AIA

®

Document A133

TM

– 2009

Guaranteed Maximum Price Amendment

AIA Document A133™ – 2009 Exhibit A. Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.

WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of

this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent

possible under the law. This draft was produced by AIA software at 14:31:08 ET on 08/22/2019 under Order No.4809592789 which expires on 12/20/2019, and is not for resale.

User Notes: (1211393890)

1 ADDITIONS AND DELETIONS:

The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions

Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.

This document has important legal consequences.

Consultation with an

attorney is encouraged with respect to its completion or modification.

AIA Document A201™–2007, General Conditions of the Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified.

ELECTRONIC COPYING of any

portion of this AIA® Document

to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.

for the following PROJECT:

(Name and address or location)

«Brazoswood High School and Associated Projects – Phase 4 » «302 West Brazoswood Drive»

«Clute, Texas 77531»

THE OWNER:

(Name, legal status and address)

«Brazosport Independent School District» «301 West Brazoswood Drive»

«Clute, Texas 77531» «Telephone: (979) 730-7000»

THE CONSTRUCTION MANAGER:

(Name, legal status and address)

«Stewart Builders, Inc.» «16575 Village Dr.» «Houston, TX 77040» «Telephone (713) 983-8819» «Fax (713) 893-8987»

ARTICLE A.1

§ A.1.1 Guaranteed Maximum Price

Pursuant to Section 2.2.6 of the Agreement, the Owner and Construction Manager hereby amend the Agreement to establish a Guaranteed Maximum Price. As agreed by the Owner and Construction Manager, the Guaranteed Maximum Price is an amount that the Contract Sum shall not exceed. The Contract Sum consists of the Construction Manager’s Fee plus the Cost of the Work, as that term is defined in Article 6 of this Agreement.

§ A.1.1.1 The Contract Sum is guaranteed by the Construction Manager not to exceed

«Eight Million Four Hundred Twenty-Five Thousand Six Hundred Sixty-Eight Dollars ($ 8,425,668 )», subject to additions and deductions by Change Order as provided in the Contract Documents.

§ A.1.1.2 Itemized Statement of the Guaranteed Maximum Price. Provided below is an

itemized statement of the Guaranteed Maximum Price organized by trade categories, allowances, contingencies, alternates, the Construction Manager’s Fee, and other items that comprise the Guaranteed Maximum Price.

(Provide below or reference an attachment.)

«Refer to GMP Letter dated April 15, 2021 and EXHIBIT A »

§ A.1.1.3 The Guaranteed Maximum Price is based on the following alternates, if any,

which are described in the Contract Documents and are hereby accepted by the Owner:

(3)

AIA Document A133™ – 2009 Exhibit A. Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.

WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of

this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent

possible under the law. This draft was produced by AIA software at 14:31:08 ET on 08/22/2019 under Order No.4809592789 which expires on 12/20/2019, and is not for resale.

User Notes: (1211393890)

2

this Amendment, attach a schedule of such other alternates showing the amount for each and the date when the amount expires.)

«Refer to EXHIBIT C»

§ A.1.1.4 Allowances included in the Guaranteed Maximum Price, if any:

(Identify allowance and state exclusions, if any, from the allowance price.)

Item Price ($0.00)

Owner Contingency

Construction Manager Contingency TAS and City Review Comments Landscaping

Flat Screen TV’s Civil Items Super Graphics

Tech Building Roof Unknown Conditions Tennis Gate Panic Devices

$ 200,000 $ 200,000 $ 20,000 $ 25,000 $ 61,180 $ 105,000 $ 10,000 $ 20,000 $ 2,500

§ A.1.1.5 Assumptions, if any, on which the Guaranteed Maximum Price is based:

«Refer to EXHIBIT B – Clarifications & Exclusions»

§ A.1.1.6 The Guaranteed Maximum Price is based upon the following Supplementary and other Conditions of the

Contract:

Document Title Date Pages

§ A.1.1.7 The Guaranteed Maximum Price is based upon the following Specifications:

(Either list the Specifications here, or refer to an exhibit attached to this Agreement.)

«Attached as EXHIBIT D»

Section Title Date Pages

§ A.1.1.8 The Guaranteed Maximum Price is based upon the following Drawings:

(Either list the Drawings here, or refer to an exhibit attached to this Agreement.)

«Attached as EXHIBIT E»

Number Title Date

§ A.1.1.9 The Guaranteed Maximum Price is based upon the following other documents and information:

(List any other documents or information here, or refer to an exhibit attached to this Agreement.)

«Addendum #1 dated April 1, 2021»

ARTICLE A.2

§ A.2.1 The anticipated date of Substantial Completion established by this Amendment:

(4)

AIA Document A133™ – 2009 Exhibit A. Copyright © 1991, 2003 and 2009 by The American Institute of Architects. All rights reserved.

WARNING: This AIA® Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of

this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent

possible under the law. This draft was produced by AIA software at 14:31:08 ET on 08/22/2019 under Order No.4809592789 which expires on 12/20/2019, and is not for resale.

