True/False
Question: XYZ when combined with FSN analysis helps to classify non-moving items into XN , YN and ZN.
Correct Answer: True Your Answer True
Multiple Choice Single Answers
Question: Forecast is based
on:-Correct Answer: Past data Your Answer Competitor's market share Select the Blank
Question: Network ________ is defined as any adjustment to the arrow diagram which becomes necessary owing to departure from the project schedule laid down earlier.
Correct Answer: Updating Your Answer Design
Multiple Choice Single Answers
Question: For goods manufactured to stock, following department is expected to periodically undertake replenishment action as stocks are
depleted:-Correct Answer: Production Planning Control Your Answer Production Planning Control
True/False
Question: CPM marks critical activities.
Correct Answer: True Your Answer True
Select The Blank
Question: A shop order may combine more than one ________ requiring identical items.
Correct Answer: Work order Your Answer Sales order
Multiple Choice Single Answer
Question: What are the customer's expectation from the supplier?
Correct Answer: Consistent good quality of products Your Answer Consistent good quality of products
Select The Blank
Question: ________ inventories help to balance company's supply with market demand.
Correct Answer: Finished goods Your Answer WIP
Select The Blank
Question: Short term forecasts are for ________.
Correct Answer: Material Planning Your Answer Cash flow management Multiple Choice Single Answer
Question: For process planning following is one of the basic document used
:-Correct Answer: Operation Layout Your Answer Process Layout
Multiple Choice Single Answer
Question: Scheduled start of an operation is authorized by issuing a document called
:-Correct Answer: Job card Your Answer Route card Multiple Choice Multiple Answer
Question: SOS Analysis involves following type of items
:-Correct Answer: Seasonal items available only for a limited period. , Seasonal items available throughout the year. , Non-seasonal items whose quantity is decided on different considerations.
Your Answer Seasonal items available throughout the year. , Non-seasonal items whose quantity is decided on different considerations. , Machine spare parts
Multiple Choice Multiple Answer
Question: The basic procedure of assignment technique is designed to solve problems wherein
:-Correct Answer: Number of tasks equal to number of facilities. , The objective function is minimization. , There are no restrictions in allocation
Your Answer Number of tasks equal to number of facilities. , There are no restrictions in allocation , Cost of machine should be taken into consideration.
True/False
Question: There are five manufacturing systems. However, many manufacturers combines two or more systems to produce a final product.
Correct Answer: True Your Answer True
True/False
Question: In LOB, the regular progress checks the future effect of any current delays and indicates degree of urgency for corrective action.
Correct Answer: True Your Answer True
Multiple Choice Multiple Answer
Question: 5 jobs are to be processed on machines M1 and M2 , first on M1 and then on M2. The processing times in hours are
PAGE NO: 2 OF 17
as follows. Find the sequence for 5 jobs that will minimize total elapsed time .also find idle time & total elapsed time. Job
Processing time [ hours ] Machine M1 Machine M2 1 5 2 2 1 6 8 9 7 6 3 8 5 10 4
Correct Answer: 2-4-3-5-1 , Minimum time 28 hours , Idle time = 1 & 2 Hours for M1 & M2 respectively.
Your Answer Minimum time 28 hours , Idle time = 1 & 2 Hours for M1 & M2 respectively.
True/False
Question: When shop floor scheduling problem larger than 3 machines arise the analytical solution procedures leading to optimality are complex and difficult.
Correct Answer: True Your Answer True
Match The Following
Question: Correct Answer:Your Answer
End piece allowance Material insufficient to produce one piece Material insufficient to produce one piece
Stock allowance Quantity to meet requirement of spares Extra material requirement
Machining allowance Extra material requirementMaterial loss in handling
Spoilage allowance Process rejection Quantity to meet requirement of spares
Select The Blank
Question: ________ is required for machine set ups as well as regular production.
Correct Answer: Performance standard Your Answer Machine design data
Multiple Choice Single Answer
Question: If a product is required within 20 days and the product can be made available in 10 days, the Critical ratio would be
:-Correct Answer: 2 Your Answer 0.5
Multiple Choice Single Answer
Question: A subcontractor is
:-Correct Answer: Another form acting as a supplier Your Answer Manufacturer of specialized products on whom the buyer is dependent for 100% of requirement of main assembly
Multiple Choice Single Answer
Question: The data regarding maximum run out between centers pertains to
:-Correct Answer: Process planning Your Answer Raw material data True/False
Question: Lead time information is required for determination of safety stock.
Correct Answer: False Your Answer True
Select The Blank
Question: Americans like to use the word 'inventory' whereas for same context British use the term________.
Correct Answer: Stock Your Answer Stock
Multiple Choice Multiple Answer
Question: SDE analysis is employed by the purchase department for
:-Correct Answer: Contract buying for some of 'easy' items. , Forward buying of some of 'scarce' items. , Scheduled buying for some of 'easy' items.
Your Answer Forward buying of some of 'scarce' items. , Scheduled buying for some of 'easy' items. , Contract buying for some of 'easy' items.
True/False
Question: Labour efficiency factor is applied after capacity requirement of equipment is calculated.
Correct Answer: False Your Answer True
Multiple Choice Multiple Answer
Question: PERT terminology uses words like
:-Correct Answer: Network diagram , Events , Slack Your Answer Network diagram , Events
True/False
Question: The LOB technique is most appropriate for assembly operations involving number of distinct components.
Correct Answer: True Your Answer True
True/False
Question: Transit time for manufactured items should be considered only when it is insignificant.
Correct Answer: False Your Answer True
PAGE NO: 3 OF 17
Question: A progress card normally contains ________squares.
