• No results found

abt meter

N/A
N/A
Protected

Academic year: 2021

Share "abt meter"

Copied!
135
0
0

Loading.... (view fulltext now)

Full text

(1)

MAHARASHTRA STATE ELECTRICITY TRANSMISSION CO. LTD.PUNE

DIN E ISO 9001: 2000 PRESENTATION BY 400 KV R.S. , Jejuri

S.M. BAKRE , M.E. , M.M.S.

EXECUTIVE ENGINEER ABT METERS ON

(2)
(3)

Basic Concepts

• Historical Preview • Principle of working • Meters Generations • First - Ferrari or Electromechanical • Second - Static • Third - Numeric

(4)
(5)

Electromechanical or

Ferrari Meters

• The First

Generation

meters based on

rotation of

Aluminum disk

within current

coil and pressure

coil.

(6)

Static Meter

Advantages • High Accuracy • Low cost Limitations • Not ‘ intelligent ‘

Tamper can not be detected.

(7)

ABT Meters

ABT means

Availability

(8)

The term ‘Availability’ of ABT

• Indicates that the power MW

should be available.

• It may specifically be noted that

energy charge (at the specified

plant-specific rate) is not based on actual

generation and plant output, but on

(9)

Availability as a base

• For example if the rated capacity of

generator is 50 MW out of which 30 MW generation is available , the base for billing would be 30 MW and not 50 MW. 30 MW

would be scheduled generation for calculating deviation if any. If 20 MW power is generated instead of scheduled 30 MW , the penalty of 30-20 = 10 MW would be imposed as UI

(10)

ABT Concept

• Traditional Concept :-

dw / dt

• Modern Concept :-

dw/df . df/dt

• dw/df :- ABT Meters

• df./dt :- Frequency Trend

(11)

Underfrequency Relay (UFR)

• UFR Settings

• 48.8 Hz

• 48.6 Hz

• 48.2 Hz

(12)

Frequency Trend Relay ( FTR )

•df/ dt

(13)

Implementation of ABT

was recommended

initially at Central

Generating Stations in the

year 1994 by M/s ECC of

USA under the study

sponsored by World Bank

and Asian Development

(14)

ABT tries to improve a quality of power and curtail the following

Unacceptable rapid and high

frequency deviations

Frequent grid disturbances which

result in generator tripping ,

power outages and grid

instability.

The pricing of power is made

(15)
(16)

ABT Operation and Billing &

Payment Mechanism

The SEB‟s give the LD its

requirement in 15-minute

blocks for the next day.

At the same time the CGS

stations also provide the LD

their 15-minute availability

(17)

ABT Operation and Billing &

Payment Mechanism

Based on the declared demand

and available supply, the LD

provides a schedule to the

SEB‟s and the CGS for drawl

and generation in

15-minute

(18)

ABT Operation and Billing &

Payment Mechanism

Based on the drawl

and generation

positions of the SEBs

and the CGS stations,

the UI bill is

(19)

The Three-part ABT Tariff

Fixed Charge

: This is

payable by the beneficiary

states based on the

capacity allocated to them,

and is irrespective of the

amount of power they draw

or schedule to draw

(20)

The Three-part ABT Tariff

Energy Charge

:

All the

scheduled energy that is

drawn is charged as per

the variable energy

charge of the station

from which power is

being drawn.

(21)

The Three-part ABT Tariff

UI Charge

: The UI

(Unscheduled Interchange)

charge is levied on those

units of energy that are a

deviation from the

schedule. This UI charge is

frequency dependent.

(22)

Billed Amount

Billed

Amount =

Fixed

Charge

+ Energy

Charge

+ UI Charge

(23)
(24)
(25)

The energy is metered in

15-minute

time blocks, since frequency keeps

changing (and the UI rate with it). The

metered energy is then compared

with the scheduled energy for that

15-minute time block, and the difference

(+ or -) becomes the UI energy.

Corresponding UI rate is determined

by taking the average frequency for

the same 15-minute time block into

(26)

ABT Meter

s

„ Intelligent „

meters

Based on

„polled

approach „

(27)

Principle of working of ABT meter

The energy is recorded in terms of

pulses per kWh . The principle of

working of static ABT meter is sampling . The voltage and current

singles are received from PT and CT

respectively .The samples of these signal at a particular instant are collected

by Sample and Hold circuit . The

phase difference between voltage and current is also found out . These values are analogue values .

