• No results found

Risk management.pptx

N/A
N/A
Protected

Academic year: 2020

Share "Risk management.pptx"

Copied!
30
0
0

Loading.... (view fulltext now)

Full text

(1)

1

Chapter Seven

(2)

2

Risk management

This lecture will touch upon:

Definition of ‘risk’ and ‘risk management’Some ways of categorizing risk

Risk management

• Risk identification – what are the risks to a project?

• Risk analysis – which ones are really serious?

• Risk planning – what shall we do?

• Risk monitoring – has the planning worked?

(3)

3

Risk

‘ Risk is an uncertain event or condition that, if it occurs,

(4)

Risk Key Elements

It relates to the future

The future is uncertain

Risks involve a possible cause and its effect(s)

e.g. developer leaves > task delayed Causes:

The use of untrained staff Poor specifications.

An inaccurate estimate of effort. Effects:

Cost over run

Low productivity.

(5)

Boundaries of Risk Management

Every plan is based on assumptions and risk management tries to plan

for and control the situations where those assumptions become incorrect.

Risk planning is carried out at steps: 3 & 6 of stepwise project

planning.

(6)

Risk Categories

Project Risks: are risks that could prevent the

achievement of the objectives given to the project manager and the project team.

These objectives are formulated toward achieving

project success.

Project success factors:

On time

• Within budget

Required functionalityQuality

Project risks can be classified under these four

categories.

(7)

Risk Categories (cont’d) 

A different way to categorize risks:

A sociotechnical model proposed by Kalle Lyytinen and his colleagues

(8)

8

(9)

Actors : refers to all people involved in the

development of the application.

Risk: A high staff turnover, leads to expertise of value to

the project being lost.

Technology: encompasses both the technology: – Used to implement the application and – That embedded in the delivered products.

Risk: – Relating to the appropriateness of the technology and –

The possible faults in it.

(10)

Structure: describes the management structures

and systems, including those affecting planning and control.

Risk: Responsibility for managing the users involvement

at the implementation stage might not be clearly allocated.

Tasks: relates to the work planned.

• Risk: The complexity of work might lead to delays because of the additional time required integrate the large number of

components.

(11)

Nature of risks

11

1. Risks caused by the difficulties of estimation

2. Risks due to assumptions made during

planning process

3. Risks due to unforeseen events occurring

1. Risks caused by the difficulties of estimation

(12)

12

A framework for dealing with risk

The planning for risk includes these steps:

Risk identification – what risks might there be?

Risk analysis and prioritization – which are the most serious risks?Risk planning – what are we going to do about them?

(13)

13

Risk identification

Risk identification consists of listing all risks that can adversely affect the successful execution of project.

Approaches to identifying risks include:

Use of checklists – usually based on the experience of past projectsBrainstorming – getting knowledgeable stakeholders together to pool

concerns

(14)

Approaches to identifying risks include:

1. Brainstorming:

Brainstorming involves a group of people working together to identify

potential risks, causes, failure modes, hazards and criteria for decisions and/or options for treatment.

Brainstorming should stimulate and encourage free-flowing conversation

amongst a group of knowledgeable people without criticising or rewarding ideas.

The inputs for successful brainstorming include the following:

A well-defined problem.

A team of people with knowledge of the problem.A brainstorming technique.

A facilitator.

(15)

2. Checklist:

Checklists are pre-populated lists of hazards, risks or control failures that have

(16)

16

Boehm’s top 10 development risks

Risk Risk reduction techniques

Personnel shortfalls Staffing with top talent; job matching; teambuilding; training and career development; early scheduling of key personnel

Unrealistic time and cost

estimates Multiple estimation techniques; design to cost; incremental development; recording and analysis of past projects; standardization of methods

Developing the wrong software

functions Improved software evaluation; formal specification methods; user surveys; prototyping; early user manuals

Developing the wrong user

(17)

17

Boehm’s top ten risk - continued

Gold plating Requirements scrubbing, prototyping,

design to cost

Late changes to

requirements Change control, incremental development

Shortfalls in externally

supplied components Benchmarking, inspections, formal specifications, contractual agreements, quality controls

Shortfalls in externally

performed tasks Quality assurance procedures, competitive design etc

Real time performance

problems Simulation, prototyping, tuning

Development technically too

(18)

Risk Analysis

After risk identification, we need some way of assessing the

importance of risk

For risk assessment, first each risk should be rated in two ways:

Risk likelihood : it is the probability of hazard’s occurring.

