Training Manual
V5 Acquisitions
Training Manual :
Acquisitions
2
© Softlink International 2011
Table of Contents
Set up ... 3
Suppliers ... 3
Cost Centres & Funds ... 4
Overview ... 4
Setting Up Cost Centres & Funds ... 4
Setting up Budgets ... 5
Define the budget date range ... 5
Setting up Budget Entries ... 6
Ordering Processes ... 8
Overview ... 8
Method 1: Acquisitions > Orders ... 9
Method 2: Cataloguing > Resources (Order Copy) ... 16
Method 3: Cataloguing > Resources (Retrospective Order) ... 17
Budgets and Reporting ... 18
Producing Budget Reports ... 20
Set up
Before using Acquisitions, the following areas need to be set up:
Funds and Budgets.
Suppliers
Supplier information is maintained in
To create a new Supplier, click the shortcut ne
Enter a Supplier Code then click the button.
New suppliers can be also created history) records, by clicking the Name information.
3
Before using Acquisitions, the following areas need to be set up: Suppliers, Cost Centres &
nformation is maintained in Acquisitions > Suppliers
To create a new Supplier, click the New link from the Suppliers
then click the Add
Enter the Supplier’s details, including name, address, phone, fax, e mail, etc.
The
mouse can be used to move between fields.
Click the
once all information has been entered.
so created when adding or editing Acquisitions (orders and orders history) records, by clicking the Add new Supplier link, available when entering Supplier
Cost Centres &
Acquisitions > Suppliers
link from the Suppliers menu or type
Enter the Supplier’s details, including name, address, phone, fax, e-mail, etc.
key or mouse can be used to move between fields.
Click the Save button once all information has been entered.
4
Cost Centres & Funds
Overview
Budgets are comprised of Cost Centres and Funds.
Cost Centres represent the entire budget of an area, e.g. Library.
Funds are how cost centres are broken down, e.g. Fiction, Non-Fiction, Books, AV. The way that funds are set up will depend on how your budget is managed.
Budgets are set up by combining Cost Centre and Fund combinations.
Example of how a budget is set up using Cost Centres and Funds:
Cost Centres Funds Budget Name Cost Centre / Fund combination
Library Books 2008-Library Books Library / Books
Archive Videos 2008-Library AV Library / AV
Training 2008-Library Training Library / Training Subscriptions 2008-Library Subs Library / Subscriptions
2008-Archives Books Archives / Books 2008-Archives Training Archives / Training
2008-Archives AV Archives / AV
Setting Up Cost Centres & Funds
Cost Centres and Funds are set up in Acquisitions > Cost Centres.
Select Cost Centres from the Acquisitions menu or type the shortcut cc
To create a new cost centre or fund, select New from the Cost Centres menu or type the shortcut of ne
Enter a Code for the Cost Centre or Fund.
This can be numbers or letters or a combination of both.
Click the Add button.
5
Enter the Cost Centre or Fund Name.
Enter a Description (if required). This field is for internal use only.
Click the Save button.
Repeat this process for all Cost Centres and Funds.
Setting up Budgets
Setting up budgets involves 2 steps:
1. Defining the date range of the budget,
2. Defining details of each budget item, i.e. combining Cost Centre and Fund combinations, then allocating funds.
Define the budget date range
Budgets are maintained in Acquisitions > Budgets.
Select Budgets from the Acquisitions menu or type the shortcut bu
Click on Select End of Year Processing from the Budgets menu or type the shortcut of ye
2. Duplicating existing budgets for the new financial period
When setting up a budget for the first time, only the Financial Period information needs to be entered, i.e. Start and End dates for the financial year for your organisation.
Click the button next to Start financial period.
Click the button next to End period.
Click the Go button at the top of the screen once you have selected both dates.
There is no need to enter any information into the
of the screen when setting up your initial budget information.
Setting up Budget Entries
1. Select New from the Budgets function menu or type the
2. Enter a name for the Budget and click the
It is suggested to include date as well as Cost Centre and Fund information the name of each budget. This makes it easier when selecting budget information during the ordering processes. Example: 2008
3. Select the Cost Centre and
6
Duplicating existing budgets for the new financial period
When setting up a budget for the first time, only the Financial Period information needs to be entered, i.e. Start and End dates for the financial year for your organisation.
