5.4 Analysis Project B

5.4.2 Analysis-Case 2 Interviewee 2

Interviewee 2 in project B was GV who is a 57 year old male working for ABC for almost 4 years. GV, who is a British national, holds a degree in quantity surveying from the UK. He acquired knowledge of claims through continuous involvement and practice in construction projects worldwide. He has served in the UAE for almost 10 years, having worked with other professional contractors based in Abu Dhabi. GV was the commercial manager for project B and the person who contributed to the formulation of ABC claim in this particular project. GV does not hold any certificates related to project management but has attended several courses in quantity surveying and commercial management of construction projects.

GV defined claims as “the guarantee for the contractor’s rights”. In his past experience, GV had encountered prolongation, EOT and acceleration claims. He pointed out that these three have occurred in project B as well. GV added that the claims were the direct result of delays caused by the Employer and the Engineer and had nothing to do with delays by the Contractor.

The team GV usually sees as essential for claims formulation are the commercial manager, project manager and the planners . He feels that the three are the key personnel who contribute most to enhancing the claim as a position, in addition to the presence of a claims specialist. However, GV feels that despite all the parties who are involved in the claim preparation, mistakes and errors continue to occur. The examples of errors he gave were mostly related to lack of substantiation of certain elements of the claim and in some instances, certain contradictions.

The lessons GV feels he has learnt from project B are mostly related to the necessity of having change orders documented. He clearly mentioned that in order to manage claims well, changes have to be noted down and recorded. He affirmed, “Some of the mistakes we committed on project B were not to document some of the

major changes. I am surprised how the site team sometimes accept to change certain features at site without at least referring to their management. This really does harm more than benefit although it may seem as a gesture of good intentions”.

When GV was asked about the proper elements of claims substantiation, he promptly answered “I guess everything we consider as not important at a certain

Claims Management and Substantiation in the

United Arab Emirates Construction Sector 85

stage of the project, turns out to be of significance to our claim. I cannot specify those documents, but can say that they are of a considerable quantity’. On the claim

presentation, GV added that the role of presenting the claim largely falls on the shoulders of the claims consultant and the commercial manager. He also contended that the project manager was a key player since he was the overall manager in the project and was empowered by the senior management.

The interviewee was then asked questions on the role of the Engineer and on his stance on FIDIC. GV felt that the Engineer had not been granted enough power by the Employer in project B. He said, “Although FIDIC gives the Engineer

administrative powers, yet in reality the Engineer is not practicing his full authorities, I feel that the Engineer in our project is a document controller who passes our letters up to the Employer and vice versa. Other than that, I have not sensed a true effective presence for the Engineer”. GV further asserted that the FIDIC is a relatively

reasonable form of contract if it were applied as whole and not in partial chunks according to what suited a party’s interests.

GV expressed his annoyance with the document control system in practice. He felt that the system was slow and certain letters which had to be sent to the Employer were sometimes delayed for trivial reasons and that delay sometimes extended over a period of several days. He also expressed his frustration at not being able to find documents in soft copies. GV said, “I wonder why we cannot have all letters provided

in soft copy on a server reachable by certain parties to maintain privacy, instead of having to look in bulky files which are wastage of time and sometimes paper”.

The interviewee then spoke about change and change management. He found that change was of very high significance and a direct cause of cost rise in construction projects. GV also saw changes as significant whenever they occurred, whether at initiation or during construction. He found that the occurrence of change to a deficiency in understanding by the Employer to his needs in not giving sufficient time for the design completion and to the fast track nature of the project which made it inevitable for changes to surface. In conclusion, GV linked changes to claims and found that changes in most cases were beneficial from a Contractor’s perspective since they were acknowledgements by the Employer of delays on his part.

Claims Management and Substantiation in the

United Arab Emirates Construction Sector 86

5.4.3 Identified Similarities and Differences

Both interviewees in Project B expressed their understanding of claims and the various types of claims they had witnessed on the project. On the elements of claims management, both SH and GV agreed on the majority of the elements. Both participants concluded that dependency exists for planning, commercial and 3rd party specialists while formulating claims. Conversely, the interviewees did not agree on two aspects which were the accessibility of important documents in a timely manner and timely notifications of the occurrence of delays. SH saw these aspects as crucial to claims management. However GV did not mention them as being essential. Another difference noticed was with regard to the usage of claims to cover delays. GV’s view was that claims are used by contractors to cover delays. On the other hand, SH disagrees by assuming that there were no delays by the contractor.

SH and GV agreed that FIDIC is a suitable form of contract. Both expressed their dismay on the role of the Engineer. Both contended in the interview that Engineers were not assessing claims the way they were supposed to. They perceived the Engineer to be biased and not acting impartially in administering the contract.

SH attributed the occurrence of changes in the project to poor design. However, GH saw fast tracking, poor design and lack of clarity on the objectives by the Employer as the main drivers for change. With respect to the period in which change is more effective, both interviewees agreed that changes are significant whether made during or pre execution stages. Change was seen as beneficial by both interviewees and was directly linked to claims.