• No results found

EVP - Certification Guide

N/A
N/A
Protected

Academic year: 2021

Share "EVP - Certification Guide"

Copied!
202
0
0

Loading.... (view fulltext now)

Full text

(1)
(2)

Earned Value Professional (EVP)

Certification Study Guide

F

F

i

i

r

r

s

s

t

t

E

E

d

d

i

i

t

t

i

i

o

o

n

n

,

,

R

R

e

e

v

v

i

i

s

s

e

e

d

d

2

20

00

08

8

(3)

Earned Value Professional (EVP)

Certification Study Guide

First Edition, Revised

Copyright © 2008

By AACE International

209 Prairie Avenue, Suite 100

Morgantown, WV 26501-5934 USA

Phone : +1.304.2968444

Fax: +1.304.2915728

Email : [email protected]

Web : www.aacei.org

Printed in the United States of America

ISBN: 978-1-885517-69-6

(4)

A Special Publication

Of

AACE International – The Association for the Advancement of Cost Engineering

Earned Value Professional (EVP)

Certification Study Guide

First Edition, Revised

(5)

Acknowledgments

The 2007-2008 AACE International Education Board is grateful to the AACE International members who have assisted in the development of this EVP Certification Study Guide, including:

Chris A. Boyd CCE (Co-editor) Mark T. Chen, PE CCE Prof. John (Jeff) Hannon Harry Jarnagan,PE CCE

Dr. Sean Regan, PhD CCE CEP (Co-editor)

2007/2008 Education Board Members:

Harry Jarnagan, PE CCE (Chair) Mahendra (Pal) Bhatia

Chris A. Boyd, CCE Mark T. Chen, PE CCE

Audrey M. Clark, CCC John O. Evans, III PSP Clive Francis, CCC Prof. John (Jeff) Hannon Prof. Dr. Mark Hastak, PhD CCE Donald F. McDonald, Jr. PE CCE PSP

Dr. Sean Regan, PhD CCE CEP Barrett Richards, CCC PSP

Peter W. Griesmyer

The assistance and support of the AACE International Headquarters (HQ) staff members are also greatly appreciated:

James Baxter, Executive Director Marvin Gelhausen, Managing Editor Noah Kinderknecht, Graphic Designer Robin Donley, IT/IM/Graphics Specialist

Charla Miller, Staff Director-Education and Administration

Dr. Randy Rapp, D.Mgt PE CCE, Subject Matter Expert for Assoc. Board Support Sandra Willard, Administrator, Certification and Education

(6)

Contents

I. INTRODUCTION TO EVP CERTIFICATION STUDY GUIDE... 1

Origin of Earned Value ... 6

EVP Certification Examination Structure... 9

CHAPTER 1 – ORGANIZATION...9

1.1 Work Breakdown Structure ... 11

1.2 Organizational Breakdown Structure... 15

1.3 Work Authorization ... 19

1.4 Responsibility Assignment Matrix ... 23

CHAPTER 2 - PLANNING SCHEDULING AND BUDGETING ... 27

2.1 Critical Path Schedule ... 29

2.2 Milestones and Deliverables... 35

2.3 Performance Goals ... 41

2.4 Performance Management Baseline ... 45

2.5 Risk Assessment and Mitigation ... 49

2.6 Control Accounts... 53 2.7 Work Package ... 57 2.8 Planning Package ... 61 2.9 Cost Elements... 65 2.10 Contingency ... 69 2.11 Management Reserve ... 73 2.12 Undistributed Budget ... 77

2.13 Over-Target Budgets and Over–Target Schedule ... 81

2.14 Contracting... 85

2.15 Integrated Baseline Reviews ... 89

2.16 Earned Value Methods... 93

CHAPTER 3 - ACCOUNT CONSIDERATION ...99

3.1 System Identification ... 101

3.2 Direct Costs ... 105

3.3 Control Accounts... 109

3.4 Indirect Cost ... 113

3.5 Unit Costs ... 117

3.6 Performance Measurement Baseline Authorization ... 121

CHAPTER 4 - ANALYSIS AND MANAGEMENT REPORTS... 125

4.1 Critical Path Analysis... 127

4.2 Progress Reporting ... 131

4.3 Variance Reporting... 135

4.4 Customer Reporting and Submittals... 139

4.5 Earned Value Mitigation... 143

4.6 Analysis ... 147

4.7 Estimate-at-Completion and Estimate-to-Complete... 151

4.8 Subcontract Management ... 155

4.9 Retainage ... 159

CHAPTER 5 - REVISION AND DATA MAINTENANCE... 163

5.1 Change Control... 165

5.2 Reconciliation... 169

5.3 Document Control... 173

5.4 Performance Measurement Baseline Authorization ... 177

(7)
(8)

PREFACE

The AACE International Earned Value Professional Certification Study Guide is being developed to accomplish two purposes similar to that of the AACE International CCC/CCE Certification Study

Guide. First, it is intended to aid professionals wishing to achieve AACE International’s specialty

certification in Earned Value Management (EVM). Second, the intent of the Earned Value

Professional Certification Study Guide is to assemble and summarize various topics considered

essential for earned value professional (EVP) knowledge, as outlined in AACE International’s Recommended Practice 11R-88, Required Skills and Knowledge of Cost Engineering and included in the current edition of AACE International’s Skills and Knowledge of Cost Engineering.

We expect that the Earned Value Professional Certification Study Guide will be as popular and useful as the CCC/CCE Certification Study Guide. This publication will serve the needs of earned value management (EVM) professionals who prepare to take the AACE International EVP certification examination. This publication is organized in a concise and easy to follow format, and covers the major skills and knowledge used by an earned value management professional.

The information contained in this Earned Value Professional Certification Study Guide parallels the related topics of the Skills and Knowledge of Cost Engineering and the CCC/CCE Certification

Study Guide. These publications can be combined for a course of study in both cost engineering and

earned value management. The publications include sample problems related to the subject matter. Terms and phrases incorporated in the Earned Value Professional Certification Study Guide are generic to the profession and listed in AACE International’s Recommended Practice 10S-90 and the Glossary of Terms of this study guide. The terms and phrases used in industry and technical software may not always agree precisely with your understanding, therefore consult the EVP Glossary found in Appendix A.

The goal of the AACE International Education Board is to continually improve this publication, making it a living document that will be revised as needed to support the EVP exam while maintaining the recognized strengths described above. All are encouraged to offer comments and suggestions for improvements in future editions. Please forward comments to the Education Board at AACE International.

(9)
(10)

1

Introduction to EVP Certification Study Guide

This is a study guide for the Earned Value Professional (EVP) certification examination sponsored by AACE International, the Association for the Advancement of Cost Engineering.

The following systematic approach was used to develop this guide: 1. Review basic earned value (EV) concepts.

