• No results found

Page 1 of 3. This alternate has been removed from the scope of work.

N/A
N/A
Protected

Academic year: 2021

Share "Page 1 of 3. This alternate has been removed from the scope of work."

Copied!
37
0
0

Loading.... (view fulltext now)

Full text

(1)

1 Per Specification 012300 there is an Alternate 01A to provide a Skyfold Classic 51 partition. Please show all work associated with this on the drawings (drywall baffle, ceiling details, electrical requirements, etc.).

This alternate has been removed from the scope of work.

2 Per Specification 012300 there is an Alternate 01B to provide a variable height horizontal sliding partition. Please provide a specification for this product. Also, is a drywall baffle required? If so, provide detail. Provide a detail of the ceiling at this sliding partition.

This alternate has been removed from the scope of work.

3 Per Specification 012300 there is an alternate to provide access flooring. Please provide a specification for this product

and drawing showing the limits of this work. The specifications will be updated to show this information.

4 Please provide information regarding the existing roof warranty. Further information is needed from the client. More information to follow with the issue of the next and final addendum (#3).

5 Per drawing E30.01, on the 1st floor there are some existing lights to be re-used. These are shown as to be demolished

on the demolition drawings. Please confirm that we are to re-use those existing lights as needed per E30.01. Per General Note #5 on Lighting Demolition Plan E21.01, retain all the demolished light fixtures and fire alarm devices for potential reuse.

6 Per specification 064023 AWI standards are required. Please confirm that it is acceptable if this work meets the intent of these standards, but does not require shop certification and product inspection.

Confirmed, it is acceptable that the work "meets the intent" of these standards.

7 Per specification 088000 heat treated float glass is to be heat-soaked. Please confirm that heat-soak is not required. The heat-soaking requirement for the glass is being tracked as an alternate. Please see alternate list in specifications.

8 Please confirm the all specifications that are "closed" (ex. Door hardware listed on drawing A00.40) are only intended to

be a basis of design only. Correct, items listed on A00.40 are "basis-of-design". Please see specifications for other approved manufacturers.

9 Detail 9 on A00.41: can we replace the steel angle with light-gauge metal framing header? There is no steel package on

this project. Light gauge framing header can be used in lieu of steel. Light gauge framing will need to be designed and engineered by the light gauge manufacturer.

10 Detail 13 on A00.41: indicates that the G.C. is to provide proper structural support for door weight for overhead. Please

provide structural detail in order to bid this work. Light gauge framing support can be used in lieu of steel. Light gauge framing will need to be designed and engineered by the light gauge manufacturer and coordinated with the overhead door manufacturer's requirements.

11 General Note I on A2.01 - A2.04: "GC TO COORDINATE SOUND MASKING WITH OWNER AND AV CONSULTANT."

Please provide details of what is required. This note will be revised. Sound masking is not part of the scope of work.

12 General Note M on A2.01 - A2.04: cost for floor levelness and survey for such was removed during schematic budget

reviews with the Owner and design team. Please remove this note from the drawings. This note will be revised to exclude Levels 02 -04. This note will still pertain to Level 01 since we are creating larger spaces from existing sub-divided spaces.

13 General Note N on A2.01 - A2.04: during schematic budget reviews with the Owner and design team, cost for existing poke-through patching was agreed that these devices would be left in-place. Please remove this note from the drawings.

Scope of work to include removal of these devices, patching of floor and new carpet installed as shown on the revised drawings.

14 Per specification 081416 there are clear finish and opaque finish doors. Per the drawings the new doors are painted. Please confirm that there are no new clear finish doors. Also confirm that existing doors on the 2 - 4 floors are not to be painted or otherwised refinished. Also, confirm that the existing doors to remain on the 1st floor are to be painted.

Sheet A00.40 shows a finish for the door and a finish for the frame. All of the wood doors are to be veneer wood (clear finish) and not painted. The intent is to match the existing doors.

(2)

16 Is new water supply required for the new owner furnished ice maker and refirgerators? New plumbing work is not shown on the current drawings at these locations. If required please show in the plumbing drawings. Also confirm that new drains will not be required at these locations; that the equipment will be ordered with pumps to the sink drains.

See revised Plumbing Drawings for water supply to refrigerator locations that do not have an existing water supply already in place.

17 Please confirm that the 1st floor bathroom doors are existing to remain. The drawings seem to indicate they are door

type A1. This will be corrected on the drawings. These doors are existing to remain.

18 Does the Owner want an alternate to remove any of the lockers that are shown to remain? If so, please show this work on

the drawings. The removal of the lockers on Levels 02 - 04 is an alternate. Please see alternate section in specifications.

19 There look to be some missing Sheet Notes on the casework elevations (ex. Detail 3 on A07.03). The sheet has been revised to show the missing sheet notes.

20 There is a relocated work bench in Air Quality. Please confirm that the peg board / tool rack above it is also relocated

from the Owner existing facilities. Scope of work to include blocking in the wall above tool bench to allow for attachment of a new CFCI peg board to be 4'-0" high x 6'-0" wide.

21 There seem to be 2 separate specification sections that cover the same, or similar, scope of work: 017320 Selective Demolition and 024119 Selective Demolition. Please combine these or remove 1 of the specification sections.

The duplicate section has been removed from the specifications.

22 Please provide a specification and location for the glass film / graphics that the Owner has requested be added. See revised A07.00 sheet for extent of glass film/graphics.

23 Per detail 1 on A06.00 there is an existing lab hood that is owner furnished, contractor installed. There appears to be

another lab hood, but there is no note stating that it is OFCI. Is this a new lab hood? If so, provide a specification for it. There are two new lab hoods in the scope of work. These have been corrected on the drawings to be CFCI. See revised equipment schedule on A00.20.

24 Per the Finish Material Legend on A00.20 there are alternate materials listed (RF1 ALT., RF2 ALT., T2 ALT.), which are no found in the Division 1 Alternates specification. Please add these to this specification and associate a number (ex. Alternate #6) with each.

The alternates section in the specifications have been updated to include this information.

