Managing Project Procurement

(2)

© Copyright 2007 WorleyParsons Services Pty Ltd

This document has been prepared on behalf and for the exclusive use of WorleyParsons.

This document may not be reproduced without the express permission of the Business

Process Owner

Level 12, 333 Collins Street

Melbourne Vic 3000 Australia

Telephone:

+061 3 8676 3500

Facsimile:

+061 3 8676 3505

www.worleyparsons.com

WorleyParsons Services Pty Ltd

ABN 61 001 279 812

Facilitator Guide Module 9 Managing Project Procurement

Rev Description

Orig

Review

WorleyParsons

Approval

Date

A

Initial draft

Joslin Guest

1

Reissued for Use

Jane Woodhead

Greta Ooms

Mike Reilly

7/12/07

(3)

Rev 2 30/10/08

Managing Project Procurement Page i

Managing Project Procurement

About this Facilitator Guide... 1

Before You Start... 2

Preparation ... 2

Planning ... 2

Resources... 2

Agenda... 2

Resources Checklist ... 3

Agenda... 4

Introduction ... 6

Overview of Procurement ... 8

Responsibilities For Procurement ... 10

Commencing the Procurement Process/Procurement Planning... 11

SmartPlant Materials ... 18

Procurement Reports ... 20

Procurement Initiation... 21

Procurement Execution ... 22

Procurement Close-out ... 26

(4)
(5)

Rev 2 30/10/08

Managing Project Procurement Page 1

ABOUT THIS FACILITATOR GUIDE

The Managing Project Procurement Facilitator Guide has been designed to assist

facilitators to effectively deliver the training module. The guide provides support and

guidance in how to engage the participants and work through the training materials in an

effective way.

This module is the 9th module in the suite of WorleyParsons Project Management Skills

Development Training. The modules in the suite are:

¾

Module 1

Project Initiation, Scope Management and Project Close-out

¾

Module 2

Project Controls and Commercial Management

¾

Module 3

Managing Project Risk

¾

Module 4

Business Management Systems

¾

Module 5

HSE Management

¾

Module 6

Proposals

¾

Module 7

Managing Project Quality

¾

Module 8

General Management and Leadership

¾

Module 9

Managing Project Procurement

(6)

BEFORE YOU START

Preparation

Read the module 9, Managing Project Procurement several times to thoroughly

understand the content and be able to answer participants’ questions.

Planning

Plan to arrive at the training venue one hour before your presentation is due to start. Use

this time to set up and check the technology, set out the materials and greet participants

when they arrive. If you are well-prepared this will help create a relaxed environment that

is supportive of learning.

Resources

For Resources Checklist, see page 3.

Agenda

(7)

Rev 2 30/10/08

Managing Project Procurement Page 3

RESOURCES CHECKLIST

Resources

9

Training materials

Managing Project Procurement, module 9 Participants Manual (one copy per participant)

Managing Project Procurement Module 9 Facilitator’s Guide (one copy for facilitator)

Managing Project Procurement Training Module 9 PowerPoint Presentation

Prepare flipcharts (Agenda)

Handouts—Activity:

• Procurement Status Report

• Procurement Expediting Report

Attendance List

Evaluation sheet

Equipment

Tables and chairs in U-shape

Laptop with presentation loaded (and extra copy on CD)

Data show

Projection screen

Flipchart

Flipchart paper

Flipchart pens

Whiteboard

Whiteboard pens

Water and glasses

Minties in bowls

(8)

AGENDA

This is a sample agenda for the Managing Project Quality Training Module. This agenda

assumes a 9.00am start and 4.30pm finish.

Topic

Time

Introduction

About this training session

)

Learning Objectives

) 20 mins

Learning Outcomes

)

Agenda – Module 9 Managing Project Procurement )

9.00-9.20

Overview of Procurement

What is procurement?

)

What does procurement involve?

) 30 mins

What is the role of procurement in a project

)

9.20-9.40

Responsibilities for Procurement

WorleyParsons’ procurement capability

) 15 mins

Procurement Resourcing

)

9.40-9.55

Commencing the Procurement Process/Procurement Planning

Commencing the Procurement Process for a Project 15 mins

9.55-10.10

Procurement Planning

) 20 mins

Procurement Strategy

)

10.10-10.30

Break (15 mins)

10.30-10.45

Procurement Strategy (continued)

)

Project Procurement Plan

)

Materials Management Planning

) 60 mins

Contracts Planning

)

Approving the Project Procurement Plan

)

10.45-11.45

SmartPlant Materials

Using SmartPlant Materials to record and track projects

)

Setting up SmartPlant Materials

) 45 mins

SmartPlant Materials Training

)

11.45-12.30

Lunch (60 mins)

12.30-1.30

Procurement Reports

Procurement Status Report

) 30 mins

Procurement Expedition Report

)

1.30-2.00

Procurement Initiation

Procurement initiation

)

Purchasing initiation

) 25 mins

Contracts initiation

)

(9)

Rev 2 30/10/08

Managing Project Procurement Page 5

Topic

Time

Procurement Execution

Materials Management Execution

)

• Materials Management Pre-Award Process

)

• Materials Management Award Process

)

• Materials Management Post-Award Process

)

Contracts Execution

) 20 mins

• Contracts Pre-Award Process

)

• Contracts Award Process

)

• ContractsPost-Award Process

)

Purchase Order and Contracts Variation

)

2.25-2.45

Case study — Group Discussion

30 mins

2.45-3.15

Break (15 mins)

3.15-3.30

Procurement Close-out

Responsibilities for close-out

)

Materials management close-out

) 45 mins

Contracts close-out

)

3.30-4.15

Summary and Feedback

15 mins

(10)

INTRODUCTION

Slide 1

1

Welcome to Worley Parsons Project Management

Process (WPMP) Training

Module 9 – Managing Project Procurement

Welcome

• Start on time.

• Welcome participants to the WorleyParsons Project

Procurement Management training.

