DESIGN PHASE CONSTRUCTABILITY CONCEPTS IN

HIGHWAY PROJECTS

SITI HAFIZAN BINTI HASSAN

A project report submitted in partial fulfilment of the

requirements for the award of the degree of

Master of Science (Construction Management)

Faculty of Civil Engineering

Universiti Teknologi Malaysia

(2)

iii

(3)

iv

ACKNOWLEDGEMENTS

First and foremost, grateful thanks to Allah S.W.T for guiding and helping me in

this dissertation. Giving me chances in a way to complete it.

I would like to extend my deepest appreciation and thanks to my supervisor,

Ir. Dr. Rosli Mohamad Zin for his continuous guidance and encouragement in the effort

to complete this thesis.

I would also like to thank to all the engineers and architects who participated in

the questionnaires survey and field interviews and also to those who were involved

directly or indirectly in the completion of this project.

(4)

v

ABSTRACT

(5)

vi

ABSTRAK

(6)

vii

TABLE OF CONTENT

CHAPTER

TITLE

PAGE

THESIS TITLE

i

DECLARATION SHEET

ii

DEDICATION

iii

ACKNOWLEDGEMENT

iv

ABSTRACT

v

ABSTRAK

vi

TABLE OF CONTENTS

vii

LIST OF TABLES

xi

LIST OF FIGURES

xiv

LIST OF APPENDIX

xvi

1 INTRODUCTION

1

1.1

Introduction

1

1.2

Problem

Statement

3

1.3

Aim and Objectives of the Study

4

1.4

Scope

of

Research

4

(7)

viii

2 LITERATURE

REVIEW

6

2.1

Constructability

Definitions

6

2.2

General Overview Constructability in

7

Highway

Project

2.2.1

Government

Agency

Observations

8

2.2.2 Design Firm Observations

11

2.2.3 Construction Firm Observations

14

2.3

Constructability in the Highway

14

Construction Project Process

2.3.1 Feasibility Design Stages

16

2.3.2

Design

Stages

17

2.3.3

Construction

18

2.3.4

Operation

18

2.4

Maximum Benefit of Constructability

19

2.5

Constructability Concepts in Highway Projects

22

2.6

Design Phase Constructability Concepts

32

2.6.1 Carry Out Thorough Investigation of the Site 34

2.6.2 Design for Minimum Time Below Ground

36

2.6.3

Design

for

Simple

Assembly

39

2.6.4

Encourage

Standardisation/Repetition

40

2.6.5 Design for Preassembly or Modularisation

40

2.6.6 Analyse Accessibility of the Jobsite

41

2.6.7 Employ Any Visualisation Tools

42

to Avoid Physical Interference

2.6.8

Investigate

Any

Unsuspected

Unrealistic

42

or Incompatible Tolerances

2.6.9 Investigate the Practical Sequence of

43

Construction

(8)

ix

2.6.11 Consider Storage Requirement at

43

the Jobsite

2.6.12 Investigate the Impacts of Design on

44

Safety

during

Construction

2.6.13 Design to Avoid Return Visit by Trade

45

2.6.14 Design for the Skills and Resources

45

Available

2.6.15 Consider Suitability of Designed Materials 46

2.6.16 Provide Detail and Clear Information

45

2.6.17 Design for Early Enclosure

46

2.6.18 Consider Weather Effect in Selecting

Materials or Construction Methods

47

2.7

Summary

48

3 RESEARCH

METHODOLOGY

3.1

Introduction

50

3.2

Research Process

50

3.3

Determining the Research Objectives

51

3.4

Steps in Methodology

52

3.4.1

Conceptualization

52

3.4.2 Literature Review

53

3.4.3

Questionnaire

53

3.4.4

Analysis

56

3.5

Development of Guidelines

57

4

DATA ANALYSIS AND DISCUSSION

4.1

Introduction

58

(9)