25 For RF1 ALT.: Finish Material Legend on A00.20 lists this as being installed in "BACK OF HOUSE CORRIDORS/STORAGE ROOMS." Please confirm that this is correct. Please confirm that Vestibule 01E01, Computer Area, Air Quality Lab, etc. (other areas shown as RF1 in the base bid) are not to be included in this alternate. Is Corridor 01F11 (CPT3 in the base bid) to be included in this alternate?

RF1 ALT would replace everything that is shown as RF1 on A04.01 except for the following rooms - Public Educ. & Vol. Stor. 01J10, Monitoring Equip. Stor. 01J11, Battery Charging & Stor. 01I13

26 For RF2 ALT.: Finish Material Legend on A00.20 lists this as being installed in "LABS." In the base bid RF2 is included in Chem Storage 01I09, Water Quality Lab 01J08, D.I. Water 01I06, and Bio. Lab 01J06. Please confirm that these are the rooms are to receive RF2 ALT. in this alternate pricing.

RF2 ALT would replace everything that is shown as RF2 on A04.01.

27 A specification for fire protection specialties has been provided, but none can be found on the drawings. Please show

these on the drawings. See Life Safety Plans on A00.04 and A00.05 for locations of fire extinguishers, cabinets, and brackets.

28 Per detail 9 on drawing A07.01 there is a recessed pan with floor drain in Lab Loading 01G02. This location is an existing slab-on-grade. Please confirm that a pan that is not recessed is acceptable. Also, provide a specification for this pan.

Provide a fiberglass roll-in type pan (non-recessed) with integral floor drain with dimensions as shown on detail 02/A06.00 - 5'-10" wide by 4'-0" length.

29 Provide elevations of cabinets in Computer Area 01I01. Please see detail 01/A07.01 for this elevation (it is the far right side of the elevation)

30 Per detail 2 on drawing A07.01 there is a work bench that is relocated. Is this OFCI? Also, in this detail there is a peg

(3)

31 There are multiple items tagged with Sheet Notes #11 on details 1 and 3 on drawing A07.03. Please provide a description of these items.

These are various items that will be relocated from the existing Bio Lab, including but not limited to work benches, loose floor cabinets and upper cabinets. These are all OFCI. The upper cabinets will need blocking in the wall for attachment.

32 Provide an elevation of the cabinets on the plan north side of the Bio. Lab. Please see detail 04/A07.03 for this elevation.

33 Provide elevations / section cuts / specifications of the items shown in the middle of Air Quality General Lab. These will be OFCI lab benches.

34 Per the plumbing there are P-3 sinks in the lab areas the are integral to the counter top and "provided by others." Per the only casework section cut (1/A08.00) the sinks are under mount. Please clarify and provide a specification for the P-3 sinks.

Further coordination is required with the user. We will resolve and answer this in the final Addendum (#3).

35 Sheet P01.01 does not clearly show the demo work to be performed. Line weights for existing system is the same as that

for the portion being removed. This may be misinterpreted. Lineweights for phases was originally assigned by REVIT and were left on default type. Lineweights have been adjusted and should be more visible.

36 Sheet M01.02 demo drawing is showing the same ductwork as the M02.02 drawing, but we are not demolishing and reinstalling the identical ductwork, correct?

Correct. For Dwg. M01.01, ductwork to be removed is shown dashed. Refer to demolition notes 1 and 2. Ductwork to remain is shown solid. For Dwg. M02.01, existing duct is shown light line weight and new duct is shown in a heavier line weight. New duct also has a new to existing duct connection symbol located at the new duct connection point. 37 Sheet M02.01 implies almost all new air distribution (grilles) since most are in heavy line weight. Is this correct? No. New grilles have a grille mark such as "A", "B", "C", etc. as shown on air device schedule on dwg. M03.01. Existing

grilles have an ( E ) listed at the end of the grille size and no grille mark. Slot diffusers in lay-in ceilings at the south end of the building are existing, as well as, many of the open return air grilles labeled with a keynote 2. Most of the the grilles on the north end of the building are new. New grilles are marked with a grille mark at the beginning of the grille size such as "A", "B", "E", or "F".

38 Sheet M02.04- what is the purpose of the 20’x14” “box”? This is assumed to be a duct but has no connections points. The existing RTU-1 supply air vertical riser with level 01 supply loop and return air ductwork is existing and is to remain in place. Revit shows existing ductwork as a light line weight and new ductwork shows at a heavier line weight.

39 Sheet M02.04 is not clear on what is existing and for reference only- it may be interpreted that we are installing new Supply air ducts (72”x24” for example), etc. This will lead to unnecessarily high proposals. Same for Sheets M02.02 and M02.03.

The existing RTU-1 supply air vertical riser with level 01 supply loop and return air ductwork is existing and is to remain in place. Revit shows existing ductwork as a light line weight and new ductwork shows at a heavier line weight.

(4)

DATE: OWNER: ARCHITECT:

NOTICE TO BIDDERS:

GENERAL REVISIONS TO BID INFORMATION

1 None

REVISIONS TO DESIGN DOCUMENTS 1

2

3

4

REVISIONS TO BID PACKAGE MANUAL 1

Addendum #2 Specification Revisions (Section 011400, Section 012300, Section 013300, Section 015000, Section 017320, Section 064023, Section 081416, Section 087100, Section 095113, Section 096516, Section 096519, Section 096543)

Addendum #2 RFI Responses

None

August 14, 2015 Mecklenburg County Gensler

Addendum #2 Drawing Revisions ( A00.20, A01.02, A01.03, A01.04, A02.01, A04.04, A06.00, A07.00, A07.03, M02.01, M02.04, M03.01, M04.01)

This addendum is issued prior to receipt of bids, proposals, and its contents do hereby become a part of the pricing documents for the above referenced project.

END OF ADDENDUM

All subcontractor bidders are responsible for assuring that their subcontractors and vendors are properly apprised of the contents of this Addendum.

All information contained in this Addendum supersedes and takes precedence over any conflicting information in the original pricing documents.

All bidders must acknowledge receipt of this Addendum in the space provided on the Form of Proposal for their bid package.

