Elevating Data Center & Mission Critical Energy
Efficiency
8/14/2014 AGRION.ORG 1
August 13
th, 2014 10:00am –11:30am
Panelists:
Jeff Schnitzer, GE Critical Power, General Manager
Mark Acton, CBRE Norland, Critical Product Director
Joe Higgins, Fidelity Investments, VP Engineering & Corporate Sustainability Officer
Adam Early, P.E., Goldman Sachs, Vice President, Critical Systems & Engineering
Paul G. Hines, Sentinel Data Centers, Vice President Data Center Operations & Engineering
Robert E. McFarlane, Shen Milsom & Wilke LLC, Principal (Moderator)
Robert E. McFarlane
Data Center Design Principal
Shen Milsom & Wilke
Background & Achievements
•
International Integrated Technologies Consultants
•
Practices in Acoustics, Telecommunications, Multi-Media, Security, Medical
Equipment Planning and Data Center Design
•
Member of ASHRAE, BICSI, The Green Grid and Uptime Institute
•
Serve on ASHRAE TC 9.9
•
Chairman of ASHRAE Handbook Committee – Chapter 19 – “Data Centers”
•
Voting Member of ASHRAE SPCC 90.4 Data Center Efficiency Standards Committee
•
Adjunct Professor – Marist College: Data Center Facilities Course
•
Lead the effort to construct and commission a Remote NOC and contingency
trading floors for the NYSE and AMEX immediately following 9/11
•
Executive responsible for the design and construction of the NYSE data center in
Mahwah
•
Executive responsible for the design and construction of Sentinel data centers in
NJ and NC.
University of Hawaii
Manoa Campus – Honolulu
Mark Acton
Critical Product Director
CBRE Norland
6
Eur Ing Mark Acton
Critical Product Director -
CBRE Data Centre Solutions
Formerly:
•
Director of the Uptime Institute in
EMEA.
•
Data Centre Consultant at Intel
Solution Services
•
UK Operations Director, Global Switch
•
VP, Microsoft Service Delivery, Cable
& Wireless / Exodus Inc.
•
Director, Global Data Centre
Operations, Digital Island Inc.
7
•
Chairman of European Union Code of Conduct for Data Centres Best
Practice Committee
•
Member of BSI Technical Committee TCT/7/3 (EN 50600 - CENELEC
TC 215 WG3)
•
Member of BSI Technical Committee IST/46 (ISO/IEC 30134 series of
standards for data centre resource efficiency KPIs - ISO/IEC JCT1
SC39 WG1)
•
Committee member of BCS Data Centre Specialist Group
Paul G. Hines
Vice President
Data Center Operations and Engineering
Sentinel Data Centers
Notable Achievements
• Maintained full operation of the NYSE data center(s)
during the Perfect Storm of 1991
• Lead the effort to construct and commission a
Remote NOC and contingency trading floors for the
NYSE and AMEX immediately following 9/11
• Executive responsible for the design and
construction of the NYSE data center in Mahwah
• Executive responsible for the design and
Jeff Schnitzer
General Manager
GE Critical Power
Jeff Schnitzer
General Manager
Mechanical Engineer
20 years with GE
End-to-End Power Solutions
for the Building, Box and Board
Innovative solutions
CoreSpace
Powering New Quality and Efficiency
HP Meeting the Demand for 2.7 Zettabytes
of New Data
Distributed Power
Power direct to the rack
Telecom
DC Power for Central Office and Cell Sites
Adam Early
Vice President, Critical Systems & Engineering -
Americas
Goldman Sachs LEUP Participation Summary:
Year Eligible Maximum Incentive
Incentive Received, Actual(A), Estimate(E)
Project Cost, Actual(A), Estimate(E)
Measured Performance
Estimated Cost Avoidance, Measured(M), Estimate(E)
Payback Actual(A), Estimate(E)
2011 $419,080 $419,080(A) $1,246,293(A) 2,028,300 kWh***
$754,500 (A) 1.3 (A) vs 1.86 (E) 2012* $423,750 $357,608(A) $637,000(E) 754,005 kWh
****(E)
10%(M) vs 8%(E) 3.13 (E) 2014** $595,913 TBD TBD TBD TBD TBD
The Large Energy Users Pilot Program (LEUP) is an energy efficiency incentive program sponsored by New Jersey’s Clean Energy Program (NJCEP)
* This project is currently underway ** The 2013 program was incorporated into the 2014 Program
*** Includes 170 kW of increased Tech load **** Chiller hours vary and a full year is needed to calculate actuals
LEUP 2011
Project – 96 VFD’s on CRAC units & Cold Aisle Containment in 2 Fileds at CDC. Project was implemented in stages from 8/13 – 12/13.
Measured Performance – Actual Electrical consumption was reduced ~ 1,538,700 kWh with an increased Tech Load of 170 kW (~489,600 kWh).
Site Implementation Cost Energy Savings (kWh) Energy Cost Avoidance Simple Payback Incentive Final
Payback ECM's Included
CDC $743,950 2327721 $283,982 2.62
Warehouse lighting LED retrofit
CRAC VFD's
Chilled Water Pumps VFD's
Partial free cooling Plant 1
Chiller plant optimization
BDC $1,309,410 1305405 $164,481 7.96
Warehouse lighting LED retrofit
Cold Aisle containment
Partial free cooling
30H $88,740 932296 $141,709 0.63 CRAC VFD retrofit
Total $2,142,100 4565422 $590,172 3.63 $595,913 2.62
The above has been submitted for review and the total incentive values will be provided following evaluation.
• LEUP 2012
• Project – 6 VFD’s on chillers at the CDC. Project started 5/14 and is underway with 3 of the 6 VFD’s completed.
• Savings results of a single chiller was measured at commissioning (before and after VFD
installation) to have 26 kW less consumption at identical loads. This represents approximately a 10% reduction in power and exceeded the estimated 8% reduction in power during original analysis.
• ROI calculated for project indicates pre-tax nominal payback of 3.15 years. Initial measurements indicate project is on track to exceed expected payback.
Carteret Data Center
1.66 1.68 1.70 1.72 1.74 1.76 1.78 1.80 1.82 1.84 1.86 N ov -1 1 De c-11 Ja n-12 Fe b-1 2 M ar -1 2 A pr -1 2 M ay -1 2 Ju n-1 2 Ju l-1 2 A ug -1 2 Se p-1 2 O ct -1 2 N ov -1 2 De c-12 Ja n-13 Fe b-1 3 M ar -1 3 A pr -1 3 M ay -1 3 Ju n-1 3 Ju l-1 3 A ug -1 3 Se p-1 3 O ct -1 3 N ov -1 3 De c-13 Ja n-14 Fe b-1 4 M ar -1 4 A pr -1 4 PUE (12 Month) PUE (12 Month) PUE Linear Trendline
Bridgewater Data Center
1.34 1.36 1.38 1.40 1.42 1.44 1.46 1.48 1.50 1.52 1.54 1.56 N o v-1 1 De c-11 Ja n -1 2 Fe b -1 2 M a r-12 A p r-1 2 M a y-1 2 Ju n -1 2 Ju l-1 2 A u g-1 2 Se p -1 2 O ct -1 2 N o v-1 2 De c-12 Ja n -1 3 Fe b -1 3 M a r-13 A p r-1 3 M a y-1 3 Ju n -1 3 Ju l-1 3 A u g-1 3 Se p -1 3 O ct -1 3 N o v-1 3 De c-13 Ja n -1 4 Fe b -1 4 M a r-14 A p r-1 4 M a y-1 4 PUE (12 Month) PUE (12 Month) PUE Linear Trendline