• No results found

Rcc Sump Design

N/A
N/A
Protected

Academic year: 2021

Share "Rcc Sump Design"

Copied!
7
0
0

Loading.... (view fulltext now)

Full text

(1)

RCC SUMP DESIGN REFERENCE : 1. IS 456-2000. 2. IS 3370-2009 Part 1&2. 3. SP-16 -1978. DATA : Sump Size : 5.0m (L) X 2.0m(B) X 1.25m(H) Concrete Grade : For cover slab M20.

For Tank M25. Steel Grade : Fe 415

Unit weight of water : 10 KN/m3 Live Load for Cover slab 2 KN/m2 DESIGN:

DESIGN OF COVER SLAB: Slab size : 2.0m x5.0m L/B =5.0/2.0=2.50> 2.0

Hence the slab has to be designed as oneway slab. d required =2000/25 =80mm.

However from deflection point of view provide D=120mm d=120-20-10/2=95mm. Loads: Live Load =2.0KN/m2 Self weight 0.12x25 =3.0KN/m2 Finishing =1.0KN/m2 Total Load =6.0KN/m2 Effective span =2.0+0.095=2.095m Bending Moment =Wl2/8 = 6.0x2.0952/8 = 3.29 KN.m. Factored B.M. =4.94 KN.m. Mu.lim. =0.138 fck b d2 =0.138 x 20x 1000 x 952 =24.91 KN.m

Hence under reinforced section. K= Mu/b d2 =4.94 x106/1000 x 952 =0.55

From Table 2 of SP 16 pt =0.158 Ast= 0.158 x 1000 x 95 =150 mm2 100

Using 10mm bars spacing = ast x 1000 Ast

=78.5 x 1000 =523 mm 150

Max spacing limit to 3d (3x95=285) or 300mm whichever is less. Provide 10mm dia bars at 200mm C/c. (Ast provided=392.5mm2)

(2)

Distribution Steel :

Mini. Ast = 0.12 x 1000x 120 =144mm2 100

Using 8mm bars spacing = ast x 1000 Ast

=50 x 1000 =347 mm 144

Max spacing limit to 5d (3x85=430) or 450mm whichever is less. Provide 8mm dia bars at 200mm C/c.

Check for Deflection :

Actual span ratio = 2095/95 =22.05 d

For pt= 392.5 x 100 = 0.4132 1000 x 95

Max. Permissible Span ratio from Chart 23 of SP16 =25.20 > 22.05 d

Hence O.k.

DESIGN OF WATER TANK DESIGN OF SIDE WALL:

(3)

This has to be designed by Working Stress Method with the following permissible stresses to avoid leakage problem..Using M25 concrete and Fe415 (HYSD) steel

σ

cbc = 8.50N/mm2

σ

st=150 N/mm2 Design Constants: m=Modular ratio =280/3

σ

cbc = 280 =10.98 =11.00 3x8.5 n = m

σ

cbc = 11 x 8.5 = 0.384 m

σ

cbc+

σ

st 11x8.5+150 j= 1 – n = 1- 0.384/3 = 0.872 3 K = ½

σ

cbc n j =1/2 x 8.50 x 0.384 x 0.872 =1.423

The water tank has to be designed for the following two cases. 1) Tank is full and no earthfill outside.

2) Tank is empty and active earth pressure acting from outside.

(4)

Long Wall:

Ph = w xH=10 x 1.25 =12.5 KN/m2

Cantilever moment M= (1/2x12.5 x 1.25) x1.25/2=4.88 KN.m Ast = M/

σ

st x j = 4.88 x 106 =327 mm2

150x0.872x120

Using 10mm dia bars spacing required = = 78.5 x 1000 = 240 mm 327

Provide 10 mm bars at 150 mm C/c near inner face in vertical direction.

Horizontal bars in Long wall

Since long wall is predominantly acting as a cantilever, distribution steel is provided & checked for axial Tension when tank is full without earth

pressure from outside.

Mini. % of steel = 0.30 x 1000 x 150 = 450mm2 100

Using 10 mm bars spacing required = 78.5 x 1000 = 174 mm 450

Provide 10mm bars at 150mm C/c inside the face. Check for Direct Tension :

TL= w (H-h) B/2 = 10 x (1.25-1.0) 2.0/2=2.50KN,

Ast required = 2.50 x 103 = 17 mm2 150

Distribution steel takes care of this Tensile forces . Case 2: When Tank is empty

Ph =k 1 + wH where K= 1- sin = Φ 1-sin 30 =1/3 1+ sin Φ 1+ sin 30 1s= s- w =16-10=6 KN/m2 Ph= (1/3 x 6x 1.25) +(10x1.25) =15.0KN/m2 M=(1/2 x 15.0x HxH/3) =(1/2x 15.0 x 1.25x 1.25/3) =3.91 KN.m.