2. Establish the terminology used in EV in a way that is consistent with the EIA/ANSI-748-A standards and AACE International Cost Engineering Terminology (10S-90), which has been adopted by ANSI.

3. Review the EV process.

4. Review methods for monitoring a project by using EV.

5. Review methods of reporting, executing, and forecasting project performance using EV. 6. Ensure consistency with the Total Cost Management (TCM) Framework, as in Figure 1.

Figure 1: The outline structure of AACE International’s TCM Framework.

As shown in figure 1, EV comprises a critical part of the functional processes for project control. Earned value is a specific methodology that includes planning, measurement and assessment steps. While the TCM Framework process is not limited to EV methods, it is consistent with them. For example, the TCM process map for project performance measurement (Chapter 9) as shown in figure 2 includes general measurement steps that apply to EV.

Basic Processes of Total Cost Management

Functional Processes for Strategic Asset Management

Functional Processes for Project Control

Enabling Processes For Total Cost Management

The TCM Framework

1 Introduction

2 The TCM Process Maps 2.1 Basis

2.2 Total Cost Management 2.3 Strategic Asset Management 2.4 Project Control

3 Strategic Asset Planning 4 Project Implementation 5 Strategic Asset Performance

Measurement

6 Strategic Asset Performance Assessment

7 Project Control Planning

8 Project Control Plan Implementation 9 Project Performance Measurement 10 Project Performance Assessment

11 Enabling Processes

11.1 The Enterprise in Society 11.2 People and Performance Management

11.3 Information Management 11.4 Quality Management 11.5 Value Management

(11)

2

Figure 2: The TCM Process Map for Project Performance Measurement Overall learning objectives are:

• Understand the basis of EV within the TCM Framework process. • Know the evolution of earned value.

• Describe what is essential to plan and initiate an earned value system.

• Understand and be able to execute the measurement and tracking of earned value as a basis of project management. And,

• Provide the basis for AACE International EVP certification within the framework of figure 2.

Track Resources Plan for Progress and Performance Measurement Review Progress and Peformance Measures Initiate Progress and Performance Measurement Changes (10.3) Develop and Maintain Measurement Tools Project Implementation Basis (4.1) Project Control Plan and Control Accounts (8.1) Report Progress and Performance Information for Performance Assessment (10.1) Project Control Plan and Control Accounts (8.1) Project Cost Accounting Plans (9.1) Information for Cost Accounting (9.1) Status for Changes (10.3) Corrections to Measurement Basis Information for Enterprise Resource Planning (5.2) Measure Performance Measure Physical Progress

Work, Resource, and Process Performance

Status Schedule Historical Project Information (10.4) Historical Project Information (10.4)

(12)

3

These are the references providing the basis of knowledge outlined in this guide:

1. AACE International Recommended Practice (RP) 10S-90, Cost Engineering Terminology. (2007).

2. AACE International Recommended Practice (RP) 11R-88, Required Skills and Knowledge of

Cost Engineering. (2006).

3. AACE International Recommended Practice (RP) 14R-90, Responsibility and Required Skills for

a Planning and Scheduling Professional. (2006).

4. AACE International Recommended Practice (RP) 23R-02, Planning & Scheduling

Identification of Activities. (2007).

5. AACE International Recommended Practice (RP) 24R-03, Planning & Scheduling, Developing

Activity Logic. (2004).

6. AACE International Recommended Practice (RP) 52R-06, Time Impact Analysis--As Applied in Construction. (2006).

7. American National Standards Institute/Electronic Industries Alliance Standard (ANSI/EIA) 748-A-1998, Earned Value Management Systems.

8. Amos, S. (Ed.). Skills & Knowledge of Cost Engineering, 5th Edition. (See especially Section 4, Progress and Cost Control), (2004).

9. Bramble, B. and M. Callahan, Construction Delay Claims, 3rd

Edition, (2007).

10. Crawford, T. (Ed.). Professional Practice Guide (PPG) No. 4, Planning and Scheduling, 2nd

Edition, (2006).

11. Fleming, Q. and Koppelman, J. Earned Value Project Management, 3rd

Edition, (2005). 12. Glavinich, T. Construction Planning and Scheduling Manual, 2nd

Edition, (2004). 13. Haugan, G. Project Planning and Scheduling, (2001).

14. Hollman, J. (Ed.). Total Cost Management Framework: An Integrated Approach to Portfolio, Program, and Project Management, (2006).

15. Humphreys and Associates. Project Management Using Earned Value, (2002).

16. Kerzner, H. Project Management: A Systems Approach to Planning, Scheduling & Controlling, 9th

Edition, (2005).

17. Marshall, R. (Ed.). Professional Practice Guide (PPG) No. 5, Earned Value, 2nd

Edition, (2007).

18. National Defense Industrial Association (NDIA) Program Management Systems Committee (PMSC). Earned Value Management Systems Intent Guide. http://management.energy.gov/documents/NDIA_PMSC_EVMS_IntentGuide_Nov_2006.pdf 19. O’Brien, J. and Plotnick, F. CPM in Construction Management, 6th Edition (2005).

20. Pritchett, M. (Ed.). CCC/CCE Certification Study Guide, 3rd

Edition. (See especially Section 4, Progress and Cost Control.) (2006).

21. Wickwire, J., Driscoll, T., and Hurlbut, S. Construction Scheduling: Preparation, Liability and Claims, 2nd

Edition, (2007).

This EVP Certification Study Guide assumes a typical engineering, procurement, and construction (EPC) project as a basis for integrating the EV knowledge and skills that it contains.

This manual guides the student to learn the basic terminology and processes for the EPC earned value management process. However, an individual’s company or industry may dictate or emphasize other methods or means as part of the EVM process of a project or program implementation.

The study guide is organized according to figure 1, EVP scope of knowledge, which provides an overview of the EVP scope of knowledge that each EVP candidate will be tested on recommended examination preparation should include review of many of the references listed above. The candidate must also draw from their personal EVM experience.

(13)
(14)

5

Origin of Earned Value

The earned value management system, or EVMS, is not a new concept. In fact, according to Driessnack, it was derived from the factory floor in the late 1800’s. Planned, earned, and actual standards were the terminologies used then:

“The earned value concept came to us right off the factory floor, from the industrial engineers who were comparing their planned standards with the earned standards and the actual costs. We simply applied this same concept to our one-time only, non-recurring developmental tasks” (Driessnack, 1990).

In the 1950’s, “cost variance” was defined by industrial engineers as the difference between the actual costs expended as compared to the earned standards achieved. This is an early indication of the correct application of modern earned value analysis methods.

PERT/Cost, Late 1950s-Early 1960s

The earned value concept evolved over time in major phases. Much of the material below is taken from Quentin Fleming in his book, Earned Value Project Management, 2nd

Edition (Project Management Institute, 2000).

