Belgische Technische Coöperatie
Naamloze vennootschap van publiek recht met sociaal oogmerk
Coopération Technique Belge
Société Anonyme de droit public à finalité sociale
ADEPT TRACKER
BASIC TRAINING
1. INTRODUCTION
On September 29, 2004, the Management Committee decided to implement as from 2005 onwards the manual « M.2.1.3.01 Operation Planning of Project Activities » related to the planning of project activities. This manual supports financial planning and prepares the monitoring of projects. A support and training programme will be put to the field, and this in consultation with the GEO services.
The Management Committee also decided that « ADEPT TRACKER » would be used to implement the activity planning. The BTC has therefore purchased an « unlimited site licence of Adept Tracker Professional 3.11 ».
2. INSTALLATION OF THE TOOL
To install the application Adept Tracker download the file "setup.exe" on your hard disk form this website :
http://www.adepttracker.com/
Belgian Technical Cooperation
Double-click on “Self-extract file” to start downloading and accept all default values for the installation :
AdeptTracker Professional 3.11:
Self-extract file: 4,3MB (Sept, 2008)
Zip format:54,28 MB (Sept, 2008)
The application opens automatically after downloading.
If this is not the case, open the application (default) on the following location :
C:\Program Files\LZC Software\AdeptTracker
A message warns that you downloaded a demonstration version for 21 days.
To register the application Adept Tracker (BTC multi-users contract), open the HELPmenu and click on « Registration »
Next to "Enter your username" ,register : « BTC-CTB » Next to "Company" , register « BTC-CTB »
Finally type the following code next to "Enter Series" :
cvi9sjcsmkn43
titel van het document Garamond 17 / 3 ¦
3. INFORMATION ON THE PROJECT
Belgian Technical Cooperation
2° Define the objectives
3° Set the start date and the end date
4. DEFINE THE ACTIVITIES
1° Define the activities
titel van het document Garamond 17 / 5 ¦
2° The results and activities can be included in a WBS diagram (Work Breakdown Structure)
Tools/GantChartOptions/Columns/WBS Project/ProjectWBS Settings
After this we can easily detail the action plan for each budgetline we’ve created. We obtain the following WBS, in accordance with FIT.
Belgian Technical Cooperation
titel van het document Garamond 17 / 7 ¦
Belgian Technical Cooperation
titel van het document Garamond 17 / 7 ¦
5. DEFINE THE RELATIONSHIPS
1° Define the various types of relationships
2° Define the lag time
A lag time can exist between two activities (e.g., when a procurement notice is published, the possible candidates have X days to submit their price offer). This lag time is associated with
a type of relationship.
5. DEFINE THE ACTIVITY DURATION
Belgian Technical Cooperation
2° “Earliest Start Date” and “Latest Finish Date”
“Earliest Start Dates » and « Latest Finish Dates » can be defined for activities.
titel van het document Garamond 17 / 9 ¦
3° Milestones
Milestones are used to indicate key moments in a project. Some people use these
milestones as evaluation moments so as to measure whether deliverables are delivered on time.
Belgian Technical Cooperation
6. ASSIGN
THE
RESOURCES
1° Define the resources
2° Assign the resources to activities
titel van het document Garamond 17 / 11 ¦
3° Percentage of assigned resources
4° Resources costs
Regarding resources costs, you can always choose between a cost/rate (e.g. staff) and a cost/use (e.g. material).
Belgian Technical Cooperation
7. ANALYSIS OF ACTIVITY PLANNING
1° Critical and non-critical tasks
Critical tasks are activities for which any extension of the activity duration automatically results in an extension of the project.
Within a certain margin of time, non-critical tasks can start a little later and/or last longer. Critical tasks can be displayed by « subproject ».
a. critical tasks : in red b. non-critical tasks : in blue
titel van het document Garamond 17 / 13 ¦
2° Save a Baseline
A Baseline should always be saved when drawing up a planning. Consequently, if after e.g. 3 months, the activity planning has to be adapted, a comparison with the original planning is always possible.
3° Activities to display
Belgian Technical Cooperation
8. MONITORING OF ACTIVITY PLANNING
1° Fill in the completion percentage of activities
2° Adapt an activity planning 3° Baseline Management
titel van het document Garamond 17 / 15 ¦
If you compare a present version of a planning to a former version with a Baseline, the chart will clearly show the evolution in this planning. The Baseline version is indicated in yellow on the « Gantt Chart ».
Belgian Technical Cooperation
9. SOME
INTERESTING
ELEMENTS
1° Import from and export to MS Project
titel van het document Garamond 17 / 17 ¦
Belgian Technical Cooperation
3° Save as PDF-file
titel van het document Garamond 17 / 19 ¦
Belgian Technical Cooperation
4° Reporting possibilities: some examples
Resource Report
titel van het document Garamond 17 / 21 ¦