• Introduce yourself and your role at WorleyParsons.

• Check that everyone has a copy of the Participants Manual.

• Explain that the Participants Manual is a valuable resource

during the training and for the future.

• Explain that the training will be interactive and encourage

participants to interrupt with questions and contribute

examples from their experience.

Expectations

• Ask participants to introduce themselves (ask for a volunteer

then go round the room) – name, role and expectations of

the training.

• Document participants’ expectations on the flipchart

(optional).

Agree Ground Rules

Say that it’s useful to establish ground rules for the session, and

write on flipchart:

• Switch mobiles to off or silent

• Start and finishing on time

• Listen to others

• (Ask participants to contribute other Ground Rules).

• Ask for agreement to Ground Rules.

Safety Moment

Explain the emergency procedures

Slide 2

2

Managing Project Procurement

X Introduction

X Overview of Procurement

X Responsibilities for Procurement

X Commencing the Procurement Process \Procurement Planning

X SmartPlant Materials

X Procurement Reports

X Procurement Initiation

X Procurement Execution

X Procurement Close-out

About this training session

Agenda

Write agenda on flipchart (before the session starts) and

walkthrough topics.

(11)

Rev 2 30/10/08

Managing Project Procurement Page 7

Slide 3

3

Learning Objectives

On completion of this module, you will be able to:

X Identify and understand the procurement methodologies and tools available to Project Managers for the management of EPCM projects

Present and discuss learning objectives.

Slide 4

4

Learning Outcomes

X Early involvement of the Procurement function in project planning is essential

X The project’s procurement strategy and procurement plan must align with the overall project strategy

X Clear definition of the objectives of the Procurement Process is critical for the project team

On completion of this module, you will be able to demonstrate an understanding that:

Present and discuss learning outcomes.

Slide 5

5

X Procurement is an integral part of the WorleyParsons’ growth strategy

X Procurement shall support the company to compete more successfully as a leading provider of professional services worldwide

Procurement in WorleyParsons

Ask participants to explain what they think procurement is.

Discuss procurement in WorleyParsons.

Transition

We have covered our Introduction, and now we will move on to

(12)

OVERVIEW OF PROCUREMENT

Slide 6

6

Overview of Procurement

X Procurement is the process by which materials, equipment and third-party services are acquired for projects

X Key procurement interfaces include:

Project Management

Engineering

HSE

Quality

Cost Estimation

Project Controls

Construction Management

Legal & Risk

What is procurement?

Ask participants what each aspect means. Discuss answers.

Slide 7

7

Overview of Procurement

X At the best possible total cost of ownership

X In the right quantity and quality

X At the right time

X In the right place

X For the direct benefit of the customer

What does procurement involve?

…the acquisition of materials, equipment or third-party services:

Ask participants what does procurement involve?

Slide 8

8

Procurement and Capex

X The Capital Expenditure (Capex) of a Project can be split into a few elements:

Engineering and design – approx. 10% of Capex

Procurement:

−Materials and equipment – approx. 30 to 45% of Capex

−Contracts – approx. 30 to 45% of Capex

Balance is owners’ costs, insurance, land purchases etc

X The above is indicative only and dependent on the type and location of a project. However, on average the Capex element managed by procurement ranges between 60% and 90% of the overall project value

Ask participants what are the elements of Capex.

Slide 9

9

Overview of Procurement

X Procurement is the bridge between Engineering (design) and Construction (execution)

What is the role of procurement in a project?

Ask participants what ‘the bridge between Engineering and

Construction’ means. Discuss answers.

Slide 10

10

Overview of Procurement

X Materials Management

Purchasing, Expediting, Materials Control, Coordination of Inspection (liaising with Quality), Traffic/Logistics, Warehousing/ Inventory Control etc

Legal agreement used is a Purchase Order

X Contracts

Acquisition and management of third-party services

Legal agreement used is a Contract

X Both Purchase Orders and Contracts are written and binding legal agreements between relevant parties to supply either goods or services against agreed conditions

Procurement is divided into 2 functions

Explain that there are 2 key functions in procurement.

Explain what:

• Materials Management involves.

• Contracts involves.

(13)

Rev 2 30/10/08

Managing Project Procurement Page 9

Explain that contracts and purchase orders regulate procurement

activities.

Ask participants if they know what the difference is between a

contract and a purchase order.

Discuss participants’ answers.

Slide 11

11

Procurement Executive Directive

X To minimise risk exposure, procurement services are usually provided for and on behalf of Customers, in the Customer’s name or “on Customer paper” – this is the company’s preferred position

X However, this does not preclude provision of procurement services in WorleyParsons’ name or on “WorleyParsons’ paper” – requires CEO to proceed in any event where additional supplier-related risks and liabilities are assumed (eg warranty obligations, delivery commitments, product liability, etc)

X In most instances, procurement services are provided on behalf of the Customer, requiring active interaction with the Customer and their various approvals to proceed

Continue discussion of Contracts.

Slide 12

12

EMS Workflows and Procedures 1/2

X Contracts services cover the provision of third-party services such as construction labor, inspection services, painting and sand blasting

X The provision of contract services is governed by the Contracts Workflow in EMS containing a number of procedures, guidelines, forms and templates

X Preferred Terminology:

ITT = Invitation to Tender

Contract = legal agreement for the provision of services

Contracts

Explain that Contracts is governed by by guidelines, procedures

and forms and is available on EMS V3

These:

• Appiy to all contract situations and cover tendering, bid

evaluation, award, variations, administration, invoicing,

payments, and close-out

• Set out the key interfaces in WorleyParsons between

Engineering; Quality Management; Healthy, Safety and

Environment (HSE); Construction; contractor and

cost-control accounting

Slide 13

13

EMS Workflows and Procedures 2/2

X Materials Management includes the purchasing of goods and equipment, subsequent expediting, inspection and receipt.

