• No results found

Elevating Data Center & Mission Critical Energy Efficiency

N/A
N/A
Protected

Academic year: 2021

Share "Elevating Data Center & Mission Critical Energy Efficiency"

Copied!
19
0
0

Loading.... (view fulltext now)

Full text

(1)

Elevating Data Center & Mission Critical Energy

Efficiency

8/14/2014 AGRION.ORG 1

August 13

th

, 2014 10:00am –11:30am

Panelists:

 Jeff Schnitzer, GE Critical Power, General Manager

 Mark Acton, CBRE Norland, Critical Product Director

 Joe Higgins, Fidelity Investments, VP Engineering & Corporate Sustainability Officer

 Adam Early, P.E., Goldman Sachs, Vice President, Critical Systems & Engineering

 Paul G. Hines, Sentinel Data Centers, Vice President Data Center Operations & Engineering

 Robert E. McFarlane, Shen Milsom & Wilke LLC, Principal (Moderator)

(2)

Robert E. McFarlane

Data Center Design Principal

Shen Milsom & Wilke

(3)

Background & Achievements

International Integrated Technologies Consultants

Practices in Acoustics, Telecommunications, Multi-Media, Security, Medical

Equipment Planning and Data Center Design

Member of ASHRAE, BICSI, The Green Grid and Uptime Institute

Serve on ASHRAE TC 9.9

Chairman of ASHRAE Handbook Committee – Chapter 19 – “Data Centers”

Voting Member of ASHRAE SPCC 90.4 Data Center Efficiency Standards Committee

Adjunct Professor – Marist College: Data Center Facilities Course

Lead the effort to construct and commission a Remote NOC and contingency

trading floors for the NYSE and AMEX immediately following 9/11

Executive responsible for the design and construction of the NYSE data center in

Mahwah

Executive responsible for the design and construction of Sentinel data centers in

NJ and NC.

(4)

University of Hawaii

Manoa Campus – Honolulu

(5)

Mark Acton

Critical Product Director

CBRE Norland

(6)

6

Eur Ing Mark Acton

Critical Product Director -

CBRE Data Centre Solutions

Formerly:

Director of the Uptime Institute in

EMEA.

Data Centre Consultant at Intel

Solution Services

UK Operations Director, Global Switch

VP, Microsoft Service Delivery, Cable

& Wireless / Exodus Inc.

Director, Global Data Centre

Operations, Digital Island Inc.

(7)

7

Chairman of European Union Code of Conduct for Data Centres Best

Practice Committee

Member of BSI Technical Committee TCT/7/3 (EN 50600 - CENELEC

TC 215 WG3)

Member of BSI Technical Committee IST/46 (ISO/IEC 30134 series of

standards for data centre resource efficiency KPIs - ISO/IEC JCT1

SC39 WG1)

Committee member of BCS Data Centre Specialist Group

(8)

Paul G. Hines

Vice President

Data Center Operations and Engineering

Sentinel Data Centers

(9)

Notable Achievements

• Maintained full operation of the NYSE data center(s)

during the Perfect Storm of 1991

• Lead the effort to construct and commission a

Remote NOC and contingency trading floors for the

NYSE and AMEX immediately following 9/11

• Executive responsible for the design and

construction of the NYSE data center in Mahwah

• Executive responsible for the design and

(10)

Jeff Schnitzer

General Manager

GE Critical Power

(11)

Jeff Schnitzer

General Manager

Mechanical Engineer

20 years with GE

End-to-End Power Solutions

for the Building, Box and Board

(12)

Innovative solutions

CoreSpace

Powering New Quality and Efficiency

HP Meeting the Demand for 2.7 Zettabytes

of New Data

Distributed Power

Power direct to the rack

Telecom

DC Power for Central Office and Cell Sites

(13)

Adam Early

Vice President, Critical Systems & Engineering -

Americas

(14)

Goldman Sachs LEUP Participation Summary:

Year Eligible Maximum Incentive

Incentive Received, Actual(A), Estimate(E)

Project Cost, Actual(A), Estimate(E)

Measured Performance

Estimated Cost Avoidance, Measured(M), Estimate(E)

Payback Actual(A), Estimate(E)

2011 $419,080 $419,080(A) $1,246,293(A) 2,028,300 kWh***

$754,500 (A) 1.3 (A) vs 1.86 (E) 2012* $423,750 $357,608(A) $637,000(E) 754,005 kWh

****(E)

10%(M) vs 8%(E) 3.13 (E) 2014** $595,913 TBD TBD TBD TBD TBD

The Large Energy Users Pilot Program (LEUP) is an energy efficiency incentive program sponsored by New Jersey’s Clean Energy Program (NJCEP)

* This project is currently underway ** The 2013 program was incorporated into the 2014 Program

*** Includes 170 kW of increased Tech load **** Chiller hours vary and a full year is needed to calculate actuals

LEUP 2011

Project – 96 VFD’s on CRAC units & Cold Aisle Containment in 2 Fileds at CDC. Project was implemented in stages from 8/13 – 12/13.