x

4.2.3 Field of Specialization

61

4.2.4

Position

in

Organization

62

4.2.5 Numbers of Years Practiced in Designing 63

4.2.6 Numbers of Years Practiced in Working 64

4.3

Level of Importance

66

4.3.1

Frequency

Analysis

66

4.3.2 Average Index Analysis

77

4.4

Level of Application

81

4.3.3

Frequency

Analysis

81

4.3.4 Average Index Analysis

91

4.5

The Development of Design Phase

95

Constructability Improvement Concepts

4.6

Discussion

99

5 CONCLUSION

AND

RECOMMENDATIONS

5.1

Conclusion

100

5.1.1

Objective

1

100

5.1.2

Objective

2

104

5.1.3

Objective

3

105

5.2

Recommendations

105

REFERENCES

107

(10)

xi

LIST OF TABLES

TABLE

NO.

TITLE PAGE

4.1

Type

of

Organization

59

4.2

Level

of

Education

61

4.3

Field

Of

Specialization 62

4.4

Position

in

Organization

63

4.5

Number of Years Practiced in Designing in

64

Highway

Projects

4.6

Number of Years Practiced in Working in

65

Highway

Projects

4.7

Carry out Thorough Investigation of the Site

66

4.8

Provide Detail and Clear Design Information

67

4.9

Analyze Accessibility of the Jobsite

67

4.10

Investigate the Impacts of Design on Safety

68

during

Construction

4.11

Consider Suitability of Designed Materials

69

4.12

Investigate the Practical Sequence of Construction

69

4.13

Consider Adverse Weather Effect in Selecting Materials

70

or Construction Methods

4.14

Plan to Avoid Damage to Work by Subsequent

71

Operations

(11)

xii

Incompatible

Tolerances

4.16

Designs for the Skills and Resources Available

72

4.17

Consider Storage Requirement at the Jobsite

72

4.18

Design for Minimum Time below Ground

73

4.19

Design for Early Enclosure

73

4.20

Encourage

Standardization/Repetition 74

4.21

Employ Any Visualization Tools to Avoid

74

Physical

Interference

4.22

Design for Simply Assembly

75

4.23

Design to Avoid Return Visit by Trade

76

4.24

Design for Preassembly and/or Modularization

76

4.25

Average Index Value for Degree of Importance of

79

Constructability Concepts during the Design Phase

4.26

Carry Out Thorough Investigation of the Site

81

4.27

Employ Any Visualization Tools to Avoid

82

Physical

Interference

4.28

Encourage

Standardization/Repetition 82

4.29

Consider Storage Requirement at the Jobsite

83

4.30

Design for Minimum Time below Ground

83

4.31

Investigate the Practical Sequence of Construction

84

4.32

Design for Simply Assembly

84

4.33

Design for the Skills and Resources Available

85

4.34

Investigate the Impacts of Design on Safety during

86

Construction

4.35

Analyze Accessibility of the Jobsite

86

4.36

Design For Preassembly and/or Modularization

87

4.37

Investigate Any Unsuspected Unrealistic or

87

Incompatible

Tolerances

4.38

Design to Avoid Return Visit by Trade

88

4.39

Design for Early Enclosure

88

(12)

xiii

4.41

Plan to Avoid Damage to Work by Subsequent

89

Operations

4.42

Consider Suitability of Designed Materials

90

4.43

Consider Adverse Weather Effect in Selecting Materials 90

or Construction Methods

(13)

xiv

LIST OF FIGURES

FIGURE

NO.