Start to select the beginning of your
End to select the end of your financial
button at the top of the screen once you have
There is no need to enter any information into the Generate New Budgets of the screen when setting up your initial budget information.
from the Budgets function menu or type the shortcut
Enter a name for the Budget and click the Add button.
It is suggested to include date as well as Cost Centre and Fund information the name of each budget. This makes it easier when selecting budget information during the ordering
(Date) Library (Cost Centre) Books (Fund).
and Fund combination and allocate an amount for the Budget.
When setting up a budget for the first time, only the Financial Period information needs to be entered, i.e. Start and End dates for the financial year for your organisation.
Generate New Budgets section
ne
It is suggested to include date as well as Cost Centre and Fund information the name of each budget. This makes it easier when selecting budget information during the ordering
Select the Cost Centre.
Select the Fund.
Enter the Budget Amount.
Click the Save button.
The Start and End dates will have the dates entered via There is not usually any need to change these dates.
Repeat steps 1 - 3 for other budget entries.
____________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ____________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ____________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ____________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ 7
dates will have the dates entered via End of Year Processing There is not usually any need to change these dates.
for other budget entries.
____________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ____________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ________________________________________________________________________________________________ ____________________________________________________________________________________________ ________________________________________________________________________________________________
End of Year Processing.
8
© Softlink International 2011
Ordering Processes
Overview
There are 3 ways of using Acquisitions to update and maintain budget information. The method used will depend on the way that the library processes operate. This is an overview to help you choose the method that best suits your needs. Each method is explained in greater detail in this manual.
Method 1: Acquisitions > Orders
This is suitable for items not yet in the catalogue. Titles will not be viewable in OPAC until the order has been received.
Overview of process
Create Order + interim catalogue record in Acquisitions > Orders (Commits funds) Print Order in Acquisitions > Orders (optional)
When order arrives, create catalogue record (from interim record)
Receive order in Acquisitions > Orders (Spends funds in the budget). This deletes the order, and creates an Order History record
Import MARC record (optional) – Management > Import
Method 2: Cataloguing > Resources (Order Copy)
This method is suitable for new items or additional copies of existing resources. Titles will appear in OPAC before the order has been received.
Overview of process
Create new catalogue record in Cataloguing > Resources (or use existing catalogue record)
Create order using Order Copy link (this commits funds in the budget)
Print order in Acquisitions > Orders (optional)
Receive order. This deletes the order and creates an Order History record (Spends funds)
Method 3: Cataloguing > Resources (Retrospective Order)
This method is suitable for items already purchased and skips the steps of generating an order form & receiving. Basically just creates orders history information, updating Spent values in the budget.
Overview of process
In Cataloguing > Resources, using existing catalogue record, click Add Retrospective
Order
Enter purchasing information (exactly the same as receiving an order) – Spending the funds in the budget
9
Method 1: Acquisitions > Orders
This method is suitable for items not yet in the catalogue, can be linked to a catalogue record (if required) before being received.
Select Orders from the Acquisitions menu
or
type the shortcut or
Select New from the Orders menu
or
type the shortcut of ne
Select the required cataloguing template (e.g. Book).
Click the Create New Interim Resource button.
Enter the brief details of the resource being ordered. The key or mouse can be used to move between fields.
This will create a record in Cataloguing > Interim or OPAC).
The minimum details to enter would be ordering).
The fields and the order that they are displayed when entering an interim catalogue record can be adjusted by using Cataloguing > Bibtypes
function. E.g. you may wish to move the
other fields such as Subjects and Notes, which you may add once the order has been received.
Enter the details of the Order
The key or mouse can be used to move between fields. Click the information has been entered.
To enter Supplier name information, type the first few letters of the supplier’s name and a list of matching suppliers (as entered in Acquisitions > Suppliers
To select an existing supplier, click on it.
Supplier link.
Enter the number of Copies to order.
Enter the Unit price, i.e. the approximate price
If ordering in a foreign currency, enter the approximate price in the
by the currency code. Ensure a space is left between the amount and the currency code, e.g. 25 USD. This will allow you to enter an exchange rate, which will populate the field accordingly.
