Copyright 2014, Simplilearn, All rights reserved.
PRINCE2 is a registered trademark of AXELOS Limited.
Lesson 2—PRINCE2® Principles
PRINCE2® Foundation
● List the seven principles of PRINCE2® methodology ● Explain the seven principles of PRINCE2® methodology
After completing this lesson, you will be able to:
The seven principles of PRINCE2® are as follows:
Seven Principles of PRINCE2®
Continued Business Justification
A PRINCE2® project has continued business justification.[1]
Requirements for a PRINCE2® project are as follows:
● There should be a justifiable reason to start a project.
● The justification should remain valid throughout the life of the project. ● Although the justification should remain valid, it may change or evolve. ● The justification should be approved and documented in a Business Case.
Learn from Experience
PRINCE2® project teams learn from previous experience: lessons are sought, recorded and acted upon throughout the life of the project.[2]
The main features of this principle are:
● The teams learn from historical data based on previous similar projects in the same organisation or
from a different organisation, however in the same industry.
● They learn when the project starts, as it progresses and when it closes.
● It is the responsibility of everyone involved with the project to proactively seek lessons learnt.
A Japanese bank is to provide partial funding for an infrastructure project in a
developing country. However, they want an assurance from the local government as a similar project in the past had faced local labour problems.
Roles and Responsibilities
A PRINCE2® project has defined and agreed roles and responsibilities within an organization structure that engages the business, user and supplier stakeholder interests.[3]
Manage by Stages
A PRINCE2® project is planned, monitored and controlled on a stage-by-stage basis.[4]
The different features of this principle are:
● PRINCE2® suggests that the work be divided in multiple logical stages called management stages. ● The production of the project is carried out in phases called technical stages.
● A PRINCE2® project should have minimum two management stages: one initiation stage and one
or more further management stages.
● Shorter the stages, more the control and vice-versa.
● Stages are to be planned, delegated, monitored and controlled according to the business priority,
Manage by Exception
A PRINCE2® project has defined tolerances for each project objective to establish limits of delegated authority.[5]
Every PRINCE2® project has four levels of management. They are:
The Corporate or Programme Management appoints an Executive, whose responsibility is to get the project executed as per the tolerances defined by them.
Corporate or programme management
Project Board is responsible for providing overall direction and management to the project. Directing—Project Board
The Project Board appoints Project Manager to take care of day-to-day management of the project within the constraint set by the Project Board.
Managing—Project Manager
The Project Manager gets the work done through Team Managers, who deliver the actual specialist product of the project.
Delivering—Team Manager
Manage by Exception (contd.)
According to PRINCE2®, the Project Manager controls six aspects of the project and they are Time, Cost, Scope, Benefits, Risks and Quality.
● If the tolerances are forecast to be exceeded, they are immediately referred to the next
management layer for a decision.
Focus on Products
A PRINCE2® project focuses on the definition and delivery of products, in particular their quality requirements.[6]
The product description includes each product’s purpose, composition, derivation, format, quality criteria and quality method.
● Product description is used to: o estimate efforts.
o determine resource requirements.
o determine dependencies.
o determine schedule of activities.
● A successful project is output-oriented and not activity-oriented. An output-oriented project is
one that agrees and defines the project’s products prior to undertaking the activities required to produce them.
Tailor to Suit the Project Environment
PRINCE2® is tailored to suit the project’s environment, size, complexity, importance, capability and risk.[7]
Project Initiation Documentation (PID) describes how the method is being tailored for a project.
● Tailor the project management method to suit the project environment such as business processes
for human resource, finance and procurement management.
● Set project controls based on: o Scale
o Complexity
o Importance
o Capability
a. b. c. d.
QUIZ
Which of the PRINCE2® principles supports the definition of tolerances for the six project objectives?Tailor to suit the project environment Focus on products
Manage by exception Manage by stages
1
a. b. c. d.
QUIZ
Answer: d.Explanation: Manage by exception principle supports the definition of tolerances for the six
project objectives.
Tailor to suit the project environment Focus on products
Manage by exception Manage by stages
Which of the PRINCE2® principles supports the definition of tolerances for the six project objectives?
a. b. c. d.
QUIZ
If the projects are based on the management by exception principle, which of the following benefits does it provide?Project is not seen as an end in itself
Provides clarity of what a project will deliver, why, by whom, and when Efficient and economic use of management time
Promotes consistency of project work
2
a. b. c. d.
QUIZ
Answer: d.Explanation: The implementation of management by exception provides efficient and
economic use of senior management time.
Project is not seen as an end in itself
Provides clarity of what a project will deliver, why, by whom, and when Efficient and economic use of management time
Promotes consistency of project work
If the projects are based on the management by exception principle, which of the following benefits does it provide?
a. b. c. d.
QUIZ
The incorporation of the primary stakeholders in the project management team supports which principle?Defined roles and responsibilities Manage by stages
Manage by exceptions
Continued business justification
3
a. b. c. d.
QUIZ
Answer: b.Explanation: The incorporation of the primary stakeholders in the project management
team supports defined roles and responsibilities principle. Defined roles and responsibilities
Manage by stages Manage by exceptions
Continued business justification
The incorporation of the primary stakeholders in the project management team supports which principle?
a. b. c. d.