(28)

Principle of working of ABT meter

The CPU [ Central Processing Units ] only

accepts digital signals . Therefore , the analogue signals are converted to digital by the circuit called ADC [Analogue to

digital converter].The CPU processes these input signals for finding KVA [VI] , kWh [ VI cos ] , RKVA [ VI sin ] and other parameters . In order to measure the

energy in terms of units , the circuit Energy to frequency converter is

provided. The energy is converted into pulses . The counter counts number of pulses .

(29)

( I1 2+ I 2 2 + I3 2 +I4 2 ……….. +In 2 ) IRMS = --- n ( V1 2 + V 2 2 + V3 2 +V4 2 ……….. +Vn 2 ) VRMS = --- n V1 I1 + V2 I2 + V3 I3 +V4 I4 ……….. +Vn In W = --- n W cos = --- VRMS IRMS

(30)

Functional Block Diagram of

ABT Meter

(31)
(32)

3 Phase , 4 Wire Meters

[ 3 wattmeter method ]

(33)

3 Phase , 4 Wire Meters

W = W1 + W2 + W3

=

VI cos

+ VI cos

+ VI cos

(34)

General

(35)

General arrangement

Keypad - 12 numeric

plus * and # keys.

LCD Display – 4 row X

20 characters

Optical Port – RS232

electrically apart

Metering Module –

with sliding guides.

Calibrated LEDs – for

dial test. MD Reset button - sealable RJ-11 Port - RS-485 interface with MODBUS.

(36)
(37)

METER TESTING LAB

SETUP

• Program the AC Power Source to

generate a particular waveform.

• Configure the reference meter.

• Set the pulse counter to zero.

• Turn ON / OFF the switch I at the

beginning / end of the test.

(38)

METER TESTING LAB

SETUP

(39)
(40)

ABT Meter Testing

• Dial Test - No. of

blinkings per kWh • Accuracy Test -

0.2

• Min. Current test

(41)

Test Terminal Block

(TTB)

(42)
(43)

Manufacturers of

ABT meters

(44)

Status of ABT meters at 400

KV Jejuri SS

Feeder / ICT Type Category

400 KV Lonikand MFM T2T 400 KV Stg IV MFM T2T ICT – HV Side ABT T2T ICT – LV Side ABT T2T 220 KV Baramati MFM T2T 220 KV Jejuri I MFM T2T 220 KV Jejuri II MFM T2T 220 KV Phursingi MFM T2T

(45)

Advantages of ABT Meters

These meters are capable of

storing data

. Therefore , the

features such as load survey

, energy history , tamper

data etc is available. If the

meter is stopped or tampered

, the evidence is recorded .

(46)

Advantages of ABT Meters

These meters

have higher

accuracy

of the

(47)

Advantages of ABT Meters

These meters are

capable of displaying

energy as per

applicable

tariff

I.e.

TOD and ABT tariff.

(48)

Advantages of ABT Meters

In the advent of

load survey data , it

is possible to

monitor the

consumption

pattern.

(49)

Advantages of ABT Meters

Using

polled approach

,

the CPU detects

abnormality in the

metering system.

(50)

Advantages of ABT Meters

The

starting current

of

is very less i.e. 0.1 % of

base current. Thus 1 A

meter will record

(51)

Advantages of ABT Meters

The ABT meters have self

diagnostic

feature by which

any error developed in the

inside component can be

detected. This feature checks

that the data stored in the

meter is safe and not

(52)

Advantages of ABT Meters

These meters are

user

friendly.

The display parameters are

easy

to understand.

Push button operation to read

display parameters is easy.

Data retrieval through MRI [

Meter Reading Instrument ] is

simple .

(53)

Advantages of ABT

Meters

MD can be reset through any of the modes :- MRI Manual Laptop Auto

(54)

Advantages of ABT Meters

Remote

data retrieval

possible through

internet and mobile.

Can be used in

AMR

[

Automatic Meter

Reading ]

(55)

“OPEN ACCESS”,

“WHEELING”

“Open access” and “wheeling” generally

involve two parties, one supplying a

certain quantum of power to the other

through the regional / State grid. Any such

transaction involves a number of parties,

and disputes could arise in scheduling,

energy accounting and commercial

settlement, unless an appropriate

framework is in place.

