velocity
Number of Channels Provided = 1
Number of Back-up Channels Provided = 1
Constant Velocity Channel Formula
Q = Q = Flow B = Width of Throat m H = Depth of Flow m Therefore, = ( Q / 1.71 / B )^0.67 Area of Parabola, A = 2/3 W H W = Width of Parabola m H = Depth of Flow m Assume: V = 0.2m/s (Per guidelines) Q = A x V = 2/3 W H x V Therefore W = 1.5 Q H x V Assume: B = 0.33m
Qavg per Channel = 517.50 0.0060
FLOW FACTOR Depth Width
( x QAVG) m3/sec H(m) W(m) 0.10 0.001 0.01 0.43 0.25 0.001 0.02 0.58 0.50 0.003 0.03 0.73 1.00 0.006 0.05 0.92 @ Qavg 2.00 0.012 0.08 1.16 3.00 0.018 0.10 1.33 4.00 0.024 0.12 1.46 4.29 0.026 0.13 1.50 @ Qpeak 5.00 0.030 0.14 1.57 6.00 0.036 0.16 1.67 7.00 0.042 0.18 1.76
Determine Length of Channel
Say settlement vel of particle Vs = 0.02m/s
Say velocity of flow V = 0.2 m/s
Depth of channel at peak flow, H = 0.13 m
Width of channel, W = 1.50 m
Length of Channel L = V x H
Vs
L = 1.29 m
Provided Length L = 3.00m
Surface Area of Channel SA = 4.49
Surface Overflow Rate SR = Qpeak / SA
= 494.50 < 1500 1.71 B (H1.5) m3/s m3/day m3/s Q AT DIFFERENT FACTOR m2 m3/m2/day m3/m2/day
Quantity of grit
Guidelines = 0.03 m3 / 1000 m3 of wastewater
Grit Quantity per Channel = Qavg x 0.03/1000
= 0.016
Provide area for 30 days storage
Grit quantity = 0.47
Dimension of hopper at bottom of grit channel
L : W ration 2:1 as per guidelines
L = 3.00 m W = 0.50m D = 0.15m Volume = 0.225 >= 0.466 ok 1500 mm 700 mm 50 mm 450 mm 1000 mm
Check ratio of grit tank dimension
Ratio W: D = 1 : 2 W D
2.00 1
Ratio W: L = 1 : 2 W L
1 2
Hydraulic Retension Time, Tr
Guidelines = 3 min @ Qpeak < 5,000 pe
Area of retangular = 1.05
Area of trapezium = 0.06
Area of grit storage = 0.45
Total Area = 1.56 L = 3.00 m Volume, V = 4.69 = 2219.31 = 1.54 Tr = = 3.04 min >= 3 min ok m3/day m3 m2 m2 m2 m2 m3 Qpeak m3/day m3/min V / Qpeak
X-Axis
Y-Axis
-0.837
0.161
-0.787
0.143
-0.748
0.129
-0.731
0.123
-0.664
0.101
-0.580
0.077
-0.460
0.049
-0.365
0.031
-0.290
0.019
-0.214
0.011
0
0
0.214
0.011
0.290
0.019
0.365
0.031
0.460
0.049
0.580
0.077
0.664
0.101
0.731
0.123
0.748
0.129
0.787
0.143
0.837
0.161
-0.500
-0.400
-0.300
-0.200
-0.100
0.000
0.100
0.200
0.300
0.400
0.500
-0.100
0.000
0.100
0.200
0.300
0.400
0.500
0.600
0.700
CONSTANT VELOCITY FLOW CHANNEL
X - SECTION
Width (m)
D
ep
th
(
m
)
-0.500
-0.400
-0.300
-0.200
-0.100
0.000
0.100
0.200
0.300
0.400
0.500
-0.100
0.000
0.100
0.200
0.300
0.400
0.500
0.600
0.700
CONSTANT VELOCITY FLOW CHANNEL
X - SECTION
Width (m)
D
ep
th
(
m
)
GRIT STORAGE
Width
Depth
X - Axis
Y - Axis
0.427
0.011
0.580
0.019
0.731
0.031
0.921
0.049
1.160
0.077
1.328
0.101
1.462
0.123
1.496
0.129
1.575
0.143
1.673
0.161
-0.500
-0.400
-0.300
-0.200
-0.100
0.000
0.100
0.200
0.300
0.400
0.500
-0.100
0.000
0.100
0.200
0.300
0.400
0.500
0.600
0.700
CONSTANT VELOCITY FLOW CHANNEL
X - SECTION
Width (m)
D
ep
th
(
m
)
-0.500
-0.400
-0.300
-0.200
-0.100
0.000
0.100
0.200
0.300
0.400
0.500
-0.100
0.000
0.100
0.200
0.300
0.400
0.500
0.600
0.700
CONSTANT VELOCITY FLOW CHANNEL
X - SECTION
Width (m)
D
ep
th
(
m
)
GRIT STORAGE
-0.650
-0.450
-0.250
-0.050
0.150
0.350
0.550
-0.150
-0.050
0.050
0.150
0.250
0.350
0.450
0.550
0.650
0.750
0.850
0.950
1.050
1.150
1.250
CONSTANT VELOCITY FLOW CHANNEL
X - SECTION
Channel Width (m)
D
e
p
th
(
m
)
GRIT
STORAGE
DESIGN OF A GRIT / GREASE CHAMBER
Guidelines : Detension time T = 360 sec @ QpeakNumber of Channels Provided = 1
Number of Back-up Channels Provided = 1
Peak Flow Qpeak = 2219.31 m3/day
= 0.026 m3/sec
Detension Time T = 6min
= 360sec
Volume Required V = Qpeak x T
= 9.25 m3
Provide:
Length L = 2.90m
Width W = 1.60m
Depth D = 0.85m
Volume Provided V = 3.94 m3 > 9.25 m3 error