Correct Answer: Less than 25 Your Answer More than 50 Multiple Choice Multiple Answer
Question: Due to the following emergent events, the queue time has to compensate for the time for which the job has to undergo an extra time
:-Correct Answer: Tool breakage , Job split up , Change in priorities
Your Answer Tool breakage , Job split up , Store inventory Multiple Choice Single Answer
Question: One of the following is not an task of progressing
:-Correct Answer: Ensuring supply of material and issue of documents to manufacturing shops
Your Answer Expediting to rush up remaining operations of the delays jobs
Multiple Choice Single Answer
Question: Production output in night shift is
:-Correct Answer: Less than I shift production Your Answer More than I shift production Multiple Choice Multiple Answer
Question: The minimum requirements for application software for line balancing are as follows
:-Correct Answer: 1 Ghz processor , 1 Gb hard Disk free memory , Windows or equivalent operating system.
Your Answer 1 Gb hard Disk free memory , Windows or equivalent operating system.
Multiple Choice Single Answer
Question: The work measurement and time study belong to the following school of management
:-Correct Answer: Scientific School of management Your Answer Functional School of management Multiple Choice Multiple Answer
Question: Before planning subcontracting points to be considered are
:-Correct Answer: Whether overtime can be given , One more shift can be started
Your Answer Whether overtime can be given , One more shift can be started , Set up time can be reduced
Multiple Choice Multiple Answer
Question: The main requirements of re-order level system are as follows
:-Correct Answer: Incoming materials and materials returned from shop must be deposited in appropriate bins and their stock cards must be posted for "goods receipt report" and "material return note" for the quantities received physically . , Items should be issued in correct quantities. , The balance on the stock cards should be periodically tallied with physical stock.
Your Answer Incoming materials and materials returned from shop must be deposited in appropriate bins and their stock cards must be posted for "goods receipt report" and "material return note" for the quantities received physically . , Items should be issued in correct quantities. , The balance on the stock cards should be periodically tallied with physical stock.
Multiple Choice Multiple Answer
Question: The following are salient features of the fixed order quantity system
:-Correct Answer: Reorder quantity is always the same which is usually economic order quantity , The time interval between deliveries varies. , Replenishment action is initiated when the stock on hand is just sufficient to meet demand during the lead time.
Your Answer Reorder quantity is always the same which is usually economic order quantity , The time interval between deliveries varies. , Percent cumulative cost of item is taken into consideration.
Select The Blank
Question: ABC company manufactures MS bolts. Given fixed cost Rs 0.5 Lac, Labour cost Rs 2 Lacs, Raw Material cost Rs 3 Lacs, overhead cost Rs 0.5 Lacs. If bough from outside, the cost of buying is Rs 8 per piece. The firm uses 100000 MS bolts every year. Under these circumstances, the firm would take a decision to ________.
Correct Answer: Make at home Your Answer Buy from outside Multiple Choice Multiple Answer
Question: Following difficulties are faced by SDE analysis
:-Correct Answer: More delivery period , Geographical location of supplier , Reliability of suppliers
Your Answer More delivery period , Reliability of suppliers , Excise duty
Select The Blank
Question: For replenishment action for stock items which are reserved by PPC, the stores work out ________ stock which equals the stock on hand less stock reserved.
Correct Answer: Free Your Answer Net
True/False
Question: Route sheets for custom built job is prepared for each new order received.
PAGE NO: 4 OF 17
Correct Answer: TrueYour Answer True Match The Following
Question: Correct Answer:Your Answer
Order quantity Factor influencing process planningCompare alternative processes
Machine capacity chart Dimensional accuracy General purpose machines with special toolings
Mass production Special purpose machines Break even analysis Standard elemental time data Compare alternative processes
Factor influencing process planning
Multiple Choice Multiple Answer
Question: Following are some of the common standard cutting tools
:-Correct Answer: Cutting saw , Inserts , Reamers Your Answer Form tool , Inserts , Reamers
Multiple Choice Single Answer
Question: The Carrying cost is stated in terms of
:-Correct Answer: Per item per year Your Answer Per order
Select The Blank
Question: The definitive statement of policy stating when to procure and how much to procure usually to ensure that the sum of all costs associated with ________ are minimised is called Inventory policy.
Correct Answer: Inventory Your Answer Buying
Select The Blank
Question: Buying for C quantities should be made in ________ quantities .
Correct Answer: Large Your Answer Medium Select The Blank
Question: In the assignment model, the________ is formed between jobs and machines.
Correct Answer: Matrix Your Answer Matrix
Select The Blank
Question: ________ analysis mainly helps to identify non-existing items for which store keeps bin cards, wastes computer
memory or wastes computer stationary while preparing stores ledger.
Correct Answer: MNG Analysis Your Answer SOS Analysis
Multiple Choice Single Answer
Question: Why customer is called the king?
Correct Answer: Customer's orders gives us work Your Answer Gives satisfaction to workers
Multiple Choice Single Answer
Question: Negative value of critical ratio
:-Correct Answer: Is meaningless
Your Answer Indicates excess of scheduled delivery period Multiple Choice Multiple Answer
Question: The main characteristics of batch production are
:-Correct Answer: Short runs , Skilled labours in specific trade , Supervisor to posses knowledge of specific process
Your Answer Short runs , Skilled labours in specific trade , Supervisor to posses knowledge of specific process
True/False
Question: If lead time available is 11days and lead time required is 10 days, the critical ratio would be 1.10.
Correct Answer: True Your Answer True
Multiple Choice Multiple Answer
Question: What are the factor affecting decision about centralized planning system?
Correct Answer: Product variety is large , Jobbing and batch production methods of manufacturing , Work is less repetitive
Your Answer Product variety is large , Jobbing and batch production methods of manufacturing , Work is less repetitive
True/False
Question: In continuous or process production , only one product is manufactured.
Correct Answer: True Your Answer True
True/False
Question: The make-or-buy decision becomes necessary when the current source of supply is not able to supply the material in accordance with buyer's quality requirements.
Correct Answer: True Your Answer True
PAGE NO: 5 OF 17
Question: Work measurement function is attached to linemanagement.
