0
Loss Prevention
Loss prevention in chemical industries involve:
–Identification and assessment of major hazards
–Control of hazards by containment, substitution, improved maintenance
–Control of process by utilizing automatic control, relief system , interlock, alarm
Loss Prevention
The major formalized techniques are:
– Hazards and Operability (HAZOP)
– Fault Tree Analysis (FTA)
– Failure mode-and-effect analysis (FMEA)
– Safety indexes
What is HAZOP?
• Systematic technique to IDENTIFY potential HAZard and OPerating problems
• A qualitative technique based on “guide-words” to help provoke thoughts about the way deviations from the intended operating conditions can lead to hazardous situations or operability problems
• HAZOP is basically for safety
4
HAZOP study are applied during : • Normal operation
• Foreseeable changes in operation, e.g. upgrading, reduced output, plant start-up and shut-down
• Suitability of plant materials, equipment and instrumentation • Provision for failure of plant services, e. g . steam, electricity,
cooling water
• Provision for maintenance.
HAZOP Team
• Team Leader
• Team Secretary
• Process Engineer
• Mechanical Engineer
• Commissioning/Operations
• Engineer/Manager
• Instrument Engineer
HAZOP studies are carried out using a
`brainstorming' approach by a team, chaired and coordinated by a qualified person experienced in HAZOPs:
6
• HAZOP is a systematic, reasonably comprehensive and flexible.
• It gives good identification of cause and excellent identification of critical deviations.
• The use of keywords is effective and the whole group is able to participate.
• HAZOP is an excellent well-proven method for studying large plant in a specific manner.
7
• HAZOP is very time consuming and can be laborious with a tendency for boredom for analysts.
• It tends to be hardware-oriented and process-oriented, although the technique should be amenable to human error application.
• HAZOP does not identify all causes of deviations and therefore omits many scenarios.
8
NONE /No e.g., NO FLOW caused by blockage; pump failure; valve closed or jammed :
REVERSE Opposite, e.g., REVERSE FLOW caused by pump
failure
MORE Quantitative increase, e.g., MORE FLOW, Temp,
LESS Quantitative increase, e.g., LESS FLOW, Temp,
As Well As Qualitative increase, e.g. impurity
.
PART OF Qualitative decrease, Change in composition high or
low concentration of mixture; additional reactions in reactor or other location ; feed change.
Other than Nothing of the intent happen, completely different
occurs
HAZOP Steps
• These guide words are applied to flow,
temperature, pressure, liquid level and composition. • Deviation of these variables from normal operation
is considered
• The consequences of these deviations on the process is then assessed.
• The measures needed to correct these consequences are then established
This process enables a comprehensive evaluation of
Hazard control systems and produces recommendations for any necessary modifications. The overall result is a reduction in both hazards and potential operational problems
11
HAZOP STUDY REPORT FORM TITLE :
Sheet 1 of LINE 1 :
DEVIATION
CAUSES CONSEQUENCES EXISTING PROVISIONS ACTIONS, QUESTIONS OR
RECOMMENDATIONS
Storage Tank
Storage Tank TIA FICA PI PICA LIA To flare To atmosphere Nitrogen To process From tank trucks H H L L H V-2 V-3 V-1 V-5 V-4 FV-1 V-8 V-7 PV-2 PV-1RV-1 Equipment & Valve
FV Flow control valve
T Tank
P Pump
PV Pressure control valve RV Relief valve V Valve Instrument L Level T Temperature P Pressure F Flow I Indicator C Controller A Alarm
HAZOP Table - level
Action Safe guard Consequences Deviation Cause LevelEstimate release quantity LIA Potential fire Reagent release 1. Rupture discharge line Less
Estimate release quantity LIA Potential fire Reagent release 2. V3 open or broken V1 protection LIA Potential fire Reagent release 3. V1 open or broken
What external event cause tank rupture LIA
Potential fire Reagent release
4. Tank rupture
Does RV1 allow for liquid release? Consider high level alarm
shutoff LIA
Reagent release via RV1
Overfill 5. Too much truck
unload More
Consider check valve at pump discharge Consider high level alarm
shutoff at feed LIA
Reagent release via RV1 Overfill 6. Reverse flow from process Same as less NO
HAZOP Table - pressure
Pressure Consider independent PLA PICA Potential fire Reagent release 9. Break in nitrogen or flare line LessConsider vacuum break valve PICA Reagent release Tank implode 10. Lose nitrogen Consider PAL PICA Reagent release Tank implodes 11. PV2 fails closed
Tank not designed for vacuum Reagent release Tank implodes 12. PICA fails, closing PV2 What PV1 and RV1 capacity PICA Tank rupture if RV1 fails
Reagent release via RV1 13. PICA fails, closing PV1 More Consider independent PAH PICA Tank rupture if RV1 fails Reagent release via
RV1 14. PV1 fails closed Is V7 locked open PICA Tank rupture if RV1 fails
Reagent release via RV1
15. V7 closed
Consider second high level shutoff PICA Tank rupture if RV1 fails Truck unload 16. Overfill tank
What prevent high temp of feed Consider PAH PICA Tank rupture if RV1 fails Reagent release in RV1 17. Temperature of inlet higher than normal Consider PAH
Consider sampling before unloading PICA Tank rupture if RV1 fails Reagent release in RV1 18. Volatile impurities in feed
Hazop Table - composition
Action Safe guard Consequences Deviation Cause CompositionConsider sampling before unload
Tank rupture Possible reaction
7. Wrong reagent Other than
Are other material delivered in tank Are unloading connection
different Problem in reactor
8. Impurities in reagent As well as
HAZOP Table - Temperature
Temperature
What are temp limits of tank
Thermal stress on tank Possible vacuum
19. Temperature of inlet cooler than usual Less
What are pressure limits of tank
Thermal stress on tank See 9-12
20. Low tank pressure
What are temp limits on tank
Thermal stress on tank See 17
21. temperature of inlet is higher than usual High
What could cause external fire What are fire protection
capabilities Is fire protection adequate Reagent release Tank fails 22. external fire
17
Preliminary HAZOP Example
T C
Cooling Coils Monomer
Feed
Cooling Water to Sewer
Cooling Water In
Thermocouple
Refer to reactor system shown.