X The provision of Materials Management services is governed by the Materials Workflow in EMS containing a number of procedures, guidelines, forms and templates

X Materials Management activities are managed and tracked through SmartPlant Materials, WorleyParsons’ Materials Management system which starts from creation of the requisition through to final material reconciliation on site

X Preferred Terminology:

RFQ = Request for Quotation

Purchase Order (PO) = legal agreement for the supply of goods

Materials Management

Discuss Materials Management.

Slide 14

14

Overview of Procurement

WorleyParsons procurement process

Pre-award Activities * Materials Management * Contracts

Obtain quotations Select the preferred suppliers Project Procurement Plan

Determine procurement requirements Procurement Initiation Identify potential suppliers Post-award Activities Manage the supplier Administer POs and contracts Manage POs/ contract variation Expediting / Inspection Materials Field Administration

Activities Field Purchasing Transport/ Logistics Receipt on site Warehousing Close-out Activities Conclude the engagement of the

suppliers Record the performance against

each order & contract

Explain that:

• The slide shows the procurement process for Materials

Management. The process for Contracts is essentially the

same. The differences will be explained in the training

where relevant.

• WorleyParsons delivers procurement services through a

suite of well defined business processes.

These processes are listed on page 6 of the Participants Manual.

Transition

We have covered an overview of Procurement. Now we will

(14)

RESPONSIBILITIES FOR PROCUREMENT

Slide 15

15

Responsibilities for Procurement

X As Project Manager, you are responsible for the overall management of procurement activities associated with the project

X You are not responsible for the execution of procurement activities That is the responsibility of your Project Procurement Manager

X To fulfill your responsibilities, you should work closely with the Procurement Manager

Explain the Project Manager’s role and responsibilities for project

procurement.

Tell the participants that the Project Manager’s specific

responsibilities are listed on page 9 of the Participants Manual.

Explain that execution of procurement is the responsibility of the

Project Procurement Manager.

Ask the participants to turn to page 9 of their Participants

Manuals. Discuss.

During discussion emphasize the necessity and benefits of taking

advantage of the Procurement team’s knowledge, experience

and world-wide supplier contacts.

Slide 16

16

Responsibilities for Procurement

X Procurement specialists in each region

X Detailed procurement procedures, guidelines and associated documentation

X Deployment of SmartPlant Materials as the company-wide materials control system to record, track and report on procurement activity

X Global supplier database for materials, equipment and services

X Global Sourcing initiatives

X Supply arrangements with key suppliers

WorleyParsons’ procurement capability

Explain WorleyParsons’ procurement capability.

Slide 17

17

X Procurement staff managing the Materials Management and Contracts activities usually:

Work either from a core Procurement group in a key company location or

Form a part of a dedicated project procurement team

X Procurement activities on the project are usually led by an experienced Project Procurement Manager

X Where warehousing staff are required for specific customers or projects, they are usually located on site

X Inspection may involve in-house or third-party inspectors, depending on the location of the inspection activities

Procurement resourcing

Responsibilities for Procurement

Explain WorleyParsons’ procurement resourcing

• At point 1 explain that specialist Procurement staff should be

retained in key company locations.

• At point 2 explain that operationally, the Project

Procurement Manager reports to the Project Manager for

direction of day-to-day matters relating to procurement.

Transition

Get the group to suggest answers to the review questions on

Page 15-16 of Participant’s Manual.

We have covered responsibilities for Procurement. Now we will

move on to discuss commencing the Procurement

(15)

Rev 2 30/10/08

Managing Project Procurement Page 11

COMMENCING THE PROCUREMENT

PROCESS/PROCUREMENT PLANNING

Slide 18

18

Procurement Process

X Establish exactly what the customer requirements are andwhat WorleyParsons has committed to do

X Establish your procurement team and set out their responsibilities

X Procurement to participate in the Project Risk Assessment and ensure that risk mitigation is included in the Procurement Plan to be developed

X Procurement to incorporate appropriate flow-down conditions from the Prime contract (the agreement between Customer and WorleyParsons) in the Project Conditions to ensure compliance and alignment (e.g. including customer’s confidentiality requirements, alignment of warranty periods etc.)

X Procurement to develop the project procurement procedures, based on EMS but incorporating as appropriate Customer’s requirements (e.g. approval interfaces)

X Arrange to have the project set up on SmartPlant Materials

X Ensure WBS is established

Commencing the procurement process for a project

Explain that Project Managers are setting the basis under which

procurement activities will be conducted.

Explain that the details that need to be considered for the

procurement plan include:

• Major items of materials, equipment and third-party services

that will be required

• The criticality and value of the goods and services that need

to be procured

• Major risks mitigation measures that need to be developed

• Market pressures that might impact on delivery times of

critical equipment and hence priority of procurement

activities.

Slide 19

19

Procurement Planning

X Planning is at the crux of all project activities

X Procurement is no exception

X The aim of procurement planning is to:

Know what needs to be procured, when, where and how

Identify critical long lead items and services

Establish order and consistency in the way the procurement activities are performed

Understand the risks involved in the project environment and identify mitigating actions

X The Project Procurement Plan is part of the Project Execution Plan

Planning

Emphasize the:

• Importance of planning

• Criticality of project procurement planning in overall project

planning.

Slide 20

20

Procurement & Risk Management

X Procurement is an integral part of risk management on the project

•Develop appropriate procurement/ contracts/ materials management strategies, identifying the various risks (market, forex, local content requirements, taxation and importation issues, logistics complexities, etc. to be managed)

•Use EMS procurement procedures to the largest extent, however, recognize Customer requirements in the project specific procedure.

•Ensure that the project specific procurement procedures are approved by the customer and shared with the project procurement team

•Develop the procurement schedule early, in line with the overall project schedule, resulting in correct priorities to achieve the Required on Site Dates

Continue discussion of planning.

Slide 21

21

Procurement Planning

What you need to plan for

Discuss the procurement bridge with regard to component

activities in:

• Planning.

• Materials Management.

