The Impact of Solar Power and Other
Variable Distributed Renewable
Generation on the Distribution Grid
Jenna Van Vliet, Hydro Ottawa Frank Chan, CEATI International Robyn Pascal, CEATI International
Project Scope
Introduction
Literature Search
Simulation Software Requirements
Data Collection and Analysis
System Description
System Impact Studies
Conclusions
Future Work
Introduction
Penetration of PV generation in distribution and
transmission systems has increased dramatically
in recent years.
Small numbers of PV generation offer few or
no problems, but as the percentage of PV
generation grows, a number of issues begin to
appear.
Large penetrations of PV generators might have
negative impacts on the system they are connected
to.
Pertinent Standards
IEEE Std. 1547-2003: Standard for Interconnecting Distributed Resources with Electric Power Systems
– IEEE Std. 1547.1-2005: Test Procedures for Interconnection Equipment – IEEE Std. 1547.2-2008: Application Guide for IEEE Std 1547
– IEEE Std. 1547.3-2007: Monitoring, Information Exchange, and Control – IEEE Std. 1547.4-2011: Design, Operation, and Integration Island
Systems
Under Development:
– IEEE Std. 1547.5: Power Sources Greater than 10MVA (Transmission
Grid)
– IEEE Std. 1547.6-2011: Secondary Networks
– IEEE Std. 1547.7: Distribution Impact Studies for Distributed Resource
Interconnection
– IEEE Std. 1547.8: Implementation Strategies for Expanded Use of
IEEE Standard 1547
Other Applicable Standards
Flicker
– IEEE Std. 1453-2004
– IEC Std. 61000-3-3, -3-5, -3-7, and -4-15
Voltage Regulation Requirements
– ANSI C84.1 – CAN3-C235
Harmonics
– IEEE Std. 519-1992
Islanding
– UL 1741Previous Work
Study Summary
Ropp (2008) • Reviews potential problems and utility concerns arising from high penetration levels of
photovoltaic in distribution systems
J. W. Smith (2011)
• Identifies limitations in the industry practice of integrating PV facility into the distribution grid, and further proffers an approach to improve PV interconnection studies
• Investigates impact of high PV penetration level on an existing network as a case study
Report IEA-PVPS
T10-06-2009
• Investigates voltage rises due to PV penetration and possible mitigation measures (Ota City demonstration project - Japan)
• Investigates reasons for power imbalances between phases of a solar settlement (PV settlement of “Schlierber” - Germany).
F. Katiraei (2007)
• Documents and reviews the results from several field experiments, measurements, and system studies performed at International Energy Agency Photovoltaic Power Systems projects in some IEA participating countries
• Covers power quality effects, voltage issues of high PV penetration and planning/design requirements to mitigate these effects
J. Widen (2009)
• Discusses limiting factors of distributed PV systems in Swedish energy system, using a simulation approach.
IEA Report published in 2007
Penetration levels less than 7%
Reviewed field experience in
– Japan (Gunma)
– Germany (Schlierberg)
– Australia (Olymp. Village)
– Netherlands (Nieuwland)
– Greek Islands
Reference:
F. Katiraei, K. Mauch, L. Dignard-Bailey, “Integration of Photovoltaic Power Systems in High-Penetration Clusters for Distribution
EPRI’s Work
Lots of case studies for lots of feeders
Relatively low PV penetration levels
Did not investigate imbalance in great detail
November 8-9, 2010 Reference:
J. Smith,
“PV Modeling for Distribution System Impact Assessment Using the OpenDSS,” Utility/Lab Workshop on PV Technology and Systems,
NREL’s (National Renewable Energy Laboratory) Work
Three criteria dictating
penetration limits
– Fault current sensitivity
– Reverse power
– Voltage/overload restrictions
– DER Penetration Limits Application
Our questions
– Is it really that simple?
– How about imbalance?
Effects of PV on Utility Operation
Potential issues and concerns associated with
increased PV generation in power systems. Effects on:
Overcurrent protection coordination
Voltage regulation
Reliability
Power losses
Detection of unintentional islanding
Overvoltage during islanding
Voltage change during DG tripping
What are the issues?
12
Category Issue OpenDSS PSCAD
EMTP-RV Reverse Power Flow Overcurrent protection get “confused” -> false trips, no trips X
Line regulators get “confused -> high/low voltage on DG side X
Voltage Fluctuation
Capacitor switching, LTC operation, and line VR operation
caused by cloud shading. X
Flicker caused by step voltage change during switching. X X Capacitor switching transients (synchronous closing,
pre-insertion impedance, point-on-wave) X X
Modification of Feeder Section Loading
Low/medium PV penetration -> PV offsets load thereby decreasing section loading
X High PV penetration -> PV may exceed base load, capacity
sufficient to distribute surplus power?
