• No results found

Cesc Cable Joints

N/A
N/A
Protected

Academic year: 2021

Share "Cesc Cable Joints"

Copied!
15
0
0

Loading.... (view fulltext now)

Full text

(1)

 Analysis of HT cable

 Analysis of HT cable

and joint failures

and joint failures

and associated

and associated

design modifications

design modifications

 Authors:

 Authors:

K. Rana,

K. Rana,

Manager (Jointing), CESC Ltd.

Manager (Jointing), CESC Ltd.

B. Dasgupta,

B. Dasgupta,

Mains Engineer,CESC Ltd

Mains Engineer,CESC Ltd

CESC Ltd , in existence since 1897, CESC Ltd , in existence since 1897,

generates and distributes electricity to the generates and distributes electricity to the twin cities of Calcutta and Howrah on either twin cities of Calcutta and Howrah on either side of river

side of river Hooghly spanning over an areaHooghly spanning over an area of 567 sq. km, serving a

of 567 sq. km, serving a demand of 1657demand of 1657 MW. It is now

MW. It is now a RP-Sanjiv Goenka groupa RP-Sanjiv Goenka group company.

company.

Both the cities being highly congested, need Both the cities being highly congested, need was felt from the early days for

was felt from the early days for

underground transmission and distribution underground transmission and distribution on preference to

on preference to cheaper overhead optioncheaper overhead option because of greater way leave requirement because of greater way leave requirement of overhead lines. We presently have 4950 of overhead lines. We presently have 4950 ckt kms of 6/11KV cable network with a ckt kms of 6/11KV cable network with a consumer base of 1673 HT and 2.49

consumer base of 1673 HT and 2.49 millionmillion LT consumers.

LT consumers.

This paper discusses the cable and joint This paper discusses the cable and joint fault analysis which is regularly conducted fault analysis which is regularly conducted in our system consequent to faults. All new in our system consequent to faults. All new  joint failures and XLPE C

 joint failures and XLPE Cable failures in runable failures in run are analyzed in stages to identify the

are analyzed in stages to identify the rootroot cause of such failure. The observations cause of such failure. The observations regarding failure and statistical analysis of  regarding failure and statistical analysis of 

trends are used to as a tool

trends are used to as a tool to developmentto development of our cable construction and joint design. of our cable construction and joint design.

Why cables fail?

Why cables fail?

Power cables are manufactured in

Power cables are manufactured in factoriesfactories under controlled environment and

under controlled environment and sophisticated online monitoring. The sophisticated online monitoring. The completed cables are further tested completed cables are further tested according to standard testing guidelines according to standard testing guidelines before acceptance for use.

before acceptance for use.

However, the cables laid at site may not However, the cables laid at site may not deliver the required performance due to deliver the required performance due to adverse installation conditions and

adverse installation conditions and

unintentional damage during cable laying. unintentional damage during cable laying. Jointing is required to be done at

Jointing is required to be done at site of site of  installation where the trench is often installation where the trench is often

infested with dust, moisture, vibrations etc. infested with dust, moisture, vibrations etc. these unavoidable factors can be

these unavoidable factors can be

detrimental for a high tension cable joint detrimental for a high tension cable joint which requires a clean environment for which requires a clean environment for manufacture. Human factors are also manufacture. Human factors are also present in jointing as the job is done present in jointing as the job is done

manually. Though joints are always done by manually. Though joints are always done by trained and experienced jointers of 

trained and experienced jointers of 

sufficient reliability, human error can creep sufficient reliability, human error can creep in which is unavoidable.

in which is unavoidable.

Furthermore, a joint is a weakest part of an Furthermore, a joint is a weakest part of an underground cable system owing to the 3 underground cable system owing to the 3 types of stresses which are predominant in types of stresses which are predominant in  joint. These are the th

 joint. These are the thermal stress (causedermal stress (caused mainly by the externally applied insulation mainly by the externally applied insulation build up and joi

build up and joint encapsulation), electricalnt encapsulation), electrical stress (caused mainly due to termination of  stress (caused mainly due to termination of  cable screen in high tension cables) and cable screen in high tension cables) and mechanical stress (as the conductor jointing mechanical stress (as the conductor jointing region is more prone to stress

region is more prone to stress and strainand strain during normal cable loading and

during normal cable loading and

development of transient overcurrent development of transient overcurrent

(2)

during fault conditions superimposed on daily and annual temperature variations).

