• No results found

HAZOP

N/A
N/A
Protected

Academic year: 2021

Share "HAZOP"

Copied!
30
0
0

Loading.... (view fulltext now)

Full text

(1)

0

(2)

Loss Prevention

Loss prevention in chemical industries involve:

–Identification and assessment of major hazards

–Control of hazards by containment, substitution, improved maintenance

–Control of process by utilizing automatic control, relief system , interlock, alarm

(3)

Loss Prevention

The major formalized techniques are:

– Hazards and Operability (HAZOP)

– Fault Tree Analysis (FTA)

– Failure mode-and-effect analysis (FMEA)

– Safety indexes

(4)

What is HAZOP?

• Systematic technique to IDENTIFY potential HAZard and OPerating problems

• A qualitative technique based on “guide-words” to help provoke thoughts about the way deviations from the intended operating conditions can lead to hazardous situations or operability problems

• HAZOP is basically for safety

(5)

4

HAZOP study are applied during : • Normal operation

• Foreseeable changes in operation, e.g. upgrading, reduced output, plant start-up and shut-down

• Suitability of plant materials, equipment and instrumentation • Provision for failure of plant services, e. g . steam, electricity,

cooling water

• Provision for maintenance.

(6)

HAZOP Team

• Team Leader

• Team Secretary

• Process Engineer

• Mechanical Engineer

• Commissioning/Operations

• Engineer/Manager

• Instrument Engineer

HAZOP studies are carried out using a

`brainstorming' approach by a team, chaired and coordinated by a qualified person experienced in HAZOPs:

(7)

6

• HAZOP is a systematic, reasonably comprehensive and flexible.

• It gives good identification of cause and excellent identification of critical deviations.

• The use of keywords is effective and the whole group is able to participate.

• HAZOP is an excellent well-proven method for studying large plant in a specific manner.

(8)

7

• HAZOP is very time consuming and can be laborious with a tendency for boredom for analysts.

• It tends to be hardware-oriented and process-oriented, although the technique should be amenable to human error application.

• HAZOP does not identify all causes of deviations and therefore omits many scenarios.

(9)

8

NONE /No e.g., NO FLOW caused by blockage; pump failure; valve closed or jammed :

REVERSE Opposite, e.g., REVERSE FLOW caused by pump

failure

MORE Quantitative increase, e.g., MORE FLOW, Temp,

LESS Quantitative increase, e.g., LESS FLOW, Temp,

As Well As Qualitative increase, e.g. impurity

.

PART OF Qualitative decrease, Change in composition high or

low concentration of mixture; additional reactions in reactor or other location ; feed change.

Other than Nothing of the intent happen, completely different

occurs

(10)

HAZOP Steps

• These guide words are applied to flow,

temperature, pressure, liquid level and composition. • Deviation of these variables from normal operation

is considered

• The consequences of these deviations on the process is then assessed.

• The measures needed to correct these consequences are then established

This process enables a comprehensive evaluation of

Hazard control systems and produces recommendations for any necessary modifications. The overall result is a reduction in both hazards and potential operational problems

(11)
(12)

11

HAZOP STUDY REPORT FORM TITLE :

Sheet 1 of LINE 1 :

DEVIATION

CAUSES CONSEQUENCES EXISTING PROVISIONS ACTIONS, QUESTIONS OR

RECOMMENDATIONS

(13)

Storage Tank

Storage Tank TIA FICA PI PICA LIA To flare To atmosphere Nitrogen To process From tank trucks H H L L H V-2 V-3 V-1 V-5 V-4 FV-1 V-8 V-7 PV-2 PV-1

RV-1 Equipment & Valve

FV Flow control valve

T Tank

P Pump

PV Pressure control valve RV Relief valve V Valve Instrument L Level T Temperature P Pressure F Flow I Indicator C Controller A Alarm

(14)

HAZOP Table - level

Action Safe guard Consequences Deviation Cause Level

Estimate release quantity LIA Potential fire Reagent release 1. Rupture discharge line Less

Estimate release quantity LIA Potential fire Reagent release 2. V3 open or broken V1 protection LIA Potential fire Reagent release 3. V1 open or broken