Addendum #1 Drawing Revisions (A00.01, A00.11, A00.15, A00.20, A00.40, A01.02, A01.11. A01.12, A02.01, A02.02, A03.01, A03.02, A04.01, A04.02, A04.03, A04.04, A06.00, A06.30, M01.01, M02.01, M03.01, M03.02, M04.01, E20.01, E20.02, E30.01, E40.01, E40.02, E40.03, E40.04, E70.01, E70.02, E70.03, E70.05)

(5)

WORK RESTRICTIONS 011400 - 1

SECTION 011400

1.1 WORK RESTRICTIONS

PART 2 -GENERAL

2.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and all Divisions of the Technical Specifications, apply to this Section.

2.2 USE OF PREMISES

A. Use of Site: Limit use of premises to work in areas indicated on the drawings. Do not disturb portions of site beyond areas in which the Work is indicated.

B. Use of Existing Building: Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations.

C. Protect building and its occupants during construction period. If the Work requires that the Contractor make any modifications to an existing fire alarm and/or fire protection system, the Contractor shall be responsible for Fire Watches.

2.3 OCCUPANCY REQUIREMENTS

A. Partial Owner Occupancy: Owner reserves the right to occupy and to place and install equipment in completed areas of building, before Substantial Completion, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the total Work.

1. Consultant will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied before Owner occupancy.

2. Contractor shall obtain a Certificate of Occupancy from authorities having jurisdiction before Owner occupancy.

3. Upon occupancy, Owner will provide, operate, and maintain mechanical and electrical systems serving occupied portions of building.

4. Upon occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of building.

(6)

WORK RESTRICTIONS 011400 - 2

PART 3 -PRODUCTS (Not Used) PART 4 -EXECUTION (Not Used)

(7)

ALTERNATES 012300 - 1

SECTION 012300

1 ALTERNATES

PART 2 - GENERAL

1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and all Divisions of the Technical Specifications, apply to this Section.

2 SUMMARY

A. This Section includes administrative and procedural requirements for alternates.

3 DEFINITIONS

A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the Bidding Requirements that may be added to or deducted from the Base Bid.

4 PROCEDURES

A. Coordination: Modify or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.

1. Include as part of each alternate; equipment, labor, profit & overhead, sales tax, material, miscellaneous devices, accessory objects, and similar items required to execute the alternate as described.

B. Execute accepted alternates under the same conditions as other work of the Contract. C. Schedule: A Schedule of Alternates is included at the end of this Section. Specification

Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate.

(8)

ALTERNATES 012300 - 2

PART 3 -PRODUCTS (Not Used) PART 4 - EXECUTION

1 SCHEDULE OF ALTERNATES

Alternate No. 1

Provide security/public access on Levels 02 and Level 03.

Level 02: Includes providing 110 linear feet of new wall, with 4 new secure access doors and 3 existing doors retrofitted with secure access hardware.

Level 03: Includes providing 40 linear feet of new wall, with 5 new secure access doors and 3 existing doors retrofitted with secure access hardware.

(9)
(10)

SUBMITTAL PROCEDURES 013300 - 1

SECTION 013300

1 SUBMITTAL PROCEDURES

PART 2 - GENERAL

1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and all Divisions of the Technical Specifications, apply to this Section.

2 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals.

B. Related Sections include the following:

1. Division 1, of the Technical Specifications Section "Payment Procedures" for submitting Applications for Payment.

2. Division 1, of the Technical Specifications Section "Project Management and Coordination" for submitting Coordination Drawings.

3. Division 1, of the Technical Specifications Section "Construction Progress Documentation" for submitting schedules and reports, including Contractor's Construction Schedule and the Submittals Schedule.

4. Division 1, of the Technical Specifications Section "Photographic Documentation" for submitting periodic construction photographs.

5. Division 1, of the Technical Specifications Section "Quality Requirements" for test and inspection reports and Delegated-Design Submittals and for erecting mockups.

6. Division 1, of the Technical Specifications Section "Closeout Procedures" for submitting warranties Project Record Documents and operation and maintenance manuals. 7. Division 1, of the Technical Specifications Section "Project Record Documents" for

submitting Record Drawings, Record Specifications, and Record Product Data.

8. Division 1, of the Technical Specifications Section "Operation and Maintenance Data" for operation and maintenance manual requirements.

3 DEFINITIONS

A. Action Submittals: Written and graphic information that requires Consultant's responsive action.

B. Informational Submittals: Written information that does not require Consultant's approval. Submittals may be rejected for not complying with requirements.

(11)

SUBMITTAL PROCEDURES 013300 - 2

4 SUBMITTAL PROCEDURES

A. The Contractor shall provide the submittals as required by the Consultant’s Submittal Log and the Contract Documents.

B. General: Electronic copies of CAD Drawings of the Contract Drawings will not be provided by Consultant for Contractor's use in preparing submittals.

C. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Consultant reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

D. Submittals Schedule: Comply with requirements in Division 1, of the Technical Specifications Section "Construction Progress Documentation" for list of submittals and time requirements for scheduled performance of related construction activities. (Submittal Log)

E. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on Consultant's receipt of submittal.

1. Initial Review: Allow seven (7) days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. Consultant will advise Contractor when a submittal being processed must be delayed for coordination.

2. Concurrent Review: Where concurrent review of submittals by Consultant's

consultants, Owner, or other parties is required, allow twenty one (10) days for initial review of each submittal.

3. If intermediate submittal is necessary, process it in same manner as initial submittal. 4. Allow seven (7) days for processing each re-submittal.

5. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

F. Identification: Place a permanent label or title block on each submittal for identification. 1. Indicate name of firm or entity that prepared each submittal on label or title block. 2. Provide a space approximately 4 by 5 incheson label or beside title block to record

Contractor's review and approval markings and action taken by Consultant.

3. Include the following information on label for processing and recording action taken: a. Project name.

b. Date.

(12)

SUBMITTAL PROCEDURES 013300 - 3

d. Name and address of Contractor. e. Name and address of subcontractor. f. Name and address of supplier. g. Name of manufacturer.

h. Unique identifier, including revision number.

i. Number and title of appropriate Technical Specifications Section. j. Drawing number and detail references, as appropriate.

k. Other necessary identification.

G. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

H. Additional Copies: Unless additional copies are required for final submittal, and unless Consultant observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

1. Submit one copy of submittal to concurrent reviewer in addition to specified number of copies to Consultant.

2. Additional copies submitted for maintenance manuals will be marked with action taken and will be returned.

I. Transmittal: Package each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Consultant will return submittals, without review, received from sources other than Contractor.