10
Cataloguing > Interim (this is not visible in Cataloguing > Resources
minimum details to enter would be Title and ISBN (along with any other fields required when
The fields and the order that they are displayed when entering an interim catalogue record
Cataloguing > Bibtypes or by using the System > Page
function. E.g. you may wish to move the ISBN field closer to the Title field and remov other fields such as Subjects and Notes, which you may add once the order has been received.
key or mouse can be used to move between fields. Click the Save button once all
information, type the first few letters of the supplier’s name and a list of
Acquisitions > Suppliers) will be displayed.
To select an existing supplier, click on it. A new Supplier can be created by clicking the
to order.
approximate price per copy.
If ordering in a foreign currency, enter the approximate price in the Foreign
by the currency code. Ensure a space is left between the amount and the currency code, . This will allow you to enter an exchange rate, which will populate the
Cataloguing > Resources
(along with any other fields required when
The fields and the order that they are displayed when entering an interim catalogue record
System > Page
field and remove other fields such as Subjects and Notes, which you may add once the order has been received.
button once all
information, type the first few letters of the supplier’s name and a list of
by clicking theAdd New
Foreign field followed
The Total is calculated and displayed amount not yet allocated to a budget.
Click the Add button to select Budget
Repeat the process of adding Budget entries until the been allocated to budgets)
Budget entries can be adjusted by using the
If required, multiple Budget entries can be assigned, i.e. to share the cost between different areas.
The button can be used to select the required dates.
The Order Method field allows you to select how the item will be ordered.
11
calculated and displayed. Total = Copies x Unit. The Balance field shows the amount not yet allocated to a budget.
Budget allocations.
Select a Budget entry from the list.
Select the Amount as %, fraction ½, 2/3, etc) or actual amount.
Click the OK button.
Repeat the process of adding Budget entries until the Balance is 0.00 (i.e. the full amount has
d by using the Modify and Delete buttons.
If required, multiple Budget entries can be assigned, i.e. to share the cost between different
If required, enter the names of the
Borrowers who requested the item being
ordered. A borrower can be selected for each copy being ordered. E.g. if o
is ordered, only one name can be entered.
The Requested date defaults to the current date and can be changed if required.
Enter a Required date, if necessary. Once this date has passed, the order will be regarded as late and will appear in the
Acquisitions > Late Orders
The Ordered date defaults to the current date and can be changed if required.
button can be used to select the required dates.
field allows you to select how the item will be ordered.
field shows the
entry from the list.
as %, fraction (e.g. or actual amount.
he full amount has
If required, multiple Budget entries can be assigned, i.e. to share the cost between different
If required, enter the names of the
who requested the item being ordered. A borrower can be selected for each copy being ordered. E.g. if only 1 copy is ordered, only one name can be entered.
date defaults to the current date and can be changed if required.
date, if necessary. Once this date has passed, the order will be regarded as late and will appear in the
Late Orders list.
12
Click the Save button once all information has been entered.
This process creates an order in Acquisitions > Orders, and updates the amount Committed for the selected budget(s).
To make changes to the order, click the Edit button or type the shortcut ed
If the Supplier has an email address, the Email link will be displayed. Click the Email link or type the shortcut em to send the order to the supplier via email.
Print the order by clicking the Print link or by typing the shortcut pr
An electronic document will be created. Click the Download Order letter report link to open and print the letter.
Click the Update Printed Orders button.
Receiving an ordered item
To receive an ordered item once it arrives from the Supplier:
Select Orders from the Acquisitions menu
or
type the shortcut or
Alternatively, select menu then Search
After locating the required supplier, click the r
Select the required item by clicking the number on the left side of the screen.
Enter the number of copies received and click the Receive button.
Partial orders can be received if required. Example: If order was for 3 copies, but only 2 arrive.
13
elect Suppliers from the Acquisitions
Search from the Suppliers menu.
After locating the required supplier, click the record number on the left side of the screen
Click the Current Orders link.
The number in brackets indicates the number of items (titles) on order.
Select the required item by clicking the number on the left side of the screen.
Click the Receive button the keyboard shortcut
Enter the number of copies received and
received if Example: If order was for 3
on the left side of the screen.
link.