Correct Answer: False Your Answer True
Multiple Choice Single Answer
Question: Placement of purchase orders in case of 'A' type of items is usually
:-Correct Answer: Frequent Your Answer Frequent
Match The Following
Question: Correct Answer:Your Answer
Economic order quantity Quantity at which there is neither overstocking nor under stocking. Quantity at which there is neither overstocking nor under stocking.
Carrying cost Cost of 'holding' the material in store Cost of transportation [carrying] of material
Procurement cost Administrative cost for procurement Cost of procurement of material
Inventory cost Sum of carrying and inventory cost Sum of carrying and inventory cost
True/False
Question: To solve "n jobs - 3 machines" sequencing problem, the largest of time of any job on the second machine must be smaller than or equal to the smallest time of any job on first machine or third machine.
Correct Answer: True Your Answer False True/False
Question: Systematic procedures must be set in the operating functions prior to installation of PPC in the firm.
Correct Answer: True Your Answer True
Select The Blank
Question: Time waste is the earliest of all wastes and yet the________ to correct because it does not litter the floor.
Correct Answer: Hazards Your Answer Big hazard Multiple Choice Single Answer
Question: If the annual usage of a material is 1200 units and the reorder point is at 120 Units, find the lead time.
Correct Answer: 4 months Your Answer 1.2 Months
Multiple Choice Single Answer
Question: Which factor influence plan for meeting seasonal or occasional increase in demand?
Correct Answer: Subcontracting Your Answer Subcontracting
Multiple Choice Single Answer
Question: Which of the following is the function of Production Planning?
Correct Answer: Process planning and scheduling Your Answer Progressing
Select The Blank
Question: Because of uncertainty of activity timings, PERT acquired a shape of ________ model.
Correct Answer: Probabilistic Your Answer Statistical
True/False
Question: Scientific inventory control system requires to be followed for machine aid, work aid and inspection aid
:-Correct Answer: False Your Answer True
True/False
Question: Job schedule is a chart showing work ahead of each machine with respect to time.
Correct Answer: False Your Answer True
Match The Following
Question: Correct Answer:Your Answer
Tooling cost Jigs and Fixtures Jigs and Fixtures
Opportunity costsMonitory value sacrificed in rejection Cost of giving opportunity to do a business
Incremental cost Vary with decision to make or buy Vary with decision to make or buy
Labour cost Wages and other benefits Wages and other benefits
Multiple Choice Single Answer
Question: The goods are manufactured as per customer's definite order in case of
:-Correct Answer: Job production Your Answer Batch production
PAGE NO: 6 OF 17
Multiple Choice Multiple Answer
Question: The commonly used network techniques other than PERT and CPM are as follows
:-Correct Answer: MOSS [ Multi Operation Scheduling System ] , PCS [ Project Control System ] , GERT [ Graphical Evaluation Review Techniques ]
Your Answer MIS [ Management Information Systems ] Multiple Choice Multiple Answer
Question: To minimize total throughout time we are required to minimize
:-Correct Answer: Queuing , Idle time , Inventory Your Answer Queuing , Idle time
Multiple Choice Multiple Answer
Question: Following conditions are required to be fulfilled for processing n jobs through 2 machines
:-Correct Answer: The jobs are ready to be processed before the period under consideration begins . , Transient time to move a job from one machine to the another is negligible. , In process inventory is allowed.
Your Answer The jobs are ready to be processed before the period under consideration begins . , In process inventory is allowed.
Select The Blank
Question: An inventory control technique based on selective approach to stock items is called ________ analysis.
Correct Answer: Pareto's Your Answer Pareto's
Multiple Choice Multiple Answer
Question: While communicating to customer on delays in delivery following information should be given
:-Correct Answer: Information on identification of job , Reasons for delays , Revised date of delivery
Your Answer Reasons for delays , Revised date of delivery Select The Blank
Question: CPM is ________ oriented system.
Correct Answer: Activity Your Answer Activity
Multiple Choice Single Answer
Question: One of the following is not consumable tool
:-Correct Answer: Arbors Your Answer Arbors
True/False
Question: LOB is a manual planning and scheduling technique similar in nature to MRP [Material Resource Planning].
Correct Answer: True Your Answer False Select The Blank
Question: ________ is required when expediting fails to bring deviated plan to its actual path.
Correct Answer: Replanning Your Answer Replanning
Multiple Choice Multiple Answer
Question: The process of contraction or compression involves extra cost because extra money is required to be spent on factors such as
:-Correct Answer: Overtime engagement of workforce , Purchase of additional machinery , Use of better materials
Your Answer Overtime engagement of workforce , Purchase of additional machinery , Purchase of stationary of good quality
Multiple Choice Single Answer
Question: In job production one single product is
manufactured while a batch of group of products is turned out at a time under a system of
:-Correct Answer: Batch production Your Answer Process production Multiple Choice Multiple Answer
Question: The 'F' group of GOLF analysis involves following requirements
:-Correct Answer: Search for foreign suppliers , Opening of letter of credit , Arrangements for shipping and port clearance
Your Answer Search for foreign suppliers Multiple Choice Single Answer
Question: The production system characterized by complex set of activities that must be performed in a particular order within a given period and within an estimated expenditure is known as
:-Correct Answer: Project production Your Answer Project production
Multiple Choice Single Answer
Question: Proper Production Planning and Control can reduce cost in
:-Correct Answer: Overtime cost Your Answer Overtime cost
Select The Blank
Question: ________ is the specific instant of time that marks start and end of activity.
Correct Answer: Event Your Answer Event
PAGE NO: 7 OF 17
Select The Blank
Question: Overlapping of operations help to ________ manufacturing time.
Correct Answer: Reduce Your Answer Reduce
Multiple Choice Multiple Answer
Question: "Difficult" items have following attributes
:-Correct Answer: Available indigenously but are not easy to procure , Items which come from longer distance , Items which are difficult to manufacture
Your Answer Available indigenously but are not easy to procure , Items which come from longer distance , Items having complex specifications
Multiple Choice Multiple Answer
Question: They are type of analytical estimate
:-Correct Answer: Moving average , Exponential smothering , Curve fitting
Your Answer Moving average , Curve fitting Select The Blank
Question: The performance standard is required by
________ to determine individual machine capacity for the purpose of machine loading and assigning machine hours and man hours .