1. On an attached separate sheet, prepared on Contractor's letterhead, record relevant information, requests for data, revisions other than those requested by Consultant on previous submittals, and deviations from requirements of the Contract Documents, including minor variations and limitations. Include the same label information as the related submittal.

2. Include Contractor's certification stating that information submitted complies with requirements of the Contract Documents.

3. Transmittal Form: Use on form to be defined by the Consultant.

J. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

K. Use for Construction: Use only final submittals with mark indicating action taken by Consultant in connection with construction.

PART 3 -PRODUCTS

1 ACTION SUBMITTALS

(13)

SUBMITTAL PROCEDURES 013300 - 4

1. Number of Copies: Submit 6 copies of each submittal, unless otherwise indicated. Consultant will return 4 copies. Mark up and retain three returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable. 3. Include the following information, as applicable:

a. Manufacturer's written recommendations. b. Manufacturer's product specifications. c. Manufacturer's installation instructions. d. Standard color charts.

e. Manufacturer's catalog cuts.

f. Wiring diagrams showing factory-installed wiring. g. Printed performance curves.

h. Operational range diagrams. i. Mill reports.

j. Standard product operating and maintenance manuals. k. Compliance with recognized trade association standards. l. Compliance with recognized testing agency standards. m. Application of testing agency labels and seals.

n. Notation of coordination requirements. o. Manufacturer’s location.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data. 1. Preparation: Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams and existing conditions.

e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

f. Shopwork manufacturing instructions. g. Templates and patterns.

h. Schedules.

i. Design calculations.

j. Compliance with specified standards. k. Notation of coordination requirements.

(14)

SUBMITTAL PROCEDURES 013300 - 5

2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.

3. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 40 inches . 4. Number of Copies: Submit 6 blue- or black-line prints of each submittal, print will be

required for operation and maintenance manuals. Consultant will retain two prints; remainder will be returned.

D. Coordination Drawings: Comply with requirements in Division 1 Section "Project Management and Coordination."

E. Samples: Prepare physical units of materials or products, including the following:

1. Comply with requirements in Division 1 Section "Quality Requirements" for mockups. Verify the samples are true presentation of the materials to be used.

2. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available. 3. Preparation: Mount, display, or package Samples in manner specified to facilitate

review of qualities indicated. Prepare Samples to match Consultant's sample where so indicated. Attach label on unexposed side that includes the following:

a. Generic description of Sample.

b. Product name or name of manufacturer. c. Sample source.

4. Additional Information: On an attached separate sheet, prepared on Contractor's letterhead, provide the following:

a. Size limitations.

b. Compliance with recognized standards. c. Availability.

d. Delivery time.

5. Submit Samples for review of kind, color, pattern, and texture for a final check of these characteristics with other elements and for a comparison of these characteristics between final submittal and actual component as delivered and installed.

a. If variation in color, pattern, texture, or other characteristic is inherent in the product represented by a Sample, submit at least three sets of paired units that show approximate limits of the variations. The consultant will return submittal with the option selected.

b. Refer to individual Specification Sections for requirements for Samples that illustrate workmanship, fabrication techniques, details of assembly, connections, operation, and similar construction characteristics.

6. Disposition: Maintain sets of approved Samples at Project site, available for

quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

(15)

SUBMITTAL PROCEDURES 013300 - 6

a. Samples that may be incorporated into the Work are indicated in individual Specification Sections. Such Samples must be in an undamaged condition at time of use.

b. Samples not incorporated into the Work, or otherwise designated as Owner's property, are the property of Contractor.

F. Product Schedule or List: Prepare a written summary indicating types of products required for the Work and their intended location. Include the following information in tabular form: 1. Type of product. Include unique identifier for each product.

2. Number and name of room or space. 3. Location within room or space.

G. Delegated-Design Submittal: Comply with requirements in Division 1 Section "Quality Requirements."

H. Submittals Schedule: Comply with requirements in Division 1 Section "Construction Progress Documentation."

I. Application for Payment: Comply with requirements in Division 1 Section "Payment Procedures."

J. Schedule of Values: Comply with requirements in Division 1 Section "Payment Procedures." K. Subcontract List: Prepare a written summary identifying individuals or firms proposed for

each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2 INFORMATIONAL SUBMITTALS

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit two copies of each submittal, unless otherwise indicated. Consultant will not return copies.

2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

B. Contractor's Construction Schedule: Comply with requirements in Division 1 Section "Construction Progress Documentation."

(16)

SUBMITTAL PROCEDURES 013300 - 7

C. Qualification Data: If requested, prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of Consultants and owners, and other information specified. D. Product Certificates: Prepare written statements on manufacturer's letterhead certifying

that product complies with requirements.

E. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements. Submit record of Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) on AWS forms. Include names of firms and personnel certified.

F. Installer Certificates: Prepare written statements on manufacturer's letterhead certifying that Installer complies with requirements and, where required, is authorized for this specific Project.

G. Manufacturer Certificates: Prepare written statements on manufacturer's letterhead certifying that manufacturer complies with requirements. Include evidence of manufacturing experience where required.

H. Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements.

I. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation for the application.

J. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with requirements. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests

performed by a qualified testing agency.

K. Coordinate individual Specification Sections with paragraph below by including specific model code organization in that Section. If all are same, insert name below.

a) Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with requirements in Division 1 Section "Closeout Procedures Operation and Maintenance Data." L. Manufacturer's Instructions: Prepare written or published information that documents

manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer. Include the following, as applicable:

1. Preparation of substrates. 2. Required substrate tolerances. 3. Sequence of installation or erection.

(17)

SUBMITTAL PROCEDURES 013300 - 8

4. Required installation tolerances. 5. Required adjustments.

6. Recommendations for cleaning and protection.

M. Manufacturer's Field Reports: Prepare written information documenting factory-authorized service representative's tests and inspections. Include the following, as applicable:

1. Name, address, and telephone number of factory-authorized service representative making report.

2. Statement on condition of substrates and their acceptability for installation of product. 3. Statement that products at Project site comply with requirements.

4. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.

5. Results of operational and other tests and a statement of whether observed performance complies with requirements.

6. Statement whether conditions, products, and installation will affect warranty. 7. Other required items indicated in individual Specification Sections.

