• No results found

(LEAN) PROCESSPLANNING in the DESIGN PHASE

N/A
N/A
Protected

Academic year: 2021

Share "(LEAN) PROCESSPLANNING in the DESIGN PHASE"

Copied!
31
0
0

Loading.... (view fulltext now)

Full text

(1)

CASE: ACADEMY OF ART AND DESIGN IN BERGEN (KHIB)

(LEAN) PROCESSPLANNING in the DESIGN PHASE

(2)
(3)

KHIB: SOME FACTS…

Projectstart and designcompetition: Autumn 2005 Granting of final construction work fundings: June 2013

Total budget (pr. July 2013): 1.038 mill. NOK (incl. VAT) Floor space (pr. July 2013): 14.500 sqm

Schedule:

2014: Detailled design / Demolition / Ground preparations 2015: Foundation works / Framework / Enveloping

2017: Scheduled completion Q2

OWNER - CLIENT: Statsbygg

ARCHITECTS: Snöhetta

(4)

1) Experiences from Lean Construction (ie. UiO Domus Medica, Oslo) 2) Lean construction seminars (ie. Porsche Consulting)

3) Takt - Train

4) Film-clip: 30 floors in 14 days (China)

And as an objective: A very lean project.

(5)

• Strategy

- An as lean project as possible in design and construction. - Lean on all levels and in all phases.

• Tools - BiM

- dRofus (room functional database)

KHIB PLAN

(6)

GENERAL PROJECT PRINCIPALS

Transparency / Overview / Collaboration

Culture for continous improvement

Lean included in all contract documents

Extended lean requirements for contractors

Reduce, minimize or (preferably) eliminate waste

Flow where possible

(7)

KHIB LEAN STEP BY STEP

1) Pre-Seminar

Discussing and preparing a lean construction strategy. Getting to know the building.

2) Product Creation Process (w/ Porsche Consulting) Project top level overview.

Mindshifting.

3) Now what ..? A design train and takt ..?

4) Developing and improving the lean design process «Unfamiliar territory!»

5) Extended use of lean takt planning and construction with contractors. - Contract review.

- Contract handover (from design to contractors). - Frontloading (putting the puzzle together).

- Lean construction. 6) Lessons learned

(8)

PLANNING USING LAMINATED A0-DRAWINGS

(9)

DRAFT 2ND FLOOR CONSTRUCTION

(10)

1) Pre-Seminar

Discussing and preparing a lean construction strategy. Getting to know the building.

2) Product Creation Process (w/ Porsche Consulting) Project top level (1) overview.

Mindshifting.

3) Now what ..? A design train and takt ..?

4) Developing and improving the lean design process «Unfamiliar territory!»

5) Extended use of lean takt planning and construction with contractors. - Contract review.

- Contract handover (from design to contractors). - Frontloading (putting the puzzle together).

- Lean construction. 6) Lessons learned

(11)
(12)
(13)

COMPLETE PROCESSMAP LEVEL 1

DEPENDENCIES & TRANSPARENCY EVERYONE ON THE SAME PAGE

(14)

«LEVEL 2 & 3»

COMPLETE PROCESSMAP LEVEL 1

PROCESSES (7)

STATSBYGG PHASES & MILESTONES (MAINTAINED)

(15)

Everyone developed the PCP-level-1-map together.

Everyone’s «on the same page».

Everyone has «the same mind».

Everyone has the same objectives.

(16)

1) Pre-Seminar

Discussing and preparing a lean construction strategy. Getting to know the building.

2) Product Creation Process (w/ Porsche Consulting) Project top level overview.

Mindshifting.

3) Now what ..? A design train and takt ..? From construction to design.

4) Developing and improving the lean design process «Unfamiliar territory!»

5) Extended use of lean takt planning and construction with contractors. - Contract review.

- Contract handover (from design to contractors). - Frontloading (putting the puzzle together).

- Lean construction. 6) Lessons learned

(17)

Cutting the elephant into minor manageable pieces.

Continous flow to BiM and physical construction.

Restructure flow according to contracts and milestones.

Issues/topics have appointed owners.

2-week «takt» with one 3-day big-room co-location.

Continous priority 1-2-3 (or: must-should-can).

Iteration-steps: 5 fw and 1 bw (instead of 4-3).

