Orange County Convention Center Orlando, Florida | June 3-5, 2014
Using SAP PS Earned Value to Manage IT Projects
What is a typical problem with IT projects?
What is Earned Value (EV)? How can EV help IT projects?
Steps to get IT projects ready for Earned Value (EV)
Steps to set up SAP EV in Project System (PS) How to make the best use of EV for your
organization
Unlike projects that build physical objects such as buildings or houses, it is hard to measure progress on IT projects
On IT projects, it is easy to spend money without knowing where it is being spent
Money is spent with no meaningful or measurable progress
Money & resources are gone and you still have work that is
not complete
By the time you realize your mistakes, it is TOO LATE
You cannot Manage what you cannot Measure
Earned Value Management is a project management technique for measuring project performance and progress in an objective manner.
EV is commonly used by government contractors and companies that work on Engineering and
Construction projects, such as Power Plants and Aircraft Development
NASA, DOD, DOE, Utilities, Aerospace & Defense Contractors
and Construction Companies are some of the biggest EV users
Using the objectivity EV provides, it can help
alleviate the typical IT problem we discussed earlier
For more examples and explanations of EV, please
refer to http://en.wikipedia.org/wiki/Earned_value
Most Plan vs. Actual Reports show planned vs. actual only
This does not provide enough insight into progress
Is the project shown below…behind or ahead on schedule
and budget?
Most Reports do not show
Progress
0 20 40 60 80 100 120 140 1 2 3 4 5 6 Cum. Budget Cum. Actual Period 1 2 3 4 5 6 Cum. Budget 20 40 60 80 100 120 Cum. Actual 17 34 50
EV ($54) is greater than Actual Costs ($50), i.e., project “earned” more than it spent – got more bang for the buck
EV ($54) is less than Plan ($60) – project is behind schedule
EV adds the third dimension,
Progress
0 20 40 60 80 100 120 140 1 2 3 4 5 6 Cum. Budget EV Cum. Actual Period 1 2 3 4 5 6 Remarks
Cum. Budget 20 40 60 80 100 120 BAC (Budget At Completion)
% Complete 15% 30% 45% PC (Percent Complete)
Earned Value 18 36 54 EV = PC * BAC
Using EV forces Project Manager to use rigor & discipline Since you cannot manage what you cannot measure, break
up IT deliverables in measurable “chunks” of work
For each project, come up with a list of deliverables or tasks
in chunks of 80 to 100 hours each
For example, if an Enhancement requires 400 hours of work,
try to divide it down to four 100 hours per deliverable
Use an objective EV method such as Start/Finish (0/100,
20/80, or 50/50) or Milestones to determine progress
If possible, try to avoid Percent Complete (Estimates) method
- it is hard to make this a consistently objective figure
Measure progress every week or two, and identify issues and
risks early on, before these turn into disasters
EV can be used as an early warning system for IT projects.
Eight EV methods are supported in Standard SAP PS
For IT Projects Milestones & Start/Finish Methods
are recommended
Shown below are the minimum CONFIGURATION Steps Required
Create a Progress Version (a special CO Version) 100 is a Standard Progress Version reserved for EV, so
this can be used
More than one Progress Version can be used
Set Plan Version, EV basis, Early/Late Dates
Set up PS Value Categories
Labor, Material, ODC, OH, G&A, etc. are recommended
The best way to do this is to map CO CE Groups to PS Value Categories
Assign Default Methods for WBS, NW Activity, CO/PM Order, etc.
Shown below are APPLICATION Steps
Required
Depending on business requirements, more steps may be required
Use CJ20N to perform the following tasks:
Plan labor, material, and ODC on WBS or Network Activity
Assign EV methods on WBS or Network Activity
Perform Progress Update on WBS or NWA each period
Use CNE1 to calculate EV
After the EV parameters are set up, CNE1 should run to update EV figures in ECC
Run EV Reports
CNE5 – Tabular Report and Period Drilldown Report
S_ALR_87015124 - Report Painter Report
Using a typical PS structure, EV can be set up on the WBS element or NW Activity Level
The Start/Finish 20/80 Method is selected
The Milestones Method is shown as an example Milestones method chosen for both Plan & Actual
Prog. Analysis must be checked with POC completed
Multiple Milestones can be set up for WBS/NWA
Using a typical PS structure, EV can be set up on the WBS element or NW Activity Level
The Estimates Method is shown as an example
Resistance from Change Management Perspective
Many PM’s will view EV as a tax on their time and resources
How to Handle the Challenge
After Senior Management agrees to implement EV, use a
small number of key projects to implement EV to demonstrate the following:
EV is a standard solution in SAP – it is free and you already have it
You already have it. Why not use it to improve project management and objectivity in evaluating performance?
Use 3 to 6 pilot projects and savvy Project Analysts to start with
After initial training and set up, EV is simple to maintain
EV - by definition - will enforce discipline among project personnel
Incorporate lessons learned from pilot
Come up with company-wide EV requirements and Rollout to
strategically important projects
CNE5 shows the basic three key figures in EV: BCWS, BCWP and ACWP or Plan EV, Actual EV and Actual Costs.
In CNE5 use Period Drill Down Menu Selection for the Graph
S_ALR_87015124 shows the key EV figures as well as Performance Indicators such as CPI, SPI and EAC
This is a Report Painter Report that can be modified
without ABAP
Get Senior Management Buy In - without this you will fail
Allocate budget for EV implementation – it takes time to set up and maintain
Educate Project Managers and PM Analysts on Earned Value
Align the Charge Numbers - Cost Objects such as WBS,
Network Activity, Internal Order, PM/PP Order, etc. - with the Work or Work Packages for which you want to
implement EV
Ideally, the charge numbers to work packages should be one
to one
However, in reality, many organizations using one charge
number for multiple work packages and EV can still work if you set it up properly
What is Earned Value?
Project Management Technique used by many PM’s
How can it help IT projects?
By introducing rigor and discipline, it can be useful as an early
warning system for IT projects
What will it take for EV to be successful for my organization?
Management Leadership, Commitment, and Support
Business Readiness
Rigor and Discipline
Willingness to put in rigor for meaningful and measurable
progress
THANK YOU
THANK YOU FOR PARTICIPATING
Please provide feedback on this session by completing a short survey via the event mobile application.
SESSION CODE: 2204
For ongoing education on this area of focus, visit www.ASUG.com