• No results found

Commissioning, qualification and validation 1621

In document GMP guidelines for HVAC (Page 62-76)

MPPS Integral

9. Commissioning, qualification and validation 1621

1622

9.1. General 1623

9.2.

1624

9.2.1. The heating, ventilation and air-conditioning (HVAC) system plays 1625

an important role in the protection of the product, the personnel and the 1626

environment.

1627 1628

9.2.2. For all HVAC installation components, subsystems or parameters, 1629

critical parameters and non-critical parameters should be determined.

1630 1631

9.2.3. Some of the parameters of a typical HVAC system that should be 1632

qualified include:

1633

Working document QAS/15.639 page 63 1634

• room temperature and humidity;

1635

• supply air and return air quantities;

1636

• room pressure, air change rate, flow patterns, particle count and clean-up 1637

rates;

1638

• unidirectional flow velocities and HEPA filter penetration tests; and 1639

• critical alarms, etc.

1640 1641

9.3. Commissioning 1642

1643

9.3.1. Commissioning should involve the setting up, balancing, 1644

adjustment and testing of the entire HVAC system, to ensure that the 1645

system meets all the requirements, as specified in the user requirement 1646

specification, and capacities as specified by the designer or developer. The 1647

commissioning plan should start at the early stages of a project so that it 1648

can be integrated with qualification and verification procedures.

1649 1650

9.3.2. Acceptable tolerances for all system parameters should be specified 1651

and agreed by the user prior to commencing the physical installation.

1652

These tolerances should be specified in the User Requirement 1653

measured data should fall within the acceptance criteria.

1657 1658

9.3.4. System installation records should provide documented evidence 1659

of all measured capacities of the system.

1660 1661

9.3.5. The i n s t a l l a t i o n r e c o r d s should include items such as the 1662

design and measured figures for airflows, water flows, system pressures 1663

electrical amperages, etc. These should be contained in the operating 1664

and maintenance manuals (O & M manuals). The installation records of 1665

the system should provide documented evidence of all measured capacities 1666

of the system.

1667 1668

9.3.6. Typical information that should be contained in the O&M 1669

manuals is the following:

1670 1671

• system description;

1672

• operating instructions, 1673

• trouble shooting;

1674

Working document QAS/15.639 page 64

• commissioning data schedules;

1675

• maintenance instructions;

1676

• list of equipment suppliers;

1677

• spare parts lists;

1678

• equipment capacity and data schedules;

1679

• supplier’s literature;

1680

• control system operation;

1681

• electrical drawings;

1682

• as-built drawings;

1683

• maintenance records.

1684 1685

9.3.7. O & M manuals, schematic drawings, protocols and reports should 1686

be maintained as reference documents for any future changes and upgrades 1687

to the system. As-built drawings should be available and should be kept up 1688

to date with all the latest system changes. Any changes from the originally 1689

approved system should be covered by change control documentation and 1690

risk assessment studies where deemed necessary.

1691 1692

9.3.8. Training should be provided to personnel after installation of the 1693

system, and should include how to perform operation and maintenance.

1694 1695

9.3.9. Commissioning should be a precursor to system qualification and 1696

validation.

1697 9.4.

1698

9.5. Qualification 1699

9.6.

1700

9.6.1. Manufacturers should qualify HVAC systems using a risk-based 1701

approach. The basic concepts of qualification of HVAC systems are set out 1702

in Figure 35 below.

1703 1704 1705

Working document QAS/15.639 page 65 Figure 35

1706

Qualification is a part of validation 1707

1708

9.6.2. The qualification of the HVAC system should be described in a 1709

validation master plan (VMP), or a subsection of the VMP.

1710 1711

9.6.3. The validation master plan should define the nature and extent of 1712

testing and the test procedures and protocols to be followed.

1713 1714

9.6.4. Stages of the qualification of the HVAC system should include 1715

design qualification (DQ), installation qualification (IQ), operational 1716

qualification (OQ) and performance qualification (PQ). The relationship 1717

between the development stage of a project and the qualification/validation 1718

stage is given in the V-Diagram (Figure 36) below.