N. Material Safety Data Sheets: Submit two copies for the Consultant and the Owner and keep a copy at the job site. Post warning signs when appropriate.

PART 4 - EXECUTION

1 CONTRACTOR'S REVIEW

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Consultant.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

2 CONSULTANT'S ACTION

A. General: Consultant will not review submittals that do not bear Contractor's approval stamp and will return them without action.

B. Action Submittals: Consultant will review each submittal, make marks to indicate corrections or modifications required, and return it. Consultant will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken, as follows:

C. Informational Submittals: Consultant will review each submittal and will not return it, or will reject and return it if it does not comply with requirements. Consultant will forward each submittal to appropriate party.

(18)

SUBMITTAL PROCEDURES 013300 - 9

D. Submittals not required by the Contract Documents will not be reviewed and may be discarded unless a justification is also submitted.

(19)

TEMPORARY FACILITIES AND CONTROLS 015000 - 1

SECTION 015000

1.1 TEMPORARY FACILITIES AND CONTROLS

PART 2 -GENERAL

2.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and all Divisions of the Technical Specifications, apply to this Section.

2.2 SUMMARY

A. This Section includes requirements for temporary facilities and controls, including temporary utilities, support facilities, and security and protection facilities.

B. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.

C. Temporary utilities include, but are not limited to, the following: 1. Sewers and drainage.

2. Water service and distribution.

3. Sanitary facilities, including toilets, wash facilities, and drinking-water facilities. 4. Heating and cooling facilities.

5. Ventilation.

6. Electric power service. 7. Lighting.

8. Telephone service.

D. Support facilities include, but are not limited to, the following: 1. Temporary roads and paving.

2. Dewatering facilities and drains.

3. Project identification and temporary signs. 4. Waste disposal facilities.

5. Field offices as required. 6. Storage and fabrication sheds. 7. Lifts and hoists.

8. Temporary elevator usage. 9. Temporary stairs.

10. Construction aids and miscellaneous services and facilities.

(20)

TEMPORARY FACILITIES AND CONTROLS 015000 - 2

1. Environmental protection. 2. Stormwater control. 3. Tree and plant protection. 4. Pest control.

5. Site enclosure fence.

6. Security enclosure and lockup. 7. Barricades, warning signs, and lights. 8. Temporary enclosures.

9. Temporary partitions. 10. Fire protection.

F. Related Sections include the following:

1. Division 1, of the Technical Specifications Section "Submittal Procedures" for procedures for submitting copies of implementation and termination schedule and utility reports. 2. Division 1, of the Technical Specifications Section "Execution Requirements" for progress

cleaning requirements.

3. Divisions 2 through 16, of the Technical Specifications for temporary heat, ventilation, and humidity requirements for products in those Sections.

2.3 DEFINITIONS

A. Permanent Enclosure: As determined by Consultant, permanent or temporary roofing is complete, insulated, and weather tight; exterior walls are insulated and weather tight; and all openings are closed with permanent construction or substantial temporary enclosures.

2.4 USE CHARGES

A. General: Cost or use charges for temporary facilities are not chargeable to Owner or

Consultant and shall be included in the Contract Sum. Allow other entities to use temporary services and facilities without cost, including, but not limited to, the following:

1. Owner's construction forces. 2. Occupants of Project. 3. Consultant.

4. Testing agencies.

5. Personnel of authorities having jurisdiction. B. Sewer Service: Provided by Owner

C. Water Service: Provided by Owner

D. Electric Power Service: Provided by Owner

E. Communications: Pay all charges associated with communications (on-site internet access, etc)

(21)

TEMPORARY FACILITIES AND CONTROLS 015000 - 3

F. Streets, Sidewalks, and Temporary Easements: Pay all charges associated with the Work where charges will occur.

2.5 SUBMITTALS

A. Implementation and Termination Schedule: Within 15 days of date established for submittal of Contractor's Construction Schedule, submit a schedule indicating implementation and termination of each temporary utility.

2.6 QUALITY ASSURANCE

A. Standards: Comply with ANSI A10.6, NECA's "Temporary Electrical Facilities," and NFPA 241. 1. Trade Jurisdictions: Assigned responsibilities for installation and operation of

temporary utilities are not intended to interfere with trade regulations and union jurisdictions.

2. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.

B. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.

2.7 PROJECT CONDITIONS

A. Temporary Utilities: At earliest feasible time, when acceptable to Owner, change over from use of temporary service to use of permanent service.

1. Temporary Use of Permanent Facilities: Installer of each permanent service shall assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities.

B. Conditions of Use: The following conditions apply to use of temporary services and facilities by all parties engaged in the Work:

1. Keep temporary services and facilities clean and neat.

2. Relocate temporary services and facilities as required by progress of the Work.

PART 3 -PRODUCTS: 3.1 MATERIALS

A. General: Provide new materials. Undamaged, previously used materials in serviceable condition may be used if indicated on the plans and/or specifications. Provide materials suitable for use intended.

(22)

TEMPORARY FACILITIES AND CONTROLS 015000 - 4

B. Chain-Link Fencing: Minimum 2-inch , 0.148-inch- thick, galvanized steel, chain-link fabric fencing; minimum 6 feet high with galvanized steel pipe posts; minimum 2-3/8-inch- OD line posts and 2-7/8-inch- OD corner and pull posts, with 1-5/8-inch- OD top rails.

C. Portable Chain-Link Fencing: Minimum 2-inch 9-gage, galvanized steel, chain-link fabric fencing; minimum 6 feet high with galvanized steel pipe posts; minimum 2-3/8-inch- OD line posts and 2-7/8-inch- OD corner and pull posts, with 1-5/8-inch- OD top and bottom rails. Provide concrete or galvanized steel bases for supporting posts.

D. Wood Enclosure Fence: Plywood, 6 feet high, framed with four 2-by-4-inch rails, with preservative-treated wood posts spaced not more than 8 feet apart.

E. Lumber and Plywood: Comply with requirements in Division 6 Section."

F. Gypsum Board: Minimum 1/2 inch thick by 48 inches wide by maximum available lengths; regular-type panels with tapered edges. Comply with ASTM C 36.