Ratio L : W = 1.81 : 1.0
W : D = 1.88 : 1.0 ok
Determine Length of Channel
Provided Length L = 2.90 m
Width of channel, W = 1.60 m
Surface Area of Channel SA = 4.64 m2
Surface Overflow Rate SR = Qpeak / SA
= 478.30 m3/m2/day
< 1500 m3/m2/day ok
Quantity of grit
Guidelines = 0.03 m3 / 1000 m3 of wastewater
Grit Quantity = Qavg x 0.03/1000
= 0.016 m3/day
Allow for storage of 30 days = 0.47 m3
Quantity of grease
Average quantity of grease S = 8kg / 1000 m3
Specific gravity of grease sg = 0.95
Therefore quantity of grease Qs = Qavg x S
= 4.14 kg/day
Flowrate of Grease Fs = Qs / 1000 / sg
= 0.0044 m3/day
Allow for storage of 30 days Vs = 30 x Fs
= 0.131 m3
Grit/Grease Drying Bed Sizing
Accumulated grease for 30 days Vs = 0.131 m3
Accumulated grit for 30 days = 0.466 m3
Depth of Feed D = 0.25m
Therefore, Area required A1 = 2.39 m2 Grease
Dimension of Grit/Grease Drying Bed
Length = 1.50m
DESIGN OF A GREASE CHAMBER
Guidelines : Detension time T = 180 sec @ Qpeak
Number of Chamber Provided = 1
Number of Back-up Chamber Provided = 1
Peak Flow Qpeak = 2219.31
= 0.026
Detension Time T = 180sec
Volume Required V = Qpeak x T
= 4.62 Provide: Length L = 3.80m Width W = 1.20m Depth D = 1.10m Volume Provided V = 5.02 4.62 ok Grease Quantities
Average quantity of grease S = 8
Specific gravity of grease sg = 0.95
Therefore quantity of grease Qs = Qavg x S = 4.14 kg/day Flowrate of Grease Fs = Qs / 1000 / sg
= 0.0044
Allow for storage of 30 days Vs = 30 x Fs
= 0.13
Depth of grease baffle required to contain scum for 30 days
Length L = 3.80 m
Width W = 1.20 m
Depth of water below baffle D = 0.02m
Volume of grease storage provided V = 0.09 0.13 ok
m3/day m3/sec m3 m3 > m3 kg / 1000 m3 m3/day m3 m3 > m3
WEIR BEFORE AERATION BASINS
not useDesign Population, PE 2300
Design Flow, Qavg 517.50 m3/day 0.01 m3/sec
Peaking Factor, PF 4.29
Peak Flow, Qpeak 2219.31 m3/day 0.03 m3/sec
Number of Aeration Basins, N = 1
Peak Flow to Each Aeration Basin = Qpeak / N
= 0.026 m3/sec
Formula Q(m3/sec) = Cw x Le x H^1.5
where Cw = 1.84 Weir Coefficient
Le = 0.3704 m Length
H = 0.148 m Height
With end contraction
Le = L - (0.1)nH
where L = 0.40m Length
n = 2 Number of side contractions
H = 0.148m Height of Flow
Therefore Le = 0.3704 m
Therefore Q = 0.039 m3/sec >= 0.026 m3/sec ok
Height of water above weir = 102mm Qpeak if both tanks open
Height of weir = 170mm Qpeak if one tank open
Therefore, size opening for 400mm x 250 mm H = 272 mm
RECTANGULAR WEIR AT OUTLET BOX
Design Population, PE 2300
Design Flow, Qavg 517.50 m3/day 0.01 m3/sec
Peaking Factor, PF 4.29
Peak Flow, Qpeak 2219.31 m3/day 0.03 m3/sec
Formula Q(m3/sec) = Cw x Le x H^1.5
where Cw = 1.84 Weir Coefficient
Le = 0.578 m Length
H = 0.11 m Height
With end contraction
Le = L - (0.1)nH
where L = 0.60m Length
n = 2 Number of side contractions
H = 0.110m Height of Flow
Therefore Le = 0.578 m
Therefore Q = 0.039 m3/sec >= 0.026 m3/sec ok
90 DEG V-NOTCH WEIR AT OUTLET BOX
Design Population, PE 2000
Design Flow, Qavg 450.00 m3/day
Peaking Factor, PF 4.35
Peak Flow, Qpeak 1959.73 m3/day 0.023 m3/sec
90 deg V-Notch Weir Formula
5/2
q (m3/sec) = 1.417 H
H (m) = 192mm or 0.192 m at Qpeak
Therefore, q = 0.023 m3/sec >= 0.023 m3/sec ok
DESIGN OF ANOXIC CHAMBER
Population PE = 2300 Peak Flow = 2,219.31 = 92.47 = 1.54 = 0.026 = 25.69 l/s Design Flow = 517.50 = 21.56 = 0.36 = 0.01 = 5.99 l/s Peaking Factor PF = 4.29Using the Lodification Ludzack-Ettinger Process
Assume
Influent Ammonia-N Ni = 30mg/l
Effluent Ammonia-N Ne = 10mg/l
Mixed liquor Suspended Solids MLSS = 3600mg/l
Mixed Liquor Volatile Suspended Solids MLVSS = 2880 mg/l (MVLSS = 0.8 x MLSS
Temperature Temp = 28deg C
Dissolved Oxigen Do = 0.1mg/l