The scheduling methodologies that underlie today’s earned value systems derived from two types of schedule logic networks:

• Activity-on-node (AON) network. And, • Precedence diagram method (PDM) network.

The program evaluation and review technique (PERT) was developed by the US Navy in 1958 to manage the Polaris missile program. Its objective was to simulate the schedule risk of the missile R&D program work using a flow diagram technique that, in turn, lent itself readily to scheduling and network analysis. However, its complexity made it unpopular and limited its applicability as a tool for general scheduling. The scheduling methodology called critical path method (CPM) was developed at about the same time by a DuPont engineer using the activity-on-arrow (AOA) method for network development, and it became a more readily accepted basis for scheduling. While not identical, procedures for both techniques were similar and leveraged the computational capabilities provided by electronic computers.

According to Fleming, “Most of the networks today that are called PERT are actually precedence diagram method (PDM) networks, not true PERT networks.” The importance of PERT to earned value, however, lies in the implementation of the PERT/cost models in industry. With the implementation of PERT in 1962, eleven reporting formats were required, one of those being a “cost of work report,” which required the measurement and comparison of “value of work performed” versus the “actual costs.” This was a beginning of the modern earned value technique as a project management tool as we know it today.

Cost/Schedule Control Systems Criteria (C/SCSC): 1967 to 1996

The development of the C/SCSC system was led by the US Air Force, which endeavored to determine if contractors involved in the development of systems could do so while observing certain simple management criteria. According to Driessnack, an interview of an individual who was actually involved.

(15)

6

• Does the contractor break down the work into short span packages that can be budgeted, scheduled, and evaluated?

• Does the contractor have a system for accumulating costs?

• Does the contractor measure performance on these work packages? And,

• Does the contractor report status and variances to their own internal management?

When initially implemented, the US Department of Defense (DOD) imposed 35 criteria on any contractor desiring to perform work on cost reimbursable or cost incentive contracts over a certain funding threshold. This system was adopted by many governmental agencies.

According to Fleming, although generally beneficial in its ultimate effect, the C/SCSC system had mixed results; much valuable project data was gained, but the system grew ever more bureaucratic and difficult for contractors to implement and maintain on projects. Many of the more detailed aspects of system implementation were resisted by contractors. In fact, it was not adopted by private industry for a number of reasons. Much of the rejection of the C/SCSC system was based on the need to understand a new set of terminologies that were not intuitive to many project managers, such as using the term budgeted cost of work scheduled (BCWS) instead of the word “planned”; budget cost of work performed (BCWP) instead of “earned;” and actual cost of work performed (ACWP) instead of “spent.” Additional frustration was experienced by practitioners in the field through the adoption of other confusing terms within the system that, they felt, served to only cloud the simpler project issue of cost overruns.

EVMS (ANSI/EIA 748): 1996 to Present;

Feedback from practitioners and the refusal of private industry to adopt the C/SCSC system led the US government to revise it and develop a simpler system that would be accepted by the private sector. The National Defense Industrial Association (NDIA) led this effort, reducing the number of system performance criteria (from 35 to 32), and simplifying the terms for various types of data (moving away from the more cumbersome phrases of BCWS, BCWP, and ACWP). The result of NDIA’s work was called the “earned value management system” (EVMS), which was adopted by the Department of Defense in December 1996, and incorporated into DOD Instruction 5000.2R. Wider application of this system outside the realm of the DOD was the goal of its 32 criteria being reflected in American National Standard Institute/Electronic Industry Association (ANSI/EIA) 748 Guide that was issued in 1998.

With a return to a simpler, more intuitive approach as represented by EVMS, private industry adoption of earned value management techniques grew in recognition of it being a best-practice methodology. The passage of the Sarbanes-Oxley (SOX) Act in 2002, which intended to more effectively detect fraud in corporate operations, has further strengthened the standing of the EV method. It is a robust means to ensure that project execution proceeds in a transparent way and in accordance with SOX requirements.

(16)

7

EVP Certification Examination Structure

Introduction

Certification as an Earned Value Professional (EVP) requires passage of a written examination in addition to other experience criteria as set forth by AACE International. This study guide provides direction for preparing to meet these requirements.

Examination Basis

The purpose of any professional certification or licensing program is to provide a mechanism to formally and objectively evaluate and publicly recognize the capabilities of an individual in a defined skill area. Certification as an Earned Value Professional (EVP) recognizes certificate holders who have demonstrated their expertise in earned value management (EVM). Specifically, EVM includes the following.

• critical path method (CPM) scheduling; • performance measurement techniques; and, • reporting and analysis.

These EV components provide the basis for the AACE International certification examination. The examination tests for proficiency across these areas.

To define earned value more specifically in terms of expected skills and knowledge, AACE International has published AACE International Recommended Practices- Project Controls. Earned value is a dynamic management system affected by advances in philosophies, methodologies, and technology. A professional project controls engineer specializing in earned value measurement is expected to keep abreast of these advances and demonstrate this awareness in the examination. In summary, the definition of EVM and the Recommended Practice 11R-88, Required Skills and

Knowledge of a Cost Engineer (EV portion) form the basic scope for the EVP certification

examination. In recognition of this, the examination addresses the following. • minimum knowledge covered by the basic skills documents; and • advanced knowledge based upon earned value experience. Examination Schedule

At each Annual Meeting, AACE International offers a general sitting for all of its certification examinations. AACE International also offers examinations on demand, along with various local sections hosting examinations. There are opportunities throughout the year to sit for the examination at a time and location most convenient for the certification applicant.

Examination Format

The examination consists of four parts (105 minutes each, in one day):

• Part I tests basic EVM knowledge. It consists of multiple-choice questions concerning the basics of earned value measurement.

• Part II tests EV applications. It consists of multiple- choice questions involving earned value scenarios.

• Part III is a practical exercise. This part entails answering a series of multiple-choice questions concerning various aspects of a single earned value measurement problem.

(17)

8

• Part IV is a practical communications exercise. It requires the candidate to draft a one-page memorandum to simulate reporting on an earned value issue of a project, explaining their analysis and proposing a solution.

The examination is closed book with simple, non-programmable calculators allowed. The examination is not based upon use or knowledge of specific software, but rather embodies the knowledge and experience of an earned value practitioner using such tools. All materials provided during the examination, including work paper, are required to be turned in upon completion of each examination phase.

• Recognizing that there are many industries and fields within the profession – engineering, construction, manufacturing, process facilities, mining, utilities, transportation, aerospace, environment and government – the applicant can expect some questions from any of those settings. However, as a practical matter, no one can be expected to be conversant in all areas, and the exam is designed to take this into account through its multiple option format and extensive use of questions of general applicability.