• Contracts.

(16)

Slide 22

Discuss the strategy development and detailed plan development

phases of procurement planning.

Slide 23

23

Procurement Planning

X Project Procurement Strategy (PPS) is the:

Process for identifying and documenting the procurement opportunities applicable to the project

First step in developing the Project Procurement Plan

X Typically, the PPS is first developed during the scoping stages of a project

X Sometimes the customer provides the initial procurement strategy for further development in the Project Procurement Plan

Project Procurement Strategy

Introduce the concept of a Project Procurement Strategy.

Slide 24

24

Procurement Planning

X Purchasing activities can involve long lead times

X Certain materials and equipment may be particularly critical to a project’s success

X Purchasing activities usually involve multiple countries (infrastructure and logistics, local legislation etc.)

X Market and technology developments can impact on the success of a project and therefore need to be monitored on an ongoing basis

During the development of the PPS, the following factors need to be considered:

Project Procurement Strategy

Discuss the factors that need to be considered when developing

a Project Procurement Strategy.

Slide 25

25

Procurement Planning

X The PPS is a hierarchical matrix covering the entire work scope of a project, broken down into separate ‘work packages’

X Only the major critical items are separately identified as work packages

X These packages are created and identified according to:

Unique technical and commercial attributes of the work activities they comprise

Methods by which they are to be executed

Project Procurement Strategy

Continue discussion of the factors that need to be considered

when developing a Project Procurement Strategy.

(17)

Rev 2 30/10/08

Managing Project Procurement Page 13

Slide 26

26

Procurement Planning

Example of a PPS matrix N/A Contract Part of Supplier B Purchase Order Part of Supplier A Purchase Order Commissioning / Start-up Assistance

Part of Project Management Services Specialist Quality Contract – All-in

rates – $10m Quality Inspection

Installation Contract – Lump Sum – $10m Construction / Erection Services

Materials Control Construction Contract –Reimbursable Cost and Equipment Rates with Incentives Fee - $100M total Fabrication Specialist Supplier B – Lump Sum Purchase Order – $100m total Specialist Supplier A – Lump Sum Purchase Order – $200m total Procurement

Facilities E & P Contract – Reimbursable Costs with Fixed Fee – $30m total Design Contract – Lump Sum – $10m Design

Project Management Services Contractor – Reimbursable Costs with Incentives Fee – $ 70m total

Project Management Civil Works Balance of Plant Special Equipment Item B Special Equipment Item A Components Physical ⇓ Discipline

Explain purpose and structure of the Project Procurement

Strategy.

Explain that

• The PPS should be structured in a manner and contain

information that allows it to be used to:

o

Develop alternative ways of structuring work packages

and executing the project.

o

Analyze trade-offs between the size of work packages,

resource availability and the number of interfaces

required.

o

Interpret and illustrate the interfaces between various

work packages and those responsible for executing

them.

• It must show how the project’s procurement activities

(Materials Management and Contracts) interface with other

work activities of the control, organization, technical and

construction functions.

Explain that a Project Procurement Strategy template is included

in the Project Procurement Plan Template (PPF-0102) EMS V3.

Slide 27

27

Procurement Planning

X The structure of the PPSdepends on the:

Scope of work

Nature and complexity of the project

Requirements of the customer

X The PPS assists in:

Administrative and commercial planning

Cost/schedule control functions of a project

Project Procurement Strategy

Discuss the other uses of the Project Procurement Strategy.

Slide 28

Summarize by explaining the benefits of developing a Project

Procurement Strategy.

Explain how the Project Procurement Strategy:

• Can be used to facilitate communication between the

various project disciplines/departments

• Provides strategic input to the cost estimating, scheduling

and supplier administration activities.

Invite questions and/or ask review questions on page 21 of the

Participants Manual.

Slide 29

Explain at what stage of the WPMP the Project Procurement

Plan is developed.

(18)

Slide 30

Discuss what sort of planning takes place in the various WPMP

phases to emphasise the role/difference between the Project

Procurement Strategy and the Project Procurement Plan.

Slide 31

31

Procurement Planning

X Documents the basis for obtaining and managing materials, equipment and third-party services required for project execution

X Addresses relevant aspects of both materials management and contracts for the project

X Maps out the various anticipated risks and constraints and identified mitigating actions

X Identifies critical supplies (see also Procurement Strategy) and outlines general strategy

X Ensures that the procurement activities align with the overall project schedule

Project Procurement Plan

Explain that the Project Procurement Plan:

• Identifies the materials, equipment and third-party services

required to execute the project

• Specifies the methodologies and commercial basis for

procuring third-party services

• Provides procurement input to other parts of the project,

such as scheduling, cost estimating, finance and risk

assessment to enable completion of their Identify, Evaluate

or Define phase deliverables

Discuss the components of the Project Procurement Plan:

• The Project Procurement Strategy (PPS)

• Identification of the materials, equipment and third-party

services required (with emphasis on long-lead and critical

items)

• Review of the current market situation, supply options,

foreign exchange considerations, etc for the materials,

equipment and third-party services identified

• Identification of the procurement organizational structure

• Early preparation of project vendor and contractor bid lists

• Identification of major procurement risks or issues, and

mitigation measures that can be put in place

• Other deliverables specified by the customer.

Slide 32

32

Procurement Planning

X The Project Procurement Plan:

Must clearly define the deliverables of the procurement process

Needs to be ‘fit for its purpose’ Project Procurement Plan

Discuss the criteria for a good Project Procurement Plan.

Explain fitness for purpose, ie, the degree of details should

reflect the:

• Scope of the work

• Nature, requirements and scale of the project

• Requirements of the customer, WorleyParsons’ scope of

work and the nature and complexity of the project.