Types of failures

Most of the failures that occur in cable system have a cause that is well known. For instance, failures due to digging activities of  other utilities which damages our cable or due to ageing of older

components(eg.Insulation or metallic sheath) at their end of life. If we study the type of failures keeping in mind the basic cable construction, then we categorize the failure along following line:

a) In conductor : Most found in joints at the conductor connection points b) In insulation : In joint or cable and

mostly related to ageing

c) In sheath (metallic or non-metallic): Mostly in cable and generally it is not the ultimate cause but always the incipient one.

Failures in insulation of cables and

accessories are mostly related to ageing and typical basic ageing processes are:

 Thermal breakdown  Partial discharge  Electrical treeing  Water treeing 

Thermal breakdown:

It is a very common form of breakdown in cable insulation. Generally a thermal breakdown is recognized by:

 The breakdown channel

is radial.

 There is typical burning

smell from the breakdown zone. Thermal breakdown occurs when rate of  energy and heat transfer to insulation material as a result of electric field exceeds the rate of heat dissipation and absorption. This type of breakdown is therefore not common in XLPE cables but if the properties of insulating material are quite inferior then there is always possibility of such failure.

Electrical breakdown:

Electrical breakdown in polymeric cables can occur due to treeing. Treeing is a phenomenon occurring in polymer insulated cables in 2 forms:

Electrical treeing:

In high tension cables (11KV and above), the

voltage stress appearing across cable insulation is considerably high. Every precaution is taken in cable factories so that the

polymeric insulation is free from voids, impurities,

(3)

semicon protrusions etc. However, in real life, it is not possible to design a 100% void and impurity free cable insulation. The voids and impurities are region of  localized discharge and heating which ultimately develops into a carbonized path in the insulation. Formation of carbonized pockets cause the effective insulation thickness to reduce and develop a carbonized conducting tracking path which ultimately results in

dielectricbreakdown(Fig : 1).

Water treeing:

Polymeric insulations are

hygroscopic to some extent. The seepage of moisture through the cable sheath can percolate through the insulation(Fig : 2). The water molecules get charged as the conductor acts as cathode and the screen as anode. The charged water molecules travel through the

insulation from the earthed screen towards the live conductor via insulation by a process called electrophoresis.

(Fig : 2)

(Fig : 1)

Water causes conducting path through the insulation resulting in dielectric failure in the long run unlike electrical treeing, water treeing is a very slow process which develops over a long period of time. Different seamless water barrier tapes and extruded metallic sheaths are used in cable to provide “water tightness” to the cable.

 Ageing:

The term ‘ageing’ is used for old PILC cables in service for more than 50 years. Ageing is the natural degradation of the cable

insulation caused by various reasons. The major reason of ageing in PILC cables is the cyclic overloading. Overloading heats up the paper insulation causing the impregnation oil to dry up. Dry paper insulation greatly hampers the dielectric strength of the same which is often sufficient enough to cause breakdown.

The quantity of paper degrades over a period of time as it is made up of cellulose.

(4)

This phenomenon along with drying of  impregnating oil can cause failure. The Lead sheath of the cable reacts with the

chemicals present in the soil and gets corroded over a period of time. This can cause seepage of moisture into the paper insulationand subsequent breakdown of the cable dielectric.

Our experiences

Now we will focus on our experiences regarding cable faults. Our primary high tension network comprises of 6 and11KV and Sub transmission voltage of 33KV. We are recently installing 3 core XLPE insulated cables in our primary distribution network and single core XLPE cables for 33 KV networks.