(18)

9

Chapter 1.0 - Organization

Introduction

Organizing the work is the initial task for planning any project or task. Organization entails defining the project or task scope of work and the groups or individuals that will be responsible for the various execution phases of any task or project. The organizational elements of a project management office (PMO) consist, at a minimum the work breakdown structure (WBS), organizational breakdown structure (OBS), work authorization (WA), and a responsibility assignment matrix (RAM).

The project organization structure (POS) which is comprised of the above elements reflects the company’s organization as integrated with a particular PMO to support a specific project. Many organizations operate as a matrix organization and others may use an integrated product team approach. A PMO is usually established to be responsible for the business and technical management of the project.

Terms to Know

Project management office (PMO); Work breakdown structure (WBS); Organization breakdown structure (OBS); Work authorization (WA);

Responsibility assignment matrix (RAM); and, Project organization structure (POS)

Key Points for Review

Organization is the key in developing a system for execution and management of a project supported by an earned value management system.

Figure 1.0: Body of Knowledge Diagram

1.0 Organization

(19)
(20)

11

Section 1.1 Work Breakdown Structure (WBS)

Introduction

The work breakdown structure (WBS) is the fundamental definition of the program. The WBS provides the framework by which all project effort is organized so it can be scheduled, budgeted, authorized, measured, and reported. The WBS is an organized, hierarchical decomposition of project scope that serves as the backbone for the planning and management of the project.

The WBS is developed by decomposing the program into its various deliverables and services. Each deliverable and service is continually decomposed until all tasks necessary to complete the project are identified and assigned to a specific party or team, and all resources essential to accomplish the tasks are assigned in detail to the tasks. The deliverable-orientation of the structure allows for effort to be estimated for the identified tasking, the effort to be translated into an estimated cost, and the estimated costs to be rolled-up to sub-deliverables of the program. This, in turn, allows for the delicate balancing of scope to budget that is crucial for a successful earned value management program.

The lowest level of each branch of the WBS is defined as a work package. The work package is assigned to an individual resource or an integrated team of resources. The work packages identified by the WBS are used to produce the program schedule, by logically linking together work packages as the work is planned to be accomplished over time. The work package level is also where the data points used to perform earned value analysis, i.e., the budget cost of work scheduled (BCWS), budget cost of work performed (BCWP), and actual cost of work performed (ACWP), are collected and rolled-up the structure of the WBS for problem identification and management control decision making.

The grouping of work packages that make up a sub-deliverable (WBS) and are assigned to resources from a particular department within the organization (OBS) responsible for the program or portion of the program is defined as a control account. A management-level resource is assigned authority of the control account and is defined as the control account manager (CAM). The CAM accepts the responsibility of collecting the earned value data and is accountable for the accomplishment of the work packages

The WBS dictionary provides a cross reference between WBS elements and the corresponding project statement of work, mission statement, or other customer documents that define the scope of work.

The WBS should be designed with the intent that each WBS level may be used to report information of a similar level of detail consistently across the WBS.

The WBS should be numbered such that each element is associated with a unique identifier. Terms to Know

• Work breakdown structure (WBS); • Statement of work (SOW);

• WBS dictionary; • WBS number; • WBS level; • Work package;

(21)

12

• Control account; and,

• Control account manager (CAM) Key Points for Review

1. Know why the WBS should never over- or under-represent the full project scope.

2. Know how the WBS graphically explains the project deliverables that must be completed. 3. Know the relationship between the WBS and SOW.

(22)

13

Sample Questions for Section 1.1:

1. Which of the following is not a component of the work breakdown structure?

A. Scope

B. Deliverables

C. Numerical designator

D. RAM

2. The WBS numerical designator 01.02.02.01.02.06 Low Level Waste Disposition represents what reporting level of the WBS hierarchy?

A. 4 B. 5 C. 6 D. 7

3. Which of the following statements about the WBS is not true? A. A project consists of the sum of all the WBS elements.

B. Any element that is not contained in the WBS is not part of the project.

C. Any work that cannot be identified in the WBS requires an approved change order. D. Required WBS omissions require a notice to proceed (NTP).

4. A WBS:

A. Is derived from the project schedule network logic diagram. B. Is derived from the conceptual cost estimate for the project. C. Always has five hierarchical levels.

(23)

14

Solutions to Sample Questions for Section 1.1:

1. D. The responsibility assignment matrix (RAM) combines the WBS and organizational breakdown structure (OBS) to identify who is responsible for what CA.

2. C. Six levels, as identified by the break, which is normally a period or dash.

3. D. The NTP is related to the project as an entity and not to individual elements of the WBS.

4. D. The WBS divides the project into manageable scopes of work, which are assigned to responsible parties with necessary management authority.

(24)

15

Section 1.2 Organizational Breakdown Structure (OBS)

Introduction

The organizational breakdown structure (OBS) or the project organization structure as it is called by some companies reflects the company’s organization as integrated with a particular project management office to support a specific project. The OBS is usually illustrated by a graphical or tabular listing of the control account managers (CAMs), structured in a hierarchical manner. The OBS provides flexibility in reporting the internal organization of a company.

The OBS is a direct representation of the hierarchy of the organization established to provide the necessary resources to plan and perform the required work. The procedures in this document provide guidelines for establishing an OBS for contracts requiring a certified EVMS. The OBS helps management establish the most efficient organization by taking into account the availability and capability of management and technical staff—including subcontractors—to achieve the project objectives. The OBS is an integral part of the formation of the responsibility assignment matrix (RAM) and ultimately determines who has responsibility for control accounts.

There are three main types of organizational structures: functional, matrix, and project:

• The functional organization structure is one of indians and chiefs. Each functional group has a manager over the group’s function such as engineering services, and experienced individuals reside in the functional group performing tasks assigned to the group.

• The matrix organization is one in which functional professionals are grouped together to support a specific project, while simultaneously remaining a member of their functional organization. The “matrixed” individual receives their assignments from the person whom they are supporting. However, the administrative needs of the matrixed individual remain the responsibility of the functional manager while on assignment to a ”matrixed” project.

• The project organization is one in which a project is authorized to proceed, given a budget to allocate expenditures, and has a definite start and finish date. The project organization has an appointed manager or task leader and develops an organizational structure from which they draw specific resources in order to execute the project. The individuals assigned to the project support the project execution until released by the manager, when they then return to their respective functional organization for re-assignment or continue their functional management duties.

Terms to Know

• Organizational breakdown structure (OBS); • Functional organization;

• Matrix organization; and • Project organization. Key Points for Review

1. Explain the differences between the OBS and WBS. 2. State the purpose of the OBS.

(25)
(26)

17

Sample Questions for Section 1.2:

1. Which of the following is not considered an element of the OBS for EV?

A. Functional organization

B. Matrix organization

C. Project organization

D. Labor counsel organization

2. Which organizational manager has administrative responsibility of an individual assigned to a project?

A. Functional manager

B. Project manager

C. Business manager

D. Human resource manager

3. Which organizational manager is responsible for the job specific training of an individual assigned to a matrix organization?