(56)

“OPEN ACCESS”,

“WHEELING”

Suppose party - A has contracted to supply 10 MW round the clock to party -

B (in the same State) at a certain price (which need not be disclosed to

others), through the State grid. Suppose the transmission loss apportioned to this transaction has been determined as 0.5 MW. Party - B would then be

entitled to receive 9.5 MW, provided party - A is actually injecting 10.0 MW into the State grid at its end. In actual operation, both injection by A and drawl by B may fluctuate over the day and the differential may vary from 0.5 MW. Who would pick up the commercial liability arising on account of these deviations? Since A and B are physically apart and operationally independent, a pragmatic solution for commercial treatment in such a case would be to

meter the actual injection of A and actual drawl of B in 15-minute time blocks, and separately compute their deviations from their respective schedules (10.0 MW / 2.5 MWh for A and 9.5 MW / 2.375 MWh for B).

(57)

4 Quadrant Import Export Meter

Q2

Export

Lead

Q1

Import Lag

Q3

Export Lag

Q4

Import Lead

(58)

ABT Specifications

Parameter Value

Standard

IEC 687 , CBIP 88

Definition

Billing Energy

Type of meter

3 phase , 4 Wire

Voltage Rating 400KV to 11KV/110 /3 V Temperature 27 0C

(59)

ABT Specifications

Parameter

Value

Current Rating 1 Amp

Maximum Current [ 200 % of Ib ] 2 Amp Minimum Current [ 0.1 % of Ib ] 1 mA Class Of Accuracy 0.2

Frequency

50 Hz [ +- 5% ]

(60)

ABT Specifications

Display Parameters

1 ] 3 Voltages - Vr , Vy , Vb 2 ] 3 Currents - I r , Iy , Ib

3 ] Kwh Import &

4 ] Rkvah [ Lead ] Export modes 5 ] Rkvah [ Lag ]

6 ] Kvah

7 ] Date and Time 8 ] Power Factor 9 ] KVA MD

(61)

ABT Specifications

Modes of MD Reset

Manual Auto MRI Laptop Mobile Phone Remote end

(62)

Load Survey Data

60 days data

on FIFO

Integration

period of 15

minutes

LS reset

available

LS Parameters 3 Voltages – Vr , Vy , Vb 3 Currents – Ir , Iy , Ib

Date and Time

kWh

RKVAH [ Lag ] RKVAH [ Lead ]

KVAH

KVA [ MD ]

Pf

(63)
(64)

Tamper Data

Meter CPU generates tamper

events on polled approach.

At least 320 tamper events

should be memorized.

Current Tamper

CT Reverse

CT Short

(65)

Tamper Data

Voltage Tamper

PT Missing

PT Low

Power Tamper

Meter bypass

(66)

ABT Specifications

Minimum retention time for NV

RAM >= 10 Years

Total Energy for billing = true

energy + harmonic energy

Principle of working – sampling

PCB – SMT [ Surface mounting

(67)

Surface Mount Technology

[ SMT ]

Lesser heat dissipation Long life of PCB and Components No component disconnection due to dry solder.

(68)
(69)
(70)
(71)
(72)
(73)
(74)

Specifications of MRI

standard IEC 1109 CBIP 111 ANSI

Communication UART , RS-232 , RS-485

rate of data transfer 130 bps [ bits per second ] to 115 Kbps.

Battery 7.2 Volts , 800 mah ‘Nickel Cadmium ‘ battery

(75)

Maintenance of MRI

Charging of MRI is the main

maintenance activity to be carried out. For 8 hour working , the MRI should be charged for 1 hour.

If the MRI is not in use , it should be

charged once in a week .

It should be checked at least within a

month that all MRI commands are working properly .

Clean the surface of MRI with smooth

(76)

MRI Commands

DOS Commands DIR Date Time CLS Ver Vol Path Firmware Commands Master import Master export PC_Term SH TP MSZ TPRMRM

(77)

The following disturbances are

recorded by ABT meter

:-•

· Harmonics

· Voltage dips and short

interruptions

· Conducted transients

· DC & AC magnetic fields

· Electromagnetic fields

(78)

Energy Management Software

EMS

The EMS is provided at all

substations , Central Monitoring

Station [ LD ] , Corporate / Zone /

Circle / Division Office . The EMS

is implemented for monitoring

energy at interface points with

inter-state / intra-state grid

including all incoming & outgoing

feeders / transformers / ICTs .

