• No results found

HDPE Application Technique

N/A
N/A
Protected

Academic year: 2021

Share "HDPE Application Technique"

Copied!
84
0
0

Loading.... (view fulltext now)

Full text

(1)

Geberit HDPE

(2)

100 212 90 194 80 176 70 158 60 140 50 122 40 104 35 95 30 86 25 77 20 68 15 59 10 50 5 41 0 32 –5 23 –10 14 –15 5 –17,8 0 –20 –4 –25 –13 –30 –22

Converting tables

Converting table Inch–Millimeter

Inch 3

8" 1⁄2" 3⁄4" 1" 11⁄4" 11⁄2" 2" 21⁄2" 3" 31⁄2" 4" 5" 6" 8" 10"

mm 9,5 12,7 19 25,4 31,8 38,1 50,8 63,5 76,2 88,9 101,6 127 152,4 203,2 254

Geberit Ø outside - - - 32 40 50 56 63 75 90 110 125 160 200 250 Geberit Ø inside - - - 26 34 44 50 57 69 83 101,4 115,2 147,6 187,6 234,4

Temperature scales Pressure scale

1 bar = 1000 mbar 1 bar = 100 000 Pa (= ) 1 bar = 10,2 m Water column 1 bar = 14,5 psi

1 psi = 6896.43

1 psi = 1 lb/square inch

Length scale 1 m = 1000 mm 1 m = 100 cm 1 m = 10 dm 1 cm = 10 mm 1 dm = 10 cm = 100 mm

°°C

C

°°F

F

To convert Centigrade to Fahrenheit: Multiply Centigrade by 1,8 and add 32. °F = (°C x 1,8) + 32

To convert Fahrenheit to Centigrade: Subtract 32 from Fahrenheit and divide by 1,8. °C = (°F –32) : 1,8 N m2 N m2

(3)

Geberit HDPE

page

Drainage system 3

Application field for pipes and fittings 4

HDPE pipes, fittings and tools 5– 7

Jointing methods 8–17

Water proofing 19

Thermal movement

20–21

Accomodating thermal movement

Deflection leg 22

Expansion socket 23

Anchor brackets and guide brackets 24–26

Installation examples 27–30

Prevention of thermal movement

Rigid installation 31

Brackets, embedded fixed points 32–33

Mounting instructions

Butt welding 34–36 Electro welding 37–39 Prefabrication 40–42 Repair tool 43 Expansion sockets 44

Special application fields

Underground drainage 45–49

Pipe penetration through building walls 50

Connection to manhole 51

Drainage of bridges 52–53

Low pressure installation 54

External and internal pressure 55

Fire protection 56–58

Geberit HDPE characteristics

Physical characteristics 59

Ecological properties 60–61

Comments on individual properties 62–65

Tempering (Geberit Licence) 66–67

pH Value 68

Chemical resistance list 69–78

(4)
(5)

Drainage system

1 Ground pipe 2 Main stack 3 Branch pipe 4 Connector pipe 5 Ventilation stack

6 Rainwater down pipe

7 Domestic drainage 8 Public sewer

2

4

5

6

6

7

8

3

1

(6)

Description Symbol House Underground Bridge Pressure Pluvia drainage drainage drainage load

Pipe X X X X X Bend 45° X X X X X Bend 881⁄2° X — — — X Bend 90° X X X X X Branch 45° X X X — X Branch 881⁄2° X — — X X Ball fittings X — X — — Reducer X X X X X Apparatus connections X — — — —

Butt welded joints X X X X X

Electroweld sleeve coupling/flange X X X X X

Expansion socket X X X — ❍

Ring seal socket X — — — —

Flange bushing X X X X X

Double flange bushing X X X X X

Access pipe X X X X X

X = Applicable — = Not applicable

❍ = For horizontal installation max. ∅ 110

(7)

Geberit HDPE pipes

5 m

HDPE pipes

Nominal (Outside) Wall Inside Area Weight Weight Pressure* Series

dia. thickness dia. empty full nominal (ISO)

d (mm) s (mm) di (mm) A (cm2) kg/m kg/m PN S Art. No. 32 3 26 5,3 0,259 0,790 10 5 379.000.16.0 40 3 34 9,0 0,331 1,239 6 6,3 360.000.16.0 50 3 44 15,2 0,420 1,940 6 8,3 361.000.16.0 56 3 50 19,6 0,471 2.434 6 — 363.000.16.0 63 3 57 25,4 0,536 3,087 4 10 364.000.16.0 75 3 69 37,3 0,644 4,383 4 12,5 365.000.16.0 90 3,5 83 54,1 0,903 6,313 4 12,5 366.000.16.0 110 4,3 101,4 80,7 1,350 9,424 4 12,5 367.000.16.0 125 4,9 115,2 104,5 1,750 12,171 4 12,5 368.000.16.0 160 6,2 147,6 171,1 2,840 19,947 4 12.5 369.000.16.0 200 6,2 187,6 276,4 3,580 31,216 3,2 16 370.000.16.0 250 7,8 234,4 431,5 5,630 48,774 3,2 16 371.000.16.0 315 9,8 295,4 685,3 8,920 77,442 3,2 16 372.000.16.0

Standard length of Geberit HDPE pipes = 5 meters (5000 mm)

*

= Nominal pressure refers to pipe only not to fittings ISO = International Standard Organisation

Standards

– International ISO 8770 / 8772

– European CEN / TC 155 / CEN EN 12056 – Switzerland SN 592 000 – Germany DIN 8075 / 19535 / 19537 – Austria B 5177 – France NF T 54 072 – Italy UNI 8451 – Belgium NBN 42-112 – Netherlands NEN 7008 – Denmark NKB Nr. 8 – Great Britain BS /6367/5572/6437/5114 cmA2 d s di

(8)

Geberit HDPE fittings

Prefabricated or conventional installation. Pipeline embedded in concrete. Underground drainage pipes. HDPE fittings

(9)

Geberit tools

Pipe Cutter Hand Mitre Saw

"B ARY" "BARY" Kunststoff-Schweissapparate Kunsts toff -Schweissapparate Type: A-Type: A-Volt 230 Volt 230Watt WattNr.Nr. W.Riesen Basel (Schweiz) W.Riesen Basel (Schweiz) Dittingerstrasse 45 Dittingerstrass e 45

Welding Plate Repair Tool

B.356.220/001

(10)

Geberit HDPE jointing methods

Overview

The many Geberit

jointing methods

offer solutions

for all situations.

Butt weld Electroweld sleeve

coupling

Ring-seal socket Screw-threaded joint

Linear expansion socket

Flange joint Contraction sleeve Coupling for PE-Silent

and adaptor only

These connections have different properties, and are therefore classified according to the way in which they are assembled as follows:

a) To be opened

Jointing methods which can be disconnected after assembly.

b) Not to be opened

Jointing methods which cannot be disconnected after assembly.

c) Tension-resistant

Connections which withstand tensional forces.

d) Non-tension-resistant

Connections which cannot withstand tensional forces.

Butt weld Jointing methods Situation Tension resistant Not to be opened Tension resistant To be opened Non-tension resistant Not to be opened Non-tension resistant To be opened Ring-seal socket Screw-threaded joint with-out flange bushing Screw-threaded joint with flange bushing Expan-sion soc-ket Contrac-tion sleeve Coupling Flange joint

Application

X

X

X

X

X

X

X

X

X

Electro-weld sleeve coupling

(11)

All diameters from ∅ 32 to 315 mm can be welded. Connection properties

b) not to be opened c) tension-resistant

Use

Welding is the easiest jointing method, providing the many advantageous bene-fits of prefabrication; HDPE needs no other component in order to be welded. It can be used in all circumstances where prefabrication is used on site or in the workshop.

