BASEMENT
DCQ3043 CONSTRUCTION
TECHNOLOGY 3
TOPIC: BASEMENT
BASEMENT
Syllabus Content :
2.1
Understand the construction of basement.
2.1.1 Explain methods of excavation for the construction of
deep and huge basement.
2.1.2 Explain usage of waterproofing system in basement
construction.
2.1.3 Identify clauses in Uniform Building By-Laws for
basement construction.
2.1.4 Describe construction of earthwork support system.
2.1.5 Justify the purpose of earthwork support system.
BASEMENT
Definitions:
1.
A storey with a floor that at
some point is
more than 1.2m
below the highest level of
ground adjacent to the outside
wall.
2.
A storey of a building
constructed wholly or partly
below ground level
exposed to
soil, water and/or water
vapour pressure.
BASEMENT
Types of Basement:
1.
Semi-basement
Single storey with only one, two or three
wall fully or partially below ground
level.
2.
Residential basement
A shallow or semi-basement providing
space for storage and/or accommodation,
associated with housing.
3.
Shallow basement
Not more than one storey wholly below
ground level.
BASEMENT
Types of Basement (cont’d):
4.
Deep basement
More than one storey wholly
below ground level.
5.
Cellar basement
Used for storage, heating plant
and for purpose other than
BASEMENT
Basement Requirements:
Primary functional requirements
of basement /wall below ground
may be summarized as follows:
1.
Structural stability
2.
Durability
3.
Moisture exclusion
4.
Buildability
BASEMENT
Basement Grades:
Basements are graded according to BS8102 depending on their specific
performance requirements.
BASEMENT
METHOD OF EXCAVATION FOR THE
CONSTRUCTION OF DEEP & HUGE BASEMENT
Classification of Excavation:
Excavation may be classified in the following manner:
1.
Shallow
excavation –
up to 1.5m deep.
2.
Medium
excavation –
1.5m to 3.0m deep.
3.
Deep
excavation –
over 3.0m deep
.
Factors that Affect Excavation Work:
Method of excavation depends on:
1.
Nature of the subsoil
- to determine the type of plant or hand tools and the type
of earthwork supports.
2.
Purpose of the excavation
- to determine the sizes, depth and volume of
excavation.
3.
Presence of ground water
- to determine dewatering techniques.
4.
Location and surrounding condition
- needs permit from local authorities such
as JKR, DBKL, etc. and impose certain restrictions and precautions.
BASEMENT
METHOD OF EXCAVATION FOR THE
CONSTRUCTION OF DEEP & HUGE BASEMENT
Method of Excavation:
There are 3 method of excavation for the construction of Deep and
Huge Basement that can be used:
1. Excavation with sloping sides / Open excavation.
2. Excavation with temporary support.
3. Excavation with permanent embedded retaining walls to deep
basements.
BASEMENT
1. Excavation with sloping sides /
Open excavation
Excavation basement on an open site can
be carried out by cutting the perimeter
back to the natural angle of repose of the
soil.
This method required sufficient site space
around for the over excavation and to
allow for the creation of a stable slope to
sides of the excavation.
No temporary or permanent earth support
so saving the cost of excavation but
increase in volume of back filling.
BASEMENT
BASEMENT
2. Excavation with temporary support
Suitable where the space around the
excavation is insufficient for open excavation.
Very economical compare with permanent
support such as contiguous piles, secant piles
or diaphragm walls.
Temporary support elements such as
Steel
Sheet Piles, Cross-lot bracing, Rakers and
Tiebacks.
Temporary support are placed within the
ground around the perimeter of the intended
area to be excavated.
When the earth is done excavate, the void will
become the basement area.
Permanent basement walls are than
constructed and after completion the
temporary support is removed.
BASEMENT
Temporary Support
Elements:-a) Steel Sheet Pile
Sheet piling is an earth retention and excavation support technique that retains soil, using steel sheet sections with
interlocking edges.
The interlocked sheet piles reduced groundwater inflow.
Vibratory hammers are used to install sheet piles. If soils are too hard or dense, an impact hammer can be used to
complete the installation. At certain sites where vibrations are a concern, the sheets can be hydraulically pushed into the
ground.
Sheet piles are also a sustainable option since recycled steel is used in their
construction, and the piles can often be reused.
Hydraulic vibratory hammer
BASEMENT
b) Cross-lot Bracing
Cross-lot bracing using steel sheet piles or I-beam as waler that are driven into the earth.