(79)

Energy Management Software

EMS

The ABT / MFM meters are installed

at the required points . The system software automatically collects data from these meters . The metering system is provided with RS485 communication port [ in form of RJ11 connector on its back ] . The communication cable has RJ11-to-RJ11 configuration. The data is collected online on RS485 MODBUS protocol.

(80)

Energy Management

Software EMS

The data is made available at

substations at the refreshing rate of 5 min using multiplexer or Data Concentrator Unit [ DCU ] and interfacing devices. The DCU stores 5 min. data for 30 days [ on FIFO ] basis . The reports can be generated. The EMS at LD has an access to their existing database i.e. Oracle 10g.

(81)
(82)

The system comprises of the

following components

Energy meters [ ABT and MFM ] at each

substation.

Data Concentrator Unit [ DCU ] at each

substation.

Global Positioning System [ GPS ] on PC

at each substation.

Data Acquisition Software [ DAS ] at

each substation MYSQL as backend database.

Networking [ switches and cables ] at

each substation.

EMS at LD with access to their existing

(83)
(84)

Pin Configuration

No Pin Description

1 VR Red Phase Voltage

2 VY Yellow Phase Voltage 3 VB Blue Phase Voltage 4 IRIN Red Phase Current IN 5 IROUT Red Phase Current OUT 6 IYIN Yellow Phase Current IN 7 IYOUT Yellow Phase Current OUT 8 IBIN Blue Phase Current IN

9 IBOUT Blue Phase Current OUT 10 VN System neutral

(85)

Pin Configuration

No Pin Description

11 Vac(L) Auxiliary AC Supply ( Live ) 12 Vac(N) Auxiliary AC Supply ( Neutral ) 13 Vdc(+) Auxiliary DC Supply ( Positive ) 14 Vdc(-) Auxiliary DC Supply ( Negative ) 15 г Earth connection

(86)
(87)
(88)

Reports Generation

PC Software

Instantaneous

Data

Billing Data

Load Survey

Data

Tamper Data

(89)

Reports generated by EMS

Energy Loss Report

Voltagewise Energy Loss

Report

Transformerwise Energy

Loss Report

Power ON/OFF Report

(90)

Reports generated by EMS

Min-Max report for current , voltage

, MW , MVAR , PF < frequency.

Transformer Loading Report

Alarm Report.

Meter Replacement Report

Load Survey Report

Load Shedding Report [ manual data

entry ]

(91)
(92)
(93)
(94)
(95)
(96)
(97)

CEA Regulations on Installation &

Operation of meters

MEAA

– Meter for energy

audit & accounting

MIT

-Meter for interface

tariff

(98)

ABT Metering in MSETCL

• Interstate ABT Metering

• Intra-state ABT Metering

• No of ABT / MFM meters = 9000

• No. of interface locations = 1500

(99)

Basics of Tulip

Communication

(100)

Network Connectivity

Devices

• Modems • Repeaters • Hubs • Bridges • Multiplexers • Switches • Routers • Brouters

(101)
(102)
(103)

Modem

• Performs

modulation

and

(104)

Repeater

• Perform

amplification

of the signal to

reduce

attenuation.

(105)

Hubs

• Hub is the

multiport

repeater

(106)

Bridge

•Connects

two

different

networks

(107)

Multiplexer ( MUX )

• Combines

two or more

signals on

high speed

transmission

media

(108)

Switches

• Connects /

disconnects

internet

(109)

Routers

•Intelligent

(110)

Brouters

•Routers

that

follow all

protocols

(111)
(112)
(113)
(114)

Ensure that

• Proper earthing is

done.

• Network switch is ‘

ON ‘

• UPS is ‘ ON

(115)

How to test Tulip connectivity ?

• Contact ‘ ABT Room ‘ at SLDC , Kalwa

• At Substation end , make following operations

on ABT PC –

• Click on ‘ Start ‘ button . • Click on ‘ Run ‘

• Type the word ‘ CMD’ and click ‘ OK ‘ .

• Type ‘ IPCONFIG ‘ and press enter button. • Type ‘ PING_code ‘ and press enter button. • The indication ‘healthy ‘ indicates healthiness

(116)

Check tulip configuration

• Visit the following website :-

www.myconnect.tulipconnect.com

• Enter the following :-

username :- 6086

(117)

Maintenance of ABT-Tulip

System

• AC/DC supply of PC / DCU /Tulip Devices

should not be switched off in any case.