1719 1720

Working document QAS/15.639 page 66

Figure 36 1721

User Requirement Specification

Functional Design Specification

Detail Design and Configuration Specifications

Build & Project Implementation

V-Model for Direct Impact Systems

PQ Test Plan (incl. UAT)

OQ Test Plan (incl. FAT)

IQ Test Plan (incl. PDI)

Design Qualification

DQ Test Plan

1722

9.6.5. Critical and non-critical parameters for all HVAC installation 1723

components, subsystems and controls should be determined by means of a 1724

risk analysis.

1725 1726

9.6.6. Any parameter that may affect the quality of the pharmaceutical 1727

product should be considered a critical parameter.

1728

Note: A realistic approach to differentiating between critical and 1733

noncritical parameters, systems or components is required, to avoid 1734

making the validation process unnecessarily complex.

1735

Example 1736

• The humidity of the room where the product is exposed should be 1737

considered a critical parameter when a humidity-sensitive product 1738

is being manufactured. The humidity sensors and the humidity 1739

monitoring system should, therefore, be qualified. Components or 1740

equipment such as the heat transfer system, chemical drier or 1741

steam humidifier, which is producing the humidity-controlled air, is 1742

Working document QAS/15.639 page 67 further removed from the product and may not require operational 1743

qualification.

1744

• A room cleanliness classification is a critical parameter and, 1745

therefore, the room air-change rates and high-efficiency particulate 1746

air (HEPA) filters should be considered critical parameters and 1747

components, and therefore require qualification. Items such as the 1748

fan generating the airflow and the primary and secondary filters 1749

are considered non-critical components, and may not require 1750

operational qualification.

1751 1752

9.6.8. Non-critical systems and components should be subject to 1753

verification by good engineering practice (GEP) and may not necessarily 1754

require full qualification.

1755 1756

9.6.9. A change control procedure should be followed when changes are 1757

planned to the HVAC system, its components and controls, that may affect 1758

critical parameters.

1759 1760

9.6.10. The design condition, normal operating ranges, operating range 1761

and alert and action limits should be defined and be realistic. Alert limits 1762

should be based on system capability.

1763 . 1764

9.6.11. All parameters should fall within the design condition range 1765

during system operational qualification. Conditions may go out of the 1766

design condition range during normal operating procedures but they should 1767

remain within the operating range.

1768 1769

9.6.12. Out-of-limit results (e.g. alert or action limit deviations) should be 1770

recorded and form part of the batch manufacturing records, and their 1771

impact should be investigated.

1772 1773

9.6.13. The relationships between design conditions, operating range and 1774

qualified acceptance criteria are given in Figure 37. There should be SOPs 1775

to determine action to be taken when alert and action limits are reached.

1776 1777

Working document QAS/15.639 page 68

Figure 37 1778

System operating ranges 1779

1780 1781

9.6.14. A narrow range of relative humidities coupled with a wide range of 1782

temperatures is unacceptable as changes in temperature will automatically 1783

give rise to variations in the relative humidity.

1784 1785

9.6.15. Some of the typical HVAC system parameters, based on a risk 1786

assessment, that should be qualified for a pharmaceutical facility may 1787

include:

1788 1789

— temperature 1790

— relative humidity 1791

— supply air quantities for all diffusers 1792

— return air or exhaust air quantities 1793

— room air-change rates 1794

— room pressures (pressure differentials) 1795

— room airflow patterns 1796

— unidirectional flow velocities 1797

— containment system velocities 1798

— HEPA filter penetration tests 1799

— room particle counts 1800

— room clean-up or recovery rates 1801

— microbiological air and surface counts where appropriate 1802

— operation of de-dusting 1803

— warning/alarm systems where applicable.

1804 1805

9.6.16. The maximum time interval between tests and re-qualification 1806

should be defined by the manufacturer. The type of facility under test and 1807

the product level of protection should be considered.

1808 1809

Working document QAS/15.639 page 69 Note: Table 5 gives intervals for reference purposes only. The actual test 1810

periods may be more or less frequent, depending on the product and process 1811

and subject to risk assessment.