We have 3 types of 33KV Grade cables existing in our system:

• PILC Cables (3 core H Cables and Single core ‘HSL’ type cables

• XLPE CABLES (Single core only)

• Gas Filled PILC Cables 6/11KV Grade cables:

 PILC belted cables (both

Aluminum and Copper conductors)

 XLPE cables (3 core

aluminum conductors)

We are using only XLPE cables in all voltage grades now but we still have a large part of  our existing network comprising of PILC

cables and few Gas filled cables (33KV). Due to the above reason, we often require to  join our and existing PILC cables to maintain

network continuity mainly during cable breakdowns. It is our observation that these ‘transition joints’ is more prone to fault. The  joint is designed to suit our requirements.

6/11KV Joint 

failures

The major areas of fault as observed in our system in a 6/11KV straight through joint and terminations are discussed below:

The continuity of the lead sleeve

with the PILC cable lead sheath:

In our transition joint design we have a lead sleeve prepared at site by beating up a rectangular flat lead sheet to size, to

encapsulate the joint. The earth continuity of the joint is ensured by a tinned copper braid of suitable size, connected to the armour wire of XLPE cable with jubilee clips and solder tacked on to lead sleeve of the  joint. The lead sleeve is plumbed on to the

sheath of PILC cable and provides actually a hermetic sealing on the PILC side of the  joint which is most vulnerable to moisture

ingress(Fig : 3).

(5)

The region of contact of the lead sleeve with the PILC lead sheath is of crucial importance. Insufficient application of  plumbing metal or inappropriate

workmanship during plumbing can pose high resistance to the earth fault current due to any fault in downstream network. Repetitiveoccurrence can melt the plumb and allow subsoil water to enter the belt paper insulation beneath and cause

dielectric failure (Fig : 4 and 5). Most of our failures in transition joint have been

attributed to the failure of paper insulation near the crutch region due to moisture ingress.

The above pie chart shows the percentage of fa ilure of transition joints for various reasons in our system.

(Fig : 4)

(Fig : 5)

The above 3 pics show failure of XLPE-PILC transition joints from the plumb region.

Crutch region of the PILC Cable

PILC Cables existing in our system are mostly aged and as a result the strength and durability of the paper insulation has degraded over the period of long service. The oil impregnation of the paper can also get partially dried making the paper brittle. During breakdown repair jobs, we need to  join these old PILC Cables with new XLPE

Cables.

(6)

Handling of the old PILC Cables during aligning for jointing is therefore of an extremely skillful task to avoid cracking of  paper insulation at the crutch region which is most mechanically stressed. Bad cross in PILC cores and damage to paper during core handling can cause phase-to phase short at the crutch region which is in turn most electrically stressed also(Fig : 6).

Conductor jointing region:

The next most fault prone portion of our  joint is the ferrule zone. In Al-Al conductor  jointing in 6/11KV, we employ crimping

technique using ratchet type crimping tool. Failure from crimping area has been mostly due to unacceptable gap between

successive crimps and incorrect crimping sequence resulting in inadequate cold flow of the metal inside the ferrule (Fig : 7). On dissecting such poorly crimped ferrules, we have found voids inside the ferrule and consequent radial failure during heating under load cycle(Fig : 9).

(Fig : 7)

(Fig : 9)

(Fig : 8)

However, some of our existing PILC Cables have Copper Conductors. We employ solder basting technology using weak back Copper ferrule for jointing the same with Aluminum conductors. It is necessary to ensure that the conductor jointing region has low resistivity in order to allow smooth flow of  current across it.

Insulation build up:

In our 6KV and 33KV joints, failure at

conductor joint region was also observed in our design in hand applied polymeric

insulating tape. Analysis of faulty joints reveled that failure in all cases have

occurred from the edge of the ferrule. The root cause behind the failure was improper

(7)

insulation build up profile. The insulation build up on ferrule was done by hand applied self-amalgamating insulating tape over the conductor jointing region. The varying tension of hand applied insulating tape can cause insufficient thickness of  build up at some places over the ferrule(Fig : 10). Dielectric breakdown occurs from the region of minimum insulation build up which is usually at the edge of ferrule(Fig : 11).