The reaction is exothermic. A cooling system is provided to remove the excess energy of reaction. In the event of cooling function is lost, the temperature of reactor would increase. This would lead to an increase in reaction rate leading to additional energy release.
The result could be a runaway reaction with pressures exceeding the bursting pressure of the reactor. The temperature within the reactor is measured and is used to control the cooling water flow rate by a valve.
18
Preliminary HAZOP on Reactor
Guide Word Deviation Causes Consequences Action
NO No cooling Cooling water valve
malfunction
Temperature increase in
reactor Install high temperature alarm (TAH)
REVERSE Reverse cooling
flow
Failure of water source resulting in backward flow
Less cooling, possible runaway reaction
Install check valve
MORE More cooling flow Control valve failure,
operator fails to take action on alarm
Too much cooling, reactor cool Instruct operators on procedures
AS WELL AS Reactor product
in coils More pressure in reactor Off-spec product
Check maintenance procedures and schedules
OTHER THAN Another material
besides cooling water
Water source
contaminated May be cooling inefffective and effect on the reaction
If less cooling, TAH will detect. If detected, isolate water source. Back up water source?
19
Case Study – Shell & Tube Heat
Exchanger
• Using relevant guide works, perform HAZOP study on shell & tube
heat exchanger
Process fluid
20
HAZOP on Heat Exchanger
Guide Word Deviation Causes Consequences Action
NONE No cooling water flow Failure of inlet cooling
water valve to open
Process fluid temperature is not lowered accordingly
Install Temperature indicator before and after the process fluid line Install TAH
MORE More cooling water
flow
Failure of inlet cooling water valve to close
Output of Process fluid temperature too low
Install Temperature indicator before and after process fluid line
Install TAL
LESS Less cooling water Pipe leakage Process fluid temperature too
low
Installation of flow meter
REVERSE Reverse process fluid
flow
Failure of process fluid inlet valve
Product off set Install check valve (whether it is crucial have to check?)
CONTAMINATION Process fluid
contamination
Contamination in cooling water
Outlet temperature too low Proper maintenance and operator alert
Documents needed for HAZOP Study
• For Preliminary HAZOP
– Process Flow Sheet ( PFS or PFD ) – Description of the Process
• For Detailed HAZOP
– Piping and Instrumentation Diagram ( P & ID ) – Process Calculations
– Process Data Sheets – Instrument Data Sheets – Interlock Schedules
– Layout Requirements
– Hazardous Area Classification – Description of the Process
Planning for HAZOP
Additional required information:
• Safety procedures documents
• Relief/venting philosophy
• Chemical involved
• Piping specifications
Planning for HAZOP
• Carry out the study
• Record the results (may need a secretary) • Follow-up of actions noted
– final report contain resolution of all recommended actions
– must appoint someone as leader to check progress of action
– team may meet again if answers to questions do not simply lead to an action
– team may meet again if significant design changes in interim report
Responsibility of HAZOP Team
Members
HAZOP leader
• Plan sessions and timetable • Control discussion
• Limit discussion
• Encourage team to draw conclusion
• Ensure secretary has time for taking note • Keep team in focus
• Encourage imagination of team members • Motivate members
• Discourage recriminations • Judge importance issues
HAZOP Secretary
• Take adequate notes
• Record documentations
• Inform leader if more time required in taking
notes
• If unclear, check wording before writing
• Produce interim lists of recommendations
• Produce draft report of study
• Check progress of chase action
• Produce final report
Responsibility of HAZOP Team
Members
Process Engineer
• Provide a simple description
• Provide design intention for each process
unit
• Provide information on process conditions
and design conditions
• Provide a simple description
• Provide design intention for each process
unit
• Provide information on process conditions
and design conditions
Responsibility of HAZOP Team
Members
Mechanical Design Engineer
• Provide specification details
• Provide vendor package details
• Provide equipment and piping layout
information
Instrument Engineer
• Provide details of control philosophy
• Provide interlock and alarm details
• Provide info on shutdown, safety features
Responsibility of HAZOP Team
Members
Plant Engineer or Manager
• Provide information on compatibility with any existing adjacent plant
• Provide details of site utilities and services
• Provide (for study on existing plant) any update on maintenance access and modifications
Shift Operating Engineer or Supervisor
• Provide guidance on control instrumentation
integrity from an operating experience view point • Provide (for study on existing plant) information on
plant stability at the specified control parameters • Provide information on experienced operability
deviations of hazard potential