Risk impact: It is the effect that the resulting problem will have on projectRisk exposure or value: It is the importance of risk.

The risk value is calculated as:

(19)
(20)

Reducing the Risks

There are 5 strategies for risk

reduction:-1. Hazard prevention:

Ex: risk of staff unavailable for meetings can be minimized by early scheduling.

2. Likelihood reduction: Some risks cannot be prevented, so their likelihoods can be reduced.

 Ex: risk of late changes in requirements specification can be reduced by prototyping.

3. Risk Avoidance : Some risks can be avoided , Ex: Risk of a project overrunning a

schedule by increasing duration estimates.

4. Risk Transfer: the impact of some risk can by transferred away from project by

taking insurance.

(21)

21

Risk planning:

Risks can be dealt with by:

• Risk acceptance

• Risk avoidance

• Risk reduction

• Risk transfer

(22)

Risk acceptance

This is the do-nothing option.

We could decide that damage inflicted by risks would be less than the

(23)

Risk Avoidance

Risk avoidance is the elimination of hazards, activities and exposures

that can negatively affect an organization's assets.

(24)

Risk reduction

Here we decide to go ahead with a course of action despite the risks,

(25)

Risk Transfer

Risk transfer is a risk management and control strategy that involves

(26)

SPM (5e) risk management© The McGraw-Hill Companies,

2011 26

Evaluating Risk to schedules:

Using PERT to evaluate the effects of

uncertainty

• Project evaluation and review technique (PERT) charts are a more sophisticated form of activity chart.

• The duration assigned to tasks by the project manager are only estimates.

Therefore, in reality the duration of an activity is a random variable with

some probability distribution.

PERT charts can be used to determine the probabilistic times for reaching

various project mile stones, including the final mile stone.

PERT charts like activity networks consist of a network of boxes and

(27)

When we use PERT ?

• PERT is used when activity times are uncertain. – Determine the duration of the project .

(28)

28

Three estimates are produced for each activity

Most likely time (m) : the time we would expect the task to take

normally

Optimistic time (a) : the shortest time that could be realistically be

expected

Pessimistic (b) : worst possible time

‘expected time’ te = (a + 4m +b) / 6

‘activity standard deviation’ S = (b-a)/6

SD is the average deviation from the estimated time.

• Standard deviation indicates degree of uncertainty for each activity OR Risk for each activity .

(29)

SPM (5e) risk management© The McGraw-Hill Companies,

2011 29

Assessing the likelihood of meeting a target

Z values are calculated for each node that has a target date. Say the target for completing A+B+C was 52 days (T)

Calculate the z value thus

z = (T – te)/s , where T is target date and te is expected date .

(30)

30

References

Related documents

Research based primarily on mixed methods of quantitative and quantitative aspects was undertaken and a small online survey conducted exploring: the experiences of foster

Select the correct answer and then mark you r selection on your answer sheet...

In order to compare the computational costs of cuTauLeaping with respect to a standard CPU-based implementation of the original tau-leaping algorithm, we carry out different batches

The studied variables were farming system and cultivated land holding, cattle breeding practice, purpose of keeping female and male Ogaden cattle, selection criteria

India, Japan, South Korea, Taiwan, Vietnam, Thailand, Malaysia, Singapore, Philippines, Indonesia, China, Hong Kong. Standard price: USD 2,500 Earlybird price:

Số người và tư vấn viên liên hệ (email, gọi điện, găpj…) trong ngày Là số khách hàng làm và gửi lại bài kiểm tra cho AROMA (tính theo ngày nhận được). Số

A prime case in point of the theoretical and practical relevance of this theme, which at the same time exposes a significant gap in past research in international marketing, can