Depth of balanced section = sqrt M/k b = Sqrt 3.91 x 106 1.423x1000 =52.42mm

(5)

Ast required = M/ σst j = 3.91 x 106 150 x0.872x 128 =234mm2

Using 10mm bars spacing required = 78.5 x 1000 =335mm 234

Provide 10mm bats at 150mm C/c near inner face of the wall. DESIGN OF SHORT WALL :

Vertical reinforcement :

Cantilever action height for lower portion h= H/4 or 1m whichever is more =1m.

When water tank is empty and outside soil is saturated ph=(1/3x6x1.25)+(10x1.25)=15KN.m2 M= 1/2x15.0x1.0x1.0/3 =2.50KN.m Ast = M = 2.50 x 106 σst x j 150x0.872x128 = 129mm2

Direct compression due to load on 1m wide long wall P= 15.0 x (1.25-1.0) x1.0 =3.75 KN.

Concrete alone can resist if water tank is full and no earth fill. Ph= 10 x 1.25 =12.50KN/m2

M= ½ x 12.50 x 1.0x 1.0/3 =2.08 KN.m quite small.

Provide mini reinforcement in vertical direction which is 10mm at 150mm C/c

At Mid span :

B.M. is half of 2.08/2 =1.04 KN.m

Provide same reinforcement 10mm bars at 150mm C/c near outer face.

(6)

DESIGN OF BASE SLAB:

Assume thickness of base slab =200mm d = 200-50-12/2=144mm

Height from base slab =1.25+0.20=1.45m

Upward pressure when soil is saturated =10x1.45 =14.50 KN/m2 In bottom slab there is no projection.

Downward Loads:

Weight of top slab =0.12x5.30x2.3x25 =36.57KN. Weight of long wall =2x0.15x5.30x1.25x25 =49.69KN Weight of short wall =2x0.15x2.3x1.25x25 =21.56KN Weight of bottom slab =5.30x2.30x0.20x25 =60.95KN Total Load =168.77KN Uplift force on bottom slab= 14.50(5.30+2.30)=110.20KN

Since downward force is more than uplift force on bottom slab, projection is not required.

Provide 150mmx 150mm haunches at junction. Provide junction reinforcement 10mm bars at 150mm C/c.

Self weight of slab directly get transmitted to soil. Net upward soil pressure=(10x1.45)- (0.2x1x1x25) =14.50-5.0=9.50KN/m2

Bending moment:

Considering net upward pressure B.M.=9.50x2.152/8=5.49 KN.m

Considering weight of water alone B.M. =(10x1.25)x 2.152/8=7.22KN.m Considering higher moment,

Ast required = M = 7.22 x 106 σst x j 150x0.872x144

(7)

Minimum Ast = 0.3 x 1000x 200 = 600mm2 100

Using 12mm bars spacing = 113 x 1000= 188mm 600

Provide 12mm bars at 150mm C/c Distribution Steel:

Mini. Ast = 600mm2

Ast on each face =600/2 = 300mm2

Using 10mm dia bars spacing = 78.5 x 1000 300

Provide 10mm dia bars at 150mm C/c in longitudinal direction near both faces.

References

Related documents

This breadth of experience allowed me to recognise what was important to me when looking for a firm at which to complete my training contract. In particular, I hoped to be

The second stage aimed to help students identify the foci of an ellipse resulted from cutting the cone by using concrete manipulative based on Dandelin’s spheres and relate the foci

Polished and use these resume descriptions if you have a receptionist resume that ingenuity into your industry in your career accomplishments with your work as a diverse job.. Chef

BSI provides a wide range of information on national, European and international standards through its Library and its Technical Help to Exporters Service.. Various BSI

Results Customer Benefit Customer Training Number of people trained 1000 1500 5,275 Not Met 17403 2009 Prevent Terrorism and Promote the Nation s Security Mission and Business

19 Since the UK average value of in-vehicle time is calculated using data from urban as well as rural areas and therefore partially reflects substantially more congested

We chose the values of N based on the subjects’ average order quantities in simple revenue sharing and buyback contracts (benchmark experiments) in a way that the number of