Increase in Power Losses PV changes loading (see row above). Impact on losses X
Fault Current PV increases fault current. Impact on relay protection. X X Unintentional Islanding Utility system reclosing into live island may damage
switchgear and loads. X X
Ground Fault Overvoltage Single-phase fault -> TOVs on unfaulted phase. X X
Harmonics Harmonics caused by PV inverter X
Dynamics
Effect of fast transients caused by cloud shading and system disturbances. Dynamic interaction of transients with other conventional and non-conventional control devices.
X X
Feeder Imbalance Imbalance caused by uneven distribution of PV causing
Load Profiles
Residential and Commercial Load Profiles
from
Manitoba Hydro
Southern California Edison
Hydro One
Manitoba Hydro: Commercial
Manitoba Hydro: Summary
Residential
Commercial
Unit Size Min Load (kW) Max Load (kW) Max. Down-Ramp (kW/h) Max. Up-Ramp (kW/h) Consumption (MWh) Under 1000 0.5 15.1 -6.8 8.4 38.4 1000-1500 3.2 10.9 -4.9 3.7 52.4 1500-2000 2.4 17.4 -7.6 6.2 67.4 2000-2500 2.1 29.2 -10.2 14.9 77.3 Over 2500 3.4 38.2 -22.4 27.2 94.6
Type Min Load (kW) Max Load (kW) Max. Down-Ramp (kW/h) Max. Up-Ramp (kW/h) Consumption (MWh) Drive-Through 64.6 523.0 -162.5 186.8 1,753.1 Restaurants 48.6 197.7 -44.2 51.2 776.7 Shopping Mall 1,658.3 7,392.6 -1,724.1 1,457.0 32,832.3 Generic Grocery 207.0 459.2 -81.5 106.7 2,957.9 Grocery Store 495.4 1,092.8 -209.8 169.8 6,502.6 Superstore 1,748.9 4,071.4 -787.5 629.9 24,779.1
Generation Profiles
PV Generation Profiles from
Manitoba Hydro (Winnipeg)
Southern California Edison (Long Beach)
Hydro One (Toronto)
BC Hydro (Vancouver)
PV Variation (Months)
Manitoba Hydro Hydro One
PV Variation (Hours and Seconds)
Net Zero Scenario
Annual consumption matches annual local PV
generation
Building does not need outside power IF perfect
Financial Net Zero Scenario
Annual consumption cost matches annual cost of
the electricity generated by a solar PV system
Building does not need outside power IF perfect
storage available
Shingles Scenario
Thin-film photovoltaic shingles produce between
50 and 200 watts
A roof of an average household is assumed to fit
Feeder Systems
Initial simulation on IEEE 34-bus test feeder
More detailed simulation on modified EPRI
Test circuit
– System Voltage: 12.47 kV
– Number of Customers: 1379
– Service XFMR kVA: 16310
– Total feeder kVAr: 1950
Feeder Systems (continued)
Load Distribution
Customer load profiles were integrated into the test feeder
by substituting the original loads
To provide reasonable comparison between the three
resulting systems, the total loading of the phases was kept
constant
Number of customers connected to a specific service
transformer resulted from the respective customer’s
maximum annual demand
Load Distribution – Hydro One
Load profiles Distribution
Phase Average Load (kW)
Eastern Connection Central Connection Western Connection
A 13.76 10.88 10.95
B 10.90 12.61 13.61
C 12.98 10.96 10.86
Net Zero– Hydro One
Scaling factors
Phase Average PVNetZero (kW)
Eastern Connection Central Connection Western Connection
Financial Net Zero– Hydro One
Scaling factors
Phase Average PVFinancial (kW)
Eastern Connection Central Connection Western Connection
A 5.01 3.93 3.96
B 3.94 4.65 4.93
C 5.00 4.22 4.13
Shingles – Manitoba Hydro
Scaling factors
Average kW per customer
Phase Average PVShingles (kW)
Eastern Connection Central Connection Western Connection
Cases - Daily
Case # Description PV Profile
Case Phase with PV Scenario Season
1 A, B, C 100% Consumption Net Zero Spring
2 B 100% Consumption Net Zero Spring
3 A, B, C Shingles (MH & SCE) Spring
Financial Net Zero (HO) Spring
4 A, B, C 25% Consumption Net Zero Spring
5 A, B, C 50% Consumption Net Zero Spring
6 A, B, C 75% Consumption Net Zero Spring
7 A, B 100% Consumption Net Zero Spring
8 A, C 100% Consumption Net Zero Spring
9 B, C 100% Consumption Net Zero Spring
10 A, B, C 100% Consumption Net Zero Fall
11 A, B, C 100% Consumption Net Zero Summer
Cases – Daily (continued)