User Notes: (1211393890)

3

Field Events – December 31, 2021 District Technology – January 31, 2022 »

OWNER (Signature) CONSTRUCTION MANAGER (Signature)

Mark A. Stewart - President

(5)

JOB: Brazoswood HS Phase IV Schedule of Values

--- ---

---Division ITEM DESCRIPTION * TOTAL

--- --- ---1 General Conditions Fixed

General Conditions Non-Fixed (Addendum 1 RFP) $122,627

General Liability $56,876

Builders Risk $70,325

Payment & Performance Bonds $66,210

Contractor Fee $112,231

Allowances

Owner Contingency $200,000

Contractor Contingency $200,000

TAS & City Comments $15,000

Landscaping $25,000

Flat Screen TVs $64,180

Missing Civil Items (Softball) $105,000

Super Graphics $10,000

Panic Hardware at Tennis $2,500

Roof Repair at Technology $20,000

2 Demolition $174,395

3 Concrete (Including Site Concrete ) $540,703

4 Masonry $268,000

5 Structural & Misc. Steel $123,294

6 Rough Carpentry, Fiber Panels Millwork & Drywall $348,484 7 Roofing, Sheet Metal, Waterproofing & Insulation $418,388

8 Doors, Hardware, Storefront $267,855

9 Ceilings, Tile, Flooring & Painting $495,802

10 Building Specialties $207,904

11 Equipment $14,200

12 Furnishings (Blinds) $1,390

13 Pre-Engineered Buildings, Press Box, Bleachers $351,286

21 Fire Protection (Server Room Tech Only) $73,878

22 Plumbing $455,980

23 HVAC $902,000

26 Electrical $1,277,430

27 Communications $232,290

28 Electronic Safety & Security $137,555

31&32 Earthwork & Site Improvements $885,685

33 Utilities $179,200

--- ---

---TOTAL * $8,425,668

GMP $8,425,668

(6)

Stewart Builders, Inc.

General Contractor Construction Managers

Page 1 of 2 Brazoswood High School and Associated Projects – Phase #4

EXHIBIT “B”

Clarifications and Exclusions Clarifications:

1. Construction schedule is based on demolition start dates as follows: Softball 5/11/21

Baseball 6/1/21

Technology Building 6/3/21

2. We include concrete locker base per 75% drawings in lieu of the wood bench detail at Baseball.

3. The existing batting cage slab is to be reused. Holes will be sawcut in existing for the new footings.

4. Any owner salvage must take place prior to start of demolition. After demolition starts all salvage belongs to the Demo Contractor.

5. The sanitary sewer at Baseball is to be run outside the building to the existing sanitary manhole in lieu of tying into the existing locker room and saw cutting the slab.

6. We include an allowance of $105,000 at Softball for missing Civil items (lift station, added storm, concrete, trench grate & frame)

7. The rebar cages shown on S2.03 will only apply to fencing at the Baseball & Softball Field of play all other fence to have standard footings.

8. Builders Risk policy is included for all work specified under this amendment. Policies for flood, wind, and hail damage is included.

9. Payment and Performance Bonds for all work specified under this amendment are included.

(7)

Stewart Builders, Inc.

General Contractor Construction Managers

Page 2 of 2 Exclusions:

1. HVAC Controls, units are packaged units with local controls.

2. Removal, remediation, and/or disposal of any hazardous materials, asbestos, mold, mildew in existing buildings, and unforeseen subsurface site debris 3. Dewatering/Well Pointing

4. Any work on the ball field playing areas. 5. Scoreboards or scoreboard related work

6. Fire Sprinkler systems (FM 200 Fire Suppression System at Technology Server Room D116 is included)

7. Metal fabricated logo on vinyl fence gate 8. JV Bullpen at Baseball (not shown)

9. Relocation of existing utilities unless specifically shown. 10. Termite Treatment at ROTC Pad

11. Rerouting storm drainage from 9th Grade roof onto ROTC Pad 12. Any new netting and/or wall pads at Baseball

13. 60 FT Suspension Netting System at Baseball

14. Any Metal Shelving at Technology Building (all shown dashed by owner) 15. Removal, remediation, and/or disposal of any hazardous materials, asbestos,

mold, mildew in existing buildings, and unforeseen subsurface site debris 16. Fiber Optics relocation

17. Removal/relocation or storage of existing equipment, computers, furniture, etc… 18. BIM and/or BIM coordination

19. TAB and Materials Testing

20. All power company/gas company utility charges and/or assessment/impact fees. 21. Environmental testing

22. Building permits are included; Plan Check fees are excluded. 23. Commissioning

24. Special Testing and Test & Balance of Mechanical Systems

25. Submitting and/or re-permitting with municipality for any CPR’s or minor changes.

References

Related documents

EPUB Aia Document G702 1992 Template Aia Document G702 Fillable Form Aia Form G703 Excel has Excel Templates Invoice Templates Example Free.. Fill schedule of tools for the

(List here any additional documents that are intended to form part of the Contract Documents. AIA Document A201–2007 provides that bidding requirements such as advertisement

The above named Principal and Surety hereby jointly and severally agree with the Owner that every claimant as herein defined, who has not been paid in full before the expiration of

Unauthorized reproduction or distribution of this AIA ® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the

Unauthorized reproduction or distribution of this AIA ® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the

Completion of the Work or designated portion thereof or after the date for commencement of warranties established under Section 15.4.3, or by terms of an applicable special

The Design-Build Documents consist of this Agreement between Owner and Design-Builder (hereinafter, the “Agreement”) and its attached Exhibits; Supplementary and other

(g) You may, without obtaining a separate written license from the AIA, post to a password-protected intranet or extranet Web site any AIA Contract Document you prepare using