Specific Denitrification Rate U = 0.11per day Overall Denitrification rate Ua = ? per day
Residence Time Temp = ? hrs
Calculation Overall Denitrification Rate
Formula : Ua =
0.20 per day
Calculation Residence Time
Formula : T = Ni - Ne
Ua x MLVSS x 24 hrs/day
= 0.81 hrs required
Size anoxic zone for a residence time of Anox = 2 hrs
Determine size of anoxic tank
Anoxic zone volume required, Vol = Anox x Qavg 24
= 43.13
Number of Anoxic Tank, N = 2 nos Volume required per Tank, Vreq = 21.56
Tank Dimension
Length = 2.30 m
Width = 1.50 m
Depth = 4.50 m
=
Anoxic tank volume = 31.05 > 21.56 ok
Actual hydraulic retention time provided = Anoxic tank volume Qavg = 2.88 hrs Qpeak m3/day m3/hr m3/min m3/s Qavg m3/day m3/hr m3/min m3/s U x 1.09(Temp-20)X(1-DO) m3 m3 m3 m3
EXTENDED AERATION TANK DESIGN
Sizing
Number of Aeration Tank, No. = 2
Minimum Hydraulic Retention Time, HRT = 19.4 hours
Volume Required, V = 418.31
Volume Required Per Tank, Vol = 209.16
Dimension of each tank: Ratio
Area A = 46.48 L : W Length L = 10.60 m 10.60 : 4.40 Width W = 4.40m 2.41 : 1 Depth D = 4.50m Freeboard FB = 0.65 m Volume Vol = 209.88
Total Volume Provided Vp = 419.76 418.31
Therefore, HRT Provided = 19.47 hrs > 19.4 hrs ok
Sludge Age (MCRT)
Guidelines > 20 days
Assume, MLSS = 3600mg/l
SA = Total solids in aeration tank
Excess sludge wasting / day + Solids in effluent Total solids in aeration tank = MLSS x Vp / 1000
= 1511.14 kg
Solids in effluent = 10mg/l
= 5.18 kg/day
Sludge Yield, = 0.40 @ 24 hours HRT = 0.60 @ 18 hours HRT Determine Sy @ Actual HRT
Via Interpolation Therefore actua = (24 -21.9) x (0.6 - 0.4) + 0.4 (24 - 18)
Sy = 0.55 kg / kg BOD removed based on HRT interpolation
Excess sludge wasting / day Sd = QAVG x Sy (BOD5-EBOD5)
(Sludge accumulation per day) = 68.45 kg/day
SA = 20.53 days ok
Waste Activated Sludge (WAS)
Excess Sludge Wasting / day WAS = 68.45 kg/day
Assume underflow concentration = 1% or 10,000 mg/l or 10 kg/m3
Volume of WAS = 6.84 = 6844.61 l/day m3 m3 m2 m3 m3 > m3 m3/day
Return Activated Sludge Flow (RAS)
QRAS = MLSS x QAVG
Cu - MLSS
Cu = Underflow concentration assume at 0.8 % solid or 8,000 mg/l
QRAS = 423.41 4.92 l/s
Set QRAS = 465.75 5.42 l/s
Qavg = 517.50
Ratio of QRAS : QAVG = 0.90 ok
Oxygen Requirements
Oxygen required per kg of BOD5 re OR = 2.00kg O2 / kg BOD5 Actual Oxygen Required AOR = OR x BOD5 removed
= 248.40 kg/day
Maintain DO of 2 mg/l in aeration tank
QAVG = 517.50
Total = 517.50
Oxygen required in tank = Total x 2 / 1000
= 1.04 kg/day
Total AOR = 249.44 kg/day
Oxygen correction factor AOR/SOR
AOR/SOR = (((BETA * ACF * Csf @ 28 deg) - C ) / Css ) * ALPHA * 1.024^T-20
Where BETA = 0.98 ACF = 0.989 Csf = 7.83 C = 1.5 Css = 9.08 Alpha = 0.75 T = 30 Therefore AOR/SOR = 0.64
Standard Oxygen Required SOR = 391.23 kg/day
O2 transfer efficiency O2eff = 20% @ 6 (See catalog)
Actual O2 transfer efficiency O2act = SOR kg/day
O2eff/100 x 1.201 kg/m3 x 0.232 kg O2/kg air x 1440 min/day Total amount of air required
= 4.88 m3/min
Number of diffusers required
Flowrate per diffuser = 0.10 or 6
= 100.00 L/min
Quantity = Total air required / Flowrate
= 48.75 Use 52 ok
Number of diffusers per tank = 26 Nos in each Aeration tank m3/day m3/day m3/day m3/day m3/day m3/hr m3/min m3/hr
Check F/M Ratio
Guidelines for F/M ratio is between 0.05 to 0.10 kg BOD / kg MLSS
Influent BOD5, = 250 mg/l = 129.38 kg/day MLSS = 3600mg/l Volume provided, Vp = 419.76 F/M Ratio = INBOD / (MLSS x Vp) = 0.086 ok
Check Aeration Loading
AL = INBOD / Vp
= 0.31 ok
Check Mixing Rate
Volume of air from Blower Va = #NAME? (See Blower calculations)
Volume of tank provided Vp = 419.76
Therefore, Mixing Rate = Va / Vp
= #NAME? #NAME?