Slide 33

33

Procurement Planning

X The Project Procurement Plan may also include details about the targeting of procurement efforts

X The Project Procurement Manager will consider the assessment in the strategy development

Criticality-Value Assessment

Project Procurement Plan

Bottleneck, e.g. special alloy steel grade Ensure continuity Develop alternatives Revise specifications

Critical, e.g. turbine compressor Form closer relationships Direct negotiations

Routine, e.g. piping bulk blanket orders Simplify procurement process Automate Rationalise supplier base

Leverage, e.g. customer’s standard agreement Maximise commercial advantage Competitive tender Standardisation Criticality Low Low High Value Potential High

Explain that the Project Procurement Plan needs to assess the

criticality of procured items.

Show the Criticality-Value matrix. Discuss.

Explain the criticality-value assessment for procurement is

different to the engineering criticality assessment that determines

the levels of inspection. Discuss.

Invite answers to review questions on Page 25 of Participants

Manual.

(19)

Rev 2 30/10/08

Managing Project Procurement Page 15

Slide 34

34

Procurement Planning

Project Procurement Plan

XWhere the complexity and / or size of the project warrant it, the Project Procurement Plan may be further developed in separate plans:

A detailed Project Materials Management Plan

Separate detailed Project Contracts Plan for major contract packages

Separate detailed Procurement Plans for key procurement packages

• Explain that the Project Procurement Plan has 2

components, to deal separately with:

o

Materials and equipment (Materials Management)

o

Third-party services (Contracts)

• Explain that for large or complex projects a Project

Procurement Plan may need to be broken separate:

o

Project Materials Management Plan(s)

o

Project Contracts Plan(s)

Slide 35

35

Procurement Planning

The various elements of the Procurement Plan are further defined in the Materials Management Plan, including:

X Specific strategies for buying materials and equipment

X Associated activities for managing the expediting, traffic/logistics etc

X The materials control and reporting systems

X Prioritization of procurement activities and associated engineering deliverables in line with the ROS (Required on Site dates) as defined in the project schedule

Materials Management planning

Explain the purpose of the Materials Management Plan.

Explain (again) that the Materials Management Plan:

• Can be a subset of the Project Procurement Plan or

• For complex projects, can be a separate plan.

Slide 36

36

Procurement Planning

X Level of procurement effort based on cost, schedule, criticality, and other relevant factors

X POs/activities already executed and/or underway prior to engagement of WorleyParsons

X Transition of early purchase agreements from the customer

X Material control systems

X Quality management, verification and inspection, which includes an outline of inspection to be undertaken

X Site materials management plans

Materials Management planning (cont’d)

Discuss what Materials Management planning focused on.

Discuss criticality in terms of:

• Schedule

• Financial profitability

• Safety

• Design/execution efficiency

• Manufacturing complexity.

Explain that consolidation can be within the project or with other

projects.

Slide 37

37

Procurement Planning

Subsets of the Material Management Plan

X Engineered equipment planning

X Bulk materials planning

X Prefabrication planning and modularization

Materials Management planning

Explain that prioritization and level of procurement effort based

on cost, schedule, criticality, and other relevant factors.

Introduce the categories of materials and equipment that need to

be considered separately in the development of the Materials

Management Plan.

Slide 38

38

Procurement Planning

X The primary objective is to ensure that items are acquired and released in time to meet the overall project schedule

X The dates on which items are required on site to meet construction needs drive the engineering and procurement planning and activity for engineered equipment

X A major equipment list for the project needs to be developed early

Engineered equipment planning

Briefly discuss engineered equipment planning.

Explain some of the drivers for engineered equipment Planning

• ROS dates

• Lead times for supplier data and fabrication

• Milestones required in the acquisition process for

engineered items

(20)

Slide 39

39

Procurement Planning

X Planning for bulk materials can be more complex than planning for engineered equipment

X Bulk materials control starts with an examination of the project schedule to assess:

What bulk materials are required over time

Critical required on site (ROS) dates

Bulk material planning

Briefly discuss bulk materials planning.

Explain that quantities required are never exactly known until the

job is complete.

Explain that planning for acquiring bulk materials should also

evaluate opportunities to consolidate purchases and establish

POs to take advantage of volume discounts.

Slide 40

40

Procurement Planning

X Procurement planning:

Is usually very complex for extensive prefabrication

modularization often involving multiple sites

X An extensive prefabrication program demands an early procurement planning effort that addresses the interfaces between vendors, fabricators and site construction

Prefabrication planning and modularization

Briefly discuss prefabrication planning and modularization.

Slide 41

41

Procurement Planning

X The Contracts Plan can be:

Subset of the Project Procurement Plan or

Separate plans—complex projects

X The main focus of project contracts planning is the selection the best contractor under the best available terms and conditions

X Needs to:

Analyze the options and the marketplace for the required services

Define the number, type, scope, timing, interfaces, compensation basis, etc of major contracts to be developed for the project from early planning through start-up

Contracts planning

Explain the purpose of the Contracts Plan.

Invite answers to review questions on Page 28 of Participants

Manual.

Slide 42

42

Procurement Planning

X For Projects in the Definephase the Project Contracts Plan needs to document:

Critical contracting issues (e.g. labour resource constraints, market constraints) for the major contracts

How will the impact be managed and the risk mitigated?

What is the schedule to meet timely completion of the Project?

Contracts Planning in Define Phase

Explain what types of matters need to be considered in the early

stages of developing a Contracts Strategy/Plan.

Emphasise the following points for the Define phase:

• Detailed individual contract bidder’s lists applicable to each

of the major contracts

• The number, scope, estimated value and timing for each

contract

• Critical or long duration contracts requiring special attention

• Pre-qualification approach to bidder selection

• Contractor selection criteria

• Interfaces with other functions

• Other considerations based on the latest construction

work-hour/ schedule estimates.

Summarize the major contracting issues for the project and

actions necessary to address them.

(21)

Rev 2 30/10/08

Managing Project Procurement Page 17

Slide 43

43

Procurement Planning

X For Projects in the Executephase, the Project Contracts Plan review the constraints and identify mitigation measures similar to the Define phase projects but not just for major contracts.