Seasonal simulation cases
Used parameters – Installed PV Capacity in kW
Location Spring Summer Fall Winter
Manitoba Hydro Mar. 15 Jun. 7 Sep. 14 Feb. 5
SCE Apr. 4 Jul. 4 Sep. 19 Feb. 13
Hydro One May 1 Jun. 4 Sep. 28 Feb. 19
Location NetZero (kW) Financial (kW) Shingles (kW)
A B C A B C A B C
Manitoba Hydro 5,874 4,885 6,622 -- -- -- 321 201 545
SCE 6,072 7,061 4,695 -- -- -- 2,727 248 3,276
Hydro One 8,920 9,882 9,354 843 934 888 -- --
Case 1: Hydro One - Primary
Case 1: Hydro One - Primary
Case 1: Hydro One - Primary
Voltage (p.u.) Eastern Connection
Voltage (p.u.) Central Connection
Voltage (p.u.) Western Connection
Phase No PV With PV
Max Min Diff Max Min Diff
A 1.036 1.029 0.008 1.044 1.023 0.020
B 1.037 1.029 0.008 1.043 1.017 0.026
C 1.034 1.021 0.013 1.039 1.015 0.023
Phase No PV With PV
Max Min Diff Max Min Diff
A 1.036 1.031 0.005 1.046 1.023 0.023
B 1.037 1.027 0.010 1.040 1.017 0.023
C 1.034 1.029 0.005 1.019 1.007 0.012
Phase No PV With PV
Max Min Diff Max Min Diff
Case 1: Hydro One – Secondary
Snapshot during hour with highest solar activity
Case 1: Hydro One – Secondary
Voltage (p.u.) Eastern Connection
Voltage (p.u.) Central Connection
Voltage (p.u.) Western Connection
Phase No PV With PV
Max Min Diff Max Min Diff
A 1.032 1.018 0.014 1.075 1.035 0.039
B 1.032 1.018 0.013 1.078 1.028 0.050
C 1.024 1.007 0.016 1.080 1.033 0.046
Phase No PV With PV
Max Min Diff Max Min Diff
A 1.032 1.023 0.010 1.069 1.036 0.033
B 1.032 1.009 0.023 1.112 1.028 0.084
C 1.028 1.017 0.011 1.052 1.014 0.038
Phase No PV With PV
Max Min Diff Max Min Diff
A 1.032 1.020 0.012 1.083 1.036 0.047
B 1.032 1.017 0.015 1.081 1.028 0.053
Cases - Annually
PV penetration – Net Zero
Simulation duration – 8760 hours
The obtained results provide an estimate over the
number of times the feeder voltage cycles above
1.05 pu and below 0.95 pu
Annually: Hydro One - Primary
Annually: Hydro One
Primary
Secondary
Connection # of Buses (All Phases)
Cycles above 1.05 Cycles below 0.95
Eastern 177 10466 1
Central 203 23692 2
Western 281 25930 2
Connection # of Buses (All Phases)
Cycles above 1.05 Cycles below 0.95
Eastern 246 0 17
Central 126 0 2
Western 267 0 269
Cases – Unsymmetrical Penetration
Simplified system
Adjusted parameters:
Transformer connection (i.e. D-Y, D-D, Y-D, and Y-Y)
Unsymmetrical Penetration
46 Scenario Line Length (km) Imbalance Factor Phase A Load (kW) Phase B Load (kW) Phase CLoad (kW) Impact Evaluated 1 10 2 341.6 170.8 170.8
Transformer Connection 2 1 4 683.2 170.8 170.8
3 1 2 341.6 170.8 170.8 4 5 2 341.6 170.8 170.8
Line length for positive imbalance loading factor 5 10 2 341.6 170.8 170.8
6 20 2 341.6 170.8 170.8 7 5 -2 -341.6 170.8 170.8
Line length for negative imbalance loading factor 8 10 -2 -341.6 170.8 170.8
9 20 -2 -341.6 170.8 170.8
10 1 2 341.6 170.8 170.8 Load imbalance severity for positive imbalance loading factor
11 1 4 683.2 170.8 170.8 12 1 8 1,366.4 170.8 170.8
13 1 -2 -341.6 170.8 170.8 Load imbalance severity for negative imbalance loading factor
14 1 -4 -683.2 170.8 170.8 15 1 -8 -1,366.4 170.8 170.8
Line Length
Positive imbalance factor
Negative imbalance factor
Load Imbalance Severity
Positive imbalance factor
Cases – Secondary Network
1. No PV
2. With PV – no mitigations
3. With PV – System meets IEEE Std. 1547 (tripping if phase voltage deviates from permitted range)
4. With PV – System meets IEEE Std. 1547 (controlled dump loads to consume excessive power from PV)
PV1 PV2 PV3 Load3 Load2 Load1 Z1 Z2 Z3 V1 V2 V3 50
1. No PV
Cases – Secondary Network
2. With PV – no mitigationsCases – Secondary Network
3. With PV – System meets IEEE Std. 1547 (tripping if phase voltage deviates from permitted range)
Cases – Secondary Network
4. With PV – System meets IEEE Std. 1547 (controlled dump loads to consume excessive power from PV)
Project Summary
– Objectives: Provide a technically sound method of aggregating PV impacts on distribution feeder voltage control. Develop quantitative measures of the voltage control impacts from a variable DG source