Correct procedure of tape buildup: ~

1.6 times the insulation thickness on

cable

Wrongprocedure of tape build up

(Fig : 11)

(Fig : 10)

A typical failure due to inadequate tape build up thickness at the edge of the ferrule

Improper core disposition:

Fault can also develop in transition joints where the cores can be in contact with the metallic lead sleeve at earth potential due to improper disposition of the cores as shown in the diagram below:

(8)

XLPE Insulation and Insulation

screen cut region

The extruded XLPE insulation screen is required to be removed up to a

predetermined distance away from the insulation cut as specified by the joint manufacturer in order to provide the necessary safe creepage distance. The screen cut region is a region of high electric stressand improper termination of screen and inadequate stress control can cause high partial discharge inside the joint.

Void filling high permittivity mastics applied at the screen cut point

Accidental nick on exposed portion of XLPE insulation or semicon screen can cause concentration of high electrical stress at the nick point and resultant dielectric failure may occur within a short period of time due to electrical treeing. The picture below depicts such a breakdown which was

probably caused for the above reason (Fig : 12 a and Fig : 12 b).

(Fig : 12 a)

(Fig : 12 b)

A typical fault due to inadequate

stress control at screen cut region

Failure at termination:

The major fault prone areas of a XLPE and PILC Termination are:

• The conductor Jointing region • Semicon screen cut region

(9)

• The contact region of the lug

with the dropper or stud

• Earthing region

(Fig : 13) Failure at semicon screen cut region

The reason of failure due to improper conductor jointing is the same as explained above in straight through joints. In

termination joints, it is important to ensure sufficient surface area of contact between the palm of the lug and the surface onto which it is connected. In our system, it is often required to fit the lug made of  Aluminum with Copper droppers or studs. In that case, use of bimetallic washer is absolutely essential.

33KV Joint failures

In our 33KV system, we have observed fault at the following regions of joint:

Region of armour connection

 In an XLPE – XLPE single core

straight through joint, the subsoil water can enter the cable sheath due to improper joint encapsulation. The water can easily travel through the Copper Earth braid inside the  joint used for armour continuity by

capillary action. The water readily oxidizes the Aluminum armour wires and the Poly Al sheath. This

phenomenon is accelerated due to the cumulative heating of the screen wires resulting from the continuous flow of circulating current as both ends of the cable screen are solidly earthed.

 Due to oxidation of the Al screen

wires, the effective electrical cross sectional area of the armour gets reduced causing continuous over heating of the same which in turn facilitates further oxidation.

Moreover, use of spring band of  different metal at this region to make armour and Poly Al

connectivity has an inherent heating due to bimetallic contact of the two. This cumulative heating results in the thermal breakdown of insulation at this region (Fig : 14 a and Fig 14 b).

(10)

(Fig : 14 a)

(Fig : 14 b)

 It was also seen in some cases

that the spring band has lost its ‘constant pressure’ property over a period of time during breathing of the cable under varying load cycle. This has loosened the compression and causes heating at the point of  current transfer between

aluminum armour wires and the copper braid.

Failure at heat shrink PILC

terminations

 The impregnation of oil of the

paper insulation often oozes out due to the effect of gravity and breathing of the cable at

terminations. This causes drying of the paper insulation which in turn greatly hampers the

dielectric property of the same.

 This is specifically pronounced in

heat shrinkable outdoor type terminations in PILC cables.

Failures in cable

run

Apart from joint failures, fault also occurs in cable run for the following reasons:

Direct spiking:

-In a metropolitan city like ours, the route of  underground power cables are often shared with other utilities like telecommunication, municipal sewage or water supply works, civil construction works like road widening, pillar erection for flyover etc. This can cause accidental damage to the power cables laid undergrounddue to direct spiking during excavation. This problem is specifically pronounced in a city distribution network as in our case. Direct spiking by pickaxe, JCB or other metallic digging instruments is

therefore a common occurrence which is beyond anybody’s control.(Fig : 15 a and Fig:15 b)show typical direct spike cases.

