Filename: ICT Project Management Procedure Version: 1.0 Page 1 of 15

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

ICT

 

Project

 

Management

 

Procedure

 

 

 

 

   

 

           

 

 

(2)

Filename: ICT Project Management Procedure Version: 1.0 Page 2 of 15 PROJECT PLAN    1. Scope      The purpose of this procedure is to ensure that ICT projects are managed in a  structured way using a subset of the Prince2 project management method, ensuring  that ICT projects are fully documented and controlled at all stages of implementation.    The project flowchart attached shows the stages of an ICT project.     2.  Process      2.1 The ICT Manager will assign a project manager to the project. The project manager  will establish a project file and complete a  project initiation summary form (PM1).     2.2  The project manager will contact the internal audit manager to request a member of  the internal audit section to be assigned to the project in a quality assurance role where  projects are likely to exceed £50,000 in total cost of implementation.    2.3  The project manager liaising with the ICT Manager will put together a project team to  be involved with the day to day work of the project and details shall be recorded on a   project team definition  form (PM2).    2.4  A project initiation meeting will be held where the roles of the project team are  explained, as well as the requirements of the project team members in terms of the  reporting of issues etc involved with the project. The frequency of meetings will be  agreed at this initial meeting as will a skeleton timetable to allow the project manager  to complete a project timetable form (PM3) outlining the timetable for elements of the  project.  An initial risk assessment of the project will be made at this initial meeting,  which will be re‐visited at each project meeting.  Comment will also be made at this  time regarding the system acceptance and the testing of the new system ‐ the project  team must ensure sufficient time is put aside to enable comprehensive testing to be  carried out ‐ this is frequently under estimated.  See Appendix A for internal audit  guidelines on system acceptance and testing.    2.5  Minutes of all project meetings will be recorded.    2.6  A project timetable form (PM3) produced by the project manager will be subject to  amendment throughout the project where circumstances dictate ‐ any previous forms  should be archived prior to amendment.    2.7  For ICT projects a system development form (PM4) will be completed detailing the  program, JCL and file developments.     2.8  The documentation involved with the project will be kept in a project folder.   

(3)

Filename: ICT Project Management Procedure Version: 1.0 Page 3 of 15 2.9  It is the responsibility of the project manager to keep the ICT Manager informed of  progress on the project, this may be in the form of the issue of the minutes of  meetings, verbal reports, or written reports. The frequency or otherwise of any such  reporting is at the discretion of the ICT Manager.  If something arises that cannot easily  be resolved, an exception report form (PM5) must be completed and reported to the  ICT Manager, detailing what the occurrence is.  These will be kept in the project folder.    2.10  For major new developments, ICT staff and users should consult at all stages in the  development process to ensure the operational efficiency of the proposed system  design.     2.11  On completion of the project it will be closed and any project related documentation  will be retained within ICT with an index of the contents.    2.12  ITEX group will perform project reviews after a minimum of six months after the project  has been completed.             

(4)

Filename: ICT Project Management Procedure

Version: 1.0 Page 4 of 15

Appendix A 

System acceptance and testing criteria System acceptance criteria

Acceptance criteria for new information systems, upgrades and new versions are established by the project management group. System testing of the system is carried out prior to acceptance. Project managers must ensure that the requirements and criteria for acceptance of new systems are clearly defined, agreed, documented and tested using the test criteria below. The following controls should be considered and defined:

Performance and computer capacity requirements.

Error recovery and restart procedures, and contingency plans.

Preparation and testing of routine operating procedures to define standards. Agreed set of security controls in place.

Consideration has been given to the effect the new system has on the overall security of the organisation.

Training in the operation and use of new systems.

Appropriate tests should be carried out to confirm that all acceptance criteria are fully satisfied.

Systems Development Testing criteria   Overall Objective    To determine if the system is adequately tested prior to implementation, the test plan  includes all aspects of the new system, and all unexpected results are thoroughly resolved.    Outline objectives    The test plan should include interfaces, restarts, re‐runs, and back‐ups.  There should be documented evidence that all the tests have been satisfactorily completed  and conducted in accordance with established standards.  Manual procedures should be tested.  Recovery and back‐up procedures should be adequately tested.    A.   Test Plan    To determine if the test plan is adequate :    1.   Determine if the project team had developed a test plan.  Has the test plan been written?  Will there be system and acceptance tests?  Are the users included in the testing? 