A. Functional manager

B. Project manager

C. Engineering manager

D. Site training manager

4. Which of the following statements does not reflect the use of the organization concepts when developing a project execution and management plan?

A. The organizational structure becomes an element of the planning grid, usually represented on the Y-axis of the grid.

B. The WBS becomes an element of the planning grid, usually represented on the X-axis of the grid.

C. The RAM becomes an element of the planning grid, usually represented on the Z-axis of the grid.

D. The functional organization annual performance evaluation numerical ranking value becomes an element of the planning grid based on the value represented by the intersection of the other elements of the grid.

(27)

18

Solutions to Sample Problems for Section 1.2:

1. D. The labor counsel organization relates to project management, not EV.

2. A. The functional manager is responsible for the personnel that are assigned to the team. This is demonstrated by the personnel who manage the staff which work under a CAM’s authority.

3. B. The project manager is responsible for the staff working on their project and must see they are trained to function in the assigned positions. They work under a CAM’s budget authority but are managed by function and project.

4. D. Functional organization annual performance evaluation relates to staffing and not execution.

(28)

19

Section 1.3 – Work Authorization

Introduction

Work authorization is a formal process related to various levels of the organization. Each level of authorization is agreed to by the parties involved so that there is not any question as to what is required to authorize work. The work authorization approvals normally involve two types; outside or customer-client authorization and internal authorization within the organization performing the work. The customer-client authorization is applicable to items such as the basic contract, contract change notices, and supplemental agreements. The internal authorization will vary based on individual company policies and procedures starting at the highest level of management down to the control account manager (CAM). The sublevel managers have an established level of authorization based on company policy and can delegate their authority to subordinate mangers as they deem appropriate. The above organizational process flow of work authorization is captured in the work authorization document (WAD). It is the abstract by which governments, companies, and organizations provide the processes, directions, policies, procedures, and signature authority to commence work.

At the organization or project level where the work scope is executed, the WAD is developed for authorizing work to each CAM. It includes the scope of work to be performed and the associated budget and schedule. The WAD is a contract between the PM and the CAM and carries the task definition, its start and completion dates, the total task budget, defined delivery milestones, and the WBS element that will be used to summarize costs for the task. A WAD, completed and signed by the authorizing agent for a specified project scope is the formal authorization document issued to perform the stated work.

There are three types of authority encountered in the delivery of construction projects, and the WAD shall differentiate each type:

1. Actual Authority: This is authority from the project owner which is granted (expressly stated) in the contract to the owner’s representatives, as possibly to designers, contracting officers, etc.

2. Implied Authority: This is authority which is not expressly communicated (implicit) from the owner, but is necessary for the designated owner’s representative(s) to exercise their granted actual authority. An example would be when a contracting officer has the actual authority to demand performance and payment bonds from the prime contractor. Courts have determined that in such situations, the representative implicitly has the authority to demand the same from subcontractors.

3. Apparent Authority: Refers to authority which is neither expressly stated in the contract nor implied by actual authority. It describes authority which is ‘perceived’ to be held by the owner’s representative by other parties to the contract (i.e., the contractor, subcontractors, vendors, etc.). An example would be when a contract states that an engineer has the authority to solicit change order requests (CORs). The contractor may therefore perceive that the engineer also has the authority to accept or reject the COR, when contractually the engineer does not.

Terms to Know

• Change order request (COR);

• Work authorization document (WAD); and, • Project management office (PMO).

(29)

20

Key Points for Review

1. What is the purpose of work authorizations? 2. When is work authorized?

3. How do work authorizations relate to the execution of work?

The following organizational chart pertains to the sample questions of section 1.3:

CEO / Manager of Projects

Project

Manager Manager Engineer Business Manager

Project #1 Engineering Discipline

Department Managers Procurement Contracts Project Controls Manager Human Resources

Owner-Client

(30)

21

Sample Questions for Section 1.3:

1. A multi-national construction company has bid on a request for proposal (RFP) and won the contract. Of the following list of managers, which one has the authority to award the contract in normal circumstances?

A. Client project controls manager B. Client procurement manager C. Client contracting manager D. Client general counsel.

2. A multi-national construction company has won a contract and received the notice to proceed (NTP) by the client. The engineering design phase has been authorized, and the project manager has directed the design to commence. Which one of the following managers has the authority to assign specific work to the engineering personnel on the project?

A. Project manager.

B. Contracting manager

C. Engineering manager

D. Client representative

3. During the execution of the contract scope the contractor encounters a “soft-spot” during the excavation and has to bring in extra fill to bring the elevations up to grade. This situation was not shown on the excavation drawing or in the soil boring report. The contractor prepares a contract change order for the additional scope. Which one of the following managers has the authority to approve the change notice?

A. Client project manager B. Client contracting manager C. Contractor engineering manager D. Contractor client representative

4. The Work Authorization Document (WAD) is the “contract” of the scope, plan, and schedule between the ________ and the ______ for the project.

A. Client and the project manager

B. Project manager and the control account manager C. Project manager and the functional manager D. Client and the control account manager (CAM)

(31)

22

Solutions to Problems for Section 1.3:

1. C. Only the contracting officer or contracts manager has such authority.

2. C. The functional manager is responsible for assigning the scope of work his personnel shall work on. The CAM is responsible for the budget and maybe at a lower level, pending the RAM and scope of work.

3. B. Only the client contracting officer or contracts manager can approve changes and assign work.

4. B. The project manager is responsible for issuing the WAD, and the CAM is responsible for implementing the WAD.

(32)

23

Section 1.4 Responsibility Assignment Matrix (RAM)

Introduction

The responsibility assignment matrix is a resource matrix of the organizational breakdown structure with the WBS which identifies the resources associated with the control account levels established for the project and cross references these levels to the appropriate WBS elements. The control account is important because it is the point at which technical performance, schedules, and costs are integrated. The RAM includes the functional organization and the named CAM.

The RAM is a direct result of the intersection between the WBS and the OBS and permits the measurement of cost and schedule performance by elements of both structures. This intersection results in the designation of a focal point for management control—the control account.

A potential control account exists where a single OBS element and a single WBS element intersect. It is defined as the point where a functional organization has responsibility for work designated to a WBS element. The control account is also where work is authorized, actual costs are collected, and budget and performance are summarized. The RAM will be updated as required based on changes in the CAM, WBS, OBS, and scope of work.

The RAM is expressed as a graphic or tabular listing of the intersection of the WBS and the responsible organizations (OBS) at the control account level.