The number in brackets indicates the on order.
Enter the Invoice Number, Invoice Date
Dates must be entered in the format dd/mm/yyyy or can be selected from a calendar by clicking
the button.
The Date Certified is the date that will be used for budget calculations.
Enter the Actual Price (as per the item’s invoice) into the
If a foreign currency is being used, enter the price into the
currency code, e.g. 30 USD, followed by the
The Actual Price amount will update the
The Budget allocation can be adjusted, if required, by using the
Click the Save button at the top of the screen,
An Order History record is created, and is viewable in If the order was completed (i.e. all copies
If you answer “No”, the next step will not be displayed, i.e. no copy records will be created (you will not be prompted to enter barcodes).
14
Invoice Date and Date Certified.
Dates must be entered in the format dd/mm/yyyy or can be selected from a calendar by clicking
is the date that will be used for budget calculations.
(as per the item’s invoice) into the Unit field.
If a foreign currency is being used, enter the price into the Foreign field, including the
currency code, e.g. 30 USD, followed by the key (to use the currency calculator).
amount will update the Spent amount of the budget(s) specified.
allocation can be adjusted, if required, by using the Add, Modify and
at the top of the screen, once all information has been entered.
Order History record is created, and is viewable in Acquisitions > Orders History (i.e. all copies received), the order record is deleted.
Click Yes.
A catalogue record will be created in Cataloguing >
Resources, based on the Cataloguing > Interim
If you answer “No”, the next step will not be displayed, i.e. no copy records will be created will not be prompted to enter barcodes).
Dates must be entered in the format dd/mm/yyyy or can be selected from a calendar by clicking
field, including the
key (to use the currency calculator).
and Delete buttons.
once all information has been entered.
Acquisitions > Orders History
Cataloguing > Cataloguing > Interim record.
A copy record is added for each barcode specified. You may need to edit the resultant copy record (by clicking the E link) to change
Resource Loan Category.
The default Resource Loan category is defined in parameter 2100 Resource Loan Category (Default)
In the copy record(s), the Price field is populated with the Quote
while the Cost field is populated with the Actual Price from the order history record. Both values can be edited in the copy record without affecting your budget figures.
Click the Edit button at the top of the screen to (e.g. Title, Author, Subjects, Series, etc.
If available, a MARC record could be imported using
catalogue record to be updated with more complete details (e match on ISBN.
Click the Orders History link to view the Orders History information.
15
The receiving process will create copies information automatically, based on the number of copies received.
Type or scan the barcode. If typing a barcode, click the button.
The barcode is added to the list.
The Remove button can be used to delete any incorrect barcodes.
Click the Save button.
A copy record is added for each barcode specified. You may need to edit the resultant copy change information such as the Collection, Classification
The default Resource Loan category is defined in Management > Parameters
2100 Resource Loan Category (Default)
field is populated with the Quoted Price from the order record, field is populated with the Actual Price from the order history record.
Both values can be edited in the copy record without affecting your budget figures.
button at the top of the screen to make any changes to the resource information (e.g. Title, Author, Subjects, Series, etc.
If available, a MARC record could be imported using System > Import. This would allow the catalogue record to be updated with more complete details (e.g. subjects, series, etc) and c
link to view the Orders History information.
The receiving process will create copies information automatically, based on the number of copies received.
Type or scan the barcode. If typing a barcode, click the Add
button can be used to delete any incorrect
A copy record is added for each barcode specified. You may need to edit the resultant copy
, Classification and
Management > Parameters in
Price from the order record, field is populated with the Actual Price from the order history record.
make any changes to the resource information
16
Method 2: Cataloguing > Resources (Order Copy)
This method is used when ordering new resources or additional copies of existing resources. Titles will be visible in OPAC before the order has been received.
Add a catalogue record in Cataloguing > Resources (minimum information suggested for the catalogue record would be title and ISBN) or locate the existing record using Search from the Resources function menu
View the details of the resource by clicking the record number on the left side of the screen.
Click the Order Copy button or type the shortcut rd.
17
Method 3: Cataloguing > Resources (Retrospective Order)
This method is suitable for items already purchased and skips the steps of creating and receiving the order. This method basically just creates orders history information and updates Spent values on the selected budget(s).