The essential conditions for a perfect weld are:

• Cleanliness of the welding plate and the parts which are to be welded. • A correct welding plate temperature.

• The correct pressure for jointing the parts. • The parts to be welded must be cut square <) 90°.

Butt welding takes up little space. The edge of the weld does not obstruct the pipe, leaving its internal cross-section virtually unchanged. Even quite complica-ted distribution parts can be assembled in a small space, without wastage of material, because lengths of pipe or elbow sections can be easily reused through butt welding.

The allowance for butt welds is approx. as big as the wall thickness of the pipe.

pipe diameter (mm) 32–75 90 110 125 160 200 250 315

butt weld s (mm) 3 4 5 5 7 7 8 10

Butt welding

A simple and reliable connection

Machine welding Media ø 40 – 160 mm Universal ø 40 – 315 mm

Manual welding

up to Ø 75 mm

Indicative values

of operating pressure

W

elding time in min.

Welding time Warming-up time 5 4 3 2 1 0 mm 2 4 6 8 10 12 ø kg 32 5 40 6 50 7 56 8 63 9 75 10 90 15 110 22 125 28 160 45 200 57 250 90 315 140

Warming-up and welding times Guide values for welding pressure

A

Allowance for butt welds

ø 56 110 250

Pipe wall thickness

(12)

Electroweld sleeve coupling

A short, simple and reliable connection Available from ∅ 40 to 315 mm. Connection properties b) not to be opened c) tension-resistant Use

On-site welding, conversion, additional installations, repairs. The small outside diameter

provides a great advantage.

Conventional assembly, on the nesting principle, made for easy use. The joint obtained is simple, quick and reliable.

The heating and melting zone is divided into two fields, as there are no electrical resistances in the centre of the sleeve. This provides a very satisfactory safety factor.

Also the ends of the pipes are not heated, the zones remain effectively cold, and provide

further reinforcement, thus cancelling out shrinkage of the pipe.

The pressure required for welding is obtained from the shrinking effect of the sleeve when it is heated, and is evenly distributed over the entire weld. This shrinkage has a compensating effect on pipe diameter measurement toleran-ces.

The electrical resistance wires will not corrode. Once the weld has been made they are

entirely covered by PE.

The use of original Geberit equipement, especially tempered Geberit HDPE pipes, are

recommended for correct welding.

Electrical sleeves can be made to slide by removing the central stop ring, thus making system conversion and repair work easier.

B.500.000/191

The stop ring can easily be removed with a screwdriver.

60

150

Ø 40 – 160

Ø 200 – 315

(13)

Assembly instructions are the same for both ring-seal sockets and screw-threaded joints, the sleeve lengths are the same for corresponding diameters. The effective sleeve length, i. e. the measurement – X – from the O-ring to the base of the socket governs the maximum length of pipe which can be connected by individual joints.

For HDPE approximately 15 mm of spigot should be allowed for every 1 m of pipe.

The pipe must be fully inserted into the socket, because the socket does not act as an expander. Owing to the pipe thickness and the low thermal conductivity of HDPE, the socket seal has very satisfactory resistance to heat and no shrinkage of the O-ring occurs.

The O-ring has a round seat regardless of pipe movements. The O-ring remains fixed in the seat and is always in contact with the pipe.

Protection cap

x

Ring-seal socket joint

Available from ∅ 32 to 160 mm. Connection properties

a) to be opened d) non-tension-resistant

Use

Ring-seal socket joints can be used to provide a connection between various prefabri-cated parts for simpler assembly.

Assembly

May be used either vertically or horizontally. The small overall dimensions provide an advantage where space is limited. Can easily be assembled or released even where access is difficult.

Ring-seal sockets are provided with a yellow protection cap to prevent the ingress of debris during installation.

(14)

Screw-threaded joint

Available from ∅ 32 to 110 mm. Connection properties a) to be opened d) non-tension-resistant Use

Screw-threaded joints are used for assembly of various prefabricated parts when it is necessary to easily dismantle and also as the connection to sink traps and shower trays.

1 2 3 4 Complete screw-threaded joint 1. Nut 2. Washer 3. Seal 4. Thread

The seal is pressed against the thread.

A minimum surface area of the seal is in contact with water.

The seal is pressed against the flange bushing and the thread.

Available from ∅ 32 to 110 mm. Connection properties

a) to be opened c) tension-resistant

Use

Wherever there is the possibility that a pipe can be pulled out of a screw-threa-ded joint by axial tensile forces a flange bushing must be used to ensure that the connection will resist these forces. It is also recommended that a screw-threaded joint with flange bushing should be used when installing in floors or slabs, where the length of pipe between two connections (elbows, branches or sleeves) is longer than 2 metres.

1 2 3 4 1. Nut 2. Flange bushing 3. Seal 4. Thread

Screw-threaded joint

with flange bushing

Screw-threaded joint

without flange bushing

1 2 3 4 1 2 3 4

(15)

Expansion socket

Available from ∅ 32 to 315 mm. Connection properties b) not to be opened d) non-tension-resistant Use

An expansion socket is recommended between anchor brackets, particularly on installations assembled with rigid joints and where excessive thermal movement is anticipated.

At least one expansion joint must be provided on vertical stacks running from floor to floor, long collector pipelines and before connecting to the buried drain pipework.

Different conditions apply for underground installations. For this application field see page 48.

Installation

Can be used either vertically or horizontally. One advantage is the depth of the sleeve which makes the assembly of downpipes and mains easier, allowing both vertical and horizontal corrections (e.g. in level, and in the precise positio-ning of the direction of branches and elbows).

A firm anchor bracket must always be located behind the expansion socket to avoid any movement of the socket in the event of expansion or contraction.

The special shape of the seal allows the pipe to slide within the socket during expansion and contraction, ensuring that the connection remains perfectly watertight even under heavy hydraulic load.

Horizontal assembly (e.g. at 20°C)

Example: Insertion depth in an ambient temperature of 20°C

(Vertical assembly).

The following conditions are important to ensure perfect and easy assembly of the sleeve:

1. Chamfering the inserted pipe end to approximate <) 15°.

2. Check the scale on the outer surface of the expansion socket for insertion depth.

(16)

Flanged joint

Loose flange

Nut and bolt

Seal Flange adaptor Blind flange Bolts Loose flange, PE coated Flange adaptor Seal Flange adaptor Loose flange Nuts Available from ∅ 50 to 315 mm. Connection properties a) to be opened c) tension-resistant Use

Flanges are normally used as disconnectable joints for low pressure installations (industrial plant, pump connection, tanks and swimming pools).

The flange connection system offers easy connection to existing iron and steel installations.

As inspection access opening made by using a blind flange.

Flanges are sintered, i.e. they are coated with polyethylene, and have standard dimensions (PN 3.2 – PN 10).

(17)

PE-Silent coupling

d D H E E Available from ∅ 56 to 135 mm. Connection properties a) to be opened

d) non tension resistant

Use

The application field of the coupling for HDPE-Silent is to connect HDPE-Silent pipes and fittings. The coupling enable an even inner surface of the connections and the noise requirements can be fulfilled.

Installation

It is advisable to mark the inseration depth of HDPE Silent coupling.Do the pipe ends accordingly in order to ensure that they are not subject to tension. Support rings are not required for the Silent pipes and fittings.