m3
Guidelines : 0.1 - 0.4 kg/m3/day
kg/m3/day
Per EPA guidelines, 0.010 to 0.025 m3/min. m3
m3/min m3
CLARIFIER DESIGN
Guidelines : Hydraulic retension time (HRT) = 2 hours @ Qpeak Guidelines : Surface overflow rate = 30 m3/m2/day
Guidelines : Side water depth (SWD) = 3 m
Surface Area =
= 73.98
Number of clarifiers = 2
Surface area required per clarifier = 36.99 Dimension of each clarifier
L = 6.20m
W = 6.20 m
Therefore, actual area provided = 38.44 36.99 ok
Provided Length, L = 6.20 m
Provided Width, W = 6.20 m
Effective Volume = Volume of cone with slope of 60 deg.
SWD in cone = 3.46 m (See attach volume cals)
Cone volume = 65.73 ok Vertical SWD = 1.04m Vertical SWD volume = 39.98 Total Volume = 105.70 Total SWD = 4.50 m HRT
Per guidelines: < 2 hours
=
= 2.29 >= 2 hours ok
Overflow Weir
Per guidelines: 150 - 180 m3/day/m
Max weir loading rate, Wr = 180 Peak Flow, Qpeak = 2219.31
Min Weir Length Required per Clarifier = Qpeak / Wr / No. of Clarifiers
= 6.16 m
Total length of weir provided per Clarifier, Tw = 3.00m
Actual weir loading rate = 369.89 error
Solids Loading Rate (SLR)
Guideliness : < 150 kg/m2/day at Qpeak < 50 kg/m2/day at Qavg
MLSS = 3600mg/l or 3.6
Total Q = Qpeak + QRAS
(For QRAS look under Extended Aeration Tank Sizing)
= #NAME?
SLR (Qpeak) = (Total Q / Actual Surface Area) x MLSS kg/day
= #NAME? #NAME?
SLR (Qavg) = (Qavg + Qras) / Actual Surface Area x MLSS kg/day
= #NAME? #NAME? Qpeak / 30 m3/m2/day m2 m2 m2 > m2 m3 m3 m3
Total Volume m3 / Qpeak m3/day x 24 hours
m3/day/m m3/day m3/day/m kg/m3 m3/day kg/m2/day kg/m2/day
Launder Calculation
Overflow from weir to lauder = Qpeak / number of tank
= 1109.66
Launder size
Length = 3.00 m
Width = 0.25m
Flow velocity = 0.80m /s < 1.0 m/s ok
Depth of flow in launder = 21.41 mm < 0.3m as provided
Determine Volume of Cone
L W L W h h 60 y BW 1 A BW2 B L = 6.20 m W = 6.20 m BW 1 = 2.20 m BW 2 = 2.20 m A = (L - BW1) / 2 = 2.00 B = (W - BW2) / 2 = 2.00 h = height of cone = A x Tan 60 3.46 m Tan y = h /B y = Tan -1 (h/B) = 60.00 degreesTherefore, Volume of Cone V = [ (1/3 x 2A x 2B x h) +(1/2 x 2A x BW2 x h) + ( 1/2 x (W + BW2) x h) ] V = 65.73 m3 L (m) W (m) h (m) A (m) BW1 (m)
Scum Withdrawal Airlift Pipe Design
Percent submergence
=
Hs / (Hs + Hl) x 100
Hs
=
Depth (m) of air pipe below water surface
Hl
=
Height (m) of lift
Scum Airlift
Hs
=
3.8
m
Hl
=
0.7
m
Percent Submergence
=
84.44 %
With reference to the attached chart, Discharge
=
45
gpm
2.84 l/s
Velocity
=
2
ft/sec
0.61 m/s
AEROBIC SLUDGE HOLDING TANK DESIGN
Guidelines: Sludge yield = 0.6 kg/kg BOD5 (Standard "A")
Design Population, PE = 2300
Design Flow, QAVG = 517.5
Sludge Yield Ys = 0.55kg/kgBOD5/day (Calculated earlier)
Sludge accumulation per day Sd = QAVG x Ys (BOD5-EBOD5)
= 68.31 kg
Temperature of Wastewater T = 28 Deg C
Percent Volatile Suspended Solid (VSS) VSS = 75%
Percent VSS Destruction VSSd = 55%
Influent to Digester WAS = 68.31 kg/day
Influent Solid Content Conc = 1%
Total Volatile Solid TVS = VSS/100 x WAS
= 51.23 kg/day Total Volatile Solid Destruction TVSd = VSSd/100 x TVS
= 28.18 kg/day
Therefore, Total Solids Remaining After Digestion TSd = Nonvolatile Solid + VS Remaining = (WAS - TVS) + { (1 - VSSd/100) x TVS } =
TSd = 40.13 kg/day
Density of water ρ = 1000.00 Specific gravity of sludge sg = 1.015