Measured Performance – Actual Electrical consumption was reduced ~ 1,538,700 kWh with an increased Tech Load of 170 kW (~489,600 kWh).

(15)

Site Implementation Cost Energy Savings (kWh) Energy Cost Avoidance Simple Payback Incentive Final

Payback ECM's Included

CDC $743,950 2327721 $283,982 2.62

 Warehouse lighting LED retrofit

 CRAC VFD's

 Chilled Water Pumps VFD's

 Partial free cooling Plant 1

 Chiller plant optimization

BDC $1,309,410 1305405 $164,481 7.96

 Warehouse lighting LED retrofit

 Cold Aisle containment

 Partial free cooling

30H $88,740 932296 $141,709 0.63  CRAC VFD retrofit

Total $2,142,100 4565422 $590,172 3.63 $595,913 2.62

The above has been submitted for review and the total incentive values will be provided following evaluation.

• LEUP 2012

• Project – 6 VFD’s on chillers at the CDC. Project started 5/14 and is underway with 3 of the 6 VFD’s completed.

• Savings results of a single chiller was measured at commissioning (before and after VFD

installation) to have 26 kW less consumption at identical loads. This represents approximately a 10% reduction in power and exceeded the estimated 8% reduction in power during original analysis.

• ROI calculated for project indicates pre-tax nominal payback of 3.15 years. Initial measurements indicate project is on track to exceed expected payback.

(16)

Carteret Data Center

1.66 1.68 1.70 1.72 1.74 1.76 1.78 1.80 1.82 1.84 1.86 N ov -1 1 De c-11 Ja n-12 Fe b-1 2 M ar -1 2 A pr -1 2 M ay -1 2 Ju n-1 2 Ju l-1 2 A ug -1 2 Se p-1 2 O ct -1 2 N ov -1 2 De c-12 Ja n-13 Fe b-1 3 M ar -1 3 A pr -1 3 M ay -1 3 Ju n-1 3 Ju l-1 3 A ug -1 3 Se p-1 3 O ct -1 3 N ov -1 3 De c-13 Ja n-14 Fe b-1 4 M ar -1 4 A pr -1 4 PUE (12 Month) PUE (12 Month) PUE Linear Trendline

Bridgewater Data Center

1.34 1.36 1.38 1.40 1.42 1.44 1.46 1.48 1.50 1.52 1.54 1.56 N o v-1 1 De c-11 Ja n -1 2 Fe b -1 2 M a r-12 A p r-1 2 M a y-1 2 Ju n -1 2 Ju l-1 2 A u g-1 2 Se p -1 2 O ct -1 2 N o v-1 2 De c-12 Ja n -1 3 Fe b -1 3 M a r-13 A p r-1 3 M a y-1 3 Ju n -1 3 Ju l-1 3 A u g-1 3 Se p -1 3 O ct -1 3 N o v-1 3 De c-13 Ja n -1 4 Fe b -1 4 M a r-14 A p r-1 4 M a y-1 4 PUE (12 Month) PUE (12 Month) PUE Linear Trendline

(17)

Joe Higgins

VP of Engineering & Chief Sustainability Officer

Fidelity Investments

(18)
(19)

Digital Infrastructure - Breaking the Power Curve

2000

2014

Data Center

Power (KW)

50%

Power Cost Reduction from Business as Usual

2 Megawatts of IT Load

reduction since 2008

2008

References

Related documents

Circuit breaker solutions for higher available short-circuit currents either (a) use fully rated circuit breakers (each circuit breaker has an individual interrupting rating equal

Consequently, available indices may be grouped into meteorological, agricultural and hydrological and include the Decile Index, Percent of Normal Standardized Precipitation

Urbanization facilitates synanthropic species such as rodents, which benefit the diets of many preda- tors in cities. We investigated how urbanization affects the feeding ecology

49 It is the task of each institution’s physicists to create a treatment plan for each test case, irradiate a solid water stack in accordance with said treatment plan, measure

The teaching staff taking part in the SLI programme during the 2010-11 course taught the following subjects: Mathematics I; Architectural Drawing I; Descriptive

If the lab supply room has only 50% and 20% sulfuric acid solution on hand, how much of each should be mixed to obtain twelve liters of a 30% solution..8. If the total value is

into their host systems for mission critical data that requires fast access. This is particularly important in the mainframe space where most of the mission critical applications

SAFETY REIMAGINED ORCHESTRATE MANAGED & SUPPORT SERVICES VIDEO SECURITY & ANALYTICS MISSION-CRITICAL COMMUNICATIONS COMMAND CENTER SOFTWARE.. Safety, efficiency