PE-Silent coupling d(mm) D(cm) H(cm) E(cm) Art. No. 56 7.2 5.0 2.3 305.003.14.2 63 7.9 5.6 2.6 359.429.00.1 75 9.1 5.0 2.3 307.003.14.2 90 10.6 5.0 2.3 308.003.14.2 110 12.6 5.0 2.3 310.003.14.2 135 14.5 5.2 2.5 312.003.14.2

(18)

Geberit HDPE contraction sleeve

d di(mm) H(cm) h(cm) h1(cm) K(cm) for Ø(mm) Art. No.

50/ 60 30 24 6 17 53– 54 152.651.16.1 73 27,5 22 5,5 17 60– 67 152.197.16.1 80 28,5 23 5,5 17 67– 74 152.198.16.1 90 30,5 23,5 7 17 80– 84 152.652.16.1 100 31 24 7 17 90– 94 152.653.16.1 56/ 60 26,5 20,5 6 14 53– 54 152.654.16.1 73 24,5 19 5,5 14 60– 67 152.149.16.1 80 24,5 19 5,5 14 67– 74 152.150.16.1 63/ 73 26,5 20,5 6 14 60– 67 152.657.16.1 80 24,5 19 5,5 14 67– 74 152.658.16.1 90 26,5 19,5 7 14 80– 84 152.659.16.1 75/ 80 25 19 6 12 67– 74 152.152.16.1 90 24,5 17,5 7 12 80– 84 152.151.16.1 100 15 8 7 12 90– 94 152.661.16.1 90/110 17 7 10 – 84– 98 366.550.16.1 110/125 16 6 10 – 102–111 367.551.16.1 140 18 8 10 2,5 102–126 367.550.16.1 125/150 18 8 10 1 116–136 368.550.16.1 160/195 20 8 12 1 148–180 369.550.16.1 230 30 14 18 5 189–212 369.551.16.1

200–315 available on request (see HDPE catalogue)

d AB di K H h h1 pipe end ring seal rubber ring Geberit HDPE contraction sleeve Laboratory sink Available from ∅ 50 to 160 mm Connection properties b) rigid, non-removable d) non-tension-resistant Use

The Geberit HDPE contraction sleeve is a convenient connection possibility for most uneven, irregular or special materials.

A common additional application method is also the connection from HDPE to different clay ware apparatus, e. g. for Laboratory sinks.

Installation

The enclosed rubber ring will be placed over the pipe end. Make sure that the rubber ring will be placed in the middle of the sleeve length (h2). Then push the contraction sleeve over the pipe end. Apply low heat (approx. 125°C) evenly around the socket, moving the blow lamp constantly.

The sleeve will now shrink and give an absolute watertight and strong connection. Afterwards fix the contraction sleeve pipe with an anchor bracket.

For Ø 125–315 mm use two soft flames.

Contraction sleeve with seal

approx. 125°C Geberit contraction sleeve Anchor bracket rubber ring AB

(19)

Geberit HDPE adapter clamp

Important:

If the joint from HDPE to steel – cast iron or earthenware – is made with a coupling, it has to be secured by an anchor

bracket.

Install the anchor bracket as close as possible to the coupling.

1 Anchor bracket 2 Butt weld seam 3 Coupling

4 PE adaptor with reinforcement ring 5 Steel, cast iron, clay, fibre cement

pipes Available from ∅ 48 to 326 mm.

Connection properties

a) to be opened

d) non tension resistant

Use

The adapter clamps have multiple functions and can consequently be used as adapters to thirdparty materials as well as any other types of connection.

Installation

It is necessary to insert an appropriate reinforcement ring into the ends of the HDPE-pipe first when these clamps are used as adapters to HDPE-pipes or for HDPE-pipe connections.

(20)

Geberit HDPE adaptors

Pipe threads (for detail information see HDPE catalogue)

Connection to: Thread dia. Geberit dia. Material

Male pipe thread 1

/2”–21/2” 40–75 mm HDPE with steel ring

reinforcement

Female pipe thread 11

/4"–21/2” 50 – 75 mm HDPE with steel ring reinforcement

Female pipe thread 11

/2"–2" 50 + 56 mm Adaptor in brass + PE nut

Threaded pip ends (for detail information see HDPE catalogue)

Soldering / Welding (for detail information see HDPE catalogue)

Connection to: Thread dia. Geberit dia. Material

Connection to: Pipe dia. Geberit dia. Material

Male-thread 11

/4”–2" 32–50 mm HDPE, upon request also

available with nut in brass

Male-thread 60 x1

/8” 40 + 50 mm HDPE

Female-thread 1

/2”–1" 40 + 50 mm HDPE, with brass nipple

Male pipe thread 2"– 3" 56 + 75 mm Adaptor in brass + PE nut

Lead 50/60 56 mm Brass with PE nut for

soldering

Lead 50/60 56 mm Lead with PE nut

for welding or soldering

PVC 50 + 63 56 mm PVC for solvent

(21)

Water proofing

Attention: Thermal expansion or contraction of the pipe is to be prevented.

Maximum water pressure 0,1 bar.

Installation examples

50 cm 50 cm Pipe Sealing Waterproofing membrane Waterproofing membrane

Electroweld sleeve coupling (to prevent expansion or contraction)

Expansion socket Anchor Bracket Reducer Access pipe Sealing Waterproofing membrane

Wherever a water proof layer is required, the Geberit sealing for passages through walls or ceilings provides a perfect watertight seal between the HDPE pipe and the water proof membrane.

Type 1: «Resistit» for connection with bitumn Type 2: PVC to be welded with PVC sheet Type 3: PE to be welded with Sarnafil FPO-A-foil For Geberit HDPE pipes Ø 50, 56, 75, 110, 125 mm

(22)

Thermal movement

Physical principal: All materials expand as temperature increase. If the temperature falls, the material contracts.

α

= 0,2 mm/m

K

Rule of thumb: ∆t 50° = 10 mm/m

Geberit HDPE

Expansion Coefficient

Length Variation Table

30°C

80°C

0°C

Example: 1. Sought: Thermal expansion ∆L 2. Given: Maximum temperature = 80°C Installation temperature = 20°C Temperature difference ∆t = 60°C Pipe length = 4 m 3. Result: Thermal expansion ∆L = 4,8 cm = 48 mm Pipe length Te mperatur e dif fer ence ∆ t in °C Determination of thermal expansion of HDPE

(average linear expansion coefficient 0,2 mm/m K) 1000 mm 1010 mm 994 mm 5000 mm 5050 mm 4970 mm

(23)

Thermal movement

There are alternative

methods of installing the

Geberit HDPE Drainage

System.

Factors that will influence

thermal movement

Methods of accomodating

thermal expansion

and contraction

Prevention of thermal expansion

and contraction

Deflection Leg

Expansion

Socket

Rigid Fastening

Installation

Embedded in

(24)

2 4 6 8 10 12 14 16 18 20 0 20 40 60 80 100 120 140 160 180 200 220 240 260 4,8 73

Länge des Biegeschenkels BS in cm aus Formel BS = ca. 10 x L x D

Bestimmung des Biegeschenkels aus PE

Aussen-ø

Längenänderung L des Dehnungsschenkels in cm

40

32 50-63 75 90 110 125 140 160 200 250 315

Deflection leg

Compensating thermal expansion by deflection leg

+80°C +20°C –10°C 4000 G G A A DL + 60 – 30 G Guide bracket A Anchor bracket DL Deflection leg

Determining the length

of the deflection leg by

calculation

Length of the deflection leg (DL) in mm according the formula

Outer-Ø

Linear expansion or contraction

L in cm

Determination of the deflection leg of HDPE

10 x

∆L x ∅

Example: DL = 10 x

48 x 110 = 730

Determining the length

of the deflection leg from

chart

Length of deflection leg DL in cm. Formula DL = ca. 10 x √∆L x ∅

(25)

Expansion socket

The Geberit expansion socket is designed to counteract the variation in length due to thermal expansion and contraction of max. 6 m Geberit HDPE pipes.