Therefore, TSd in term of volume = 3.95
Storage days provided T = 30days
Volume of Tank Required Vtank = 118.62
Number of Tank Provided No. = 1
Volume of Tank Required V = 118.62
SIZE OF EACH TANK
Depth = 4.5m Width = 3.3m Length = 8.0m Volume = 118.80 118.62 ok m3/day (26.73 - 20.05) + { (1 - 55/100) x 20.05) kg/m3 m3/day m3 m3 m3 > m3
OXYGEN REQUIREMENT FOR DIGESTION
Guidelines: 1.5kgO2/kgBOD
Wt of sludge digested Ws = Sd - TSd
= 28.18 kg
Amount of oxygen required, (AOR) Ws x 1.5 = 42.27 kg
Oxygen correction factor AOR/SOR
AOR/SOR = (((BETA * ACF * Csf @ 28 deg) - C ) / Css ) * ALPHA * 1.024^T-20
Where BETA = 0.98 ACF = 0.989 Csf = 7.83 C = 1.5 Css = 9.08 Alpha = 0.75 T = 30 Therefore AOR/SOR = 0.64
Standard Oxygen Required SOR = 66.29 kg/day Assume O2 transfer efficiency O2eff = 10%
Total amount of air required = SOR kg/day
O2eff/100 x 1.201 kg/m3 x 0.232 kg O2/kg air x 1440 min/day
= 1.65
Number of diffusers required
Flowrate per diffuser = 200.00L/min 0.200 Quantity =
Total air required / Flowrate =
8.26 Use 10 ok
m3/min
DRYING BED DESIGN
Digested Sludge From Aerobic Digester DS = #NAME?kg/day (See Aerobic Digester cals)
Concentration of Sludge C = 1%
= 10
Specific gravity of sludge sg = 1.015
Volume of Digested Sludge Vds = #NAME?
Per guidelines: Provide 4 week cycle for 450mm thick feed depth
Volume of Vds required V = Vds(m3/day) x 28days (Based on 21 days drying; 7 days feeding)
= #NAME?
Depth of Feed D = 0.45m
Therefore, Area required A = #NAME?
Provide fully covered drying beds
Therefore actual area required A = #NAME?
Number of Drying Beds provided = 4
Dimension of Drying Beds Dimension of Bed
Length = 16.50m
Width = 2.50m
Area = 41.25
Total area of drying bed provided = nos of bed x bed area
= 165.0 #NAME? ###
Determine Volume of Dewatered Sludge (DS)
Assume final sludge concentration is 25%
DS = Vs x Si x SGi x n
SGo x So
DS = ? Volume of Dewatered Sludge, (m3/day)
Vs = ### Volume of Influent Sludge (m3/day)
Si = 0.01Fractional Percent Solid Content of Influent Sludge So = 0.25Fractional Percent Solid Content of Dewatered Sludge SGi = 1.015Specific Gravity of Sludge Before Thickening
SGo = 1.03Specific Gravity of Sludge After Thickening
n = 0.95Fractional Percent Capture
Therefore
DS = ### @ 25% solid
Provide covered storage for 30 days
Volume required V = DS x 30 days
= #NAME?
Dimension provided Depth = 0.50m
Width = 1.00m Length = 4.60m Volume = 2.30 #NAME? kg/m3 m3/day m3 m2 m2 ( 1/3 reduction in area) m2 m2 > m2 m3/day m3 m3 > m3 ok
Drying Bed Feed Pump Design
Pump Sizing
Pumping rate per pump P = 9.10L/sec
= 546.00 L/min
Pump Headloss Calculations
VALVES & FITTINGS K QUANTITY SUCTION QUANTITY DISCHARGE
VALUE TOTAL TOTAL
ENTRY 0.50 1 0.50 0 0.00
EXIT 1.00 0 - 1 1.00
CHECK VALVE 2.50 0 - 0 0.00
SLUICE VALVE 0.20 0 - 1 0.20
REDUCER 0.30 0 - 1 0.30
TEE THRU SIDE 1.80 0 - 0 0.00
TEE THRU RUN 0.60 0 - 1 0.60
ELBOW - 45 DEG 0.23 0 - 0 0.00
ELBOW - 90 DEG 0.30 0 - 5 1.50
SUM OF K's FOR FITTINGS 0.50 3.60
PIPE DIAMETER 0.10m 0.10
PUMPING RATE 9.10 L/sec 9.10
V = VELOCITY 1.16 m/sec 1.16
F = TOTAL FITTING HEAD LOSS 0.03 m 0.25
= (K x V2 / 2g)
L = LINEAR METER OF STRAIGHT PIPE 0.00m 15.00
M = MULTIPLYING FACTOR 1.10 1.10
C = HAZEN-WILLIAMS ROUGHNESS COEFFICIENT 100.00 100.00
P = HEAD LOSS USING HAZEN-WILLIAMS EQATION 0.00 m 0.39