Efficiency: 80% effort & 20% time spent (instead of 100-100).

(18)

TOPICS WITH ISSUSES & OWNERS

CONTINOUS FLOW TO THE VIRTUAL BUILDING (BIM) AND

THE PHYSICAL BUILDING

(19)

OWNER TOPIC ISSUES: - RESOURCES - TIME - INPUT DEADLINE «PRODUCT»/OUTPUT

(20)

2-WEEK «TAKT» INCL.

3-DAYS BIG-ROOM CO-LOCATION «TAKT and TRAIN»

(21)

2 WEEK TAKT / WORK PROCEDURE

(22)

1) Pre-Seminar

Discussing and preparing a lean construction strategy. Getting to know the building.

2) Product Creation Process (w/ Porsche Consulting) Project top level overview.

Mindshifting.

3) Now what ..? A design train and takt ..?

4) Developing and improving the lean design process «Unfamiliar territory!»

5) Extended use of lean takt planning and construction with contractors. - Contract review.

- Contract handover (from design to contractors). - Frontloading (putting the puzzle together).

- Lean construction. 6) Lessons learned

(23)
(24)

TOPICS / OWNERS / PRIORITY / STATUS CONNECTED TO: PROCESSES AND KEYPOINTS (LEVEL 1) «LEVELS 2 & 3» PROCESSES (7)

MILESTONES & KEYPOINTS & BIM-DEVELOPMENT

LEVEL 2 PROJECT DESIGNPLAN (TOPIC OVERVIEW)

(25)
(26)

3-DAYS BIG-ROOM CO-LOCATION

3-DAY MEETING SESSIONS BOOKING LIST

TOPIC OWNER SHARING

TOPIC OWNER

(27)

1) Pre-Seminar

Discussing and preparing a lean construction strategy. Getting to know the building.

2) Product Creation Process (w/ Porsche Consulting) Project top level overview.

Mindshifting.

3) Now what ..? A design train and takt ..?

4) Developing and improving the lean design process «Unfamiliar territory!»

5) Extended use of lean takt planning and construction with contractors. - Contract review.

- Contract handover (from design to contractors). - Frontloading (putting the puzzle together).

- Lean construction. 6) Lessons learned

(28)

The lean processes in the project are ongoing.

Lean takt-planning and construction are yet to come.

(From 2015 onwards.)

KHiB goal:

The lessons so far learned in KHiB lean design, have

been visualized in this presentation.

(29)

Common mindset for all parties involved in the project

Common objectives and tools and agreed transparency

Lean project strategy (for mindshift, construction and design)

Complete and transparent project processoverview («all in»)

Agreeing on «minor pieces» and continous flow

Assign topics with issues and owners

Agree on work-procedures and managing (decision)levels

Big-room transparency

Putting the pieces together (BiM & construction)

(30)

QUESTIONS…?

(If time…)
(31)

Hans Thomas Holm / Statsbygg

Projectmanager with Statsbygg since 2007.

Projectmanager for KHiB since June 2013.

Email: [email protected]

Cell-phone: +47 - 915 73 626

Sven Wertebach / Terramar

Projectmanager with Terramar since 2013.

Designmanager for KHiB since September 2013.

Email: [email protected] / [email protected]

References

Related documents

While Integrated Pest Management (IPM) was a good concept for professional pest control, in time it simply came to define what was already practiced or practical for most

2001-2002: Teaching Assistant, Observational Astronomy (Astro 310), University of Maryland, College Park 2001-2003: Teaching Assistant, Introduction to Astrophysics I and II (Astro

7.34: Average inpainting processing time of file music11_16khz with gap size of 1600 samples and various window length.... 7.35: Ratio of synthesis/analysis average

Large dose of IV PPI reduces the rebleeding rate in high-risk patients with bleeding peptic ulcers who have obtained initial hemostasis with epinephrine

In order to do this the course will expose students to the major theoretical approaches in international politics and look at historical and current cases to evaluate how well

 For  further  information  please  consult  the  Disability  Services

Highway workers are at risk of injury from passing traffic, from con- struction equipment operating inside the work zone, and in supporting ancillary areas that support

suburban white neighborhoods placed the burden of the desegregation efforts on those black children. In most cases in Jacksonville, black students were bused outside of