Application: Horizontally Vertically Diameter: Ø 32 – 315 mm

Legend: Expansion socket: compensates the change of length

Bracket: provides an anchor point

Electroweld sleeve: holdes anchor bracket in position

Note: Each expansion socket needs to be fixed with

1 anchor bracket.

(26)

Anchor bracket for expansion socket

Thrust force «P» when in operation Ø Thrust force P (kg) 50–63 10 75 12 90 20 110 30 125 40 160 70 200 100 250 150 315 220

The table beside shows the correct pipe nipple diameter required depending on distance «L» to effectively withstand thrust force «P».

The main purpose of the anchor bracket is to prevent any movement of the expansion socket.

The distance «L» and the thrust forces «P» have to be taken in account, when selecting the diameter of the pipe nipple between mounting plate and bracket.

The thrust force «P» is the slide resistance between rubber seal and HDPE pipe. This force depends on the pipe diameter.

Diameters of Geberit HDPE pipe

Distance 50/56/63/75/90 110 125 160 200 250 315

from ceiling Pipe nipple used

L (mm) Ø Ø Ø Ø Ø Ø Ø 100 1⁄2" 1 2" 1⁄2" — — — — 150 1⁄2" 1 2" 1⁄2" 1⁄2" — — — 200 1⁄2" 1 2" 1⁄2" 1⁄2" 3⁄4" 1" 250 1⁄2" 1 2" 1⁄2" 3⁄4" 1" 1" 5⁄4" 300 1⁄2" 1 2" 1⁄2" 3⁄4" 1" 5⁄4" 5⁄4" 350 1⁄2" 1 2" 1⁄2" 1" 1" 5⁄4" 11⁄2" 400 1⁄2" 1 2" 3⁄4" 1" 1" 5⁄4" 11⁄2" 450 1⁄2" 1 2" 3⁄4" 1" 5⁄4" 5⁄4" 11⁄2" 500 1⁄2" 3 4" 3⁄4" 1" 5⁄4" 11⁄2" 2" 550 1⁄2" 3 4" 3⁄4" 1" 5⁄4" 11⁄2" 2" 600 1⁄2" 3 4" 1" 1" 5⁄4" 11⁄2" 2"

P

(27)

Guide brackets

The main purpose of guide brackets is to support the pipe and allow the axial movement caused by the effects of expansion and contraction.

Application:

For all fixations of Geberit HDPE pipes Ø40-315mm except for anchor brackets.

+

B.362.826/001

+

+

+

+

+

+

Diameter Ø 40 –160 mm

+

+

B.362.837/001 B.362.826/001 B.362.826/001 1 2" 1⁄2" 1 2" 1 2" 1⁄2" 1 2" 1" 1" 1" M10 M10 M10 Diameter Ø 200 –315 mm Geberit PE-Silent Ø 75 +110 mm

OR

(28)

Spacing for brackets

Horizontal installation:

SA = max. 10 x

Vertical installation:

SA = max. 15 x

A = Anchor Bracket G = Guide Bracket

SA = Spacing between anchor bracket and guide bracket SB = Spacing between guide brackets (see table below) E = Expansion socket

A

SB SA

Spacing of guide brackets SB:

The table indicates the maximum distance between guide brackets (G) for Geberit HDPE pipes.

Nominal Spacing outside of brackets (SB) diameter d Horizontal Vertical (mm) (m) (m) 32 0,5 1,2 40 0,5 1,2 50 0,8 1,2 56 0,8 1,5 63 0,8 1,5 75 0,8 1,5 90 1,0 2,0 110 1,5 2,0 125 1,5 2,0 160 1,5 2,0 200 2,0 2,0 250 3,0 3,0 315 3,0 3,0 max. 6 m SB SA max. 15 x ∅ A G G G A

Geberit HDPE pipes are to be fixed with anchor brackets (A) and guide brackets (G).

The distance between the anchor bracket and the first guide bracket must be respected as follows:

(29)

A

Examples of installing

Geberit HDPE expansion socket

Principal: Every pipe installation exceeding a certain distance (6 meters) must be protected against mechanical load with an expansion socket.

A

Rainwater downpipe

Rainwater downpipes are generally not subjected to large temperature changes except for those outside of buildings exposed to sunlight.

In vertical pipelines the distance between the brackets can be calculated approx. as follows:

15 x pipe diameter

(max. distance see p. 26)

A = Anchor bracket G = Guide bracket

(30)

B

Examples of installing

Geberit HDPE expansion socket

B

Stacks

Not only does the HDPE expansion socket absorb thermal expansion and contraction due to temperature changes caused by water discharge, but it also makes pipe assembly easier, assisting connection at each floor level.

Rule:

One Geberit HDPE expansion socket

at each floor level

1. Free-standing stack with branch 2. Stack with branch in concrete

Anchor point

A

G

G

A

G

A

G

A = Anchor bracket G = Guide bracket

(31)

C

Examples of installing

Geberit HDPE expansion socket

C

Horizontal suspended collector pipeline

When fitting collector pipelines extend 6 m it is necessary to fit expansion sockets and secure them with anchor brackets (see p. 24).

Between the anchor brackets, guide brackets must be installed at the distance SA or SB (see p. 26).

Rules: – Maximum distance between Geberit HDPE expansion sockets 6 m

– Inserting depth depending on ambient temperature – Anchor bracket directly on each Geberit HDPE expansion

socket

– Guide brackets located along the collector pipeline (see page 26).

Example

max. 6 m max. 6 m max. 6 m

A = Anchor bracket G = Guide bracket

G

G

G

G

G

G

G

G

G

A

A

A

A

A

(32)

D

Examples of installing

Geberit HDPE expansion socket

D

Combination of stacks and collector pipelines

Rules: – One Geberit HDPE expansion socket at each floor level – One Geberit HDPE expansion socket at each branch – One Geberit HDPE expansion socket at each change

of direction

– Anchor bracket on each Geberit HDPE expansion socket.

Example 8 m 4,2 m

A

A

A

A

A

A

A

A

A

A

8,4 m 4,2 m 5,5 m 10 m 5 m 5 m 5,5 m A = Anchor bracket

(33)

Principal: Any variation in length must be prevented by embedded fixed points (electroweld sleeve couplings,

branches, bends or collar bushes) or by the provision of corresponding fixed point structures.

A

Rigid installation with anchor brackets

Anchor brackets for rigid fixings must be stronger than possible expansion or contraction forces (P) of the HDPE pipe (see table).

Expansion and contraction

forces

Geberit Ring- Column 1 Column 2

HDPE pipe square (Normal installation) (Outside installation)

ca. + 20°C bis + 90°C ca. + 20°C bis – 20°C

d cm2 force kg force kg 40 3,5 85 221 50 4,4 105 277 56 5,0 125 315 63 5,8 140 365 75 6,8 170 428 90 9,5 240 598 110 14 350 882 125 18,5 460 1165 160 29,6 740 1865 200 37,7 940 2375 250 59,5 1490 3750 315 93,9 2350 5915

Example:

This table shows that in the low temperature range (column 2) the forces are greater than in the high temperature range (column 1).

Prevention of thermal movement

(34)

Anchor bracket for rigid installations

Rules: Anchor brackets must be stronger than the

possible forces generated during thermal expansion or contraction of Geberit HDPE pipes.

Examples of anchor

brackets

Dimension of pipe nipple

or flat iron profile

Mounting plates

The examples of anchor brackets below show a typical rigid installation.

Anchor bracket with double electroweld sleeve coupling.