TOTAL LOSS = F + P 0.03 m 0.64
TOTAL SUCTION + DISCHARGE LOSS 0.73 m
S = STATIC HEAD LOSS (Worst Case Scenerio) 4.00m
TOTAL DYNAMIC HEAD 4.73 m
Size pump for 9.10 L/sec @ 4.73 m TDH
The submersible pump selected is as
follows:-Make = Ebara
Model = 65DVS51.5
Capacity = 9.10 L/sec
Total Head = 4.73 m
Power = 1.50kW
Discharge Size = 65mm connect to 100 mm
No. of Units = 1(1 duty)
Determine Size of Force Main Guideline: 1 - 2.5m/s velocity in pipe
Required size of sludge pump =
=
= 0.068 m
= 80 mm > 68 mm ok
Actual velocity in selected pipe = 1.81 m/s > 2.5 m/s ok
[ 4 x Qsludge / (2.5 m/s x 3.14] 1/2
Determine Total Dynamic Head ( TDH )
TDH =
Where ; = Static head (m) …………A
= Losses through the pipe ( Hazen - William Formula ) …………B
= Losses through fittings …………C
A = 4.00m
B Hazen - William Formula
= 6.82 V 1.85 X L
C
Where ; V = Velocity m/sec 1.16 m/s
V = Q / A = 8 L/sec = 1.16 m/sec C = Coefficient of roughness 0.00 L = Length of pipe, m 15.00 D = Diameter of pipe, m 0.10 = #DIV/0! m
C Losses through fittings
= KV²
2g
Where ; K = Head loss coefficeint 4.10
V = Velocity m/sec 1.16
G = Gravity, m/s² 9.81
= 0.29 m
Therefore ,
Total Dynamic Head ( TDH ) =
= ### m
To plot chart for the System Curve & Pump Curve from the above
equitition:-Q (L/s) V (m/s) TDH (m) Pump head (m) 18.6 4 0 0.00 4 18.6 16.4 4.04 2 0.25 4.04 16.4 14.2 4.15 4 0.51 4.15 14.2 13 4.23 8 1.02 4.57 8.3 8.33 4.57 9.5 1.21 4.80 4.2 4.2 4.8
* refer to Chart attached
hst + hf + hm
hst
hf
hm
Thus, static head of pump, hst
hf
D1.167
1000 x 3.142 x 0.10 2 / 4
Thus, losses through the pipe, hf
hm
hm
0
2
4
6
8
10
0
2
4
6
8
10
12
14
16
18
20
DRYING BED FEED PUMP
Submersible Pump
EBARA Model 65DVS51.5
Flowrate, Q (L/sec)
H
ea
d
(m
)
System Curve
Pump Curve
Pump Operating Point
9.2 L/sec @ 4.7 m
X-Axis
Pump
System
Pump
System
0
16.2
4
0
3.3
14.2
4.25
198
6.67
12.4
4.92
400.2
10
11
5.97
600
13.33
9
7.39
799.8
16.67
7.4
9.17
1000.2
19.98
5.6
11.27
1198.8
65DVS
X-Axis
Pump
System
0
18.6
4
2
16.4
4.04
4
14.2
4.15
8
8.33
4.57
9.5
4.2
4.8
3.580986
Blower- 1 Sizing
Air Requirement for Aeration = #NAME?
Air Requirement for Aerobic Sludge Digestion = #NAME?
TOTAL AIR REQUIREMENT = #NAME?
= Qd x (1.0332 + Pd) x 1.0332
= ? Air flow under standard condition = #NAME? Air flow under discharge condition = 0.41 Discharge static pressure PS = -0.05 Suction static pressure
= 30 Suction temperature = 38 Discharge temperature Therefore, = #NAME? = - 1 x 1.0332 1.0332 + PS = 0.48
Size blower for 9.09 m3/min @ 0.48 kgf/cm2 Provide 2 blowers : 1 duty, 1 standby
Model: Fu Tsu Model TSC 125, 920rpm, 15.0kW
m3/min m3/min
Qd m3/min
Determine air flow under standard condition, Q s
Qs 273 + St 273 + Sd Qs (m3/min) Qd (m3/min) Pd (kgf/cm2) (kgf/cm2) St oC Sd oC Qs m3/min
Determine discharge pressure under standard condition, P s
Ps 1.0332 + Pd
Blower-3 Sizing
Air Requirement for Scum Airlift
=
0.20
Air Requirement for RAS
=
#NAME?
Air Requirement for WAS
=
#NAME?
Air Requirement for MLSS
=
#NAME?
TOTAL AIR REQUIREMENT
=
#NAME?
=
Qd x (1.0332 + Pd)
x
1.0332
=
?
Air flow under standard condition
=
#NAME?
Air flow under discharge condition
=
0.45
Discharge static pressure
PS
=
-0.05
Suction static pressure
=
30
Suction temperature
=
38
Discharge temperature
Therefore,
=
#NAME?