All anticipated contracts are identified.

If the project is a continuation of a Define phase project, the Contracts Plan developed for the Define phase will be reviewed and updated by the Project Procurement Manager to reflect project progress and significant new developments

X A list of matters that typically need to be considered are listed on page 32 of the participants manual

Contracts Planning in Execute Phase

Explain that Contracts planning takes place during the Execute

phase of a project.

Slide 44

44

Procurement Planning

X The customer must approve the Project Procurement Plan as part of the Project Execution Plan

Approving the Project Procurement Plan

Explain that the Project Procurement Plan is approved by the

customer as part of the Project Execution Plan.

Invite questions and/or ask review questions on page 33 of the

Participants Manual.

Transition

We have covered commencing the Procurement

process/Procurement planning. We will now discuss SmartPlant

materials.

(22)

SMARTPLANT MATERIALS

Slide 45

45

SmartPlant Materials

X WorleyParsons uses a suite of project management systems to

record, track, control and report on projects

Introduce WorleyParsons Business Management Systems and

SmartPlant Materials.

Explain that SmartPlant Materials’ functionality is covered in

greater detail in module 4, Business Management Systems.

Slide 46

46

SmartPlant Materials

X SmartPlant Materials is used to:

Identify

Record

Track

materials and equipment required and purchased for a project

Explain SmartPlant Materials’ functions for Procurement.

Slide 47

47

SmartPlant Materials

SmartPlant Materials has four integrated modules, which are described on page 36 of the workbook

Explain that SmartPlant Materials has four integrated modules.

Slide 48

48

SmartPlant Materials

X Maintains the Material Stock Code catalogue

X Generates bulk requisitions via interface to design systems (e.g. PDS)

X Generates equipment and services requisitions

X Preparation of RFQs

X Supports bid evaluations

X Creates and, if required, amends POs

X Facilitates expediting

X Facilitates Traffic/Logistics

X Facilitates stores management

X Can undertake invoice reconciliation via Invoice Matching Interface module

Tell participants that a brief description of the modules is

provided on page 36 of the Participants Manual.

Slide 49

49

SmartPlant Materials

X SmartPlant Materials imports bills of materials from 2-D/3-D engineering

design software and other sources

X SmartPlant Materials supports better material planning on site and material reconciliation through the ability to track imported bills of materials from Requisition to Material Issue

X Materials are identified as being in any of the following phases:

•Requisition •RFQ •Purchasing •Expediting •Shipping •Warehouse receipt •Storage •Material Issue

Explain that SmartPlant Materials imports bills of materials from

2-D/3-E engineering design software.

(23)

Rev 2 30/10/08

Managing Project Procurement Page 19

Slide 50

50

SmartPlant Materials

X SmartPlant Materials was designed as a system for controlling materials and equipment, not for administering contracts

X SmartPlant Materials can, however, be used to record basic information about contracts

Using SmartPlant Materials for recording and tracking contracts

Explain that SmartPlant Materials is used chiefly for recording

and tracking materials and equipment.

Explain that SmartPlant Materials’ functionality for contracts

tracking is limited.

Briefly explain how contracts are tracked.

Slide 51

51

SmartPlant Materials

X Each individual project needs to be set up in SmartPlant Materials so that its procurement activities can be recorded, monitored and reported

X SmartPlant Materials should be set up as soon as the Project Procurement Plan or Materials Management Plan has been approved

X You are responsible for ensuring that SmartPlant Materials is set up properly

X You work with the project Procurement Manager to identify and obtain the information for the set up

Setting up SmartPlant Materials for a project

Explain setting up SmartPlant Materials for a project.

Say this is done so that so that its procurement activities can be

recorded, monitored and reported.

Explain that two important principles apply to the setup and use

of SmartPlant Materials:

• It is important to set up SmartPlant Materials as early as is

practicable to ensure that potential critical materials

procurement issues (for example, bulk materials

requirements, control of materials from supplier to fabricator

to project site) are identified and appropriately addressed

• Clear definition of the deliverables in SmartPlant Materials

underlies effective project procurement reporting.

Slide 52

52

SmartPlant Materials—Training

X When you need to start using SmartPlant Materials, you will receive specific training on how to use it

X Contact the Business Systems Group to arrange the training

Training in SmartPlant Materials

Explain that project managers will be provided in training in how

to use SmartPlant Materials.

Invite questions and/or ask review questions on page 42 of the

Participants Manual.

Transition

We have covered SmartPlant materials. Now we will move on to

(24)

PROCUREMENT REPORTS

Slide 53

53

Procurement Reports

X Procurement activities are monitored and reviewed regularly

X SmartPlant Materials generates a range of reports which you use to monitor progress and identify actions to be taken to address issues

X Two particularly important reports for the management of procurement activities are the:

Procurement Status Report

Procurement Expediting Report Procurement reports

Explain that SmartPlant Materials produces reports.

Introduce the:

• Procurement Status Report

• Procurement Expedition Report.

Explain that the Project Procurement Manager is responsible for

providing these reports to the Project Manager.

Explain that the Project Manager and the Project Procurement

Manager, together, must review the reports regularly, and take

appropriate action on any issues identified.

Handout sample reports:

• Procurement Status Report.

• Procurement Expedition Report.

Discuss the sample reports.

Transition

We have covered Procurement reports. Now we will move on to

(25)

Rev 2 30/10/08

Managing Project Procurement Page 21

PROCUREMENT INITIATION

Slide 54

54

Procurement Initiation

X The Project Procurement Manager is responsible for completing the activities that enable purchasing and contracts to be initiated

X The initiation activities should be completed during the early stages of the project

X The initiation activities are:

•Purchasing initiation

•Contracts initiation and formulation

X Part of the initiation activities is the development of the Project terms and conditions for purchase orders and contracts.

•These may be provided by the Customer as we will typically be acting on their behalf.

•The conditions shall be checked for alignment with the Prime contract.