Terms to Know

• Control account manager (CAM); • Work breakdown structure (WBS);

• Organizational breakdown structure (OBS); • Project manager (PM); and,

• Control account. Key Points for Review

1. Understand the relationship between the OBS and WBS. 2. Understand the purpose of the RAM.

(33)
(34)

25

Sample Questions for Section !.4:

1. What is the name of the responsible individual or position where the WBS, OBS, and responsibility matrix intersect?

A. Project manager

B. Project engineer

C. Control account manager (CAM)

D. Accounting manager

2. Which of the following is not part of the RAM relationship? A. Work breakdown structure (WBS)

B. Organizational breakdown structure (OBS) C. Schedule of values

D. Control account

3. Which of the following is not addressed by the control account relationship in the RAM?

A. Technical performance

B. Schedule C. Cost D. Pricing

(35)

26

Solutions to Problems for Section 1.4:

1. C. The CAM is responsible where the WBS, OBS, and responsibility matrix intersect? 2. C. A schedule of values is not part of the WBS, OBS, RAM, or control account. It is a

basis of cost control.

(36)

27

Chapter 2.0 Planning, Scheduling, and Budgeting

Introduction

In developing a plan for a program or project there are many considerations and constraints that require identification and evaluation. Among the elements are; resources, value engineering, stakeholders, and project variable requirements necessary to understand and implement the planning process.

An important component of the baseline is the completion of a network schedule. The schedule is used to show how the work will be accomplished and contains the lists of activities to complete the physical products, milestones, and technical performance goals. A critical path schedule is simply a network schedule that depicts the activities, milestones, and the logic of how the work will be accomplished. The critical path is the network sequence of work to be done, which will take the longest time to complete the project.

2.0 Planning, Scheduling, and Budgeting

2.1 Critical Path Method Schedule 2.4 Cost Elements 2.3 Performance Measurement 2.5 Work Package 2.2 Milestones & Deliverables 2.6 Control Account / Planning Package 2.7 Budget Baseline 2.8 Overhead Pools

2.9 Contingency, Management Reserve, Undistributed Budget

2.10 Integrated Baseline Reviews

(37)
(38)

29

Section 2.1 Critical Path Schedule Introduction

An important component of the baseline is the completion of a network schedule. The schedule is used to show how the work will be accomplished and contains the lists of activities to complete the physical products, major project events (milestones), and technical performance goals. A critical path method (CPM) schedule is simply a network schedule that depicts the activities, milestones, and the logic of how the work will be accomplished. In this regard, the CPM schedule is an important mathematical model of the work needed to complete a given project. The critical path is that series of individual activities that represents the “string” or strings of logically successive activities, which will take the longest time to complete. The critical path then defines the quickest possible project completion date.

The student must understand CPM scheduling. Understanding CPM includes the components of CPM schedules; how they act both as schedule building-blocks and as drivers of CPM schedule mathematics; how the components are developed to arrive at an overall schedule model; and the importance and techniques of schedule updating.

Terms to Know ƒ Activity;

ƒ Activity description;

ƒ Arrow diagramming method (ADM); ƒ Backward pass;

ƒ Bar chart; ƒ Calendar unit; ƒ Constraint; ƒ Critical path;

ƒ Critical path method (CPM;) ƒ Duration;

ƒ Early finish date (EF); ƒ Early start date (ES); ƒ Forward pass; ƒ Free float (FF); ƒ Gantt chart;

ƒ Late finish date (LF); ƒ Late start date (LS); ƒ Logic;

ƒ Milestone; ƒ Network;

ƒ Original duration;

ƒ Program evaluation and review technique (PERT); ƒ Planning;

ƒ Precedence diagramming method (PDM); ƒ Schedule update;

ƒ Scheduling; ƒ Status;

ƒ Target schedule; ƒ Total float (TF);

ƒ Work breakdown structure (WBS); and, ƒ Work Unit

(39)

30

Key Points for Review

1. Define what a bar chart (“Gantt Chart”) is, and explain the steps in preparing one. 2. Define PERT, and summarize how such a schedule is developed.

3. Define CPM and common schedule components.

4. Define, compare, and contrast the ADM and PDM approaches to scheduling and how such schedules are developed.

5. Describe the different types of logical relationships that can interrelate the work flow between activities (finish-to-start; finish-to-finish; start-to-start; start-to-finish).

6. Explain coding techniques that can be used in schedules.

7. Define the purpose of forward and backward passes, and explain the calculations used to complete the passes.

8. Define FF and TF.

9. Define the critical path, and how it is identified in the schedule.

10. Define constraints, and discuss how constraints can be effectively used and misused in schedules.

11. Discuss schedule updating and the reasons for it; discuss time intervals for updating schedules; and discuss procedures that should be used in updating schedules.

(40)
(41)

32

Sample Questions for Section 2.1:

1.

When constructing a PERT schedule, each schedule activity is assigned three durations. These durations represent:

A.

Total float, free float, and lag.

B.

Original duration, Remaining duration, and percent complete.

C.

There should not be three durations; each schedule activity should have only one duration when doing a PERT schedule.

D.

Optimistic duration, pessimistic duration, and most likely duration.

2.

You have performed a schedule update. You have reviewed the update, and all the schedule mechanics appear correct. The TF value now shown on the “Project Complete” milestone is

negative 15 workdays. What does this tell you?

A.

That the project can be delayed by 15 days and still meet the required completion date.

B.

That the project is now forecasted to be completed 15 workdays behind the required completion date.

C.

That there must be an error. There is no such thing as negative float values in CPM scheduling.

D.

That the percent of critical path activities physically complete is greater than what is scheduled to be complete at this point for those specific activities.

E.

That the project is progressing satisfactorily and no adjustments to the to-go work plan is required.

Questions 3 through 5 concern the CPM network schedule shown below. The time unit is workdays:

ES EF LS LF OD TF AD ES = Early Start EF = Early Finish OD = Original Duration AD = Activity Description LS = Late Start LF = Late Finish TF = Total Float 2 B 3 C 4 A 2 D 5 E 7 F G 1 Proj. Start Proj. Compl. 3 ES EF LS LF OD TF AD ES EF LS LF OD TF AD ES = Early Start EF = Early Finish OD = Original Duration AD = Activity Description LS = Late Start LF = Late Finish TF = Total Float 2 B 3 C 4 A 2 D 5 E 7 F G 2 B 2 B 3 C 3 C 4 A 4 A 2 D 2 D 5 E 5 E 7 F 7 F G G 1 Proj. Start Proj. Compl. 3

(42)

33

3.

What is the total duration of this project?

4.

What activities comprise this project’s critical path?