(5)

Filename: ICT Project Management Procedure Version: 1.0 Page 5 of 15 2.   Determine if all aspects of the system will be tested, as outlined in the detail  requirements, including, but not limited to:         ‐   data entry       ‐   editing       ‐   reports       ‐   calculations       ‐  error reporting       ‐   interfaces with other systems       ‐   network communications  - print handling   Are all critical functions tested?  Are all existing capabilities tested?  Are all changes tested?    3.   Determine when testing will take place and ensure it will be completed prior to  implementation.  Does the test plan allow for retesting of errors and changes?    4.    Determine if a parallel test will be run.  Have the criteria for the termination of the parallel run been identified?    5.   Determine if month‐end, quarter‐end, and year‐end tests will be run, if needed.  If  there are month‐end, quarter‐end, and year‐end processing, then these tests should  be run.    6.   Determine if volume and/or stress testing will be done.  Volume testing should include a "normal" processing day's transactions as well as a  high‐volume day's transactions, printing, etc.  Stress testing should include a more than normal or high‐volume transaction testing  as well as printing, etc.  The stress test should try to "overload" the system.  Stress  testing should also test system response time in this situation.      B. Test Procedures    To determine if there are adequate test procedures developed:    1.   Determine if test data have been prepared.  Does this include all possible conditions,  including errors?  Have test scripts been prepared?  Have the test files been defined?  Are the data files synchronized?  Are the detail steps for the tests defined?    2.  Determine if there are procedures developed to evaluate the test results.  Have predetermined results been set up in advance?  Is there a problem resolution scheme and logging procedures?  Is the logging and problem resolution consistent with other implementations?  Are the users included in the testing and evaluation of the results? 

(6)

Filename: ICT Project Management Procedure Version: 1.0 Page 6 of 15   3.    Determine if the expected test results have been defined prior to actual testing.  The test scripts should include all expected test results.  Have procedures been developed to monitor test results?    4.    Determine if there has been a problem resolution procedure designed for those tests  not meeting the expected results.  Are unexpected test results logged and monitored?    C.  Test Results    To determine if test results are consistent and unexpected results are monitored:     1.   Determine if there was user acceptance of the final test results.  Have standards for the final acceptance test been established?  Has the user department management reviewed the system performance and  approved of the final results?  Has the user department identified any inefficiencies in the system?  Can these be corrected?  If so, will they be prior to system implementation?    2.   Review the test results and determine if there are unexpected results.  Are unexpected test results evaluated to determine the reasons for the   variance?    3.    Determine the follow‐up on those unexpected results.  Are program corrections made if needed?  Are the problems retested after correction?    4.    Follow those unexpected results deemed of a critical nature to ensure adequate  resolution.    5. Determine if those tests with unexpected results were adequately retested after  correction to the program, etc. All results which deviated from the expected should  be retested. 

(7)

Filename: ICT Project Management Procedure

Version: 1.0 Page 7 of 15

PROJECT INITIATION SUMMARY      PM 1 

  PROJECT TITLE:            DATE:    PROJECT MANDATE: 

(This should record details of the information forming the initial terms of reference for the Project. This may be a Committee Minute, a verbal  instruction or otherwise)    BRIEF DETAILS:                     

EFFICIENCIES / BENEFITS / LEGISLATION 

(8)

Filename: ICT Project Management Procedure

Version: 1.0 Page 8 of 15

ASSOCIATED DOCUMENTATION 

 

(9)

Filename: ICT Project Management Procedure

Version: 1.0 Page 9 of 15

PROJECT TEAM DEFINITIONS           PM 2 

  PROJECT TITLE:            DATE:    PROJECT TEAM   

Name  Project Role  Telephone  Company/ Department  Added to 

Team  Left  Team                                                                                                                            MEETING FREQUENCY   

Weekly      Fortnightly      Monthly   

 

(10)

Filename: ICT Project Management Procedure Version: 1.0 Page 10 of 15 PROJECT TIMETABLE            PM 3    PROJECT TITLE:            DATE:    Completed on time      40% 

Completed within budget    30% 

Achieve objectives      30%            STAGES  PROJECT  MANAGER  START  DATE  ESTIMATED  COMPLETION  DATE  STATUS  COMPLETED  ON TIME 

Detailed project definition and  specification 

         

Interface specification        

ICT hardware specification       

ICT software specification       

Risk assessment        Contract finalised        Hardware ordering        Software ordering        Hardware installation        Programming         Software installation        System testing          

PROJECT REVIEW BOARD COMPLETION ACCEPTANCE DATE 

 

(11)