Overview of procurement initiation

Explain that the Project Procurement Manager is responsible for

project initiation.

Explain that this session is an overview of project initiation.

Emphasise that when initiating procurement you need to think

through your close-out requirements.

Slide 55

55

X Purchasing initiation involves setting up the project base for the Purchasing documentation and databases

X The main activities are:

Identifying PO provisions (including standard Terms and Conditions)

Preparing standard documentation, including Instructions to Bidders, master Request for Quotation, master purchase order document

Carrying out vendor pre-qualification

Establishing a project vendor list

Overview of purchasing initiation (Materials Management)

Procurement Initiation

Explain that the Project Procurement Manager is responsible for

project initiation.

Explain that this session is an overview of project initiation.

Slide 56

56

X Contract initiation and formulation involves:

Setting up the project base for contracts documentation (including standard Terms and Conditions)

Establishing the contracts system for the project

X The main activities are:

Establishing the contract types, sites conditions, HSE etc

Preparing common enquiry requirements and special contract provisions

Carrying out contractor pre-qualifications

Establishing the contractor list

Overview of Contracts initiation and formulation

Procurement Initiation

Briefly describe Purchasing initiation.

Briefly describe Contracts initiation.

Discuss importance of early establishment of agreed Terms and

Conditions.

Transition

We have covered Procurement initiation. Now we will move on

(26)

PROCUREMENT EXECUTION

Slide 57

57

Procurement Execution

X All procurement execution activities are undertaken by the Project Procurement Manager and the Procurement team

X You are responsible for ensuring that the procurement activities are executed in accordance with the Project Procurement Plan

X You and your Project Procurement Manager need to hold regular meetings to:

Review the status of procurement activities

Identify issues early and determine the action required to minimize any adverse impact

Overview of procurement execution

Explain that the Project Procurement Manager is responsible for

project execution.

Explain that this session is an overview of project execution.

Explain that project execution consists of:

• Pre-award activities.

• Award Activities.

• Post-award activities.

Explain that pre-award activities:

• Cover the technical and commercial activities in the

procurement of a project’s materials and equipment

• Span from Engineering’s specification of the requirement to

award of a PO to the selected vendor.

Explain the Project Manager’s and Procurement Manager’s

responsibilities for procurement execution. Discuss.

Slide 58

58

Procurement Execution

X The purpose of the Purchasing Pre-award Process is to award the POs under which the project’s materials and equipment are obtained

X The pre-award process ensures that all bidders are treated fairly and equitable, that the confidentiality of the information is maintained and that the recommendation to award is in accordance with the agreed evaluation criteria

•Agreed evaluation criteria may be as simple as ‘Technically acceptable, lowest cost’ or more complex ‘Total Cost of Ownership’ (TCO). Consider that TCO often requires Customer input as well.

•Competitive bidding is indicated. However, if single source is considered for purchase orders, justification must be provided. This may include proprietary technology or customer’s standardisation preference.

X Project Purchasing pre-award activities occur predominantly during the Execution phase

X For long-lead items some activities may occur in the Define phase

Materials Management execution—purchasing pre-award process

Materials management execution – purchasing pre-award

process

Explain why the Materials Management pre-award process is

critical.

Explain that the Procurement team implements the pre-award

purchasing process.

Slide 59

59

Procurement Execution

X Preparing enquiry packages, including special terms and requirements (for example, supplier data, support, spares)

X Issuing the enquiry packages and managing bid preparation and receipt process

X Managing all communications with bidders during bidding and evaluation

X Evaluating the bids

X Preparing recommendations for award, conducting post-bid negotiation and facilitating final issue

X Entering all data related to the purchases into SmartPlant Materials

Materials Management execution—purchasing pre-award process

Explain how the pre-award process is implemented.

Emphasise need to build all requirements (eg documentation,

reporting, inspection, etc) into the RFQ. It will cost more

post-award.

Slide 60

60

Procurement Execution

X Maintains the required level of confidentiality of information

X Ensures that engineering deliverables are aligned to support timely procurement activities

X Maintains the interfaces between Engineering, Quality and Construction

X Involves the Project Procurement Manager in the regular team progress meetings

X Undertakes and completes procurement activities in accordance with the Project Procurement Plan

Materials Management execution—purchasing pre-award process

As Project Manager, you will need to ensure that the procurement team:

Discuss the Project Manager’s and Procurement Manager’s

responsibilities.

(27)

Rev 2 30/10/08

Managing Project Procurement Page 23

Slide 61

61

Procurement Execution

X Purchase Order documents are to be prepared by Engineering and Procurement on receipt of the approved Award Recommendation

X Kick-off meetings are arranged as required

X Post-award activities are initiated by the project procurement team

X Once internal and other approvals have been obtained to place a contract or a PO theProcurement Manager is the only person with the authority to confirm the commitment for the contract or PO with the supplier on behalf of WorleyParsons and/or our customers

Materials Management execution—purchasing award process

Materials management execution – purchasing award

process

Discuss the Procurement Manager’s responsibilities.

Explain that the procurement team is responsible for ensuring

compliance with the PO contractual requirements, as consistent

with prioritized project objectives.

Slide 62

62

Procurement Execution

X Confirm that the cost of the awarded POs is within the project budget

X Provide relevant information to the project’s Cost Controls Manager

Materials Management execution—purchasing award process

You are responsible for ensuring that the award process is properly undertaken

You need to:

Discuss the Project Manager’s responsibilities.

Slide 63

63

Procurement Execution

X This process covers award of a PO through to receipt at site and financial close-out

X The purpose of the Purchasing Post-award Process is to:

Administer the POs to obtain the project’s materials and equipment on schedule and in accordance with specifications

Provide cost and schedule information to Project Services

Identify PO issues for Risk Management activities

Liaise with Inspection to ensure compliance to specifications

X The Purchasing Post-award Process covers the technical and commercial activities in the manufacture and delivery of materials and equipment

X Ensure all meetings and vendor contact are coordinated by Procurement.