As the earth is excavated down around the sheeting (waler), tiers of horizontal bracing struts, usually of steel are added to support walers, which are beams that span across the face of the sheeting.
Where the excavation is too wide for cross-lot bracing, sloping rakers are used instead, bearing against heel blocks or other temporary footings.
Steel sheet pile or I-beam
Horizontal bracing
BASEMENT
A closer view of the cross-lot bracing supporting excavation.
Horizontal Bracing Support
BASEMENT
c) Raker
For very wide excavations, raker bracing is used.
The support for the rakers are installed at the bottom of the excavation.
Construction of the soil support and removal of the remainder of the excavation then begins.
The bottom ends of the rakers are braced against the central part of the building foundation slab.
The excavation was carried to full depth at the center first so that the foundation slab could be placed.
Prior to installation of the rakers, the lower part of the slurry trench concrete wall was supported by an earth berm. The earth berm remains at the far side of
BASEMENT
BASEMENT
d) Tiebacks
To minimize wall movement and ground settlement, tieback anchors are designed to achieve the highest stiffness.
Tieback capacity depends on the vertical and horizontal spacing of anchors and on surcharge conditions.
Typical tieback spacing ranges from 2m to 4m in the vertical, and from 1.5m to 4.5m in the
horizontal direction.
First drilling a hole with an auger and then placing a bar (tendon) in the hole, concrete is then poured in the hole and the connection with wall is made.
Different types of augers are used to drill the tieback holes. The choice of the drilling method depends on the soil/rock conditions on the site. Drilling should be done carefully since
inadequate procedures can cause significant soil losses.
BASEMENT
BASEMENT
3. Excavation with permanent embedded
retaining walls to deep basement
The construction of deep basement walls
can be costly if traditional excavation and
construction techniques are used.
Limitation on access to most commercials
sites also restrict the possibility of such an
approach.
The most common options available for the
formation of deep basement wall
(permanent embedded retaining walls) are:
a)
Contiguous piles
b)
Secant piles
BASEMENT
• Piles are installed at centers generally 150mm greater
than their diameter therefore leaving gaps in the structural
wall where soil is exposed during excavation.
• This option is suitable where the retained soil is usually
firm to stiff (not generally granular) and where the
ground water table is below the level of the maximum
excavation.
• This is the most economic option and normally the fastest
method to construct.
BASEMENT
BASEMENT
b) Secant Pile RW
• Similar to the contiguous bored pile wall but the gap
between piles is filled with an unreinforced
cement/bentonite mix (1 to 2N/mm2) for the hard/soft
wall and weak concrete (in the order of 10N/mm2) for
the hard/firm wall.
• Construction is carried out by installing the primary piles
(A) and then the secondary piles (B) are formed in
reinforced concrete, cutting into the primary piles.
• By using this form of construction the ingress of water to
any subsequent excavation can be substantially reduced.
BASEMENT
c) Diaphragm Walling
This method need to construct a R.C. retaining wall along the area
of work.
The wall is designed to reach very great depth and sequence of
work includes:
a) Construct a guide wall
b) Excavation of the trench using bentonite slurry
c) Placement of reinforcements and pumped out bentonite slurry
d) Concrete casting
BASEMENT
• The excavation of the deep trenches for segments of the
diaphragm wall can be achieved by means of hydraulic
grabs, by means of hydro fraise or by means of rotary
auguring.
• Overlapping holes are drilled to form a wall section as
opposed to individual pile holes.
• Traditionally, as the spoil is removed from the excavation
it is replaced by material called ‘bentonite’ slurry.
• This can be used to support the walls of the excavation
shaft in order to prevent collapse as the excavation
BASEMENT
• Once the excavation of a particular section of walling is
complete, a reinforcement cage may be placed into the
slurry and concrete placed using a tremie pipe.
• Diaphragm walls of 450mm to 1.0m thick can be formed
by hydraulic grabs and hydro fraise, whereas thicknesses
of up to 1.50m can be achieved using rotary methods.
• Diaphragm walls can be
constructed to depths of up to
50.00m.
• Once the diaphragm walls are
placed and completed, the deep
excavation work can proceed
virtually unobstructed.
BASEMENT
• Some degree of lateral support is normally required to
resist the bending stresses that are set up by soil and
water pressure as before since a diaphragm wall is not
normally intended to act as a pure retaining wall.