Correct Answer: Scheduler Your Answer Production engineer Multiple Choice Multiple Answer
Question: The network analysis involves following works
:-Correct Answer: Obtaining a work breakdown structure to a set of individual jobs which are arranged in a logical network. , Estimation of job duration , Scheduling to discover which jobs control completion of project and reallocation of resources.
Your Answer Obtaining a work breakdown structure to a set of individual jobs which are arranged in a logical network. ,
Estimation of job duration , Scheduling to discover which jobs control completion of project and reallocation of resources.
Multiple Choice Single Answer
Question: The assembly work content [ Wi ] of the i'th station having n work stations is given by
:-Correct Answer: å Wi from i=1 to n Your Answer å Wi from i=1 to n
Multiple Choice Multiple Answer
Question: Essentials of good forecasts are
:-Correct Answer: Stability , Fairly accurate , Economical to generate
Your Answer Stability , Fairly accurate , Economical to generate
True/False
Question: The 'G' group of GOLF analysis involves moderate delivery time and availability of credit usually in the range of 30 to 60 days.
Correct Answer: True Your Answer True
Select The Blank
Question: ABC company manufactures MS bolts. Given fixed cost Rs 0.5 Lac, Labour cost Rs 2 Lacs, Raw Material cost Rs 3 Lacs, overhead cost Rs 0.5 Lacs, the total manufacturing cost would be Rs ________.
Correct Answer: 6 Lacs Your Answer 6 Lacs
LIST OF ATTEMPTED QUESTION:S AND ANSWERS Multiple Choice Multiple Answer
Question: If actual demand far exceeds forecast, it will result
into
:-Correct Answer: Better utilization of equipment , Project
margin , Higher material purchase
Your Answer Higher material purchase , Increase in labour productivity , Better utilization of equipment , Project margin
Select The Blank
Question: To know the accumulated ________ for a given
machine at a given time Load charts are necessary.
Correct Answer: Load
Your Answer Load
Multiple Choice Single Answer
Question: LOB technique was developed by US navy in the year
:-Correct Answer: 1958
Your Answer 1958 True/False
Question: In continuous or process production , only one product
is manufactured.
Correct Answer: True
Your Answer True Select The Blank
Question: ________reflects impact of money tied up in
inventory.
Correct Answer: Inventory turnover
Your Answer Inventory turnover Multiple Choice Multiple Answer
Question: Methods for recording actual progress of work for
shop orders are
:-Correct Answer: Progress card , Display board , Network
updating
Your Answer Progress card , Display board , Network updating , Job card
PAGE NO: 8 OF 17
Select The Blank
Question: A progress card is the most ________ method of
recording of progress of work.
Correct Answer: Convenient
Your Answer Convenient Multiple Choice Multiple Answer
Question: Following are some of the common standard cutting
tools
:-Correct Answer: Cutting saw , Inserts , Reamers
Your Answer Form tool , Cutting saw , Inserts , Reamers Multiple Choice Multiple Answer
Question: Tooling cost comprises the cost of :-Correct Answer: Gigs , Fixtures , Drill bits
Your Answer Gigs , Fixtures , Drill bits , Stationary Multiple Choice Single Answer
Question: The light engineering company has one special
purpose facing & centering machine And one copying lathe. The foreman has five work orders for processing . The operation Sequence is fixed [ each job is first faced and centered and then copy turned ] . The standard Hours required for each machine to process each work order are shown in the following Table :- Work Order Processing Time [Hours ] Facing & centering machine Copying Lathe I 16 40 II 30 60 III 20 6 IV 15 16 V 25 12 find sequence to minimize requirements of machine hours.
Correct Answer: IV-I-II-V-III
Your Answer I-II-III-IV-V Select The Blank
Question: ________ represents the time that elapses between the
receipt of requirement of job until the job is adopted in the production control department.
Correct Answer: Order preparation time
Your Answer Queue time True/False
Question: PERT basically does not demarcate between critical
and non-critical activities.
Correct Answer: True
Your Answer True
Multiple Choice Single Answer
Question: The assignment method is also called as :-Correct Answer: Hungarian Method
Your Answer Analytical Method Multiple Choice Multiple Answer
Question: Outside operations cost involves expenses such as :-Correct Answer: Rough blanking , Heat treatment , Plating
Your Answer Heat treatment , Plating , Inventory control , Rough blanking
Select The Blank
Question: The correct fitting of orders with capacity
considerably lessens ________ burden of control.
Correct Answer: Foreman's
Your Answer Foreman's
Multiple Choice Multiple Answer
Question: The 'F' group of GOLF analysis involves following
requirements
:-Correct Answer: Search for foreign suppliers , Opening of letter
of credit , Arrangements for shipping and port clearance
Your Answer Search for foreign suppliers , Opening of letter of credit , Arrangements for shipping and port clearance , Account in foreign bank
Match The Following
Question: Correct Answer: Your Answer
Order quantity Factor influencing process planning Break even analysis
Machine capacity chart Dimensional accuracy Dimensional accuracy
Mass production Special purpose machines Special purpose machines
Standard elemental time data Compare alternative processes Factor influencing process planning
Multiple Choice Multiple Answer
Question: The tooling data is prepared in respect of following
measuring instruments
:-Correct Answer: Vernier caliper , Micrometer screw gauge ,
Strain gauge
Your Answer Vernier caliper , Micrometer screw gauge , Strain gauge , Drill bits
Multiple Choice Multiple Answer
Question: In replenishment system, the fixed order quantity
system is also called by following names
:-Correct Answer: Fixed order system , Min-max system ,
Re-order point system
Your Answer Fixed order system , Min-max system , Re-order point system , Lead time system
Multiple Choice Multiple Answer
Question: How you will Judge the failure of production planning
and control department?