G. Insulation: Unfaced mineral-fiber blanket, manufactured from glass, slag wool, or rock wool; with maximum flame-spread and smoke-developed indices of 25 and 50, respectively.

H. Paint: Comply with requirements in Division 9 Section "Painting." I. Tarpaulins: Fire-resistive labeled with flame-spread rating of 15 or less. J. Water: Potable.

3.2 EQUIPMENT

A. General: Provide equipment suitable for use intended.

B. Fire Extinguishers: Hand carried, portable, UL rated. Provide class and extinguishing agent as indicated or a combination of extinguishers of NFPA-recommended classes for exposures. 1. Comply with NFPA 10 and NFPA 241 for classification, extinguishing agent, and size

required by location and class of fire exposure and the requirements of the local Governing agency.

C. Self-Contained Toilet Units: Single-occupant units of chemical or aerated recirculation or combustion type; vented; fully enclosed with a glass-fiber-reinforced polyester shell or similar nonabsorbent material.

D. Drinking-Water Fixtures: Containerized, tap-dispenser, bottled-water drinking-water units, including paper cup supply.

E. Electrical Outlets: Properly configured, NEMA-polarized outlets to prevent insertion of 110- to 120-V plugs into higher-voltage outlets; equipped with ground-fault circuit interrupters, reset button, and pilot light.

(23)

TEMPORARY FACILITIES AND CONTROLS 015000 - 5

F. Power Distribution System Circuits: Where permitted and overhead and exposed for surveillance, wiring circuits, not exceeding 125-V ac, 20-A rating, and lighting circuits may be nonmetallic sheathed cable.

PART 4 -EXECUTION

4.1 INSTALLATION, GENERAL

A. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required.

B. Provide each facility ready for use when needed to avoid delay. Maintain and modify as required. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

4.2 TEMPORARY UTILITY INSTALLATION

A. General: Engage appropriate local utility company to install temporary service or connect to existing service. Where utility company provides only part of the service, provide the remainder with matching, compatible materials and equipment. Comply with utility company recommendations.

1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.

2. Provide adequate capacity at each stage of construction. Before temporary utility is available, provide trucked-in services.

3. If existing easements can not be used, the Contractor shall consult and coordinate with the Consultant and Owner to secure as necessary to obtain the temporary easement. Add provisions for work not in the Contract but served by temporary facilities if required.

B. Sewers and Drainage: If sewers are available, provide temporary connections to remove effluent that can be discharged lawfully. If neither sewers nor drainage facilities can be lawfully used for discharge of effluent, provide containers to remove and dispose of effluent off-site in a lawful manner.

1. Filter out excessive soil, construction debris, chemicals, oils, and similar contaminants that might clog sewers or pollute waterways before discharge.

2. Connect temporary sewers to municipal system or private system indicated as directed by sewer department officials.

3. Maintain temporary sewers and drainage facilities in a clean, sanitary condition. After heavy use, restore normal conditions promptly.

4. Provide temporary filter beds, settlement tanks, separators, and similar devices to purify effluent to levels acceptable to authorities having jurisdiction.

(24)

TEMPORARY FACILITIES AND CONTROLS 015000 - 6

C. Water Service: Install water service and distribution piping in sizes and pressures adequate for construction until permanent water service is in use. Sterilize temporary water piping before use.

1. As soon as water is required at each level, extend service to form a temporary water- and fire-protection standpipe as required by Fire Marshall. Provide distribution piping. Space outlets so water can be reached with a 100-foot (30-m) hose. Provide one hose at each outlet.

2. Where installations below an outlet might be damaged by spillage or leakage, provide a drip pan of suitable size to minimize water damage. Drain accumulated water

promptly from pans.

3. If required, provide pumps to supply a minimum of 30-psi static pressure at highest point. Equip pumps with surge and storage tanks and automatic controls to supply water uniformly at pressures required to operate the system.

D. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking-water fixtures. Comply with regulations and health codes for type, number, location, operation, and maintenance of fixtures and facilities.

1. Disposable Supplies: Provide toilet tissue, paper towels, paper cups, and similar disposable materials for each facility. Maintain adequate supply. Provide covered waste containers for disposal of used material.

2. Toilets: Install self-contained toilet units. Shield toilets to ensure privacy. Subparagraph below may be excessive for small- and medium-size projects. 3. Wash Facilities: Install wash facilities supplied with potable water at convenient

locations as required. Dispose of drainage properly. Supply cleaning compounds appropriate for each type of material handled.

4. Drinking-Water Facilities: Provide drinking-water.

E. Heating and Cooling: Provide temporary heating and cooling as required by construction activities.

F. Ventilation and Humidity Control: Provide temporary ventilation as needed for curing or drying of completed installations or for protecting installed gas or other utility services if required for Project.

G. Electric Power Service: Provide weatherproof, grounded electric power service and

distribution system of sufficient size, capacity, and power characteristics during construction period. Include meters, transformers, overload-protected disconnecting means, automatic ground-fault interrupters, and main distribution switchgear as required.

H. Electric Distribution: Provide receptacle outlets adequate for connection of power tools and equipment.

1. Provide waterproof connectors to connect separate lengths of electrical power cords if single lengths will not reach areas where construction activities are in progress. Do not exceed safe length-voltage ratio.

(25)

TEMPORARY FACILITIES AND CONTROLS 015000 - 7

3. Provide metal conduit, tubing, or metallic cable for wiring exposed to possible damage. Provide rigid steel conduits for wiring exposed on grades, floors, decks, or other traffic areas.

4. Provide metal conduit enclosures or boxes for wiring devices.

5. Provide 4-gang outlets, spaced so 100-foot extension cord can reach each area for power hand tools and task lighting. Provide a separate 125-V ac, 20-A circuit for each outlet.

I. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations and traffic conditions for the duration of the construction.

J. Telephone Service: Provide temporary telephone service throughout construction period for common-use facilities used by all personnel engaged in construction activities.

1. At each telephone, post a list of important telephone numbers in Spanish and English. a. Police and fire departments.

b. Ambulance service. c. Contractor's home office. d. Consultant's office. e. Engineers' offices.

f. Owner Representative’s office.

g. Principal subcontractors' field and home offices.