BASEMENT
Installation of rebar cage and concreting of panel
Excavation of panel and installation of rebar cage
BASEMENT
BASEMENT
Waterproofing Work
Apart from the structural design of
basement walls and floor,
waterproofing presents the greatest
problem in basement construction.
There are 3 types of basement wall
structure:
1. Tanked / Membranes
2. Waterproof / Monolithic
Structures
BASEMENT
Tanked / Membranes:
Tanked / Tanking / Membranes is a thin
material placed either on the external or
internal face of a basement wall or floor to
provide the resistance to passage of moisture
to the inside of the basement.
Membrane material can be applied
externally (external tanking) during
construction process meanwhile membrane
also can be applied to the interior face of the
walls after construction (internal tanking).
Membrane materials such as fibre-reinforced
bituminous felt, polythene sheet,
polyisobutylene plastic, epoxy resin
compounds, bituminous compounds and
mastic asphalt.
BASEMENT
BASEMENT
BASEMENT
Mastic Asphalt Tanking
Asphalt in tanking work is laid in 3 coats to the total thickness of not less than 30mm on horizontal surfaces and not less than 20mm on vertical faces. All internal angles (angle fillet) are reinforced by means of a fillet 50mm on the face, formed in 2 coats.
BASEMENT
Waterproof / Monolithic Structures:
Basement of dense reinforced concrete
using impervious aggregates for the wall
and floor to form the barrier to water
penetration.
Its considered as ‘structurally integrated
protection’ where the waterproofing is
provided by the structural wall & floor
themselves.
Shrinkage cracking can largely be
controlled by forming construction
joints at regular intervals.
Structural joints normally incorporate
water stops made from materials such as
neoprene, rubber water bar, PVC etc.
BASEMENT
BASEMENT
BASEMENT
Drained / Drained Cavities:
Cavity drain structures make allowance for
the small amount of water that may pass
through the external wall.
The basement is constructed with 2 wall
forming a void between the external and
internal wall and cavity is formed in the
walls around the basement and below the
floor.
Traditionally cavities were formed with
floor tiles which created void and two
separate wall of masonry walling.
Any water that penetrates through the
external wall or floor is guided to drainage
channels to a sump pit and remove by
BASEMENT
BASEMENT
In-situ Concrete:
Construct the basement using in-situ reinforced concrete and tradition
formwork system:
The basement structure can be constructed upon the completion of the
excavation with the basement pit properly formed and supported.
Usually this is done in a bottom-up arrangement using in-situ reinforced
concrete formed by traditional timber formwork.
However, all the works are to be done in the congested underground
environment inside the basement pit with a lot of lateral supporting
frame and work in confined space.
Special attention including accurate construction planning and spatial
design to allow room for the erection of the formwork as well as for the
placing in of the required materials and equipments, safe access etc.
should be provided.
BASEMENT
2. Prepare perimeter walling
5. Complete excavation work 6. Waterproofing at basement
9. Concreting wall & column 10. Placing grd flr reinf. 1. Before start of work
7. Placing basement flr reinf.
3. Bulk excavation 4. Excavation almost complete
8. Concreting basement floor
11. Concreting ground floor 12. Finish work
BASEMENT
Sequence of Constructing Huge Basement
1. Driven sheet pile & bulk excavation
2. Excavation, ramming bottom of excavation & bracing earthwork support
3. Lean concrete & horizontal tanking
BASEMENT
7. Reinforcement & waterproofing 8. Reiforcement
10. Preparing formwork for wall 11. Wall complete
9. Concreting
12. Formwork & reinforcement for next level
BASEMENT
13. Constructing the superstructure 14. Ditto
16. Constructing the superstructure till it gets finished
BASEMENT
CLAUSES IN UNIFORM BUILDING BY-LAWS FOR
BASEMENT CONSTRUCTION
72. (1) In the design of basement wall and similar underground
structures, provision shall be made for the lateral pressure of
adjacent soil due allowance being made for possible surcharge
from fixed on moving loads.
(2) When a portion, or the whole of the adjacent soil in below a
free water surface, computations shall be nased on the weight
of the soil diminished by bouyancy plus full hydrostatic
pressure.
(3) In the design of basement floors and similar structures
underground, the upward pressure of water, if any, shall be
taken as the full hydrostatic pressure applied over the entire
area.
(4) The hydrostatic head shall be measured from the underside of
the construction.