(11)

(Fig : 15 a)

(Fig : 15 b)

Typical cases of direct spiking on XLPE cables

 After effect of spiking

Direct spiking can damage the cable but often that does not cause feeder tripping immediately if the penetration is not that serious. However, the damage meted out to the cable outer sheath and armour in case of PILC Cables can cause corrosion of Lead Sheath and provide path for moisture seepage into the paper insulation causing dielectric breakdown of the cable. XLPE cable can also fail in case of damage to screen or due to damage in armour as XLPE insulation is to some extent

hygroscopic.(Fig : 16)

(Fig : 16)

Improper cable laying

Deviation from standard installation

procedures can occur in some places due to hindrances on cable route like previously existing concrete construction,

communication cables etc. The inadequate depth of laying can increase the chance of  damage to the cable due to spiking or heavy vehicular movement above the cable.

 Ageing of cable

This is applicable in case of PILC Cables which are in service for more than 50 years in our system. Apart from the above

external reasons, failure of cable in run can also occur due to natural ageing. Ageing can be accelerated due to adverse installation conditionsand cyclic overloading. The dielectric strength of paper insulation can degrade due to irregular load pattern, frequent overloading with cables installed in soil having high thermal resistivity and bending the cable beyond the safe radius. Corrosion of Lead sheath can also occur due to presence of strong chemicals in soil

which can puncture the Lead sheath and allow subsoil water to enter the paper insulation.

(12)

Manufacturing defects

The cables manufactured in factory in controlled environment are always tested prior to acceptance according to Indian Standards for Acceptance Testing. However, defects can persist in cable like

discontinuity of screen, damaged insulation etc. These defects can generate into fault when the cable is placed in cyclic load.

 ____________________________________

Failure Analysis

The analysis of failures is done in stages to arrive at probable root cause of the failure. We do the following routine analysis to all our failures.

Information from fault site: the fault site is visited after occurrence of the fault. This visit is aimed to obtain relevant information which may guide us to identify the cause of  fault. The type of information includes:

 Installation conditions: The cable

installed at improper depth,

inadequate bend etc. can give rise to fault. The condition of soil is tested to estimate subsoil water level which may have entered inside the cable or joint during fault.

 Availability of tiles and side blocks:

The positioning of protective tiles which is usually placed on the laid up cable give us an indication of any underground excavation job which may have been carried out by some other agency in near pastand

ourcable could have been damaged in the process. Scattered tiles at the fault region indicate that some other agency has exposed our cable which strengthens the probability of cable damage by spiking.

 Local reports of fault

site:Information gathered from local residents near the fault zone often provide us important clues in fault analysis. They apprise us of any digging activity along the cable route in near past, frequency of 

occurrence of fault at the region etc.

 Load of traffic: In an urban

distribution network like ours, the heavy traffic frequency above the road often causes joints to vibrate under vehicular movement and can weaken the sophisticated areas of a high voltage joint.

Equipped with the information gathered from fault site, we investigate the following records pertaining to the faulty feeder:

o Load pattern of the cable

daily and annual

o Tripping history of the cable

section over a period of time

o Statistics of nature of fault

(fault in joint or in cable run etc)

At final stage, we conduct stage by stage dissection of the faulty piece at our

materials laboratory which is equipped with various testing equipmentand tools for this type of analysis. The different parts of the faulty piece are exposed with utmost care so as to preserve the proof of reason of  failure.

(13)

The following pictures show a stage by stage post mortem of a PILC cable fault in run. The individual cable components are separated and observed for clues of failure.

Stage 1

Stage 2

Stage 3

Stage 4

Stage 5

We arrive at probable cause of failure after summing up all the relevant information and prepare the final report for archiving and necessary actions.

Inference

Consequent to the above failures, we have come to the conclusion that failure of our high tension cables and joints are mainly occurring for the following reasons:

 Uneven thickness of hand applied

insulation build up on ferrule

 Ageing of old PILC cables

 Poor mechanical strength of outer

 jacketing of the cable.