4.3 SUPPORT FACILITIES INSTALLATION

A. General: If required, Comply with the following:

1. Locate field offices, storage sheds, sanitary facilities, and other temporary construction and support facilities for easy access.

2. Maintain support facilities until approved by the Consultant to be removed. B. Temporary Roads and Paved Areas: If applicable/as needed, construct and maintain

temporary roads and paved areas to avoid damage to the site. Locate temporary roads and paved areas in same location as permanent roads and paved areas. If applicable, extend temporary roads and paved areas, within construction limits indicated, as necessary for construction operations.

C. Traffic Controls: Provide temporary traffic controls at junction of temporary roads with public roads. Include warning signs for public traffic and "STOP" signs for entrance onto public roads. Comply with requirements of authorities having jurisdiction.

D. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Containerize and clearly label hazardous, dangerous, or unsanitary waste materials separately from other waste. Comply with “Construction and Demolition Waste Management Recycling.

(26)

TEMPORARY FACILITIES AND CONTROLS 015000 - 8

E. Common-Use Field Office: If required, provide an insulated, weather tight, air-conditioned and heated field office for use as a common facility by all personnel engaged in construction activities; of sufficient size to accommodate required office personnel and meetings. F. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to

accommodate materials and equipment involved.

G. Existing Elevator Usage: Use of Owner's existing elevators will be permitted, as long as elevators are cleaned and maintained in a condition acceptable to Owner.

1. Provide protective coverings, barriers, devices, signs, or other procedures to protect elevator car and entrance doors and frame. If, despite such protection, elevators become damaged, engage elevator Installer to restore damaged work so no evidence remains of correction work. Return items that cannot be refinished in field to the shop, make required repairs and refinish entire unit, or provide new units as required.

4.4 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

B. Storm water Control: Comply as indicated on the erosion control plan/measures before any earth disturbing activities start.

C. Tree and Plant Protection: Comply with the plans and specifications for protection. D. Pest Control: Comply with the plans and specifications for control. Delete paragraph and

subparagraphs below for restricted city and urban sites where a combination fence and covered walkway or sidewalk bridge is used.

E. Security Enclosure and Lockup: Install substantial temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security.

F. Barricades, Warning Signs, and Lights: Comply with standards and code requirements for erecting structurally adequate barricades. Paint with appropriate colors, graphics, and warning signs to inform personnel and public of possible hazard. Where appropriate and needed, provide lighting, including flashing red or amber lights.

G. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities. Provide temporary weather tight enclosure for building exterior.

1. Where heating or cooling is needed and permanent enclosure is not complete, provide insulated temporary enclosures. Coordinate enclosure with ventilating and material drying or curing requirements to avoid dangerous conditions and effects.

(27)

TEMPORARY FACILITIES AND CONTROLS 015000 - 9

H. Temporary Partitions: Erect and maintain dustproof partitions and temporary enclosures to limit dust and dirt migration and to separate areas from fumes and noise.

I. Temporary Fire Protection:

1. Until fire-protection needs are supplied by permanent facilities, install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 241.

2. The Contractor shall maintain existing fire-protection facilities that are already in service for the duration of the project.

a. The Contractor shall protect all fire-detection devices to avoid damage and prevent false alarms.

1) The Contractor shall be responsible for locating and protecting both visible and hidden devices.

2) The Contractor shall be responsible for all work associated with cleaning and/or replacing any fire protection devices that trigger false alarms as a result of the construction process.

b. If the Contractor disables (zone-out) any fire detection devices over the course of the work, the Contractor shall be responsible for returning those devices to full service at the completion of the project.

c. If required, it shall be the responsibility of the Contractor to place an existing fire alarm into test mode. The Contractor shall return the fire alarm system to full service as soon as possible.

1) If a functioning fire alarm system in an occupied building is put into test mode for any period of time, the Contractor shall be responsible for paying the Owner’s chosen security personnel to perform code required Fire Watches every hour for the entire building over the course of time that the fire alarm system is not fully functioning.

4.5 OPERATION, TERMINATION, AND REMOVAL

A. Maintenance: Maintain facilities in good operating condition until removal. Protect from damage caused by freezing temperatures and similar elements.

B. Temporary Facility Changeover: Except for using permanent fire protection as soon as available. Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.

C. Termination and Removal: Remove each temporary facility when need for its service has ended, when it has been replaced by authorized use of a permanent facility, or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.

(28)

TEMPORARY FACILITIES AND CONTROLS 015000 - 10

1. Materials and facilities that constitute temporary facilities are the property of Contractor. Owner reserves right to take possession of Project identification signs. 2. At Substantial Completion, clean and renovate permanent facilities used during

construction period. Comply with final cleaning requirements in Division 1, of the Technical Specifications Section "Closeout Procedures."

(29)

SELECTIVE DEMOLITION 017320 - 1 REFERENCE SECTION 024119 SECTION 017320 1 SELECTIVE DEMOLITION PART 2 - GENERAL 1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and all Divisions of the Technical Specifications, apply to this Section.

2 SUMMARY

A. This Section includes the following:

1. Demolition and removal of selected portions of a building or structure. 2. Demolition and removal of selected site elements.

3. Repair procedures for selective demolition operations. B. Technical Specifications the following:

1. Division 1, of the Technical Specifications Section "Summary" for use of the premises and phasing requirements.

2. Division 1, of the Technical Specifications Section "Work Restrictions" for restrictions on use of the premises due to Owner or tenant occupancy.

3. Division 1, of the Technical Specifications Section "Construction Progress

Documentation" for preconstruction photographs taken before selective demolition. 4. Division 1, of the Technical Specifications Section "Photographic Documentation" for

preconstruction photographs taken before selective demolition.

5. Division 1, of the Technical Specifications Section "Temporary Facilities and Controls" for temporary construction and environmental-protection measures for selective

demolition operations.

6. Division 1, of the Technical Specifications Section “Construction Waste Management” method of disposal of construction waste.

7. Division 1, of the Technical Specifications Section "Cutting and Patching" for cutting and patching procedures for selective demolition operations.

8. Division 2, of the Technical Specifications Section "Building Demolition" for demolition of entire buildings, structures, and site improvements.

9. Division 02, of the Technical Specifications Sections for demolishing, cutting, patching, or relocating mechanical items.