1812

Table 5 1813

Strategic tests to demonstrate continued compliance 1814

(Time intervals given for re-qualification are for reference purposes only.

1815

The actual tests required will depend on specific facility requirements) 1816

Test parameter Max. time interval between tests (all classes)

Test procedure

Particle count test (verification of cleanliness)

6 months (ISO 5) 12 months

(>ISO 5)

Dust particle counts to be carried out and result printouts produced.

No. of readings and positions of tests to be in accordance with ISO 14644-1 Annex B.2

Air pressure difference (to verify absence of cross- contamination)

12 months

Log of pressure differential readings to be produced - critical plants should be logged daily, preferably continuously. In accordance with ISO 14644-3 Airflow volume

(to verify air change

rates) 12 months

Airflow readings for supply air and return air grilles to be measured and air change rates to be calculated. In accordance with ISO 14644-3 Annex B.4

Airflow velocity (to verify

unidirectional flow or containment

conditions)

12 months

Air velocities for containment systems and unidirectional flow protection systems to be measured.

In accordance with ISO 14644-3 Annex B.4

Working document QAS/15.639 page 70

HEPA filter leakage tests

(to verify filter integrity)

12 months

Filter penetration tests to be carried out by a competent person to demonstrate filter media, filter seal and filter frame integrity.. In accordance with ISO 14644-3 Annex B.6

Containment leakage (to verify absence of cross-contamination)

12 months

Demonstrate that contaminant is maintained within a room by means of:

• airflow direction smoke tests

• room air pressures. In accordance with ISO 14644-3 Annex B.13

Recovery

(to verify clean-up time)

12 months

Test to establish time that a

cleanroom takes to recover from a contaminated condition to the specified cleanroom condition. In Room temperatures

(to verify temperature

tolerance adherence) 12 months

Demonstrate that room temperatures at determined locations comply with specified tolerances. In accordance with ISO 14644-3 Annex B.8.2 Warehouse and store

temperatures (to verify temperature mapping conditions)

36 months

Demonstrate that store

temperatures are uniform within specified tolerances

In accordance with WHO 45th report (WHO Technical Report Series, No. 961), Annex 9 and WHO 49th report (WHO Technical Report Series, No. 992), Annex 5 plus Supplements 1 to 16

Room Humidities (To verify humidity tolerance adherence)

12 months

Demonstrate that room humidities at determined locations comply with specified tolerances. In accordance with ISO 14644-3 Annex B.9.2

Working document QAS/15.639 page 71 9.6.17. Requalification should also be done when any change, which could 1817

affect system performance, takes place.

1818 1819

9.6.18. Room clean-up or recovery tests are performed to determine 1820

whether the installation is capable of returning to a specified cleanliness 1821

level within a finite time, after being exposed briefly to a source of 1822

airborne particulate challenge.

1823 1824

Room clean-up or recovery tests should demonstrate a change in particle 1825

concentration by a factor of 100 within the prescribed time (as per ISO 1826

14644-3 clause B.12) (3). The guidance time period for clean-up or 1827

recovery is about 15 to 20 minutes.

1828

In some instances it is not possible to increase the concentration by a 1829

factor of 100 (such as for an ISO 14644 Class 8 condition) as the high 1830

particle concentration can damage the particle counter. In this instance the 1831

particle decay method can be used as per ISO 14644-3 clause B.12.3.2.

1832

9.6.19. If energy-saving procedures such as reducing the airflow during 1833

non-production hours are used, precautionary measures should be in place 1834

to ensure that the systems are not operated outside the defined relevant 1835

environmental conditions.

1836 1837

These precautionary measures should be based on a risk assessment to 1838

ensure that there is no negative impact on the quality of the product.

1839

Qualification tests should be carried out to demonstrate that there are no 1840

flow reversals, loss of room pressurisation cascade, temperature, humidity 1841

excursions, etc.

1842

9.6.20. Additional documents that should be included in the qualification 1843

manuals should include system airflow schematics, room pressure cascade 1844

drawings, zone concept drawings, air-handling system allocation drawings, 1845

particle count mapping drawings, etc.