TITLE PAGE

1.1

Research

Methodology

Chart

5

2.1

The Highway Construction Project Process

16

2.2

Project Life Cycle and Designers Level of Influence

20

2.3

Ability to Influence Final Cost Over Project Life

21

2.4

Process of launching girder for elevated structure

35

2.5

Problems faced during launching of some girders

35

2.6

Details of elevated highway

37

2.7

Problem of compaction and result after

38

project

start-up

3.1

Steps

in

Methodology

52

3.2

Questionnaire

Flow

Chart

55

4.1

Percentage of type of organization

60

4.2

Percentage of level of education

61

4.3

Percentage of field of specialization

62

4.4

Percentage of Position in Organization

63

4.5

Percentage of Number of Years Practiced in

64

Designing In Highway Projects

4.6

Number of Years Practiced in Working in

65

Highway

Projects

(14)

xv

4.8

Degree of Application of Constructability Concepts

94

(15)

xvi

LIST OF APPENDIX

APPENDIX

TITLE PAGE

(16)

CHAPTER 1

INTRODUCTION

1.1 Introduction

Government and private agencies that carried out highway construction

project are facing the reality that the public will no longer tolerate construction

projects that are insensitive to road users and adjacent communities. According to

Russell et al. (1993), highway construction projects are characterized by traffic

problems, changes of design, poor planning, disputes, cost overruns, poor safety

practices and time delays. Constructability is seen as one of the best solutions to

these problems where it has demonstrated the potential to minimize the number and

magnitude of changes, disputes, cost overruns, and delays during construction.

(17)

2

technology and experience into the engineering and design of a project (Anderson et

al., 1995

).

Highway project constructability can be particularly demanding for a range of

reasons. For example, some of the highway construction technologies are varying

hastily, and, as with most construction, the personnel is transient and site conditions

can vary to the highest degree. Nearly all projects are subjected to severe public

scrutiny involving open competitive bidding, thereby separating the planning and

execution phases and largely precluding a fast-tracked approach to construction.

Designs standards, authored by a multitude of organizations abound and often limit,

if not discourage selective innovation. The prerequisite for nonproprietary

specifications often leads to vagueness. In general, the perception is that project

durations are longer than necessary and that construction costs can possibly be

lowered. As a result, specifications supportive of constructability become an

important element for improving project performance (Hugo et al., 1990).

Beside the project performance, constructability also has been successfully

used to reduce project durations. Eldin (1996) provides several examples of projects

that have successfully used constructability to reduce project durations without

increasing project cost. In a CII (1995) study five projects were analyzed, reporting

11 to 30% reductions in project duration directly attributed to constructability

reviews (i.e., without cost increases). Although the majority of the projects were

associated with industrial facilities, one of them was an interstate highway

realignment that included the reconfiguration of eight bridges and the construction of

two new bridges to facilitate the addition of a high occupancy vehicle lane in each

direction (Eldin, 1996).

(18)

3

documents the best practices, guidelines, checklist, and lessons learned from

previous projects, thereby improving the ease of construction and reducing life cycle

costs. This critical process evaluates the “ability to construct” your construction

project (Milstead, 1997). Constructability reviews of highway projects during design

have the potential to minimize the number and magnitude of changes and delays

during construction and thereby reduce durations (Anderson and Fisher 1997). A

constructability analysis of six highway projects suggests that benefits may be as

large as 25 times greater as costs (Anderson and Fisher 1997). Improved processes

and management for effectively using constructability reviews to reduce total project

durations can potentially improve construction project management. The way how

to provide the best constructability review is by improving the understanding of

application and importance of constructability concepts in highway projects.

1.2 Problem

Statement

Nowadays, highway construction suffers from lack of constructability, which

causes traffic problems, changes of design, poor planning, disputes, cost overruns,

poor safety practices and time delays. Researchers in developed countries have

realized the seriousness of this shortfall and suggested solutions to resolve it. In

Malaysia, research in constructability in highway projects has not been popular

researched yet. One of the reasons is due to lack of understanding of constructability

concepts among the engineers. Design Phase Constructability Improvement

(19)

4

1.3

Aim and Objectives of The Study

The aim of this study is to establish Design Phase Constructability Guidelines

For Highway Projects in Malaysian Construction Industry. In order to achieve it,

the following objectives have been identified:

a) To identify the constructability concepts in highway projects.

b) To identify the level of importance and application of constructability concepts in

highway

projects.

c) To establish Design Phase Constructability Improvement Guidelines for highway

projects.