In Cataloguing > Resources, select the catalogue record relating to the already purchased item. Display the details by clicking the record number on the left side of the screen.
Click the Add Retrospective Order button.
Enter the information of the purchase, including Supplier name, Invoice Number and Invoice
Date, Date Certified, Number of Copies, Actual Price and Budget details.
This is the same type of information entered when using the Receive function in Acquisitions > Orders.
18
An Orders History record is created based on the information entered.
Click the View Catalogue link to view the catalogue record in Cataloguing > Resources.
The Add Retrospective Order function does not create Copy records.
If required, this has to be done manually by clicking the Add Copy link.
Click the Orders History link to view or maintain the orders history information that was created using Add Retrospective Order.
Budgets and Reporting
Budget information can be viewed at any time through Acquisitions > Budgets.
Select Budgets from the Acquisitions menu or type the shortcut bu.
Cost Centre, Fund, Budget Amount
changed.
Click the Save button when finished.
Committed, Cancelled and Spent
Editing Price and Cost information in the copies area of Cataloguing > Resources will not affect the budget in any way.
Committed is updated whenever an order record is created.
order’s Quoted Price in Acquisitions >
Cancelled is updated whenever an order is cancelled in Acquisitions > Orders.
Spent is updated whenever an order is received in Acquisitions > Orders or when Add
Retrospective Order is used in Cataloguing > Resource
To change this value, you would have to edit the appropriate records in Acquisitions > Orders History.
19
Committed = total of amounts for items on order.
This amount is updated whenever a new order record is created in Acquisitions > Orders (or when using the Order Copy button in Cataloguing > Resources_
Cancelled = total amount of cancelled orders. This
amount is updated when an order is cancelled in Acquisitions > Orders.
Spent = total amount spent on ordered items. This
gets updated when orders are received in Acquisitions > Orders, or a retrospective order is created via Cataloguing > Resources.
Click the Edit link to make changes to the budget
Budget Amount, and Start and End dates are the only fields that can be
button when finished.
values cannot be updated manually.
Editing Price and Cost information in the copies area of Cataloguing > Resources will not affect the budget in any way.
is updated whenever an order record is created. Therefore, by editing an existing order’s Quoted Price in Acquisitions > Orders, this value will be changed.
whenever an order is cancelled in Acquisitions > Orders.
d whenever an order is received in Acquisitions > Orders or when Add Retrospective Order is used in Cataloguing > Resources.
To change this value, you would have to edit the appropriate records in Acquisitions > Orders = total of amounts for items on order. This amount is updated whenever a new order record is created in Acquisitions > Orders (or when using the Order Copy button in Cataloguing >
= total amount of cancelled orders. This updated when an order is cancelled in
= total amount spent on ordered items. This gets updated when orders are received in
Acquisitions > Orders, or a retrospective order is created via Cataloguing > Resources.
link to make changes to the budget.
dates are the only fields that can be
Editing Price and Cost information in the copies area of Cataloguing > Resources will not
Therefore, by editing an existing
d whenever an order is received in Acquisitions > Orders or when Add
Producing Budget Reports
Budget reports are based on current orders history.
Select Budgets
Select Calculate Report from the Budgets
Enter the Date Range by either selecting a pre
Month or Last Month
or enter a Start date and End date
or click the button next to Start date
Select a Report Type – Summary
Click the GO button and the budget report will be displayed on the screen.
20
Budget Reports
Budget reports are based on current orders (cancelled and un-received) and (received)
Budgets from the Acquisitions menu.
from the Budgets menu or type shortcut cu.
by either selecting a pre-defined date range: YTD (Year to Date),
in the format dd/mm/yyyy
Start date and End date to select the required range of dates.
or Detailed.
button and the budget report will be displayed on the screen.
(received) orders
(Year to Date), This
21
Summary Report
The Budget amounts can be adjusted by clicking on them.
Enter the new Amount then click the Update button.
All amounts affected by the change including totals, sub-totals and balances will be re-calculated and displayed.
Detailed report
22
© Softlink International 2011
Notes:
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________
______________________________________________________________________________