1846 1847 1848

Working document QAS/15.639 page 72

9.7. Supplementary notes on test procedures 1849

1850

9.7.1. General 1851

1852

9.7.1.1. Tests should be carried as described in ISO 14644-3.

1853

However below are some supplementary notes and aspects that provide 1854

additional guidance.

1855 1856

9.7.2. Airflow measurements 1857

1858

9.7.2.1. The ISO 14644 method - "B.4.3.3 Supply airflow rate 1859

calculated from filter face velocity" - should not be used to measure the 1860

airflow at diffuser outlets. The diffuser air directional blades or swirl 1861

outlets result in highly inaccurate measurements.

1862 1863

9.7.2.2. The cone and anemometer method is more accurate. Other 1864

methods can be used such as volume flow regulators with built in orifice 1865

and pressure differential ports, whereby airflow can be read off a graph 1866

from the corresponding pressure differentials.

1867 1868

9.7.3. Non-viable air particle counts 1869

1870

9.7.3.1. Particle count test results should be calculated using the 1871

UCL (upper confidence level) formulas as described in ISO 14644-3, if 1872

there are up to nine locations. The practice of using the average value of 1873

all particle count readings as the pass criteria is not acceptable.

1874 1875

9.7.3.2. Ensure that the test certificate states the condition under 1876

which the test was taken i.e. “as built”, “at-rest” or “operational”. The 1877

operational condition should be clearly defined for each room. (For 1878

example: number of staff, staff locations, manner of equipment operating, 1879

etc.) 1880

1881

9.7.3.3. ISO 14644-1 clause B.4.3.42 states that when only one test 1882

location is determined by formula, “take a minimum of three single sample 1883

volumes (B.4.2) at that location.” A more representative result would be 1884

obtained by taking a single sample at each of three different locations in 1885

that room. The actual locations should be based on a risk assessment.

1886 1887

9.7.3.4. In addition to determining the number of the sampling 1888

locations based on the area of the clean room, a risk assessment should 1889

Working document QAS/15.639 page 73 determine if additional sample locations are warranted. Consider aspects 1890

such as personnel and/or production activities and air flow dead spots.

1891 1892

9.7.3.5. Where a UDAF is located within a room the UDAF and its 1893

background environment should be considered separately in terms of 1894

sampling location calculations, and should be individually certified.

1895 1896

9.7.3.6. The mapping drawing indicating test location should be 1897

included with the test certificate, and the same mapping locations should 1898

be used for future tests for comparative purposes.

1899 1900

9.7.4. HEPA filter integrity tests 1901

1902

9.7.4.1. Filter media, frame and seal should be tested for each filter 1903

and results for media, frame and seal penetration reflected separately on 1904

the test certificates.

1905 1906

9.7.4.2. When HEPA filters are terminally mounted at the room, it 1907

should be possible to carry out filter integrity tests from within the room.

1908

The filter housings will therefore require ports for measuring appropriate 1909

upstream concentration and penetration concentration from within the 1910

room. In addition it should be possible to measure the filter pressure drop 1911

in individual HEPA filters, also preferably from within the room. These 1912

pressure drops should be recorded on the filter test certificate as an 1913

indication of the filter life. (The practice of measuring the appropriate 1914

upstream concentration from the ceiling void or at the air handling plant-1915

room, and then measuring the filter penetration concentration in the room 1916

is unacceptable. The time lag between measuring the upstream 1917

concentration and the penetration concentration could mean that by the 1918

time the room penetration is measured, the upstream concentration is no 1919

longer the required concentration.) 1920

1921

9.7.4.3. The test procedure should not compromise the quality of 1922

the product.

1923

10.1. Maintenance records, maintenance procedures and Operating &

1928

Maintenance Manuals should be sufficient to indicate that the company 1929

has control over the HVAC systems. There should be a planned 1930

preventive maintenance programme, procedures and records for the HVAC 1931

Working document QAS/15.639 page 74

system. Records should be kept for a sufficient length of time should they 1932

be required for any product defect analysis.

