10 Organizational methods (part A)
Panel 10.2 Case study: traditional procurement – Bath Spa
Initially estimated at £11 million, the Bath Spa project, a public leisure amenity, in the historic town of Bath in Somerset, England, has become one of the most delayed and disrupted projects in recent times.
The project was funded via a £7.78 million grant from the Millennium Commission who specified that the council must opt for a traditional JCT contract. The aim was to open for Christmas 1999; however, in the event the contractor Mowlem did not start on site until 2000.
When the architect Grimshaw produced designs with more clarity, the costs rose to
£15 million then to £22 million.
In 2003 with construction complete, Grimshaw, as contract administrator, refused to certify practical completion because it had become apparent that the RIW Toughseal paint on the walls was peeling. In September it was reported that the steam room floors were also leaking.
Grimshaw claimed that the defects were construction related, while Mowlem claimed they were design related.
In February 2005 Mowlem offered to complete the project for £26.5 million under a design and build arrangement and drop all claims against the council. This proposal was never accepted.
In April 2005 following claims that Mowlem had refused to obey an architect’s instruc-tion requiring replacement of the floors in the steam room, Mowlem were told to leave the site.
A new project manager Capita Symonds was appointed to take the scheme to completion under an arrangement in which the council would have direct control of the contractors. Capita Symonds later said they found a series of significant structural problems from leaking floors, rusty and outdated fittings and £700,000 worth of windows which had begun to delaminate.
It is anticipated that the project will be completed in 2006 with an estimated final account of £40 million.
Sources: Building (11 February 2005, 18 February 2005, 8 April 2005, 13 May 2005); The Times 24 April 2006.
The possible disadvantages are as follows:
● Less certainty on price before a commitment to build;
● Competition may be diminished in negotiated tendering;
● More concentrated client involvement required to ensure efficient planning and control throughout the process.
As a post script to the traditional procurement system it is worth mentioning procurement of public works in New York city which seems out of step with the general international trend towards the use of alternative contract strategies.
New York city statutes require that contracts by state agencies for construction work be awarded to the lowest responsible bidder based on open competitive bidding. These requirements essentially mandate the traditional design-bid-build (DBB) approach to public works procurement, since competitive bidding requires a completed design, meaning that design services must be procured separately and before construction work is procured, and that the selection process cannot be based on comparative evaluation of proposals (Raved, 2003).
Anecdotal evidence from an architect who has worked in New York identified the high level of corruption prevalent in the labour unions as a possible reason for the move away from a partnering strategy back to the traditional lump-sum, fixed-price approach.
10.3 Design and build
Back in 1964 the Banwell Report remarked that ‘in no other industry is the responsibility for design so far removed from the responsibility of construction.’
Today the contractor-led design and build procurement route (see Fig. 10.3) is now established as the most popular procurement route. Furthermore, it is increasingly perceived as the appro-priate answer for large and complex projects, sometimes designed by signature architects.
Employer
Construction Contractor/
subcontractors (domestic) Pre-contract
design
Conceptual designers architect/engineer/
specialist contractors
Contracts JCT2005 (DB) NEC3/ ICE D&C FIDIC Yellow Book Post-contract
design Contractor/
architect/engineer/
specialist contractors
10.3 The design and build system.
The process
The design and build strategy requires the contractor to take overall responsibility for both design and construction in return for a fixed price lump sum. However, in practice, the client may appoint an independent project manager or quantity surveyor to safeguard their interests.
The client enters into a single contractual relationship with the contractor to design and construct the project in accordance with a performance specification prepared by the client. The contractor then enters into a series of separate agreements with consultants, specialist subcon-tractors and suppliers to deliver the project in accordance with the agreed performance specifi-cation. Since the contractor becomes solely responsible for all aspects of the project delivery process, most of the risks associated with design and construction are therefore borne by the contractor giving the client greater protection.
The client generally invites tenders based on an outline design, critical specification and workmanship standards, completion time and other key information. At the earliest stage of the construction period, the contractor completes the outstanding design development, thus generating an overlap between the design development stage and construction stage which should in theory reduce the overall duration.
In practice, there may be two separate design teams, one employed by the client to develop the client’s brief and the other employed by the contractor to undertake the detailed design work. It should be noted that the former design team may not be contractually linked with the contractor though in some cases this design team may be novated to the contractor. Equally, the design team employed by the contractor is usually contractually remote from the client, and the client can only influence the output of the design through their intervention in the design-approval process. This often leads to variations and changes in the original requirements.
Contractor’s expertise
The design and build approach allows the contractor’s design and construction team to consider, at the earliest conceptual stage, site-specific construction issues which a consultant working in isolation is not normally equipped to deal with. For example, on a large marine project the team will be able to establish the following criteria: if the site is suitable for the use of large cranes;
whether heavy floating barges can be used in a tidal location; how materials will be transported to the construction locations; whether there are suitable areas close to the site for setting up a precasting or pre-assembling yard; what skills are characteristic of the local labour force and how the local weather during the construction period will affect the construction methods.
The most economic type of structure and the most suitable method of construction will depend on the answers to the above questions, together with the contractor’s specific expertise and the availability of construction equipment. It is at this stage when the combined team has at its disposal all the relevant facts and techniques that increased productivity may be considered – thus reducing the overall cost to the client.
Flexibility
The design and build route is extremely flexible and many different versions have emerged over the past decades. The major difference between them is the amount of design input by the employer’s designers and the contractor’s designers; for example; the client’s contribution to the design may vary from 5% to 75%.
The amount of tender documentation provided by the client (known in the JCT Standard Form of Building Contract with Contractor’s Design 2005 as the Employer’s Requirements) can vary from little more than a written brief to a fully worked out scheme. The greater the priority
the client gives to design the larger the amount of information tends to be included in the tender documents. If a client’s priorities are economy and speed then less design information will be included, leaving more scope to the contractor.
Three main categories of design and build approach can be identified:
1. Direct: designer/contractor appointed after some appraisal but not competition;
2. Competitive: conceptual design prepared by consultants, several contractors offer designs in competition;
3. Develop and construct: client’s designers complete design to partial stage before asking contractors to complete and guarantee the design in competitive tender either with their own or using the client’s designers (novation).
Responsibility for design
There are two standards of care which are relevant to the design and build strategy:
Reasonable skill and care
A duty imposed on a professional consultant who provides advice or a service. It is effectively a matter for professional judgement whether in providing that advice or service the consultant has