Anchor bracket with electrowelding tape.

Anchor bracket with flat iron and electrowelding tape. Ceiling Geberit-Dimensions or wall 50–56 63–75 90 110 125 160 distance Pipe W W W L · (mm) Ø Ø Ø Ø cm3 Ø cm3 Ø cm3 100 1 2" 3⁄4" 1" 1" 5⁄4" 150 3 4" 1" 1" 5⁄4" 5⁄4" 2" 200 3 4" 1" 5⁄4" 11⁄2" 11⁄2" 2" 250 1" 1" 5 4" 11⁄2" 2" 9,3 300 1" 5 4" 5⁄4" 2" 2" 11,2 350 5 4" 5⁄4" 11⁄2" 2" 2" 13,0 400 5 4" 5⁄4" 11⁄2" 2" 9,0 15,0 450 5 4" 11⁄2" 2" 2" 10,1 16,8 500 5 4" 11⁄2" 2" 9,5 11,3 17,7 550 5 4" 11⁄2" 2" 10,5 12,4 20,5 600 11 2" 11⁄2" 2" 11,4 13,6 22,4

These plates are dimensioned on the basis of stresses which they have to withstand (force P). Plates with 1" to 2" sockets can be provided on request. The distance «L» and the thrust

force «P» have to be taken in account, when selecting the dia-meter of the pipe nipple between mounting plate and bracket. For the required pipe nipple dimension see table beside.

L P L P L P

100

(35)

Embedded fixed points

Principal: Any variation in length must be prevented by embedded fixed points in concrete (e. g. electroweld sleeve couplings, branches, bends or collar bushes) or by the provision of corresponding fixed point structures.

B

Embedding in concrete

Basically Geberit HDPE material absorbs within itself thermal movement due to its high elasticity.

However, in the case of large diameters (e.g. 315 mm) the forces «P» (resulting from expansion and contraction) are considerable. They must be absorbed by the embedded fixpoints alone, since cement/concrete will not adhere to HDPE pipework.

Since the fitting has to act as a fixpoint, do not insulate it.

Under no circumstances should a ring seal or expansion socket be embedded in concrete. Reduced small branches of large pipe diameters must be secured by an additional anchor point (electroweld sleeve couplings or collar bushes) to prevent shearing off of the branch.

Branch equal Branch equal with reducer

(36)

Cut pipe properly with

Pipe Cutter Hand Mitre Saw

Cutting surface must stay clean, therefore do not touch the cutting surface with your hands!

Cut pipe square!

Ø 32–160 mm Ø 200–315 mm

The allowance for butt welds is approx. as big as the wall thickness of the pipe

pipe diameter (mm) 32–75 90 110 125 160 200 250 315

butt weld s (mm) 3 4 5 5 7 7 8 10

Allowance for butt welds

Mounting instructions

(37)

Geberit HDPE butt welding by hand

(for pipes

32 – 75 mm)

Check temperature of the welding plate.

Do not start with welding procedure before the green light is on.

1

Only press the pipe sections at the beginning against the welding plate. Then hold without pressure. Watch melting process carefully.

2

When melted bulge is about as big as a half of the wall thikness, take off both pipe sections simultane-ously and quickly press them carefully together.

Increase welding pressure until you attain necessary pressure (see table beside).

3

Maintain the max. pressure until the welding seam has cooled (approx. 30 secs. down).

Do not accelerate the cooling down by contact with cold objects or water.

4

Check visually the

welding joint

Indicative values for welding pressure

Ø kg 32 5 40 6 50 7 56 8 63 9 75 10 Correct False: out of axial alinement Too high pressure at the start of the welding procedure

Indicative values for welding and warming-up times

W

elding time in min.

Welding time Warming-up time 5 4 3 2 1 0 mm 2 4 6 8 10 Pipe wall thickness ø 56 110 250

(38)

Geberit HDPE butt welding by machine

(for pipes

40 – 315 mm)

50 63 7511090125 160 TYP MEDIA 84 MASCH. NR.

Place pipe parts in the tension plates and fix them in a line.

1

50 637511090125 160 TYP MEDIA 84 MASCH. N R. 1 cm 1 cm

Press pipe parts lightly against the planing disc and cut the ends until they are completly clean and plane. Check the cut faces by bringing them together.

2

50 63 7511090125 160 TYP MEDIA 84 MASCH. NR. 50 63 7511090 125 160

Melt pipe ends with welding plate (green light on) until the melted bulge is about as big as half of the wall thickness de-pending on size of pipe.

3

50 63 7511090125 160 TYP MEDIA 84 MASCH. NR. Carefully press together both parts with neces-sary welding pressure (see scale). Do not release the locking handle before the complete cooling (approx. 40 secs.).

4

MEDIA ∅ 40 – 160 mm UNIVERSAL40 – 200 mm Set of accessories ∅ 200 – 315 mm

(for UNIVERSAL only)

50 637511090125 160 TYP MEDIA 84 MASCH. NR.

(39)

Geberit HDPE electro welding

Preparation

Cut pipe square

Dry, clean and scrape welding ends.

Remove burr.

Welding ends must remain dry during the whole welding process.

ø40–160 mm

ø40–160 mm

(40)

Geberit HDPE electro weld sleeve coupling

(for pipes

40 – 160 mm)

B.500.000/192

3 cm

3 cm

Insert pipe or fitting ends into the sleeve coupling.

1

Right Wrong

2

3

4

Connect electrofusion machine, start welding procedure.

Welding time approx. 70–90 sec.

After the «END» indicator has turned on, remove the connection cable.

The protruding yellow indicator indicates whether the welding process was performed correctly.

If required for the sake of appearan-ce, the electrical connector socket on 40–160 mm dia. electrowelding sleeves can be removed after the end of installation work.

Geberit Electro fusion machine ESG 40/200

Electroweld sleeve coupling

Note: Basically, electroweld

sleeve couplings should not be welded twice. However, in excep-tional cases a repetition can be done, but wait at least 1 hour until the socket has completely cooled down.

(41)

Geberit HDPE electroweld sleeve coupling

(

200 – 315 mm)

Dry, clean and scrape welding ends.

Remove burr.

Welding ends must remain dry during the whole welding process.

1

1

2

2

3

3

4

4

5

5

Mark insertion length 75 mm.

Mount centering rings to ensure proper welding.

Insert pipe or fitting ends into the electroweld sleeve coupling. Connect start switch cable. Press start button briefly.

Working temperature: –10oC - +40 oC

Wait for at least 15 minutes after weld has been completed before removing the centering rings. Do not remove the plastic sheet insulation until the sleeve has completely cooled down. Geberit Start switch 230 V/50 Hz

Thermo sleeve coupling

Welding time: ca. 5 to 7 minures at 20oC

(42)

Prefabrication

«Light weight» – easy to

handle

Wide range of fittings, excellent tools and the light weight

of Geberit HDPE = perfect performance for prefabrication.

• The good characteristics of the Geberit HDPE offer an easy way to prefabricate pipe assemblies.

• Through the butt welding technique, the pipes and fittings can be easily connected to make many big combinations.

• Complicated labour at the site is eliminated by the clean and easy organized work at the workshop.

• Afterwards, at the site the prefabricated combinations can be assembled very fast.

Description

Advantages

• Simplified work

• Easy time management • Time saving

• Higher performance • Higher quality

• Professional impression • Short time at the site • No loss of material

(43)

10

170

Prefabrication

Procedure

Measurements (Preparation)

Take measurements on site and mark the positions of all fixtures on the walls and floor.