QUIZ
Which PRINCE2® principle supports planning only to a level of detail that is manageable and foreseeable?Defined roles and responsibilities Manage by stages
Manage by exceptions
Continued business justification
4
a. b. c. d.
QUIZ
Answer: c.Explanation: Manage by stages principle supports planning only to a level of detail that is
manageable and foreseeable. A PRINCE2® project is planned, monitored and controlled on a stage-by-stage basis.
Defined roles and responsibilities Manage by stages
Manage by exceptions
Continued business justification
Which PRINCE2® principle supports planning only to a level of detail that is manageable and foreseeable?
a. b. c. d.
QUIZ
As per PRINCE2®, the three primary stakeholders in the project are:
Business, users and customers Users, suppliers and customers Customers, business and trader Business, users and suppliers
5
a. b. c. d.
QUIZ
Answer: a.Explanation: As per PRINCE2®, the three primary stakeholders in the project are business,
users and suppliers.
Business, users and customers Users, suppliers and customers Customers, business and trader Business, users and suppliers
As per PRINCE2®, the three primary stakeholders in the project are:
5
a. b. c. d.
QUIZ
Which PRINCE2® principle ensures that the project is viable, achievable and desirable?
Manage by exception Focus on products
Tailor to suit the project environment Continued business justification
6
a. b. c. d.
QUIZ
Answer: a.Explanation: Continued business justification principle ensures that the project is viable,
achievable and desirable. A PRINCE2® project has continued business justification, which should remain valid throughout the life of the project.
Manage by exception Focus on products
Tailor to suit the project environment Continued business justification
Which PRINCE2® principle ensures that the project is viable, achievable and desirable?
6
a. b. c. d.
QUIZ
Which PRINCE2® principle ensures that the PRINCE2® project delivers the product as per quality requirements?Manage by exception Focus on products
Tailor to suit the project environment Continued business justification
7
a. b. c. d.
QUIZ
Answer: c.Explanation: Focus on products principle ensures that the PRINCE2® project delivers the
product as per quality requirements. Without it, projects are exposed to major risks such as acceptance disputes, uncontrolled change (scope creep) and user dissatisfaction.
Manage by exception Focus on products
Tailor to suit the project environment Continued business justification
Which PRINCE2® principle ensures that the PRINCE2® project delivers the product as per quality requirements?
a. b. c. d.
QUIZ
Which of the following PRINCE2® principles ensures that project management effort and approach are appropriate for the needs of the project?Manage by exception Focus on products
Tailor to suit the project environment Continued business justification
8
a. b. c. d.
QUIZ
Answer: d.Explanation: Tailor to suit the project environment principle ensures that project
management effort and approach are appropriate for the needs of the project. PRINCE2® is tailored to suit the project’s environment, size, complexity, importance, capability and risk.
Manage by exception Focus on products
Tailor to suit the project environment Continued business justification
Which of the following PRINCE2® principles ensures that project management effort and approach are appropriate for the needs of the project?
a. b. c. d.
QUIZ
Justification for a PRINCE2® project is documented in:
Business Case Project Brief Stage Plan
Project Initiation Documentation (PID)
9
a. b. c. d.
QUIZ
Answer: b.Explanation: A PRINCE2® project has continued business justification. The justification is
documented in a Business Case. Business Case Project Brief Stage Plan
Project Initiation Documentation (PID)
a. b. c. d.
QUIZ
A PRINCE2® project should have at least how many management stages?
Three Four Seven Two
10
a. b. c. d.
QUIZ
Answer: a.Explanation: PRINCE2® requires a minimum of two management stages: one initiation stage
and one or more further management stages. Three
Four Seven Two
A PRINCE2® project should have at least how many management stages?
10
● A PRINCE2® project has continued business justification
● PRINCE2® project teams learn from previous experience: lessons are sought,
recorded and acted upon throughout the life of the project
● A PRINCE2® project has defined and agreed upon roles and responsibilities
within an organisation structure that engages the business, user and supplier stakeholder interests
● A PRINCE2® project is planned, monitored and controlled on a
stage-by-stage basis
● A PRINCE2® project has defined tolerances for each project objective to
establish limits of delegated authority
● A PRINCE2® project focuses on the definition and delivery of products, in
particular, their quality requirements
● PRINCE2® is tailored to suit the project’s environment, size, complexity,
Summary
Here is a quick recap of what we have learnt in this lesson:
Thank You
Copyright 2014, Simplilearn, All rights reserved.
[1] Based on Managing Successful Projects with PRINCE2®, by AXELOS. Principles, Continued Business Justification.
[2] Based on Managing Successful Projects with PRINCE2®, by AXELOS. Principles, Learn from Experience.
[3] Based on Managing Successful Projects with PRINCE2®, by AXELOS. Principles, Defined Roles and Responsibilities.
[4] Based on Managing Successful Projects with PRINCE2®, by AXELOS. Principles, Manage by Stages. [5] Based on Managing Successful Projects with PRINCE2®, by AXELOS. Principles, Manage by
Exception.
[6] Based on Managing Successful Projects with PRINCE2®, by AXELOS. Principles, Focus on Products. [7] Based on Managing Successful Projects with PRINCE2®, by AXELOS. Principles, Tailor to Suit the Project Environment.