(30)

SELECTIVE DEMOLITION 017320 - 2

3 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.

B. Remove and Salvage: Detach items from existing construction and deliver them to Owner ready for reuse.

C. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.

D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.

4 MATERIALS OWNERSHIP

A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Owner's property, demolished materials shall become Contractor's property and shall be removed from Project site.

B. Historic items, relics, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, antiques, and other items of interest or value to Owner that may be encountered during selective demolition remain Owner's property. Carefully remove and salvage each item or object in a manner to prevent damage and deliver promptly to Owner.

1. Coordinate with Owner's archaeologist or historical adviser, who will establish special procedures for removal and salvage.

5 SUBMITTALS

A. Qualification Data: For firms and persons specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names and addresses of Consultants and owners, and other information specified.

B. Proposed Dust-Control Measures: Submit statement or drawing that indicates the measures proposed for use, proposed locations, and proposed time frame for their operation. Identify options if proposed measures are later determined to be inadequate.

C. Schedule of Selective Demolition Activities: Indicate the following:

1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Ensure Owner's on-site operations are uninterrupted. 2. Interruption of utility services.

3. Coordination for shutoff, capping, and continuation of utility services. 4. Use of elevator and stairs.

(31)

SELECTIVE DEMOLITION 017320 - 3

5. Locations of temporary partitions and means of egress, including for other tenants affected by selective demolition operations].

6. Coordination of Owner's continuing occupancy of portions of existing building and of Owner's partial occupancy of completed Work.

D. Inventory: After selective demolition is complete, submit a list of items that have been removed and salvaged.

E. Pre-demolition Photographs or Videotape: Show existing conditions of adjoining

construction and site improvements, including finish surfaces that might be misconstrued as damage caused by selective demolition operations. Submit before Work begins.

6 QUALITY ASSURANCE

A. Demolition Firm Qualifications: An experienced firm that has specialized in demolition work similar in material and extent to that indicated for this Project.

B. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

C. Standards: Comply with ANSI A10.6 and NFPA 241.

7 PROJECT CONDITIONS

A. Owner will/may occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted. Provide not less than 72 hours' notice to Owner of activities that will affect Owner's operations. B. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.

1. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from authorities having jurisdiction.

C. Owner assumes no responsibility for condition of areas to be selectively demolished. 1. Conditions existing at time of inspection for bidding purpose will be maintained by

Owner as far as practical.

2. Before selective demolition, Owner will remove the following items: a. <Insert items to be removed by Owner.>

D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

(32)

SELECTIVE DEMOLITION 017320 - 4

2. If materials suspected of containing hazardous materials are encountered, do not disturb; immediately notify Consultant and Owner. Hazardous materials will be removed by Owner under a separate contract.

E. Storage or sale of removed items or materials on-site will not be permitted.

F. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations. PART 3 - PRODUCTS

1 REPAIR MATERIALS

A. Use repair materials identical to existing materials.

1. If identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible. 2. Use materials whose installed performance equals or surpasses that of existing

materials.

B. Comply with material and installation requirements specified in individual Specification Sections.

PART 4 - EXECUTION:

1 EXAMINATION

A. Verify that utilities have been disconnected and capped.

B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.

C. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged.

D. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to Consultant.

E. The consultant shall be immediately notified during selective demolition if the Contractor determines that the removal of any element may result in a structural deficiency of any portion of the structure or adjacent structure.

(33)

SELECTIVE DEMOLITION 017320 - 5

F. Perform surveys as the Work progresses to detect hazards resulting from selective demolition activities.

2 UTILITY SERVICES

A. Existing Utilities: Maintain services indicated to remain and protect them against damage during selective demolition operations.

B. Do not interrupt existing utilities serving occupied or operating facilities unless authorized in writing by Owner and authorities having jurisdiction. Provide temporary services during interruptions to existing utilities, as acceptable to Owner and to authorities having jurisdiction.

1. Provide at least 72 hours notice to Owner if shutdown of service is required during changeover.

C. Utility Requirements: Refer to Division 15 and 16 Sections for shutting off, disconnecting, removing, and sealing or capping utilities. Do not start selective demolition work until utility disconnecting and sealing have been completed and verified in writing.

3 PREPARATION

A. Dangerous Materials: Drain, purge, or otherwise remove, collect, and dispose of chemicals, gases, explosives, acids, flammables, or other dangerous materials before proceeding with selective demolition operations.

B. Pest Control: Employ a certified, licensed exterminator to treat building and to control rodents and vermin before and during selective demolition operations.

C. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

1. Do not close or obstruct streets, walks, walkways, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction. Provide alternate routes around closed or obstructed traffic ways if required by governing regulations.

2. Erect temporary protection, such as walks, fences, railings, canopies, and covered passageways, where required by authorities having jurisdiction.

3. Protect existing site improvements, appurtenances, and landscaping to remain.

4. Erect a plainly visible fence around drip line of individual trees or around perimeter drip line of groups of trees to remain.

D. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

References

Outline

Related documents

Company handled non-sent paid local calls will be rated to the end user and billed at the appropriate Company operator service charge as specified in Part 11, Section 1 or the

Across groups, there was no pattern of specific misidentification of emotion (e.g., children did not consistently misidentify one emotion, such as disgust, for a different

At 3rd level, the soul archer can cast greater magic weapon as a spell-like ability once per day (but only on her bonded bow), with a caster level equal to her class level.. At

Розглянуто аспект екологічної діяльності підприємств, спрямований на збереження і відновлення довкілля шляхом організації екологічно чистого

“NASA’s In-space Manufacturing Project: Materials and Manufacturing Process Development Update.” Proceedings of the National Space and Missile Materials Symposium.. Common

Lagna L aspects Lagna and Karyesh aspects karya Bhava, In this case Lagna is Ge and LL mercury does not aspect by Rasi or garha drishti, (Q1: what aspect should be used for such

Lee's loss prevention in the process industries: hazard identification, assessment, and control (4th ed. Acoustic Liquid Level Testing of Gas Wells. Paper presented at the SPE

If you want Microsoft SMTP Service to attempt to deliver the remote messages directly before it forwards them to the smart host, click to select the Attempt to direct delivery before