=
- 1
x 1.0332
1.0332 + PS
=
0.53
Size blower for 1.76 m3/min @ 0.53 kgf/cm2
Provide 1 blowers : 1 duty
Model:
Fu-Tsu Model TSC 80, 760 rpm @ 5.5 Kw
m
3/min
m
3/min
m
3/min
m
3/min
Q
dm
3/min
Determine air flow under standard condition, Q
sQ
s273 + S
t273 + S
dQ
s(m
3/min)
Q
d(m
3/min)
P
d(kgf/cm
2)
(kgf/cm
2)
S
t oC
S
d oC
Q
sm
3/min
Determine discharge pressure under standard condition, P
sP
s1.0332 + P
dSludge Withdrawal Airlift Pipe Design
Calculate the submerged distance of the air inlet (S) by the following formula: S = Basin SWD - ( 1 + (3 x Pump Dia) / 12 ) where
SWD (ft) = 14.76 ft 4.50m
Pump Dia (in) for RAS = 3.00 in 0.075m
Pump Dia (in) for MLSS & scum = 2.00 in 0.050m
S = 13.01 ft 3.97 m
= h / { C x LOG [ (H + 10.4) / 10.4 ] } where
h = 0.75total lift required (m)
H = 4.50 submergence (m)
C = 10.20constant for less than 15m lift
= 0.47 m3/min of air per m3 of water = 25.00air-lift efficiency (%)
SCUM = 75.0
= 0.0521
=
= 0.0981
RAS = #NAME? See Aeration Tank cals
= #NAME?
=
= #NAME?
WAS = #NAME? See Aeration Tank cals
= #NAME? = = #NAME? MLSS = = 2070.00 = #NAME? MLSS Return = #NAME? = #NAME? = = #NAME?
Calculate the Air Supply Volume (V air) required: Vair
Vair A eff
Determine Volume of Air Requirement for SCUM, V SCUM
m3/day m3/min Vair-SCUM Vair x RAS x Aeff
m3/min
Determine Volume of Air Requirement for RAS, V RAS
m3/day m3/min Vair-RAS Vair x RAS x Aeff
m3/min
Determine Volume of Air Requirement for WAS, V WAS
m3/day m3/min Vair-WAS Vair x WAS x Aeff
m3/min
Determine Volume of Air Requirement for MLSS Return, V MR 4 Qave - QRAS
- 182.3 m3/day m3/day
m3/day m3/min Vair-MLSS Vair x MLSS x Aeff
Aeration Piping Headloss To Aeration Tanks
Criteria
Ambient air temperature To = 30deg C 303.2 deg K
Ambient barometric pressure Po = 1.00atm
Air supply pressure P = 1.450atm
Blower capacity Qb = #NAME?m3/min
Blower efficiency e = 75%
Equations
Friction factor f = 0.029 x D^0.027
Q^0.148 Temperature in pipe (deg K) T = To x (P/Po)^0.283
Velocity head Hv = 9.82E-8 x TQ^2
PD^4
Headloss (mm) hL = f x (L/D) x Hv or K x Hv
A. Pipe Fittings Losses
No. Valves & Fittings Size (mm) Quantity K Value Q (m3/min) T (deg K) hL, headloss (mm)
1 Check valve 80 1 2.50 #NAME? 336.77 #NAME?
2 Gate valve 80 1 0.80 #NAME? 336.77 #NAME?
9 Reducer 80 0.20 #NAME? 336.77 #NAME?
3 Tee thru side 80 1 1.80 #NAME? 336.77 #NAME?
4 Tee thru run 80 1 0.60 #NAME? 336.77 #NAME?
5 Elbow 90 deg 80 2 0.30 #NAME? 336.77 #NAME?
6 Elbow 90 deg 80 0.30 #NAME? 336.77 #NAME?
4 Tee thru run 50 2 0.60 #NAME? 336.77 #NAME?
9 Reducer 25 2 0.20 #NAME? 336.77 #NAME?
7 Tee thru run 25 0.60 #NAME? 336.77 #NAME?
4 Tee thru run 25 0.60 #NAME? 336.77 #NAME?
5 Elbow 90 deg 25 1 0.30 #NAME? 336.77 #NAME?
8 Elbow 90 deg 25 0.30 #NAME? 336.77 #NAME?
9 Reducer 25 0.20 #NAME? 336.77 #NAME?
10 Gate valve 25 1 0.80 #NAME? 336.77 #NAME?
Subtotal #NAME?
B. Straight Pipe Losses
No. Length (m) DIA (mm) Velocity (m/min) Q (m3/min) f, fric. factor T (deg K) hL, headloss (mm)
1 8.00 100 #NAME? #NAME? #NAME? 336.77 #NAME?
2 4.00 50 #NAME? #NAME? #NAME? 336.77 #NAME?
3 7.00 50 #NAME? #NAME? #NAME? 336.77 #NAME?
4 4.00 25 #NAME? #NAME? #NAME? 336.77 #NAME?