What external event cause tank rupture LIA

Potential fire Reagent release

4. Tank rupture

Does RV1 allow for liquid release? Consider high level alarm

shutoff LIA

Reagent release via RV1

Overfill 5. Too much truck

unload More

Consider check valve at pump discharge Consider high level alarm

shutoff at feed LIA

Reagent release via RV1 Overfill 6. Reverse flow from process Same as less NO

(15)

HAZOP Table - pressure

Pressure Consider independent PLA PICA Potential fire Reagent release 9. Break in nitrogen or flare line Less

Consider vacuum break valve PICA Reagent release Tank implode 10. Lose nitrogen Consider PAL PICA Reagent release Tank implodes 11. PV2 fails closed

Tank not designed for vacuum Reagent release Tank implodes 12. PICA fails, closing PV2 What PV1 and RV1 capacity PICA Tank rupture if RV1 fails

Reagent release via RV1 13. PICA fails, closing PV1 More Consider independent PAH PICA Tank rupture if RV1 fails Reagent release via

RV1 14. PV1 fails closed Is V7 locked open PICA Tank rupture if RV1 fails

Reagent release via RV1

15. V7 closed

Consider second high level shutoff PICA Tank rupture if RV1 fails Truck unload 16. Overfill tank

What prevent high temp of feed Consider PAH PICA Tank rupture if RV1 fails Reagent release in RV1 17. Temperature of inlet higher than normal Consider PAH

Consider sampling before unloading PICA Tank rupture if RV1 fails Reagent release in RV1 18. Volatile impurities in feed

(16)

Hazop Table - composition

Action Safe guard Consequences Deviation Cause Composition

Consider sampling before unload

Tank rupture Possible reaction

7. Wrong reagent Other than

Are other material delivered in tank Are unloading connection

different Problem in reactor

8. Impurities in reagent As well as

(17)

HAZOP Table - Temperature

Temperature

What are temp limits of tank

Thermal stress on tank Possible vacuum

19. Temperature of inlet cooler than usual Less

What are pressure limits of tank

Thermal stress on tank See 9-12

20. Low tank pressure

What are temp limits on tank

Thermal stress on tank See 17

21. temperature of inlet is higher than usual High

What could cause external fire What are fire protection

capabilities Is fire protection adequate Reagent release Tank fails 22. external fire

(18)

17

Preliminary HAZOP Example

T C

Cooling Coils Monomer

Feed

Cooling Water to Sewer

Cooling Water In

Thermocouple

Refer to reactor system shown.

The reaction is exothermic. A cooling system is provided to remove the excess energy of reaction. In the event of cooling function is lost, the temperature of reactor would increase. This would lead to an increase in reaction rate leading to additional energy release.

The result could be a runaway reaction with pressures exceeding the bursting pressure of the reactor. The temperature within the reactor is measured and is used to control the cooling water flow rate by a valve.

(19)

18

Preliminary HAZOP on Reactor

Guide Word Deviation Causes Consequences Action

NO No cooling Cooling water valve

malfunction

Temperature increase in

reactor Install high temperature alarm (TAH)

REVERSE Reverse cooling

flow

Failure of water source resulting in backward flow

Less cooling, possible runaway reaction

Install check valve

MORE More cooling flow Control valve failure,

operator fails to take action on alarm

Too much cooling, reactor cool Instruct operators on procedures

AS WELL AS Reactor product

in coils More pressure in reactor Off-spec product

Check maintenance procedures and schedules

OTHER THAN Another material

besides cooling water

Water source

contaminated May be cooling inefffective and effect on the reaction

If less cooling, TAH will detect. If detected, isolate water source. Back up water source?

(20)

19

Case Study – Shell & Tube Heat

Exchanger

Using relevant guide works, perform HAZOP study on shell & tube

heat exchanger

Process fluid

(21)

20

HAZOP on Heat Exchanger

Guide Word Deviation Causes Consequences Action

NONE No cooling water flow Failure of inlet cooling

water valve to open

Process fluid temperature is not lowered accordingly

Install Temperature indicator before and after the process fluid line Install TAH

MORE More cooling water

flow

Failure of inlet cooling water valve to close

Output of Process fluid temperature too low

Install Temperature indicator before and after process fluid line

Install TAL

LESS Less cooling water Pipe leakage Process fluid temperature too

low

Installation of flow meter

REVERSE Reverse process fluid

flow

Failure of process fluid inlet valve

Product off set Install check valve (whether it is crucial have to check?)