1.4

Scope of Research

This research was carried out by questionnaires and interviews. The research

focused on Malaysian Highway Projects with contract values of more than RM 5

million. The questionnaires were distributed to the senior construction management

team like engineers, architect or project manager and etc, who involved in highway

projects.

1.5 Research

Methodology

(20)

5

of this research. Figure 1.1 shows the research methodology chart that has been used

in this research.

Figure 1.1 Research Methodology Chart

CONCLUSION/

RECOMMENDATION

CONCEPTUALIZATION

LITERATURE REVIEW

QUESTIONNAIRE

SURVEYS

DATA ANALYSIS

Phase 1

Design phase constructability

concepts in highway projects

Phase 2

Level of importance and

application of constructability

concepts

(21)

REFERENCES

Adam, S. (1989).

Practical Buildability

. The Construction Industry Research and

Information Association, London.

Al-Hammad, A-mohsen and Assaf, S. (1996). Assessment of Work Performance of

Maintenance Contractors In Saudi Arabia.

Journal of Management in

Engineering.

ASCE. 16(1): 44-49.

Anon (1986). Can Your Design Be Built?

Civil Engineering

. ASCE: 49-53.

Boyce, W.J. (1991). Design for Constructability.

Hydrocarbon Processing

. 73(12): 81

CII (1986).

Constructability – A Primer

. Publication 3-1. Austin, Texas: Construction

Industry Institute.

CIRIA (1983).

Buildability: An Assessment

. Special Publication 26: CIRIA

David N.Ford, Stuart, and Andrew. (2004). Managing Constructability Reviews to

Reduce Highway Project Durations.

Journal of Construction Engineering and

Management

, ASCE, Vol. 130, No.1, 33-42

Eldin, N.N. (1996). Constructability Improvements of Project Designs.

Journal of

(22)

107

Felix, Geogina. (1997). Assessment of Constructability Practices Among General

Contractors.

Journal of Construction Engineering and Management

, ASCE, Vol. 4,

No.3, 114-123

Fischer, Tatum. (1997). Characteristics of Design Relevent Constructability Knowledge.

Journal of Construction Engineering and Management

, ASCE, Vol. 123, No.3,

253-255

Fisher, D.J. and Rajan, N.(1996). Automated Constructability Analysis of Work-zone

Traffic-Control Planning.

Journal of Construction Engineering and Management

,

ASCE, Vol. 122, No.1,36-43

Ferguson, I. (1989).

Buildability in Practice

. London: Mitchell’s Professional Library.

Ganah, A., Anumba, C. and Bouchlaghem, N. (2000). The Use of Visualisation to

Communicate Information to Construction Sites.

ARCOM 16

th

. Annual Conference.

6-8 September. Glasgow Caledonian University, UK: 833-842.

Gambatese, J.A. and McManus, J.F. (1999). Discussion of the Constructibility Review

Process: A Constructor’s Perspective, by Roy Mandelsohn.

Journal of Management

in

Engineering

. ASCE. 15(1): 93-94.

Griffith, A and Sidwell, T. (1995).

Constructability in Building and Engineering

Projects

. London: Mac Millan Press Ltd.

Hassan, Z. (1997).

CONPLAN: Construction Planning and Buildability Evaluation in an

Integrated Intelligence Environment

. Department of Surveying, University of

Salford, UK: PhD. Thesis.

(23)

108

James E. Rowing, Steven L. Kaspar. (1991). Constructability of Cable-Stayed Bridges.

Journal of Construction Engineering and Management

, ASCE, Vol. 117, No.2,

259-275

Jergeas, P.E., John Van Der Put. (2001). Benefits Of Constructability On Construction

Projects.

Journal of Construction Engineering and Managemen

t, ASCE, Vol. 127,

No.4, 281-290

Kirby, G..J, Douglas, A.F. and Donald, K.H. (1987). Improvement in Design Review

Management.