2.1 Using the isometrics method

Part Ø c–c ./. total 1 Pipe 110 450 140 310 2 Pipe 63 620 430 190 3 Pipe 63 765 188 577 4 Pipe 63 .... .... ... 5 .... ... .... ... ... 6 ... 7 8 9

2.2 Using Geberit software

Design drawing

Prepare the design and detailed drawing.

1

2

70 60 60 70 55

16

(44)

Prefabrication

Cut pipe square B.600.000/020

Prepare pipes and fittings

Shorten fitting

Weld pipes and fittings together with the Geberit welding machine MEDIA or UNIVERSAL.

Prefabrication of assemblies

The prefabricated assemblies can be connected on site with the electroweld sleeve coupling.

Installation on site

3

4

5

(45)

Electric repair tool

(Art. No. 395.049.00.0)

Clean repair area well with scraper, knife or emery cloth.

1

Screw suitably sized insert onto front or side of heater.

2

"BARY" Kunststoff-Schwe issapparate

Type: A- Volt 230WattNr.W.Riesen Basel (Schweiz) Dittingerstrasse 45

Heat simultaneously repair area and patch.

3

Press softened patch quickly onto repair area.

4

5

6

Repairing holes in HDPE

pipes and fittings and in PE

concealed cisterns

(46)

Thermal expansion sockets

(application in buildings)

Mounting instructions

Prepare pipe insertion end.

1

Mark insertion depth on the pipe. Consider outside temperature.

2

Remove yellow protection cap.

3

Lubricate pipe end and rubber seal. Only use soft soap, Silicone or Vaseline. Do not use mineral oil or grease !

4

Push the pipe into the expansion socket.

5

On the building site, protect the seal from

ingress of dirt. Wrap a felt bandage around and secure with adhesive tape.

6

at 0°C (32°F) at 20°C (68°F)

Important:

Fix each expansion socket with an anchor bracket !

Please note:

The marking of the insertion depth and the assigned length of pipe on the expansion socket does not apply for buried pipes, unless the same temperature fluctua-tions as in the building draina-ge system are

anticipated. maximal pipe length: 6 m !

8 cm 10,5 cm

(47)

Speciall application fields

Underground drainage pipes for housing

Underground

drainage pipes of Geberit HDPE

Not only has Geberit HDPE proven itself excellently for many years for drainage systems inside of buildings such as:

– soil and waste stacks – vent pipes

– connection and branch pipes – collector pipes

but it is also suitable for under-ground applications as: – ground pipes

– domestic drainage pipes

Criteria for underground drainage pipes

1. Tightness

2. Resistance to chemicals Geberit HDPE provides the

assu-rance of universal resistance

to the greatly diversified types of chemical attack by the disposal water, as well as by external factors (acidic soils).

3. Flexibility

Geberit HDPE is a flexible, operatio-nally reliable drainage system, even in soils in which a certain degree of settling of ground must be anti-cipated.

4. Resistance to frost

Geberit HDPE has proven itself excellently for many years in frost endangered soils such as in Scandinavia. It can be used in

tem-applications. In addition to the attack from the inside, the pipes are also subjected to attacks from outside. Geberit HDPE excellently stands up to all these requirements.

1 Ground acids

1

3

2

4

(48)

D 10 cm B A D A=D + min. 100 mm

Trench profiles

Important for underground installa-tion

is correct laying of the pipe in the trench, as well as careful consolida-tion.

B = Bedding

The pipe must have a bedding of at least 100 mm.

C = Consolidation

Side fill to upper edge of pipe.

P = Protective layer

With trench profile 1A cover to above top edge of pipe over entire width of trench min. 300 mm

HS = Safety height

when using mechanical compac-tors: Vibration compactor 1,000 N HS = 0,4 m Vibration roller 3,000 N HS = 0,3 m Vibration roller 15,000 N HS = 0,5 m

D = Consolidation stratum depth

min. covering:

In area of road 0,8 m

Outside road area 0,5 m

Max. covering:

Up to 6 m without problem

In cases of minimum coverings or heavy loading, measures such as load distribution plates or appropria-te trench profiles are to be used.

Traffic loads

Heavy traffic P = 9 tons Normal traffic P = 6 tons

Away from roads:

always P = 3 tons Filling material Grain size Round gravel 0 = 30 mm Broken material 0 = 10 mm min. 60 cm 20 cm D HS P C B Profil V1A Behavior: flexible Embedment Round gravel 0 – 30 mm Broken material 0 – 10 mm 10 cm B A Profil U4A Behavior: rigid Embedment in concrete PC 200 kg/m3 Profil U4B Behavior: rigid Embedment in reinforced concrete PC 250 kg/cm3 20 cm HS P C B Profil U1A Behavior: flexible Embedment Round gravel 0 – 30 mm Broken material 0 – 10 mm

(49)

Guidelines for laying drainage pipes

Trench

The trench is to be dug as narrow as possible – but not narrower than the pipe diameter + 40 cm. The floor of the trench must be level and free from rocks and loose clumps. Correct elevation and slope are also impor-tant.

1

B = Bedding

Under normal soil condi-tions the trench is provi-ded with a bedding layer of round gravel (grading up to 30 mm) or of bro-ken material (grading up to 10 mm) of a thickness of approx. 100 mm. The bedding layer must be compacted and tamped. In certain cases it will be neccessary to reinforce the ground.

2

U = Underpinning

After the pipe has been laid, recesses are to be provided for sockets and flanges so that the pipe is supported along its entire length. The underpinning is to be done with a tamping post or the like. It must be done very carefully. If seve-ral pipes are laid, make sure that the lowest one is fully covered before the one above is placed. The pipe must lay flat, and it must be installed with the correct slope.

3

C = Consolidation layer

The material is to be filled in layers of approx. 100 mm thickness. Tamping can be done by stamping with the feet, or with a special tool. The purpose of this material is to help prevent the pipe from deforming, so that it must be compacted well on both sides at the same time .

4

1

2

P = Protective layer

Now fill in a layer of the same material (must not contain rocks which could cause point loading of the pipe) of at least 300 cm.

5

HS = Safety margin

height

For the further filling the available material is to be used. The trench must not contain rocks which can-not be lifted by hand.

6

Distribution of

ground pressure

The ground pressure and ground load distribution are gover-ned essentially by the compaction. For calcu-1 Ground load

and possible traffic load 2 Shoring pressure

For all trenching work the local guidelines, standards and regulations must be observed.

B

U

C

P

(50)

Rigid installation

Rigid fixation

The rigid fixings must be stronger

than the possible expansion or contraction forces of the HDPE pipe.

Geberit pipes can be installed rigidly with relatively low effort, for which the following elements are required:

1 Concrete mound as an anchor

point

2 Electroweld sleeve coupling 3 HDPE pipe

1

(51)

Please note:

The scale found on the outer surface of the socket does not apply in the case of underground installations.

Underground installation of

Geberit expansion sockets

In addition to the butt-welded and electrically welded connection, the expansion socket is an ideal connection in underground draina-ge systems. Since in such systems lower temperature differences are usually encountered than in stacks and connector pipes, smaller length variations can be accounted for.

For this reason in underground installations the distance between expansion sockets can be longer.

The values arev calculated accor-ding to the formula

SL – (0.3 • d)

0.006

and rounded off.

Nominal Socket Pipe length Insertion outside length SL PL (for ∆t depth ID diameter ≤ 30°C) d (mm) (mm) PL (m) (mm) 110 140 15 130 125 140 15 130 160 140 15 130 200 220 20 230 250 220 20 230 315 220 20 230

Fitting of the underground expansion socket in the installations

Insert beveled pipe to maximum socket depth, mark and pull back 40 mm.