Correct Answer: Frequent broken delivery promises ,
Underutilization of men, machines , Excessive overtime Your Answer Frequent broken delivery promises ,
Underutilization of men, machines , Excessive overtime , Better coordination with other section
Multiple Choice Single Answer
Question: In Cost Vs Quantity plot, the total inventory Cost
curve is
:-Correct Answer: Parabolic
Your Answer Inverse True/False
PAGE NO: 9 OF 17
Question: Given stock in hand = 1320 units, safety stock=840units and average daily consumption = 60 units, the lead time available would be 10 hours.
Correct Answer: False
Your Answer True
Multiple Choice Single Answer
Question: If the annual usage of a material is 1200 units and the
reorder point is at 120 Units, find the lead time.
Correct Answer: 4 months
Your Answer 4 months Multiple Choice Single Answer
Question: The assignment algorithm was developed by a
Hungarian mathematician named
:-Correct Answer: D. Konig
Your Answer Charles simony Multiple Choice Single Answer
Question: So far as possible, number of activities should be :-Correct Answer: Limited
Your Answer Limited True/False
Question: Production Planning and Control makes the supervisor
ineffective.
Correct Answer: True
Your Answer False
Multiple Choice Single Answer
Question: Unit of loading and scheduling depends on following
factor
:-Correct Answer: Operating cycle
Your Answer Unit of capacity True/False
Question: The 'G' group of GOLF analysis involves moderate
delivery time and availability of credit usually in the range of 30 to 60 days.
Correct Answer: True
Your Answer True
Multiple Choice Multiple Answer
Question: Load charts are used for following
:-Correct Answer: To know the accumulated load on a given
machine at a given time , Identify periods available for allocation in future to orders , Matching orders and loads
Your Answer Improving supply of material , To know the accumulated load on a given machine at a given time , Identify periods available for allocation in future to orders , Matching orders and loads
Select The Blank
Question: ABC company manufactures MS bolts. Given fixed
cost Rs 0.5 Lac, Labour cost Rs 2 Lacs, Raw Material cost Rs 3 Lacs, overhead cost Rs 0.5 Lacs, the total manufacturing cost would be Rs ________.
Correct Answer: 6 Lacs
Your Answer 6 Lacs
Select The Blank
Question: An inventory control system in which stock of item is
physically or conceptually divided into ________ bins is calledTwo bin system.
Correct Answer: Two
Your Answer Pair
Multiple Choice Multiple Answer
Question: They are type of analytical estimate
:-Correct Answer: Moving average , Exponential smothering ,
Curve fitting
Your Answer Moving average , Exponential smothering , Curve fitting , Opinion surveys
Multiple Choice Single Answer
Question: For goods manufactured to stock, following
department is expected to periodically undertake replenishment action as stocks are depleted
:-Correct Answer: Production Planning Control
Your Answer Production True/False
Question: Random fluctuation is addition of cyclical fluctuation
and seasonal fluctuation.
Correct Answer: False
Your Answer True True/False
Question: Scientific inventory control system requires to be
followed for machine aid, work aid and inspection aid
:-Correct Answer: False
Your Answer True
Multiple Choice Single Answer
Question: Value Analysis conducted in 'C' type of material is
usually
:-Correct Answer: Minimum
Your Answer Minimum True/False
Question: Purchase department must keep PPC informed
regarding lead time of different items specially where lead times are extended.
Correct Answer: True
Your Answer True True/False
Question: In assignment matrix, it is a must to determine
Jacobean of the determinant.
Correct Answer: False
Your Answer True Select The Blank
Question: For replenishment action for stock items which are
reserved by PPC, the stores work out ________ stock which equals the stock on hand less stock reserved.
Correct Answer: Free
PAGE NO: 10 OF 17
Multiple Choice Single Answer
Question: What are the customer's expectation from the
supplier?
Correct Answer: Consistent good quality of products
Your Answer Consistent good quality of products Match The Following
Question: Correct Answer: Your Answer
End piece allowance Material insufficient to produce one piece Material insufficient to produce one piece
Stock allowance Quantity to meet requirement of spares Quantity to meet requirement of spares
Machining allowance Extra material requirement Extra material requirement
Spoilage allowance Process rejection Process rejection Multiple Choice Single Answer
Question: Why customer is called the king? Correct Answer: Customer's orders gives us work
Your Answer Customer's orders gives us work Multiple Choice Single Answer
Question: PPC is expected to have good inter-departmental
relationships to achieve the production targets. Which is the most important factor that shall affect production targets?
Correct Answer: Timely availability of material, manpower
Your Answer Timely availability of material, manpower Select The Blank
Question: Generally for ________ flow system, Heuristic
method is preferred.
Correct Answer: Intermittent
Your Answer Continuous Select The Blank
Question: In control board________ compartment contains copy
of work orders/shop orders of the item to be processed next on the machine.
Correct Answer: Middle
Your Answer Bottom True/False
Question: Work measurement function is attached to line
management.
Correct Answer: False
Your Answer True
Multiple Choice Multiple Answer
Question: The technical feasibility of sales enquiry is carried out
on the following grounds
:-Correct Answer: Tools and plants are available , Technical
know how is available , Competent persons are present
Your Answer Tools and plants are available , Technical know how is available , Competent persons are present , Cost data of raw material is available.
LIST OF ATTEMPTED QUESTION:S AND ANSWERS
Multiple Choice Multiple Answer
Question: Following are the factors which influence tool life
:-Correct Answer: Operators efficiency , Type of tool , Material it is required to operate upon
Your Answer Operators efficiency , Type of tool , Material it is required to operate upon
Multiple Choice Single Answer
Question: The document which incorporates details of process planning for a job is called
:-Correct Answer: Route Sheet Your Answer Route Sheet
Multiple Choice Multiple Answer
Question: CPM terminology uses words like
Correct Answer: Arrow diagram , Nodes , Float Your Answer Arrow diagram , Nodes
Select The Blank
Question: Forecasting is function of ________.