Materials Management execution—purchasing post-award process

Materials management execution – purchasing post-award

process

Explain the post-award activities.

Explain that the aim of the post-award process is to receive at

the specified location, materials and equipment, and associated

supplier data covered by the PO at the cost, in accordance with

the technical specification and on the date for delivery specified.

Slide 64

64

Procurement Execution

The main activities in the Purchasing Post-award Process are:

X Expediting (including Supplier documentation)

X Inspection coordination

X Traffic/Logistics

X Receiving on site, warehousing and preservation

X Change/Claim administration

X Invoice payment

Materials Management execution—purchasing post-award process

Explain the requirements for effective post-award performance

management.

Slide 65

65

Procurement Execution

Effective procurement performance requires:

X Use of SmartPlant Materials

X Monitoring the vendor’s engineering and manufacturing processes

X Meeting documentation obligations

X Measuring and assuring conformance to the technical specification

X Administering delivery of the materials and equipment

X Managing any changes to the PO technical and commercial provisions

X Managing any claims by the vendor for additional payment or schedule time

(28)

Slide 66

66

Procurement Execution

X The Construction Manager involves the Project Procurement Manager in construction progress review meeting

Materials Management execution—purchasing post-award process

As Project Manager you are responsible for ensuring that:

X For most items, weekly status meetings are sufficient

X For critical items, daily review meetings between the Construction and Procurement Managers may be required

Discuss the Project Manager’s responsibilities for post-award

procurement activities.

Emphasise the need for the Procurement team to keep

up-to-date with the project procurement needs, including any changes

to the project affective procurement activities.

Slide 67

67

Procurement Execution

X The Materials Field Administration Process governs the day-to-day procurement activities on site

X The actual administration is the responsibility of your Project Procurement Manager

X Materials Field Administration may include site administration, purchasing and contracting

Materials Management execution—purchasing materials field administration process

You are responsible for ensuring that the requirements for materials field administration are included in the Project Procurement Plan

Materials management execution – purchasing materials

field administration process

Explain that the post-award procurement activities include field

administration.

Slide 68

68

Procurement Execution

X The purpose of the Contracts Pre-award Process is the contracting of third-party services

X Project Contracts pre-award activities predominantly occur during the Execution phase

X For early contracts, some activities may occur in the Define phase

X The deliverables of the Contracts Pre-award Process are:

Bidders lists

Enquiry packages

Approved recommendations for award

Contract documents

X Cost and schedule information provided to Project Services and contracts issues input into Risk Management activities

Contracts execution—contract pre-award process

Contracts execution – contracts pre-award process

Explain why the contracts pre-award process is critical.

Emphasise importance of specifying all requirements (eg HSE,

documentation, reporting, inspection, etc) in ITT. It will cost more

post-award.

Slide 69

69

Procurement Execution

Contractor selection

X A thorough prequalification process will normally be executed for major contracts, e.g. fabrication contracts. This will involve multiple disciplines to prepare the questionnaire for the relevant work scope, typically including construction, engineering, quality, HSE as well as project controls and procurement.

X Competitive, sealed bids are indicated for major contracts

X If single source is considered for service contracts, justification must be provided. This may include proprietary technology (e.g. software) or customer’s preference.

X Once internal and other approvals have been obtained to place a contract or a PO theProcurement Manager is the only person with the authority to confirm the commitment for the contract or PO with the supplier on behalf of WorleyParsons and/or our customers

Contracts execution—contract award process

Contracts execution – contract award process

Discuss contractor selection.

Slide 70

70

Procurement Execution

X The Contracts Post-award Process covers the technical and commercial activities

X The main activities are:

Awarding contracts

Administering and monitoring the contractors

Managing any changes to the contract

Managing any claims

Processing any payments and back charges, reconciling quantities and finalizing all contract obligations

Providing cost and schedule information to Project Services

Identifying any contracts issues for Risk Management activities

Contracts execution—contracts post-award process

Contracts execution – contracts post-award process

(29)

Rev 2 30/10/08

Managing Project Procurement Page 25

Slide 71

71

Procurement Execution

X PO and contract variation must be processed in accordance with the Management of Project Change Process

X You and the Procurement Manager must sign-off any variances before they can take effect

Purchase order and contracts variation

Purchase order and contracts variation

Explain the process for contract variation.

Invite questions and/or ask review questions on page 54 of the

Participants Manual.

Slide 72

72

X The scenario for the case study is on page 55 of your workbooks

Discussion topics:

X What would you say are the key procurement issues on the project?

X What can be done to remedy the situation?

Case study—group discussion

Case study – group discussion

Complete the case study on page 55 of the Participants Manual.

Transition

We have covered Procurement execution. Now we will move on

References

Related documents

Finally, we found a not entirely surprising dependency between the number of distinct places per week that a person goes to and how his time is distributed in different

For the case of note tracking evaluation we consider two evaluation methodologies to compare transcription T N (p, t) against ground-truth piano-roll T R (p, t): (i) a frame-based

To test whether and how signals are propagated from right FEF to distinct feature-processing areas of the visual cortex (and to left FEF) during feature attention, we combined right

Acquisition (SCADA), Product Embedded Information Devices (PEID) are expected to be rapidly used for gathering and monitoring the status data of products during their usage

Prices firm thru July 2015, automatically renewing unless Mfg increase/decrease submitted to Purchasing by vendor.. Order items listed from awarded vendor for

FedEx Service Center M-F Until 8PM Until 5PM FedEx Express, Ground, 2001 B World Wide Drive 2-8PM Returns, Packaging Supplies Fort Worth, TX 76177 Available, 24-hr Drop Box

Procurement and Contract Management Adept Project Management Advanced Manage and Develop People Adept Inspire Direction and Purpose Adept Optimise Business Outcomes Adept

Responsible for managing end-to-end procurement activities across varying categories, from sourcing through to supplier management and managing a small team of