CONTAMINATION Process fluid

contamination

Contamination in cooling water

Outlet temperature too low Proper maintenance and operator alert

(22)

Documents needed for HAZOP Study

• For Preliminary HAZOP

– Process Flow Sheet ( PFS or PFD ) – Description of the Process

• For Detailed HAZOP

– Piping and Instrumentation Diagram ( P & ID ) – Process Calculations

– Process Data Sheets – Instrument Data Sheets – Interlock Schedules

– Layout Requirements

– Hazardous Area Classification – Description of the Process

(23)

Planning for HAZOP

Additional required information:

• Safety procedures documents

• Relief/venting philosophy

• Chemical involved

• Piping specifications

(24)

Planning for HAZOP

• Carry out the study

• Record the results (may need a secretary) • Follow-up of actions noted

– final report contain resolution of all recommended actions

– must appoint someone as leader to check progress of action

– team may meet again if answers to questions do not simply lead to an action

– team may meet again if significant design changes in interim report

(25)

Responsibility of HAZOP Team

Members

HAZOP leader

• Plan sessions and timetable • Control discussion

• Limit discussion

• Encourage team to draw conclusion

• Ensure secretary has time for taking note • Keep team in focus

• Encourage imagination of team members • Motivate members

• Discourage recriminations • Judge importance issues

(26)

HAZOP Secretary

• Take adequate notes

• Record documentations

• Inform leader if more time required in taking

notes

• If unclear, check wording before writing

• Produce interim lists of recommendations

• Produce draft report of study

• Check progress of chase action

• Produce final report

Responsibility of HAZOP Team

Members

(27)

Process Engineer

• Provide a simple description

• Provide design intention for each process

unit

• Provide information on process conditions

and design conditions

• Provide a simple description

• Provide design intention for each process

unit

• Provide information on process conditions

and design conditions

Responsibility of HAZOP Team

Members

(28)

Mechanical Design Engineer

• Provide specification details

• Provide vendor package details

• Provide equipment and piping layout

information

Instrument Engineer

• Provide details of control philosophy

• Provide interlock and alarm details

• Provide info on shutdown, safety features

Responsibility of HAZOP Team

Members

(29)

Plant Engineer or Manager

• Provide information on compatibility with any existing adjacent plant

• Provide details of site utilities and services

• Provide (for study on existing plant) any update on maintenance access and modifications

Shift Operating Engineer or Supervisor

• Provide guidance on control instrumentation

integrity from an operating experience view point • Provide (for study on existing plant) information on

plant stability at the specified control parameters • Provide information on experienced operability

deviations of hazard potential

Responsibility of HAZOP Team

Members

(30)

Chemist

• Provide details of process chemistry

• Provide details of process hazards

(polymerisations, byproducts, corrosion etc)

Project Engineer

• Provide details of cost and time estimation

and also budget constraints.

• Ensure rapid approval if required

Responsibility of HAZOP Team

Members

References

Related documents

The toggle on the face of the lock at the edge of the door will automatically be pushed in at the top of the toggle when the dead bolt is thrown by either the turn piece or the

Material comprising three sets of Scots pine progeny (seed orchard test series) in ten field trials (a subset of the 36 analysed in I ) was used to further evaluate genetic

62 Lord Cultural Resources, “Interpretative Plan: Permanent Exhibitions Canadian Museum o f Immigration at Pier 21” Public papers at the Canadian M useum o f Immigration at

It produces a range of materials on finance-related matters including Equity release schemes –raising money from your home and Getting financial advice (this guide includes a list

The results of this research can be defined if a company gets an unqualified opinion, the faster it is to provide their financial reports because it is considered good information

Grabbing this opportunities will ensure a win-win situation where Proton could also benefit from the collaboration and foreing companies could penetrate into

This study evaluated several standing tree predictive methods, used to screen and select Series iii clones, compared results from a sawing study of 3-m butt logs that

Finding the best recruitment software for your company is one of the biggest decisions a recruitment organisation will make and is one that is often