C. Supply Pressure At The Blower
1 Losses in piping = #NAME? mm
2 Losses in pipe fittings = #NAME? mm
3 Losses in air filter = 50.00mm
3 Losses in silencer = 50.00mm
4 Losses in blower = 150.00mm
5 Losses in diffusers = 160.00mm
6 Static head = 4100.00mm
Total #NAME? mm @ #NAME? m
Therefore, the absolute supply = #NAME? atm pressure
D. Power Requirement of Blower, P (kw)
P = w RTo x [ (P/Po)^0.283 - 1 ]
8.41 e
where R = 8.314 kJ/k mole deg K
w = air mass flow, kg/s
Therefore, P = #NAME? Kw or #NAME? HP
Select next bigger size motor = 5.5Kw 7 HP
ok
Size blower for 9.09 m3/min @ 0.48 kgf/cm2 Fu Tsu Model TSC 125, 920rpm, 15.0kW Provide 2 blowers; 1 running, 1 standby
CHLORINATION TANK DESIGN
= 2219.31
= 1.54
Detension Time at Qpeak t = 15.00min
Volume of Tank V =
= 23.12
Number of Tanks N = 1
Number of Bays per Tank n = 4
Dimension of Tank Provided
Depth H = 1.80m ok max 3m Wetted depth h = 1.50 Width W = 0.75 m Length L = 4.50 m Number of pass n = 4 Volume Provided Vp = 24.30 23.12 Check: Ratio Ratio ok
Wetted depth : Width
1.50 : 0.75
2 : 1
Length : Width
4.50 : 0.75
6 : 1
Detension Time at Qpeak t =
= 15.77 min > 15 min ok
PARSHALL FLUME FOR DISCHARGE
Design Flow, Qavg = 517.5
Peaking Factor PF = 4.29
Peak Flow Qpeak = 2219.31
Formula for flow calculation with diffrent throat width of Parshall Flume by Harlan Bengtson
Flow thru 1" PF, Q = where
Flow tru PF Q = flow in PF in cfs = 0.9071091 cfs = Qpeak
Head over flume H = in ft
water level in PF H = 1.8263509 ft 556.7 mm Qpeak m3/day m3/min Qpeak x t m3 m3 >= m3 Vp / Qpeak m3/day m3/day 0.338 x H1.55 For Q > Qpeak,
90 DEGREE V-NOTCH WEIR AT OUTLET BOX
Design Population , PE
=
2300
Design Flow,
Qavg
=
517.5
m3/day
Peaking Factor
PF
=
4.29
Peak Flow
Qpeak
=
2219.31
m3/day
90 Deg V-Notch Weir Formula
q(m3/sec)
=
H (m)
=
150
mm or
0.15
m at Qpeak
Therefore, q
=
0.012348
m3/sec > = 0.02569
m3/sec ok
Set depth of weir @
200
mm
ok
INFLUENT INFLUENT INFLUENT SECONDARY EFFLUENT Flow (m3/d) 517.50 Flow (m3/d) #NAME? Flow (m3/d) #NAME? MLSS Flow (m3/d) #NAME?
BOD (kg/day) 129.38 BOD (kg/day) 129.38 BOD (kg/day) 109.97 Flow (m3/d) #NAME? BOD(kg/d) #NAME?
TSS(kg/d) 155.25 TSS(kg/d) #NAME? TSS(kg/d) #NAME? TSS(kg/d) #NAME?
INFLUENT SCREEN PUMP ANOXIC TANK AERATION SECONDARY FINAL
FLOW CHAMBER * STATION BASINS CLARIFIERS EFFLUENT
LAST 10 mg/L BOD MANHOLE 20 mg/L TSS RAS RAS = 1% Flow (m3/d) 423.41 TSS(kg/d) 4234.09 LIQUID FLOW SOLID FLOW WAS * Assume 15% of BOD/TSS is removed from screenings and grit
* Assume 2% of flow is removed from screenings WAS = 1% Flow (m3/d) #NAME?
TSS(kg/d) #NAME?
DIGESTED SLUDGE DEWATERED SLUDGE Flow (m3/d) 3.95 Flow (m3/d) #NAME?
TSS(kg/d) #NAME? TSS(kg/d) #NAME?
AEROBIC SLUDGE
SLUDGE HOLDING DRYING BEDS TANK (75% VSS) (25-40% SOLIDS) (55% VSS Destruction) (95% CAPTURE) SUPERNATANT Flow (m3/d) #NAME? TSS(kg/d) #NAME?
INFLUENT INFLUENT INFLUENT SECONDARY EFFLUENT
Flow (m3/d) 689.63 Flow (m3/d) 697.82 Flow (m3/d) 683.87 Flow (m3/d) 683.82
BOD (kg/day) 172.41 BOD (kg/day) 172.41 BOD (kg/day) 146.55 BOD(kg/d) 6.84
TSS(kg/d) 206.89 TSS(kg/d) 236.97 TSS(kg/d) 201.43 TSS(kg/d) 13.68
INFLUENT SCREEN AERATION SECONDARY FINAL
FLOW CHAMBER * BASINS CLARIFIERS EFFLUENT
10 mg/L BOD 20 mg/L TSS RAS
LIQUID FLOW SOLID FLOW
* Assume 15% of BOD/TSS is removed from screenings and grit * Assume 2% of flow is removed from screenings
WAS
WAS = 1%
Flow (m3/d) 9.10
TSS(kg/d) 91.03
THICKENED SLUDGE DIGESTED SLUDGE DEWATERED SLUDGE
Flow (m3/d) 2.09 Flow (m3/d) 1.23 Flow (m3/d) 0.05
TSS(kg/d) 62.79 TSS(kg/d) 36.89 TSS(kg/d) 35.05
GRAVITY AEROBIC SLUDGE SLUDGE
SLUDGE THICKENER SLUDGE HOLDING DRYING BEDS HOLDING
TANK TANK AREA
(3% Solid) (80% VSS) (25-40% SOLIDS) (30 DAYS)
(55% VSS Destruction) (95% CAPTURE)
SUPERNATANT SUPERNATANT
Flow (m3/d) 7.01 Flow (m3/d) 1.18
TSS(kg/d) 28.24 TSS(kg/d) 1.84