Correct Answer: Marketing department Your Answer Planning in charge
Select The Blank
Question: Johnsons method of scheduling can be used when operation sequence involve ________ machines.
Correct Answer: Two Your Answer Two
Select The Blank
Question: Good quality and ________are the two main requirements to secure maximum business from a customer.
Correct Answer: Competitive rates Your Answer Competitive rates
Select The Blank
Question: Sum of queue, transit, order preparation and manufacturing times is known as ________
Correct Answer: Total Lead Time Your Answer Total Lead Time
PAGE NO: 11 OF 17
Question: To conduct FSN analysis we require, last date ofreceipt or last date of issue whichever is later and period.
Correct Answer: True Your Answer True
Multiple Choice Multiple Answer
Question: Overtime can be avoided in many ways and they are
:-Correct Answer: Unrealistic delivery date , Acceptance of too many rush order , Excessive machine breakdown
Your Answer Unrealistic delivery date , Acceptance of too many rush order , Excessive machine breakdown
Multiple Choice Multiple Answer
Question: Material control function embraces a following techniques
:-Correct Answer: Make -or -buy decision , Pareto's analysis , Replenishment system
Your Answer Make -or -buy decision , Pareto's analysis , Replenishment system
True/False
Question: Work measurement is not useful for choosing between two alternate methods of production.
Correct Answer: False Your Answer False
Multiple Choice Multiple Answer
Question: Process Sheet contains following information
:-Correct Answer: Material Specification , Sequence of operation , Skill of Labour
Your Answer Material Specification , Sequence of operation , Skill of Labour
True/False
Question: More than one subcontractor should be developed for each subcontracted operation/Job.
Correct Answer: True Your Answer True
Select The Blank
Question: Classification of items on basis of their capital lock up is called ________ analysis.
Correct Answer: XYZ Your Answer XYZ
Select The Blank
Question: Purchase section must keep ________posted on the progress of purchase orders and expected delays.
Correct Answer: P.P.C. Your Answer P.P.C.
Multiple Choice Single Answer
Question: Effective Production Planning and Control, reduce investment in inventories effectively
:-Correct Answer: By proper coordination between shop floor, stores and buying department
Your Answer By proper coordination between shop floor, stores and buying department
True/False
Question: Fluctuation due to changes in season are called cyclical fluctuation.
Correct Answer: False Your Answer False
True/False
Question: Flexibility and product variety are not inter-related with each other.
Correct Answer: False Your Answer True
True/False
Question: Overlapping of operations help to reduce manufacturing time.
Correct Answer: True Your Answer True
Select The Blank
Question: The LOB technique is made more accurate and fast by using ________.
Correct Answer: Computers Your Answer Reduction techniques True/False
Question: Overtime is undesirable since it increases manufacturing cost of the product.
Correct Answer: True Your Answer False
Multiple Choice Multiple Answer
Question: The essential features of batch production are
:-Correct Answer: General purpose machines and process type layout , Manual materials handling , Flexibility of production schedule
Your Answer General purpose machines and process type layout , Manual materials handling , Flexibility of production schedule
Multiple Choice Single Answer
Question: The sourcing of vendors in case of 'B' type of items is
PAGE NO: 12 OF 17
Your Answer Few
Multiple Choice Single Answer
Question: Dispatcher withdraws required quantity of material from stores using following document
:-Correct Answer: Stores issue order Your Answer Bill of material
Multiple Choice Multiple Answer
Question: In a mass production assembly shop following work measurement techniques are used
:-Correct Answer: Time study , Work sampling , Production study
Your Answer Time study , Work sampling , Production study , Analytical estimating
Multiple Choice Multiple Answer
Question: SDE analysis is based on problems of procurement namely
:-Correct Answer: Non-availability , Scarcity , Longer lead time
Your Answer Non-availability , Scarcity , Longer lead time True/False
Question: Line balancing is a simulation technique.
Correct Answer: False Your Answer False
Multiple Choice Multiple Answer
Question: The line of balance is a device for planning and monitoring progress of
:-Correct Answer: Purchase order execution , Project execution , Targeted programs
Your Answer Purchase order execution , Project execution , Targeted programs
Select The Blank
Question: Sales persons decides ________.
Correct Answer: Synthetic forecast Your Answer Current sales
True/False
Question: Material control Card is a document for record of issues of material and receipt of unused material by production shop.
Correct Answer: False Your Answer False
Multiple Choice Single Answer
Question: Work measurement is limited to measuring
:-Correct Answer: Productive & non productive time
Your Answer Only product related activities Match The Following
Question: Correct Answer:Your Answer
Move order Transport material from and to required work centers Transport material from and to required work centers Materials Order Allocation of material required in connection with shop order Allocation of material required in connection with shop order
Work Order Bird's eye view of production programme Bird's eye view of production programme
Production Order Reserve material required in connection with sales order Reserve material required in connection with sales order
Multiple Choice Multiple Answer
Question: The software for line balancing should have following features
:-Correct Answer: Easy to operate , Easy to install , Easy to upgrade
Your Answer Easy to operate , Easy to install , Unmanaged code should be available
Multiple Choice Single Answer
Question: Man hours is commonly used unit of measurement for scheduling purposes in following industry
:-Correct Answer: Engineering Your Answer Engineering
Multiple Choice Multiple Answer
Question: Customer plays very important role due to the following reasons
:-Correct Answer: Gives us work , Dividends to share holders , Gets business from new customers
Your Answer Gives us work , Dividends to share holders , Gets business from new customers
Multiple Choice Single Answer
Question: The 4X4 assignment problem involve following job-machine operations
:-Correct Answer: 24 Your Answer 24
Multiple Choice Single Answer
Question: The best of scientific tools available for scheduling is
:-Correct Answer: CPA [ critical path analysis ] Your Answer Gantt Chart
PAGE NO: 13 OF 17
Multiple Choice Multiple Answer
Question: Work measurement is responsibility of
:-Correct Answer: PPC , Industrial Engineering , Production department
Your Answer PPC , Industrial Engineering Match The Following
Question: Correct Answer:Your Answer
Long production run Mass and Flow productionMass and Flow production
Complex activities to be performed in a particular order within a give time & estimate. Project production Project production
One or few units manufactured as per customers requirement Jobbing Production Jobbing Production Short production run Batch Production Batch Production
Multiple Choice Single Answer
Question: Value Analysis conducted in 'C' type of material is usually
:-Correct Answer: Minimum Your Answer Minimum
Multiple Choice Multiple Answer
Question: Some of significant features of HML analysis are
:-Correct Answer: To evolve buying policies to control purchases , To delegate authorities to different buyers to make petty cash purchases , Not to take consumption into account
Your Answer To evolve buying policies to control purchases , To delegate authorities to different buyers to make petty cash purchases
Multiple Choice Single Answer
Question: What is the reasons for poor labour efficiency attributed by inefficient P.P.C.?
