• No results found

Activities Involved in Process Order Creation

In document Scm340 en Col52 Fv Part a4 (Page 84-98)

Figure 23: Activities Involved in Process Order Creation

The graphic shows the main functions that are carried out when you create a process order. By making the corresponding Customizing settings, you can control how these activities are performed.

All these functions are usually carried out in the background (except for order type specification and manual quantity and dates entry in scenario (2)). The production scheduler does not have to do anything unless a problem occurs (for example, if a master recipe does not exist).

Other functions that can run automatically if the relevant Customizing settings have been made, are, for example:

Material availability, batch creation for the product, order classification, order release

Exercise 8: Order Creation

Exercise Objectives

After completing this exercise, you will be able to:

• Perform the individual conversion of a planned order

• Perform the partial conversion of a planned order

• Perform the collective conversion of planned orders

• Create a process order with reference to a material

• Create a process order with a template

• Create a process order without reference to a material

Business Example

You will get an overview of the different ways to create a process order.

Task 1:

1. Display the stock/requirements list for your material T-FI1##.

Write down the order number of the planned order that comes next in time.

____________________________________________________________

Task 2:

1. Convert the planned order of exercise 1-1 to a process order. Use individual conversion.

Choose process order type PI01 for conversion.

Task 3:

Display the stock/requirements list for material T-FI1##.

1. Display the stock/requirements list for material T-FI1##.

Continued on next page

2. Which changes have occurred?

3. Write down the order number of the planned order that comes next in time.

Task 4:

1. Convert the planned order from exercise 3-3 to a process order. Use partial conversion.

Use process order type PI01 for partial conversion.

Convert half of the planned quantity.

Task 5:

Display the stock/requirements list for material T-FI1##.

1. Display the stock/requirements list for material T-FI1##.

2. Which changes have occurred?

3. There are two more planned orders in the list.

Display the two orders.

Write down the order number, the planned opening date, and the assigned MRP controller for each of these planned orders.

Continued on next page

Planned order Creation date MRP controller

Task 6:

1. Convert the two planned orders from exercise 5-3 to process orders. Use collective conversion.

Enter the following criteria for planned order selection:

Plant: 1100

MRP controller: I##

Creation: Creation date of the planned order that is chronologically first -Creation date of the planned order that is chronologically last

Choose process order type PI01 for conversion.

Task 7:

Display the stock/requirements list for material T-FI1##.

1. Display the stock/requirements list for material T-FI1##.

Which changes have occurred?

____________________________________________________________

____________________________________________________________

Task 8:

1. Create another process order with reference to your material T-FI1##.

Choose process order type PI01 and production plant 1100.

Enter 14,000 pieces as the total quantity you want to produce and today as the basic start date.

Save the order and write down the order number.

____________________________________________________________

Continued on next page

Task 9:

1. Create another process order of order type PI01 in plant 1100.

This time, use the order created in 8-1 as a template to copy from.

Enter 16,000 pieces as the total quantity you want to produce and Today + 1 week as the basic start date.

Task 10:

1. Now create a process order of process order type PI01 in plant 1100 without reference to a material.

Create the order with reference to recipe 1 Clean-out of recipe group T-CLEAN.

Enter 1 PU (activity unit) as the total quantity and any start date you wish.

In the distribution rules of the settlement rule, define cost center 4271 Production food as the settlement receiver for the clean-out order.

Solution 8: Order Creation

Task 1:

1. Display the stock/requirements list for your material T-FI1##.

Write down the order number of the planned order that comes next in time.

____________________________________________________________

a) Logistics → Production - Process → MRP → Evaluations → Stock/Requirements List

Material: T-FI1##

Plant: 1100

The planned order number is displayed in the data on the MRP element.

Task 2:

1. Convert the planned order of exercise 1-1 to a process order. Use individual conversion.

Choose process order type PI01 for conversion.

a) (…) → MRP → Planned Order → Convert to Proc.Ord. → Individual Conversion

Planned order: Planned order number Process order type: PI01

Choose Enter. The system converts the planned order to a process order.

The Create Process Order: Header - General Data screen then appears.

Save the process order.

Continued on next page

Task 3:

Display the stock/requirements list for material T-FI1##.

1. Display the stock/requirements list for material T-FI1##.

a) Logistics → Production - Process → MRP → Evaluations → Stock/Requirements List

Material: T-FI1##

Plant: 1100

2. Which changes have occurred?

Answer: The new process order is displayed as a new MRP element. The planned order was deleted after conversion.

3. Write down the order number of the planned order that comes next in time.

Answer: The planned order number is displayed in the data on the MRP element.

Task 4:

1. Convert the planned order from exercise 3-3 to a process order. Use partial conversion.

Use process order type PI01 for partial conversion.