Journal of Construction Engineering and Management

, ASCE, Vol.

114, No.1, 549-563

Madelsohn, M. (1997). The Constructability Review Process: A Constructor’s

Perspective.

Journal of Management in Engineering

. ASCE. 13(3): 17-19.

Nabil A Kartam. (1996). Making Effective Use of Construction Lessons Learned in

Project Life Cycle.

Journal of Construction Engineering and Management

, ASCE,

Vol. 122, No.1, 14-21

Nima, A.N. (2001).

Constructability in the Malaysian Construction Industry.

, Faculty of

Engineering, UPM, PhD. Thesis.

Nima, Mohd R. Kadir, S. Jaafar. (2002). Constructability Concepts in West Port

Highway In Malaysia

. Journal of Construction Engineering and Management

,

ASCE, Vol. 128, No.4, 348-356.

Nima, Mohd R. Kadir, S. Jaafar. (2004). Constructability Concepts in Kuala Selangor

Cable-Stayed Bridge In Malaysia.

Journal of Construction Engineering and

(24)

109

O’Connor J.T. and Davis, V.S. (1988). Constructability Improvement During Field

Operations.

Journal of Construction Engineering and Management

. ASCE.

114(4):548-563.

O’Connor, Tamer El-Diraby. (2000). Urban Freeway Reconstruction Planning: Case of

Mockingbird Bridge.

Journal of Construction Engineering and Management

, ASCE,

Vol. 126, No.1, 61-67.

Philip, Gambatese, James. (2005). Assessing State Transportation Agency

Constructability Implementation.

Journal of Construction Engineering and

Management

, ASCE, Vol. 131, No.5, 569-578

Rosli Mohamad Zin (2004).

Constructability Improvement of Project Design

. Dept of

Civil Engineering, UTM, Johor, Ph.D. Thesis.

Russell, J.S. and Gugel, J.G. (1993). Comparison of Two Corporate Constructability

Program.

Journal of Construction Engineering and Management

. ASCE. 119(4):

771-785.

S.L. Hon, D.A. Gairns, O.D. Wilson. (1988). Buildability: A Research and Practice.

Australian Institute of Building Papers.

Stuart, Fisher, Suhel. (1998). Integrating Constructability Into Project Development: A

Process Approach.

Journal of Construction Engineering and Management

, ASCE,

Vol. 126, No.2, 81-88.

Stuart, Fisher, Suhel. (1999). Constructability Issues In Highway Projects.

Journal of

Construction Engineering and Management

, ASCE, Vol. 15, No.3, 60-68.

Thomas E. Glavinich. (1995). Improving Constructability During Design Phase.

Journal

Figure

Figure 1.1 Research Methodology Chart

References

Related documents

With a better understanding of the data and information being held by Geoscience Australia, it is possible now to rationalise these datasets and move towards achieving a Single

A child task must only depend on concrete refer- ences (i.e. objects that already exist) or future refer- ences to the outputs of tasks that have already been spawned (i.e. objects

Note: Technicians who possess a single FAA mechanic certificate rating (Airframe or Powerplant), and are participating in this program to pursue an additional rating, are not

Farrens, “Techniques for Extracting Instruction Level Parallelism on MIMD Architectures”, Proceedings of the 26th Annual International Symposium on Microarchitecture, Austin,

Forecasts o f 2-m temperature can be improved by initializing with observed soil moisture and by replacing Johansen's 1975 parameterization o f soil thermal conductivity in

Dalam makalah ini akan disampaikan cara penentuan nilai ketidakpastian pada material magnet permanen dengan alat ukur permagraph dengan menggunakan evaluasi tipe A

Although temporal correlation degree does not impact the average job slow down greatly, we feel that it may affect the performance of individual jobs because the same job may be

On 7 May 1823, a year and three months after the declaration of unification and three years before the promulgation of the Code Rural, the juez de paz of the commune of Higüey