Correct Answer: Failure to provide proper tools and control on work in progress on shop floor
Your Answer Failure to provide proper tools and control on work in progress on shop floor
Multiple Choice Single Answer
Question: The administrative expenses towards the procurement of materials is called
:-Correct Answer: Procurement cost Your Answer Administrative cost
Multiple Choice Multiple Answer
Question: Smoothing performs following
activities:-Correct Answer: Reallocation of resources , Improving utilization of resources , Conducting Heuristic approach
Your Answer Reallocation of resources , Improving utilization of resources , Conducting Heuristic approach
True/False
Question: As per a study on materials management practices, a typical firm spends almost half of its rupee sales on goods purchased from vendors.
Correct Answer: True Your Answer True
Select The Blank
Question: Value analysis of ________ class items is usually inadvisable.
Correct Answer: C Your Answer C
True/False
Question: PPC system in the organisation is to be tailor made.
Correct Answer: True Your Answer True
LIST OF ATTEMPTED QUESTION:S AND ANSWERS
True/False
Question: Performance benchmarking does not involves comparison of financial ratios at the aggregate level.
Correct Answer: False Your Answer False
Multiple Choice Single Answer
Question: Setup time includes
:-Correct Answer: Internal setup time & External setup time Your Answer Internal setup time & External setup time
Multiple Choice Single Answer
Question: Participants of the groups for quality circles should be decided by
:-Correct Answer: Employees coming together by their own enthusiasm
Your Answer Employees coming together by their own enthusiasm
PAGE NO: 14 OF 17
Question: Check sheet are also used as:-Correct Answer: Data gathering & interpretation tool Your Answer Data gathering & interpretation tool
Multiple Choice Single Answer
Question: SMED means
:-Correct Answer: Single minute exchange of dies Your Answer Single minute exchange of dies
Match The Following
Question: Correct Answer:Your Answer
Productivity performance measurement Turnover employee Cost of quality
Financial performance measurement Sales of the months Sales of the months
Customer satisfaction measurement Customer complaints per period Customer complaints per period
Staff attitude measurementEmployee satisfaction index Employee satisfaction index
Select The Blank
Question: ________ is an effect due to the muda of defect.
Correct Answer: Wear & tear of parts while disassembling
Your Answer Poor production planning & control Select The Blank
Question: If some defective parts are discovered by the subsequent process they should be returned to the ________ to prevent reoccurrence.
Correct Answer: Preceding process Your Answer Return to stores
Multiple Choice Multiple Answer
Question: The results oriented efforts of the quality circle should also include
:-Correct Answer: Efforts to avoid the problem
permanently , Ultimate aim of the customers satisfaction , Attacking the real root causes & all possibilities
Your Answer Efforts to avoid the problem permanently , Publication or advertisement of your contribution , Attacking the real root causes & all possibilities
Match The Following
Question: Correct Answer:Your Answer
Parato diagram always indicates Magnitude of defects
Philosophy of 20% of the activity causes 80% of the effect
Parato analysis underlines & operates on Philosophy of "vital few:trivial many" Philosophy of "vital few:trivial many"
Parato analysis is technique of identifying vital causes by
Arranging data according to the descending order of their frequency of occurrence Arranging data according to the descending order of their frequency of occurrence
Parato diagram is a Bar graph with height or value drawn by Arranging data in descending order Magnitude of defects
Multiple Choice Multiple Answer
Question: Few steps in construction in Radar chart are
:-Correct Answer: Brainstorming to enlist characteristics which require to be evaluated & draw the circle & divide it into 'slices' equal to number of characteristics , The first slice begins at 12 noon. Then draw vertical line & calibrate it equal to the number of levels required , Draw concentric circles from each gradiation using 'o' point as centre
Your Answer Brainstorming to enlist characteristics which require to be evaluated & draw the circle & divide it into 'slices' equal to number of characteristics , The first slice begins at 12 noon. Then draw vertical line & calibrate it equal to the number of levels required , Draw concentric circles from each gradiation using 'o' point as centre
Select The Blank
Question: 5 S audit result is discussed in ________ meeting.
Correct Answer: Monthly Your Answer Monthly
True/False
Question: Fishbone analysis is used both in analysis & planning.
Correct Answer: True Your Answer False
Multiple Choice Single Answer
Question: One Green Belt may head a team of
:-Correct Answer: 20 employees Your Answer 20 employees
Multiple Choice Multiple Answer
Question: Role of champions are
:-Correct Answer: Approve six sigma projects , Remove road block in the path of six sigma implementation , Monitor progress of six sigma projects
Your Answer Monitor progress of six sigma projects , Approve six sigma projects , Remove road block in the path of six sigma implementation
PAGE NO: 15 OF 17
Multiple Choice Multiple Answer
Question: To draw control charts, sample must be
representative of homogeneous segment of production for which
:-Correct Answer: The items of the sample should be from the same machine setting , The items should be of the same batch , Items should be made from the same raw material batch
Your Answer The items of the sample should be from the same machine setting , The items should be of the same batch , Items should be made from the same raw material batch
Multiple Choice Single Answer
Question: Failure mode and effect analysis (FMEA) establish
Correct Answer: Process failure and minimize frequency Your Answer Process failure and minimize frequency
Multiple Choice Multiple Answer
Question: What are the steps in deciding the benchmarking partner?