(43)

34

Solutions for Problems in Section 2.1:

1. D. PERT reflects the optimistic duration, pessimistic duration, and most likely duration. 2. B. The project is behind schedule. Negative float equates to behind schedule and

positive float equates to ahead of schedule. 3. 16 workdays.

4. A-D-F-G.

(44)

35

Section 2.2 Milestones and Deliverables

Introduction

An important component of the project management plan is the list of deliverables and milestones for the project. The list indicates which deliverables and milestones are mandatory, and it might also address the relative weight of those deliverables. The term “deliverable” is sometimes used interchangeably with “milestone,” however the two are distinct items. Completion of a deliverable need not be denoted with a formal milestone in the network, but it might be.

A milestone is a scheduled event that marks the accomplishment of a specified effort or objective. In scheduling terms, milestones are an event with zero duration that marks the start, interim step, or the end of one or more activities. A deliverable is a contract or management requirement that identifies a physical product. Deliverables across the breadth of the project scope and schedule represents a widely varying set of products, including economic studies and alternative selection; requests for proposals; contract documents and purchase orders; white papers, decision documents, and reports; environmental documents; technical models and design documents; acquisition of real estate to accommodate the project improvements; installation of permanent materials and equipment in place; punchlists; start-up plans and system performance verification documents; project closeout reports; and as-built drawings. A deliverable may be associated with a milestone, but a milestone is not necessarily a deliverable.

While the completion of both deliverables and milestones is an indicator of progress, milestones are the scheduling tools that objectively measure progress to some level of accuracy. A deliverable is usually composed of several activities, and milestones—which are events and not activities--might be inserted within that collection of activities with weighted values according to their relative importance. By using these weighted milestones, progress for an activity can be measured, either as those milestones are achieved, such milestones thus representing “progress gates;” or where individual weighted milestones can be assigned a progress value based on the performance of their associated activities, and then an overall progress value for the given deliverable can be derived mathematically. Larger scale key milestones representing comprehensive project achievements are important tools in focusing management attention, reporting, and in managing the critical path of the project or program.

Thus, the student must understand the differences between deliverables and milestones; the various types of milestones and their uses in scheduling, measuring progress, and reporting; and the calculation of progress percentages using weight milestone methods. Although deliverables and milestones are different, the terms are used in conjunction with one another.

Terms to Know ƒ Control gate; ƒ Deliverable; ƒ End Item; ƒ Input milestone; ƒ Interim deliverables; ƒ Major milestone; ƒ Milestone; ƒ Milestone level; ƒ Milestone payment; ƒ Milestone plan;

(45)

36

ƒ Milestone report ; ƒ Milestone schedule; ƒ Product; and, ƒ Progress milestone. Key Points for Review

1.

Define, compare, and contrast milestones and deliverables.

2.

Discuss the use of milestones in project plans, contracts, schedules, and EVM systems.

3.

Calculate progress in terms of physical percent complete using “progress gate” concepts.

4.

Calculate the physical percent complete using a weighted milestone method.

(46)
(47)

38

Sample Questions for Section 2.2:

1. Which of the following best represents a deliverable?

A. On the project schedule, an event entitled, “Begin plant start-up sequence.” B. Attending required safety meetings.

C. Level-of-effort project management services within a given contract. D. The project Environmental Impact Report (EIR).

2. One of the major milestones on your flood control dam project is “30 percent Design Complete.” You are the lead scheduling engineer responsible for assembling the schedule, and you have decided that you will place a constraint on this milestone to help properly manage it. What type of constraint would you likely use?

A. Finish no-later-than B. Start no-earlier-than C. Mandatory start D. None of the above

3. You have decided to use a “progress gate” type of milestone method to measure progress on a major report. Your first milestone for this type of report is entitled, “Make Preliminary Draft

Presentation,” and the milestone dictionary for your project states that delivery of this type of

presentation earns the consulting firm working for you 50 percent progress. The consultant is authorized to use their subjective assessment of percent complete in the activities that precede this presentation. In their latest monthly report, they have reported that this presentation was actually made on the last day of the month (which you have verified), and they have claimed progress of 65 percent for this report overall. What percent complete should you report in your published project monthly report?

A. 65 percent.

B. The average between 65 percent and 50 percent, say about 57 percent

C. You must first do a detailed audit of their deliverables before you can report anything D. 50 percent

The next two questions are based on the following table:

Milestone # Description Total Weighted % % Actually

Complete To-Date

Weighted % Complete

To-Date

1 Right of Way Plan Completed 15% 100% 2 List of Parcels Obtained 15% 90%

3 Surveys Completed 85%

4 Legal Descriptions Completed 10% 70% 5 Appraisals Completed 10% 65% 6 Need Justifications Completed 5% 60% 7 Negotiations Completed. 10% 40% 8 Purchase Funds Placed in Escrow 5% 40% 9 Title Transfer Documents Executed 10% 0% 10 Funds in Escrow Released 5% 0%

(48)

39

4. Your project is a rail transit project involving the purchase of various real estate parcels. You have documented the process and have decided to use a weighted milestone approach to measuring progress. You have asked a junior cost engineer to tabulate data from your latest status report, which included the table above, but you notice that a total weighted percent value for milestone #3 is missing. What should that value be?

A. 20 percent B. 15 percent. C. 10 percent D. 5 percent

5. Activities involving appraisals, negotiations, and placement of funds into or release of funds from the project escrow account are being handled by a separate consulting firm. You need to determine the percent they have earned of their consulting contract value, if you are to process their firm’s invoice. What is the consultant’s percent earned for their part of the work, according to data in the above table?

A. 64 percent B. 42 percent C. 13 percent

(49)

40

Solutions for Problems on Section 2.2:

1. D. The project environmental implementation report (EIR) is the only direct deliverable.

2. A. Finish no-later-than dictates the latest allowable completion date. (Overall constraints should be held to a minimum, per proper schedule maintenance.)

3. D. You report based on the established program or phase gate milestone from the baseline, 50 percent, not what the contractor dictates.

4. B The sum of the values in the Total Weighted percent column must equal 100 percent. The other Total Weighted percent values sum to 85 percent; so milestone #3 is 15 percent.

5. B. Milestone #5, Appraisals, shows 10% x 65% = 6.5% of all work complete; Milestone #7, Negotiations, shows 10% x 40% = 4% of all work complete; Milestone#8, Funds into Escrow, shows 5% x 40% = 2% of all work complete; and Milestone #10, Funds Released, shows 5% x 0% = 0 percent complete. The consultant has 10% + 10% + 5% + 5% = 30 percent of all work assigned, and 6.5% + 4% + 2% = 12.5 percent of their work is complete. Thus, the consultant has earned 12.5/30 = 0.417 = 42 percent of their possible value.