Prepare the pipe end

The pipe end should be chamfered and lubricated with soap to ease inserting.

d ID (insertion depth) PL (pipe length) SL (socket length) PL 4cm ID 4 cm PL ≤

(52)

With regard to the ground line between the building wall and the street sewer, where extreme settling can occur, an installation mat must be wrapped around the ground line to act as a deflection leg.

In such cases Geberit HDPE is an ideal material, since it assures tightness and at the same time provides maximum flexibility.

Deflection leg

The length of the deflection leg is dependent upon the expected settling and on the pipe diameter.

Length DL = 10 · |

/

∆ S · ∅

Note: The insulation must be

thicker than the expected settling.

Pipes penetrating through building walls

Expected settling GeberitHDPE pipe Deflection leg

∆ S ø DL

20 – 40 mm 125 – 160 /200 – 315 1,0 m /1,0 m

40 – 60 mm 125 – 160 /200 – 315 1,0 m /1,5 m

60 – 80 mm 125 – 160 /200 – 315 1,5 m /1,7 m

1 See page pipe 2 Settling 3 Insulation mat 4 HDPE pipe (Ø) 5 Foundation slab 6 See page lining DL = Deflection leg S = Insulation thickness ∆S = expected settling H d D L

(53)

Connection to manhole

Open manhole

Access pipe with oval access cover

Plastic pipes should only be connected with manholes by means

of a special manhole sleeve. Since settling of ground has to be expected such a sleeve must have the same ideal characteristics as Geberit HDPE: it must assure tightness and at the same time fle-xibility.

A rubber ring provides the flexible seal between sleeve and plastic pipe.

1 Concrete 2 Manhole sleeve 3 Geberit HDPE pipe 4 Bench

5 Anchor point if required

1 Concrete 2 Manhole sleeve

3 Access pipe (Art nr. 3xx.454.16.1)

Geberit access pipe with oval access cover

1

2

(54)

Drainage requirements for bridges

Traffic safety/Maintenance

Geberit HDPE also meets the special requirements for all types of bridges. The pipes and the wide range of fittings provide an easy design and execution at the cons-truction site. The smooth walled pipes make a trouble-free mainte-nance and service possible, whereby all modern cleaning equip-ment can be used.

Heating tape

Where the bridge crosses a river, railway or another road, an absolu-tely watertight system is essential. In accordance with the anti-pollution laws, protection must be maintained in the event of an accident.

1 Silt trap 2 Connector

pipe

3 Collectorpipe

Frost protection

Ground water protection

Piping Arrangement

Geberit HDPE can be installed in temperatures down to –40°C. However, to ensure water flow in the pipe an automatic-controlled heat trace can be fitted.

Collector pipe (The inlet into the collector pipe is made with 135° Y-branch fittings).

(55)

Drainage of bridges

Installation indications

Laid in concrete

Piping embedded in the bridge structure can never be replaced. It is therefore essential that a drainage material which offers the greatest security is used. When choosing this material, the consolidation of the concrete, temperature varia-tions, contraction and creep, as well as the prestressing of the bridge must be taken into consideration.

Thermal movement

The following points must be obser-ved

– Location of supports or piles – Horizontal movement of

the bridge on the supports – Deflection of the bridge – Swaying of the bridge

– The watertightness of the expan-sion socket (example 1)

In the case of example 2 an expan-sion funnel is required to absorb the lateral movements.

Fixing

The spacing of the guide brackets for HDPE piping is 1,5 m and may not be exceeded. With all plastic piping, the pipe bracket should have a minimum width of 60 mm, in order that the stresses due to the weight of the filled pipe is well distributed.

Expansion socket Expansion funnel

Guide bracket

(56)

Low pressure installation

Low pressure application

Discharge pipeline of a pump set

Generally the Geberit HDPE product range is designed for water drainage systems.

For the low pressure range, e. g. swimming pool, pipework through circulation pumps, Geberit has established maximum admissible stressing values for an endurance life of 10 years.

Pressure max. 1,5 bar Temperature max. 30°C Longterm

rupture strength 10 years

All connections must be butt weld joints, electroweld sleeve couplings or flange joints.

Suitable fitting range for low pressure application see page 4.

The Geberit HDPE range of products can also be used for the discharge pipeline of a pump set, provided that the mechanical stress is low, only of short time and no thermal loaded medium (e.g. warm water) is pumped.

When designing discharge pipelines for drainage pumps the following important points should be observed:

1. The discharge pipeline has to be installed higher than the lowest installed appliance by means of a pipe loop.

2. If the flow rate is smaller than 5 l/s the vertical fall section of the pipe loop has to be increased.

3. If the flow rate is above 5 l/s the vertical stack has to be vented with a ventilation pipe of at least 50 mm inside diameter.

4. Long horizontal collector pipes have to be vented. The minimal inner diameter of the vent pipe must be 57 mm or 2 dimensions smaller than the discharge pipe.

The ventilation pipe must be higher than the total delivery head of the pump and must go above the roof.

Pumped pressure pipeline Pumped pressure pipeline Vertical stack Vertical stack Vertical stack Collector pipe Pumped pressure pipeline Vertical stack Collector pipe Pumped pressure pipeline V·> 5 l/s Vent ≥ 50/56 Side vent ≥ 50/56 Collector pipe Vertical discharge stack Pumped pressure pipeline Vent ≥ 50/56 Side vent ≥ 50/56 Collector pipe

(57)

External pressures

Internal negative pressures

External pressures

Permitted external pressures

Geberit HDPE pipes will withstand external pressures according to the table below depending on the pipe diameter.

The maximum level of the groundwater table has to be taken into account when designing Geberit HDPE pipelines in a groundwater area.

Internal negative pressures

Geberit HDPE pipes will withstand internal negative pressure according to the table above depending on the pipe diameter.

Geberit HDPE pipes are sometimes used as suction pipelines for pumpsets. The higher the suction lift is, the higher the negative pressure inside the pipeline. Important with such an installation is that the foot valve and strainer are not blocked.

Foot valve and strainer of the suction pipeline should be kept free from debris, possible blockage could lead to additional pressure increase.

Pipe Wall thickness External pressure

s (mm) bar m Water column

32 3 4,8 49,0 40 3 2,5 25,5 50 3 1,4 14,3 56 3 0,82 8,4 63 3 0,64 6,5 75–160 3–6,2 0,36 3,7 200–315 6,2–9,8 0,18 1,8

For adequate fittings see page 4

Permitted internal

negative pressures

Pipe Wall thickness Internal negative pressure

s (mm) bar

32 3 1,0

40 3 1,0

(58)

Fire protection

Depending on the type of building different fire protection will be required (see local fire regulations for buildings).

Building parts

The requirments for building com-ponents are classified in fire resi-stant

classes in order to maintain maximum integrity of the relevant wall, floor or ceiling.

The weakening of a fire protection wall or ceiling is not allowed under any circumstances.

The integrity of the wall or ceiling will be maintained for the permitted periods when Geberit fire stoppers are used as illustrated.

Passing through wall and

ceiling

Installation

and time of fire resistance

Fire resistance Fire resistance Material

class time (minutes) (example)

F 30 30 50 mm gipsum board F 60 60 100 mm brick-wall F 90 90 120 mm brick-wall F 120 120 150 mm brick-wall F 180 180 250 mm brick-wall Gr. 10 Gr. 10

Installed on the ceiling Fire class F 90

Installed on both sides of the wall Fire class F 120

Use only for:

12 11 10 9 8 7615243

STOP!

90 Min 1112 10 9 8 7651432

STOP!

90 Min 12 11 10 9 8 765 4 3 2 1

STOP!