– Builds on the UWIG DG Evaluation Toolbox – Completed Tasks
• Literature Search
• Flicker Meter Implementation in OpenDSS
• Feeder Model Reduction CYME OpenDSS – Tasks to Do
• New Screener and PV Profile Aggregation Using Wavelets on Web Server
Solar Power Variability Impacts
Source: LBLN-2855E
Literature Search
– Little Available on Solar Variability – Background from Wind Variability – Existing Solar Results
• Focus on Ramp Rates for Transmission • Variability Can be Comparable to Wind • Small Separation More Correlation • Small Time Windows Less Correlation
– Selected Lave’s Wavelet Method for Use on Distribution Systems
Conclusion
No grid today is ready for 100% penetration of PV
Significant impact of the conductor type on coupling effects during imbalanced phase loading
Imbalance can be much greater than expected both from coupling impacts and changes in actual load at the location of the installation
Use of three-phase voltage regulators that do not allow for
controlling the voltage on each phase individually, and three-phase tap changers will be an issue in installation of distributed generation
Tap changers and other voltage regulating equipment will need more frequent maintenance
Conclusion
Voltage rises are not uniform and in many cases the voltage at the substation maybe well within limits while at other locations along the feeder, voltage limits may be violated during PV peak production.
Power quality issues start at low penetration levels and are greatly influenced by the quality and size of the inverters used to tie the system to the grid
With tight clustering and a poorly designed (from an acceptance of distributed generation point of view) circuit can see impacts at less than 1 percent penetration.
Recommendations
Suggestions for amendments to current interconnection standards:
– Randomization for the wait period for restart of a unit when it has
been disconnected
– Sensing significant voltage drop that would indicate that the area has
been disconnected from the main grid
– Allowing for remote disconnect and connect
– Allowing operating parameters to be programmed into the unit
– Providing a direct DC tap off the unit to power local DC based
equipment
– Setting up inverters to create VARs on demand
– Limiting the size of inverters
Mitigation Options
Options for mitigation in today’s regulatory and standards
environment can provide the ability to safety increased the level of distributed generation installed:
– Disconnect the DG and pay the owner for the lost potential generation
– Placement of voltage regulators
– Use of phase balancing equipment
Potential Future Phases
Future phases of this project will:
1. extend simulation runs described in the current report to include more realistic PV scenarios, which would:
• account for high-resolution temporal variation and spatial variation of PV,
• use large variety of measured load curves rather than few aggregated averaged ones,
• estimate additional distribution equipment maintenance requirements due to high PV penetration,
• investigate harmonics and other PQ problems due to increased power electronics deployment,
• look at the detailed impacts of PV on equipment installed in the grid, and
• investigate detailed needs for new equipment to be installed to support grid operations.
Potential Future Phases
Future phases of this project will:
2. study small wind as renewable energy source on distribution grid,
• completion of the modeling – both circuit and substation
• review of literature on small wind
• look at the impacts of small wind installations on the model circuit
• provide a report focused on small wind that covers the following
3. combine the PV and small wind models for various scenarios of Distributed Energy Resources (DER) penetration, and
4. extend DER scenarios to include storage and electric vehicle models
• Review of the impacts of storage on the distribution grid and substations
• Matrix of storage uses and characteristics of storage for each use