(50)

41

Section 2.3 Technical Performance Goals

Introduction

Critics of EVMS often claim that there is nothing in EVMS that requires the final product meet specific criteria. EVM professionals know that one can document “technical requirements to complete a work package.” What happens when this goal is not met? Is the work package never completed?

The key word here is goal. Is it a requirement or a goal? It is a better design to use notes on a work package describing contractual technical requirements and the goals for a work package rather than using these requirements as EV types. So, a good question would be: if a particular technical goal described in a contract for a product or deliverable may be difficult to achieve, is that requirement a good milestone for completing a work package?

Technical performance reflects the basis of performance measurement by establishing a set of deliverables with a value for status updates and determining progress. The measurements reflect measurable and achievable points which reflect a value for completing the work package. This physical progress is then assigned a value based on the unit pricing from the contract budget baseline (CBB).

Terms to Know

• Technical performance; • Work package; and,

• Contract budget baseline (CBB). Key Points for Review

1. Technical performance reflects measurable and achievable scope of the work package. 2. Technical scope is used to determine the physical progress of the work package.

(51)
(52)

43

Sample Problems for Section 2.3:

1. Technical performance goals are used as indicators to measure progress. A. True

B. False

2. Earned value management is an integration of:

A. Technical performance, cost control and accounting, resource loading, and risk management.

B. Technical performance, resource planning with schedules, and risk management. C. Technical performance, cost control and accounting, planning, and risk management. D. Technical performance, resource planning with schedule, cost control, and accounting. 3. Identify by “yes” or “no,” if the following are technical performance goals:

A. Installation 1000 LM/LF pipe B. Completion of hydro-test package C. IFC piping spools ISO

D. Bump motor.

E. Issue material certification/passport

(53)

44

Solutions for Problems in Section 2.3:

1. A True. They are combined with products, milestones, or other control point indicators to define progress management.

2. B Technical performance, resource planning with schedules, and risk management are the fundamentals of EVM, without which a proper EVMS cannot be established. 3. All All can be technical performance goals, if they can be measured as a scope of work.

(54)

45

Section 2.4 Performance Measurement Baseline

Introduction

The performance measurement baseline (PMB) is the assignment of budget to the scheduled scopes of work. It is established to measure the actual performance of the work against the established budget. The PMB is the basis for the EVM system and is the only effective means of evaluating progress.

The PMB will be broken into control accounts which, when authorized, become work packages. Work that cannot be assigned to a work package, are assigned into planning packages. The control accounts are measured with control account plans (CAP), which are assigned to a control account manager (CAM). It is a requirement to have control accounts from program start through the end of the contract.

The PMB represents the formal plan for each control account manager to complete the designated technical scope. It is assigned with a designated time and within the authorized budget.

In an EVM checklist or audit, if there is no PMB, then the EVM system is a failure. The PMB can be established at a summary level as there may be gaps in the plan or scope, so this will require approved changes to the PMB. There also may arise times where the budget for allocated work exceeds the CBB. This is tracked as the over-target baseline (OTB). The OTB cannot be executed until a change is authorized to place it in the CBB.

The PMB can only be changed when an approved change order has been done and incorporated. Rebaselining is done to realign the PMB, i.e., to improve the correlation between the work plan, baseline budget, scope and schedule. This is different from reprogramming, which is the comprehensive re-planning of the remaining PMB that result in a total budget or schedule in excess of contract requirements. The results of reprogramming will be an OTB.

After contract award, the emphasis turns to activities necessary to provide a smooth transition from proposal to performance of the contract effort. The project team is concerned principally with structuring the work to be performed and assigning activities to responsible organizations. These activities are accomplished by subdividing the SOW into segments (developing the WBS) and assigning responsibility (establishing the organization) for authorizing, planning, executing, and controlling the work.

The approved baseline must also be established. The baseline implementation process involves structuring the three main management objectives (schedule, budget, and scope of work) into a cohesive, integrated environment. This is known as the PMB, which represents the sum of distributed and undistributed budgets, including all associated indirect cost against which contract performance is measured. It does not include management reserve (MR). A baseline implementation schedule is published at this time. All project team staff members are responsible for meeting this schedule in preparation for the integrated baseline review (IBR) or PMB review, as required. However, if the team believes the schedule is unrealistic, the problem must be resolved immediately, so that a revised implementation schedule can be developed.

Baseline implementation is completed within a timeframe directed by the contract. Subcontractor information must be integrated into the prime PMB in a timely manner. Implementation of the baseline may undergo several revisions before it is finalized. Once established, it is subject to strict

(55)

46

change control. Formal change control does not begin until the PM approves the final baseline. For some contracts, the customer may mandate a specific date for the baseline to be established.

Terms to Know

• Contract budget baseline (CBB); • Integrated baseline review (IBR);

• Performance measurement baseline (PMB); • Authorization to proceed;

• Time-phased scope; • Control account (CA); • Planning package; • Work package; • Control account plan;

• Control account manager (CAM); • Over-target baseline (OTB); • Rebaselining; and,

• Reprogramming. Key Points for Review

1. The CBB value is used to establish the PMB.

2. The PMB represents the time-phased scope, schedule, and associated budget through the end of the contract.

3. Included in the CBB are any budgets set aside for MR and contingency.

4. The PMB should be the priority after the authorization to proceed. It is developed from the CBB into the schedule for complete resource loading.

5. An OTB is a CBB that was formally reprogrammed to include additional performance management budget, and which therefore exceed contract target cost.

(56)

47

Sample Problems for Section 2.4:

1. The PMB is developed from the __________ scope, time __________ consistent with the __________ schedule.

A. Budgeted, phased, baseline. B. Work, based, integrated. C. Work, phased, integrated. D. Planned, based, resource. 2. Over-target baseline is based on:

A. CBB plus additional scope in excess of scope. B. Rebaselining the PMB.

C. PMB plus additional scope in excess of contract. D. Overrun of the actual cost or schedule of the CBB.

3. You have a scope order of $5,000,000 over 5 years, funded at $1,000,000 a year. Which way would you list your scope and budget:

A. CBB = $5,000,000, PMB Year 1 = $1,000,000, and OTB = $4,000,000. B. CBB = $1,000,000, PMB Year 1 = $5,000,000, and OTB = $1,000,000. C. CBB = $5,000,000, PMB Year 1 = $5,000,000, OTB = $4,000,000. D. CBB = $1,000,000, PMB Year 1 = $1,000,000, OTB = $4,000,000.

(57)

48

Solutions for Problems in Section 2.4:

1. C Scope of work, with a schedule that is resource loaded establishes the PMB.

2. A Establishment of an OTB entails adding budget for either future work or in process work and possibly for adjusting of variances.

3. A You have established the contract value, funding notifications will be your change order system, so each year you will reduce the OTB and Increase the PMB.

References

Related documents