90 Min 102683_ZEI_000_00.EPS

(59)

Geberit HDPE Fire stoppers

Housing with flexible fastening brackets Foaming firestop material Insulation against solid-borne noise

Lock with locking ring

Wedge-type staybolts for fastening when retrofitting

Identification plate

Function:

Measurements:

Art. Nr. d1 (cm) D(cm) L(cm) I1 363.815.00.1 6.2 7.2 8.5 3.5 3 364.815.00.1 6.5 7.7 8.5 3.5 3 365.815.00.1 8.8 10.8 10.0 5.0 4 366.815.00.1 10.1 12.1 10.0 5.0 4 367.815.00.1 12.0 14.0 10.0 5.0 4 368.815.00.1 13.4 16.6 11.0 6.0 5 312.815.00.1 14.2 17.2 11.0 6.0 5 369.815.00.1 16.7 19.9 11.0 6.0 6 994.871.00.0 Gebe rit Roh rsch ott90 R 90 Z-19.17-1 365 Geberit GmbH, D-88630 Pfullendorf ... Roh rabsch ottung: Dispositif coupe-feu Compartim ento no n infiammabile Leidingmanchet Bran dmanchet Fire protection sle eve Feuerw iderstan dsklasse : Cla sse de résistance Cla ssificazione del fu oco Brandweersta ndsklasse Brandmod standsklasse Fire p rotectio n classification Zulas sungs-Nr .: Numéro de certific ation Numero di conce ssione Keuringsn ummer Go dkendelses n ummer Approval number Herste ller: Fabricant Produttore Fabrikant Fabrikant Manufactu rer Herste llungs datu m: Da te de f abrication Data di produzione Productie datum Pro duktionsda to Da te of fa brication Montiert dur ch: Installé par: Montato da: Gemon teerd door: Mon teret af: Installe d by: D L l1 d1

Once the temperature in the room which is ablaze reaches a certain level, the intumescent material expands as a foam and closes off the cross-section of the pipe, therefore preventning (for a certain required length of time) the fire and smoke from spreading through the opening.

(60)

Installation

Gr. 10 Gr. 10 B C C A D D B C D D C A X X X ø 56/DN 50 X= 1.0-2.0 cm ø 75/DN 70 X= 2.0-4.0 cm ø 90/DN 80 X= 2.0-4.0 cm ø(mm) A(cm) B(cm) C (cm) 50/56 9.0 9.0 17.0 63 9.0 9.0 17.5 75 10.5 10.5 20.5 90 11.5 11.5 22.0 110 12.5 12.5 24.0 125 13.5 13.5 26.5 135 14.0 14.0 27.5 160 15.0 15.0 20.0 200 17.0 17.0 34.0 ø(mm) A(cm) B(cm) C (cm) 50/56 4.0 4.0 9.0 63 4.5 4.5 9.5 75 10.5 6.0 12.0 90 11.5 7.0 13.0 110 12.5 8.0 15.0 125 13.5 9.0 18.0 135 14.0 9.5 19.0 160 15.0 10.5 22.0 200 17.0 13.0 26.0 ø 110/DN 100 X= 2.0-4.0 cm ø 135/DN 125 X= 5.0 cm Subsequent installation on the wall or ceiling

(with bent-back fastening bracket)

Installation in wall or ceiling opening

ceiling wall

ceiling wall

(61)

Physical characteristics of Geberit HDPE

Physical characteristics of Geberit HDPE

The data given below was obtained with test specimens of pressed plates and foils. Individual values can deviate from these average values depending on the conditions under which the test specimens were made.

Characteristic Unit Test method Test specimen

Density g/cm3 DIN53479 Plate

0,953...0,955

Reduced specific dl/g ISO/R 1191 0,1% solution 3,0

viscosity (viscosity

coefficient) in decalin

Melt-flow index MFI 190/5 g/10 mins. DIN 53735 granulate 0,4...0,7 Mechanical characteristics, measured under standard climatic conditions 23°C, 50% relative air humidity**

Tensile strength N/mm2 DIN 53455. ISO/ Test specimen 3 22

Elongation at yield stress % R 527; test velocity with measurements 15 Ultimate tensile strength N/mm2 125 mm/min in the ratio 1:4 32

Elongation at break % > 800

Limit bending strength N/mm2 DIN 53452 Standard small bar 28 injection moulded

Torsional rigidity N/mm2 DIN 53447 60 mm x 6,35 mm x 2 mm 240 Bending creep modulus N/mm2 Bending creep test 120 mm x 20 mm x 6 mm 800

1 minute value οb 3 N/mm2

Indentation hardness N/mm2 DIN 53456 Sheet, 4 mm 40

30 second value Test strength 132, 4N

Shore hardness D — DIN 53505 Sheet, 4 mm 60

Impact strength mJ/mm2 DIN 53453 Standard small bar, moulded*** 15 Impact strength at mJ/mm2 DIN 53453 Standard small bar, injection

+23°C and –40°C moulded

Thermal characteristics

Crystallite melting range °C Polarisation microscope Microtome section 127...131 Mean linear expansion K–1 DIN 52328; ASTM D 696 50 mm x 4 mm x 4 mm 1,7·10–4 coefficient between 20° and 90°C

W

Heat conductivity at 20°C m · K DIN 52612 sheet method Plate, 8 mm 0,43 Injection, moulded

Electrical properties, measured under standard climatic conditions of 23°C, 50% relative air humidity

Specific transmission resistance Ω · cm DIN 53482 Foil, 0,2 mm >1016 VDE 0303 Part 3

Surface resistance Ω DIN 53482 Sheet, 1 mm >1013

VDE 0303 Part 3

Electric strength kV/cm DIN 53481 Foil, 0,2 mm 700

VDE 0303 Part 2 Dielectric index εr,

(relative dielectric constant)

at 2 106Hz — DIN 53483, VDE 0303 Foil, 0,2 mm 2,50

Part 4 (immersion method)

Dielectric loss factor DIN 53483, VDE 0303 Foil, 0,2 mm

tan δ at 50 Hz — Part 4 6 · 10–4

103Hz — 5 · 10–4

104Hz — 5 · 10–4

105Hz — 6 · 10–4

Track resistance DIN 53 480 Sheet ≥ 3 mm KA 3c

VDE 0303 Part 1 KC > 600

Arc resistance DIN 53484 120 mm x 120 mm x 10 mm L4

VDE 0303, Part 5

(62)

Ecological properties of Geberit HDPE

Polyethylene (PE) is a simple compound of carbon and hydrogen atoms, harmless to man, animals and plants.

PE is the perfect material for drainage systems from an ecological point of view. It has a long life span, no toxic gases rises from incineration (e. g. hydrochloric acid HCL from PVC) during disposal. It consumes much smaller quantities of energy during fabrication process and transport than steel, cast iron or cop-per pipes.

PE environmental loads relate to the fields of manufacture and disposal. In addition to the raw material crude oil, energy is used for the preparation of the plastic granulate and in the manufacture of the products.

Fore more information about environment and sustainability, please order our report

Life Cycle Assessment Drainage pipes for buildings

(63)

Ecological properties of Geberit HDPE

Environmental impact

of different pipe material

(Ecobalance)

The diagram shows the environmental impact of 1 m pipe Ø 110 during its expected life, beginning with its raw material and ending with its disposal.

The environmental impact is measured in environmental points (UP), according to the regulations of the Swiss Federal Office of Environment, Forest and Countryside (BUWAL), Publication series 132 and 133.

7000

UP/m pipe

0

1000

2000

3000

4000

5000

6000

Cast iron

50%

recycled

Cast iron

100%

recycled

PVC

ABS

HD-PE

Disposal of pipes

Manufacture of pipes

References

Related documents