• The power points should be dedicated and

should not be used for other purpose such as mobile charging .

• GPS should be always charged and running • The clock of meter /PC/MRI should be

(118)

Maintenance of ABT-Tulip

System

• Ping test should be conducted daily to

ensure that the data is transmitted to SLDC Kalwa at ping 172.16.0.1

• Any change in CTPT ratio should be

configured in ABT meter and PC. The CC tool should be used for this purpose.

• No new transformer should be taken in

(119)

Maintenance of ABT-Tulip

System

• The wiring should be proper and should not

be disturbed.

• The installation should be neat-clean and

free from dust.

• In case AC supply is to be switched off , the

PC should be shut down properly.

• In case of CT/PT/ meter failure , proper

(120)

Maintenance of ABT-Tulip

System

• Data should be retrieved using MRI on first

date of the month particularly in respect of T2G feeder.

(121)

Problems with ABT /

Tulip

• ‘

No display ‘ problem.

• Delay in Report Generation

• MRI / MRI Software / Training not given

• PC not working . Antivirus not installed.

• The Tulip link is not healthy .

(122)

Problems with ABT

• Energy Audit of Lines is not calculated.

• Power ON/OFF Reports - EHV Substations have bus PT and not line PT. Therefore the logic

should be only ‘ Current OFF ‘ and not ‘ Voltage OFF ‘ or ‘Power OFF ‘ .

• ABT meters operate on auxiliary AC/DC supply . However , at almost all substations , ABT

meters are connected on DC . This may create problem when there is DC leakage.

(123)

Problems with ABT

• UPS of ABT trips on overvoltage /

undervoltage at EHV substations . Therefore , it is required to provide stabilizer instead of UPS.

(124)

Roadblocks in ABT meter commissioning

• At generating stations , the LV of generating transformer is connected directly to 33 KV bus. No CT / PT are provided.

• There is no adequate space in switchyard for providing CT/PT.

• Metering core not available in CTs. • 5 A CT are provided and not 1 A.

• It is difficult to install ABT meter on outdoor panels.

(125)
(126)

Commissioning of RTU

• RTU – Remote terminal Units

• DC – data concentrators

• Contract given to M/s Siemens vide

MSETCL/CO/CE/CRA/RTU/T-0907/7088 dt

31-5-08.

(127)
(128)
(129)

Connectivity with ERP

System

• The Data Centers of

ERP are connected to Tulip Hub at SLDC

kalwa .

• The substations are

connected to Tulip Hub.

• The rate of data

transfer is 4 mbps. • The connectivity is established through following servers – • - ISP Router • ( Internet Service Provider ) • - Tulip intra-net service provider router .

(130)

Connectivity with ERP

System

• Connectivity with Proxy Server • Internet Explorer > • Internet Options > • Connections > • LAN Settings • Enter IP address of

Proxy server and Port number

(131)
(132)
(133)

TOD Tariff

TOD

Slot

Shift

Surcharge /incentive

A

22.00-6.00 -0.75 per Kwh

B

6.00 – 9.00 0

C

9.00 – 12.00

+0.60 per

Kwh

B

12.00 – 18.00

0

D

18.00 – 22.00

1.00 per Kwh

(134)
(135)

References

Related documents

the [FREP] Rules laid to rest any lingering doubt regarding the justiciability of the socio-economic provisions of the Act including the right to a healthy environment,

Each provider has an application routing component (top right of each provider) that routes incoming requests in coordination with the application routing service in the

Đặc iệt trong lĩnh vực Y học, các hợp chất này đã và đang đƣợc nghiên cứu làm thuốc nhƣ thuốc kháng sinh, thuốc chữa cúm A, thuốc tim mạch…Nhiều hợp

Making sacramental wine requires special attention and care, starting with qvevri washing and marani hygiene and ending with fermentation, aging and storage. During

During this portion of the study, we examine the effect that lowering the threshold number of flow contributing cells required to distinguish between channel and overland flows has

actors like age, monthly savings, expected average readiness score of 52 – a long way short etirement age, guaranteed retirement of the 100 that would ensure people get the

The summary resource report prepared by North Atlantic is based on a 43-101 Compliant Resource Report prepared by M. Holter, Consulting Professional Engineer,

Open Deck Chart room Radio room Office r Chief Engineer Captain Hotel manager´s office Balconies Balconies Sta ff Cabin Sta ff Cabin Coffee Station Promenade deck Promenade