 Inadequate conductor connection

due to improper crimping.

 Ingress of moisture inside the cable

and joints due to elevated subsoil water level

 Inadequate path for circulating

current flow in both ends bonded 33KV system.

 Migration of impregnating

compound in 33KV PILC terminations.

(14)

Remedial

Measures

The root causes of failures that were detected from our analysis of cable and  joint failures guided us in making the

following course corrections in our cable and joint design:

 We have phased out the taped type

XLPE joint design and incorporated heat shrink technology in all our high tension jointing system.

 Crimping is to some extent

dependent on manual skill where equal spacing requires to be kept. Therefore in order to arrest failures at ferrule region due to bad

crimping, we have introduced shearing bolt connector at 33KV level.

 We have ceased to use Poly Al

sheathed cables in our 33KV system and proportionately increased the number and cross sectional area of  the armour wires to compensate reduction in area of Poly Al. In our modified joint design, the armour continuity is being done using aluminum connector which has not only eliminated the bimetallic effect of the spring band but also reduced the number of junctions in the path of the flow of the circulating current. In the process we have done away with Copper braid which was

responsible for ingress of moisture

inside the joint when the

encapsulation was not proper. We have also selectively gone for single end bonding with the other end earthed through SVL for long circuits lengths where the sheath circulating current are considerably high. For short circuit lengths where the sheath induced voltage is within limits we have gone for single end bonding.

 We have identified the repetitive

spike prone cable routes and replaced the same as far as

practicable to minimize the number of cable breakdowns caused due to the presence of innumerable joints in between a small cable length and thereby reducing chances of failure.

 Our 11KV grade cables had

previously PVC as outer sheath material which was subsequently changed to HDPE owing to its tough and rigid property in view to protect the cable components from spiking. It is also stressed upon to adhere to the installation protocols of HT cables regarding depth and protection by tiles to minimize chance of direct spiking.

(15)

Conclusion

Post mortem of fault is always a probable assumption of the cause of failure as the direct evidence for the failure is often disappeared in the flashover occurred during the fault. This makes confident reconstruction of failure difficult as most important clues are often lost. In this paper we have tried to explain how failure

analysis of joints and terminations help us to establish the most probable cause of  failure and subsequently give us a direction in which future modifications of cable and  joint designs should be carried out to

prevent such failures.

However, a more futuristic method would be an analysis which can detect a failure before It actually occurs, thereby ensuring that all the evidences of the root cause which is responsible for the imminent failure are still alive. We in CESC are now trying to preempt failures using state of the art Condition Monitoring equipments which detect abnormal hot spots, partial

discharges occurring in the joints and terminations while they are in service. Any abnormalities detected in any joint or termination is further analyzed after

arranging a planned shutdown to ascertain the root cause and take necessary

corrective measures. This technique not only helps us to avert possible shutdown or blackouts associated with joint or cable breakdown but also helps us to pinpoint the root cause more accurately.

References

Related documents

The qualitative data revealed that despite the inadequacy and challenges of implementing WLBS in place in the manufacturing firms, the employees are able to cope with work and

The proposed procedures are based on the formation of an ion-pair complex between the drug and BPB, and the complex was either extracted into chloroform and

The relationship between the extent of accounting disclosures and the outcome of analysts’ work has been established in that the dependent variable is the revisions or changes

Capital Market Authority (CMA) was established by an Act of Parliament in 1996 to regulate and promote the development of capital markets in Uganda. One of the

[r]

If the converter A changes the switching frequency to 30 kHz, the common DC bus voltage ripple will have 30 kHz component (as shown in fig 3.b). If the converter B and C can

Applications pending board approval depending on the decision for their out of state school Number 1 and 3 were tabled until the sub-committee could review the out of state

More recently, the Council of Sales Promotion Agencies offered a somewhat broader definition: “Sales promotion is a marketing discipline that utilizes a variety