BASEMENT
CONSTRUCTION OF EARTHWORK SUPPORT SYSTEM
When applying the principles of
permanent embedded retaining
walls, two common construction of
earthwork support system, there are:
1.
Bottom-up Construction
2.
Top-down Construction
1. Bottom-up Construction
Figure shown the sequence of
operation where the diaphragm
walls formed using bentonite.
Retaining walls can from
contiguous pile, secant pile and steel
sheet pile.
BASEMENT
Bottom-up Construction (cont’d)
First stage in this process is to form perimeter walls.
This will become the structural walls of the basement.
Bulk excavation then take place to the desired depth (lower level
of basement).
The next stage is to form sub-structure such as foundation,
column, basement floor up to super-structure as work proceeds.
Advantages using Bottom-up Construction Method are:
a) Speed construction
b) Save cost
c) Stability of the ground around
BASEMENT
BASEMENT
Construction of basement using Bottom-up approach
BASEMENT
The overall excavation and lateral support system for a typical large-scale
basement construction project (with cut-off wall on the sides, lateral supporting frame and other temporary
work stations/platform)
Excavation carried out using excavator and rock breaker
BASEMENT
2. Top-down Construction
Top-down construction attempts to
make use of the perimeter elements
of the construction works to
provide rigidity and bracing against
loadings from the ground.
Figure shown the sequence of
operations for top-down
construction.
First stage the formation of the
permanent retaining walls to the
perimeter of the basement area.
Retaining walls can from either
contiguous pile, secant pile or
diaphragm wall.
BASEMENT
Top-down Construction (cont’d)
Next stage is the creation of the foundation
that will support the columns of the
building structure at internal location.
These columns will provide intermediate
support for the floors of the basement and
the building superstructure as work
proceeds.
In the most cases the foundations to these
columns will take the form of CFA piles
with columns attached using pile caps or
increasingly in the case of steel framed
buildings, using the ‘plunge’ method.
Excavation then take place to remove earth
from beneath the slab through appropriate
holes in the slab.
The process is then repeated until the base
slab is reached.
BASEMENT
Construction of basement using Top-down approach.
Suitable for basement of very large size with complex environment.
BASEMENT
Removal of Soil
There will have great amount of excavated soil produced during the process of excavation.
Suitable planning for the removal of the excavated material should be made in
advance in order not to cause disruption to work and incur extra costs. Soil removal can be done by the following ways.
i. Using manual method, by wheel barrow.
ii. Using bucket and lift to ground level by crane.
iii. Using hoist rack (opening has to be provided in the basement/excavation pit first).
iv. Using gantry crane (opening has to be provided in the basement/excavation pit first).
v. Using conveyor belt
vi. Using excavating machine to removal spoil, may be in stepped position in case of very deep pit.
vii. Using dump truck but access provision has to be provided in advance (such as a temporary ramp or the permanent vehicular access into a basement)
BASEMENT
Excavating machine to take up spoil from bottom
BASEMENT
Hoisting machine is provided for removing spoil from basement
Using of a gantry crane for spoil removal
BASEMENT
The use of a material hoist for the removal of spoil from the basement interior
BASEMENT
BASEMENT
References:
http://personal.cityu.edu.hk/~bswmwong/contents/ebook/construction_technology/2e.pdf – Excavation & Basement Construction http://www.cv.titech.ac.jp/~courses/atce2/Lesson5.pdf– Excavations and Excavation Supports
http://ebooks.narotama.ac.id/files/Deep%20Excavation;%20Theory%20and%20Practice/Chapter%203%20%20Excavation%20Method s%20And%20Lateral%20Supporting%20Systems.pdf– Excavation Methods and Lateral Supporting System
http://constructionduniya.blogspot.my/2012/02/top-down-construction.html– Top Down Construction Part 1
http://constructionduniya.blogspot.my/2012/05/structural-members-required-for-top.html– Top Down Construction Part 2 https://www.youtube.com/watch?v=9DBNLAJ-bxk– Video Botton Up Construction
https://www.youtube.com/watch?v=vDvyOLD5n5w – Video Top Down Construction https://www.youtube.com/watch?v=jRgxiQSw48U– Video Top Down Construction https://www.youtube.com/watch?v=sboDavo84gc– Video Top Down Construction https://www.youtube.com/watch?v=wUlQyiHfex0– Diaphragm wall construction https://www.youtube.com/watch?v=li6N6t09J-c– Diaphragm wall construction