Filename : ICT Project Management Procedure  Version : 1.0  Page 11 of 15       SYSTEM DEVELOPMENT  PM 4    PROJECT TITLE:            DATE:    AMENDMENT DETAILS    JCL ADDED    JCL Name  Description        JCL AMENDED    JCL Name  Description        JCL DELETED    JCL Name  Description        FILES ADDED    File Name  Description        FILES AMENDED    File Name  Description        FILES DELETED    File Name  Description        PROGRAMS ADDED    Program Name  Description       

(12)

Filename : ICT Project Management Procedure  Version : 1.0  Page 12 of 15       PROGRAMS AMENDED    Program Name  Description          PROGRAMS DELETED    Program Name  Description        PROGRAMS RECOMPILED    Program Name  Description         

(13)

Filename : ICT Project Management Procedure  Version : 1.0  Page 13 of 15       EXCEPTION REPORT  PM 5    PROJECT TITLE:            DATE:    Raised by:    Date Raised:    Details:                 

 

  Actions:                   

 

  Change authorised by:    Date authorised:         

(14)

Filename : ICT Project Management Procedure  Version : 1.0  Page 14 of 15      ICT Project S t ag e 7 S t ag e 6 S t ag e 5 S t ag e 4 S t ag e 3 S t ag e 2 S t ag e 1 Complet “Project Brief” Documen IT Manager to decide on approval or referral to ICT Development (Stage 3) Project presented to ICT Development Group for CMT to approve Project Sponsor to take to CMT if

limits are exceeded .

Project team to be created and definitions agreed

Complete “Project Team Definitions” form PM2 ICT Development

Group to and discuss the

project. ICT Development Group to approve Project Initiation Meetin Complet ”Project Timetable” for 3 Carry out Assessments Agree procedure Complete ”Total Cost

Ownership” form

Complete ”ROI” form

Complet ”System Development”

form 4

Monitor Control the project

implentation

Any exceptions to be entered on “Exception Report” form 5 an

reported to the IT Manager

Project

ICT Development Group to fully review all stages of the project and make recommendations for future.

Carry out Management Process during

all stages of the Discuss and investigate feasibility with the ICT

Manager and Outline Budgetary Proposals. Ide / Servic

Need defined.

Complete “Project Definition” form PM1

Ke

Ide 

Process 

Form Completion 

Decision 

Further Investigation and full costings to be . Capital and Revenue Monitoring approval.

If the project does not approva , further investigation

and determination will be require . Stage 3 will be started again for attainment of approval.

The investigations, costing

and approval to brought back to the ICT

Development

Project Sponsor and IT Manager to take any unforeseen financial or resourcing implications to relevant group for

(15)

Filename : ICT Project Management Procedure  Version : 1.0  Page 15 of 15      

Document

 

Attributes

 

 

Document

 

Information

 

Title  ICT Project Management Procedure  File Location  K:\Strategies Procedures & Protocols\Procedures\ICT Project  Management Procedure  v1.0.doc  Description  This procedure defines the processes and forms for managing ICT  projects.  Author  Head of ICT  Date Created   June 2008  Last Review Date  April 2010  Next Review Date   April 2011   

Document

 

History

 

Date  Summary of Changes  Version 

June 2008  First version  1.0 

April 2010  Reviewed – No changes  1.0 

 

Document

 

Approval

 

Date  Job Title of Approver(s)  Version 

July 2008  ITEX  1.0   

Distribution

 

Name / Group  ICT Service   

Coverage

 

Groups  All Employees via the intranet  All Members via the intranet       

References

Related documents

24 Beamlines approved by the Council + 1 beamline beamline to be founded to be founded 18 on insertion devices and 7 on bending magnets.. 18 on insertion devices and 7 on

The target language version of SNOMED CT® should reflect established national linguistic rules, and, health and social care staff should recognize the preferred terms used in

2) Rep Exclusive- When stock becomes available for the new Shells; they will be listed on www.michebag.ca as “Available exclusively through Miche Canada Representatives.” It is

Through a process of qualitative case study, pilot questionnaire surveys, workshops and qualitative in-depth interviews, the research has identified how the

The association between RAI treatment failure and various clinical parameters includ- ing age, sex, height, weight, body mass index (BMI), thyroid gland volume, and isthmus length

Civil courts must defer to the religious group’s determination of whether its employee served an important religious role. Otherwise, civil factfinders would be involved in

This study examines the extent to which 4-H camp results in transformative learning for 4-H members who serve as camp counselors, examines the perceived changes that occur