Correct Answer: Decide level of benchmarking , List down a few prospective candidates of partnership , Collect information of short listed partners
Your Answer Decide level of benchmarking , List down a few prospective candidates of partnership , Collect information of short listed partners
Multiple Choice Single Answer
Question: One Master Black Belt may head a team of
:-Correct Answer: 15-20 Black Belts Your Answer 15-20 Black Belts
Multiple Choice Single Answer
Question: Competitive benchmarking involves identifying key competitive product, services or processes & comparing with those of
:-Correct Answer: Main competitor Your Answer Main competitor
Multiple Choice Single Answer
Question: Implication of Quality problem
is:-Correct Answer: Gap in performance Your Answer Gap in performance
Select The Blank
Question: Number of defects in an individual component, like gear, shaft, wheel etc can be monitored through ________ type of control chart.
Correct Answer: c-chart Your Answer c-chart
True/False
Question: Non-availability of files /document in time is a problem to be addressed by office TPM.
Correct Answer: True Your Answer True
Multiple Choice Single Answer
Question: Check sheet is easy to use because it is
:-Correct Answer: Simplest tool Your Answer Simplest tool
Multiple Choice Single Answer
Question: Benchmarking helps to identify the gap between the current performance of the organization and the
:-Correct Answer: Performance of the best organization Your Answer Performance of the best organization
True/False
Question: Flow chart is pictorial representation of the steps in production control.
Correct Answer: False Your Answer True
Multiple Choice Multiple Answer
Question: Breakdown problem may be stratified by
:-Correct Answer: Sections , Machines , Type of breakdown (e.g mech. Or electrical)
Your Answer Sections , Machines , Type of breakdown (e.g mech. Or electrical)
Select The Blank
Question: A control chart to exhibit counted data on number of defect is called ________.
Correct Answer: c-chart Your Answer c-chart
Select The Blank
Question: Procedure for implementation of TPM consists of ________ numbers of steps.
Correct Answer: 12 Your Answer 8
Select The Blank
Question: Capability index Cp = ________
Correct Answer: Specification width/process width Your Answer Specification width/process width
Multiple Choice Single Answer
Question: Pareto's analysis underlines & operates philosophy of
:-Correct Answer: Vital few = trivial many Your Answer Vital few = trivial many
PAGE NO: 16 OF 17
True/False
Question: Kanban signals are required when assembly work, subassembly work and manufacturing at parts is carried out at different locations.
Correct Answer: True Your Answer True
Multiple Choice Multiple Answer
Question: To reduce clamping & declamping time, following actions are desirable
:-Correct Answer: Standardize clamping bolts / screws , Cut off unnecessary threads , Use quick clamping device
Your Answer Standardize clamping bolts / screws , Cut off unnecessary threads , Use quick clamping device
Select The Blank
Question: Benchmarking allows exchange of ________ between the benchmarking partners.
Correct Answer: Information Your Answer Information
Multiple Choice Multiple Answer
Question: TQM can never flourish if the staff
are:-Correct Answer: Worried about losing jobs , Afraid of being reprimanded if there are mistakes , Scared of their bosses
Your Answer Worried about losing jobs , Afraid of being reprimanded if there are mistakes , Scared of their bosses
True/False
Question: In bar graph each bar is of same height.
Correct Answer: False Your Answer False
Multiple Choice Multiple Answer
Question: During SMED implementation, primary study consists of
:-Correct Answer: Equipment analysis , Setup change analysis , Preparation items (storage place , method) analysis
Your Answer Equipment analysis , Setup change analysis , Preparation items (storage place , method) analysis
True/False
Question: Daily work management can also be extended to non manufacturing areas like procurement, QA, HRD etc.
Correct Answer: True Your Answer True
Multiple Choice Multiple Answer
Question: Types of Poka-Yoke are
:-Correct Answer: Prevention type Poka-Yoke , Detection type Poka-Yoke
Your Answer Prevention type Poka-Yoke , Detection type Poka-Yoke
Multiple Choice Single Answer
Question: Quality problem solving tool is used to
:-Correct Answer: Improve quality Your Answer Save time
True/False
Question: Along with problem solving tools experience and judgment is also used.
Correct Answer: True Your Answer False Select The Blank
Question: JIT advocates the philosophy at elimination of waste from system which occurs due to ________.
Correct Answer: Over Production Your Answer Over Production
True/False
Question: Without measuring initial performance, target can't be set.
Correct Answer: True Your Answer False
Multiple Choice Multiple Answer
Question: An erratic patterns falling above & below the control limits indicates
:-Correct Answer: Defect in materials , Frequent adjustment of machines , Poorly trained operators
Your Answer Defect in materials , Frequent adjustment of machines , Poorly trained operators
True/False
Question: Sample size for the construction of p-chart are larger than X bar-R chart.
Correct Answer: True Your Answer True
Multiple Choice Multiple Answer
Question: Histogram is an important diagnostic tool. Analysis of the histogram gives
:-Correct Answer: It shows cause which affects the process , An idea of what is happening to the process , Whether the process is capable of meeting process or not i.e. around correct average & within specific limits
Your Answer An idea of what is happening to the process , Whether the process is capable of meeting process or not i.e. around
PAGE NO: 17 OF 17
correct average & within specific limits , A bird's eye view of the variation
Multiple Choice Single Answer
Question: Productivity improves by
:-Correct Answer: Voluntary participants of everyone Your Answer Voluntary participants of everyone