Continued on next page

Convert half of the planned quantity.

a) (…) → MRP → Planned Order → Convert to Proc.Ord. → Partial Conversion

Planned order: Planned order number Process order type: PI01

The Partial conversion indicator is set.

Choose Enter. The Plnd Ind. Reqmts Create: Initial screen appears.

The system proposes a target quantity of 6,000 kg. Change the quantity to 3,000 kg and save your order.

The following information message appears: Orders will be generated for partial quantities before saving. Choose Enter to confirm the message.

The planned order is partially converted to a process order.

Choose Back to exit the Create Process Order: Initial screen.

Task 5:

Display the stock/requirements list for material T-FI1##.

1. Display the stock/requirements list for material T-FI1##.

a) Logistics → Production - Process → MRP → Evaluations → Stock/Requirements List

Material: T-FI1##

Plant: 1100

2. Which changes have occurred?

Answer: Due to the partial conversion, the system created a process order with a corresponding order quantity.

The planned order is still available. The planned order quantity has been reduced by the converted quantity.

The planned order was firmed.

3. There are two more planned orders in the list.

Display the two orders.

Write down the order number, the planned opening date, and the assigned MRP controller for each of these planned orders.

Continued on next page

Planned order Creation date MRP controller

a) Position the cursor on the MRP element of a planned order and choose the Display element icon in the toolbar at the bottom of the screen.

Task 6:

1. Convert the two planned orders from exercise 5-3 to process orders. Use collective conversion.

Enter the following criteria for planned order selection:

Plant: 1100

MRP controller: I##

Creation: Creation date of the planned order that is chronologically first -Creation date of the planned order that is chronologically last

Continued on next page

Choose process order type PI01 for conversion.

a) (…) → MRP → Planned Order → Convert to Proc.Ord. → Collective Conversion

Plant: 1100

MRP controller: I##

Creation: Creation date of the planned order that is chronologically first - Creation date of the planned order that is chronologically last Process order type: PI01

Choose the Execute selections icon.

The Collective Conversion of Planned Orders: List screen appears.

According to the selection criteria you have entered, the system only displays your two planned orders for material T-FI1##.

Select the two planned orders and choose Convert. The planned orders are now converted to process orders one after the other.

Choose Back to exit the list.

Task 7:

Display the stock/requirements list for material T-FI1##.

1. Display the stock/requirements list for material T-FI1##.

Which changes have occurred?

____________________________________________________________

____________________________________________________________

a) Logistics → Production - Process → MRP → Evaluations → Stock/Requirements List

Material: T-FI1##

Plant: 1100

The two new process orders are displayed as new MRP elements. The planned orders were deleted after the conversion.

Continued on next page

Task 8:

1. Create another process order with reference to your material T-FI1##.

Choose process order type PI01 and production plant 1100.

Enter 14,000 pieces as the total quantity you want to produce and today as the basic start date.

Save the order and write down the order number.

____________________________________________________________

a) Logistics → Production Process → Process Order → Process Order

→ Create → With Material

Material number: T-FI1##

Production plant: 1100

Process order type: PI01

Choose Enter. The Create Process Order: Header – General Data screen appears.

Total quantity: 14,000 PC

Start: Today

Choose Enter. The system creates the process order. Save the order and write down the order number: ____________________

Task 9:

1. Create another process order of order type PI01 in plant 1100.

This time, use the order created in 8-1 as a template to copy from.

Continued on next page

Enter 16,000 pieces as the total quantity you want to produce and Today + 1 week as the basic start date.

a) (…) → Process Order →

Process Order → Create → With Material

Production plant: 1100

Process order type: PI01

Template

Process order: Order number from exercise 8-1 Choose Enter. The system creates a new order by copying from the order created in exercise 8-1.

Change the total quantity:

Total quantity: 16,000 PC

Enter the following basic start date:

Start: Today + 1 week

Choose Enter. The system schedules the process order.

Task 10:

1. Now create a process order of process order type PI01 in plant 1100 without reference to a material.

Create the order with reference to recipe 1 Clean-out of recipe group T-CLEAN.

Enter 1 PU (activity unit) as the total quantity and any start date you wish.

Continued on next page

In the distribution rules of the settlement rule, define cost center 4271 Production food as the settlement receiver for the clean-out order.

a) (…) → Process Order →

Process Order → Create → Without Material

Recipe group: T-CLEAN

Recipe: 1

Plant: 1100

Process order type: PI01

Choose Enter. The Create Process Order: Header – General Data screen appears.

Total quantity: 1 PU

Start: Any start date in the future

If applicable, choose Header → Settlement rule.

The Maintain Settlement Rule: Overview screen appears.

Type: CTR

Destination: 4271

Enter

Choose Back to go back to the order header.

Lesson Summary

You should now be able to:

• Use the different options for creating a process order

• Explain the activities involved in process order creation

In document Scm340 en Col52 Fv Part a4 (Page 84-98)

Related documents