1933 1934

10.2. O&M manuals, schematic drawings, protocols and reports should be 1935

maintained as reference documents for any future changes and upgrades 1936

to the system. These documents should be kept up to date, containing 1937

any system revisions made.

1938 1939

10.3. The O&M manuals should typically contain the following information:

1940

system description, operating instructions, trouble shooting, 1941

commissioning data, maintenance instructions, list of equipment suppliers, 1942

spare parts list, equipment data/capacity schedules, supplier’s literature, 1943

control system description, electrical drawings and as-built drawings.

1944 1945

10.4. Maintenance personnel should receive appropriate training, and training 1946

records should be kept.

1947 1948

10.5. HEPA filters should be changed either by a specialist or a trained person, 1949

and then followed by installed filter leakage testing.

1950 1951

10.6. Any maintenance activity should be assessed critically to determine any 1952

impact on product quality including possible contamination.

1953 1954

10.7. Maintenance activities should normally be scheduled to take place outside 1955

production hours, and any system stoppage should be assessed with a view 1956

to the possible need for requalification of an area as a result of an 1957

interruption of the service.

1958

1. Good manufacturing practices for pharmaceutical products: main 1963

principles. In: WHO Expert Committee on Specifications for 1964

Pharmaceutical Preparations Thirty-seventh report. Geneva, World 1965

Health Organization, 2003 (WHO Technical Report Series, No. 908), 1966

Annex 4. http://whqlibdoc.who.int/trs/WHO_ TRS_908_eng.pdf;

1967

Quality assurance of pharmaceuticals. A compendium of guidelines 1968

and related materials. Volume 2, Second updated edition. Good 1969

manufacturing practices and inspection. Geneva, World Health 1970

Organization, 2007; and Quality assurance of pharmaceuticals. A 1971

compendium of guidelines and related materials. Geneva, World 1972

Health Organization, 2015 (CD-ROM) (in print).

1973 1974

2. Expert Committee on Specifications for Pharmaceutical 1975

Preparations.Fortieth report. Geneva, World Health Organization, 1976

2005 (WHO Technical Report Series, No. 937) 1977

Working document QAS/15.639 page 75 http://whqlibdoc.who.int/trs/WHO_TRS_937_eng.pdf.

1978 1979

3. Technical supplements to Model guidance for the storage and 1980

transport of time- and temperature-sensitive pharmaceutical 1981

products. WHO Expert Committee on Specifications for 1982

Pharmaceutical Preparations. Forty Ninth report. Geneva, World 1983

Health Organization, 2015 (WHO Technical Report Series, No. 992), 1984

Annex 5.

1985

4. Model guidance for the storage and transport of time- and 1986

temperature-sensitive pharmaceutical products (jointly with the 1987

Expert Committee on Biological Standardization). WHO Expert 1988

Committee on Specifications for Pharmaceutical Preparations.

1989

Forty-fifth report. Geneva, World Health Organization, 2011 (WHO 1990

Technical Report Series, No. 961), Annex 9.

1991

Further reading 1992

1993

Quality assurance of pharmaceuticals. A compendium of guidelines and 1994

related materials, Volume 1. Geneva, World Health Organization, 1997.

1995

Quality Assurance of Pharmaceuticals. A compendium of guidelines and 1996

related materials, Volume 2, Second updated edition. Good manufacturing 1997

practices and inspection. Geneva, World Health Organization, 2007.

1998

http://

1999

www.who.int/medicines/areas/quality_safety/quality_assurance/productio 2000

n/ en/index.html; and Quality Assurance of Pharmaceuticals. A 2001

compendium of guidelines and related materials. Geneva, World Health 2002

Organization, 2015 (CD-ROM) (in print).

2003 2004

World Health Organization. Supplements and updates available at:

2005

www.who.int/medicines.

2006 2007

ASHRAE handbook 1999. HVAC Applications, SI edition. Atlanta, GA, 2008

ASHRAE, 2007. http://www.ashrae.org/technology/page/548.

2009 2010

ASHRAE handbook 2000. HVAC Systems and Equipment. Atlanta, GA, 2011

ASHRAE, 2008. http://www.ashrae.org/technology/page/548.

2012 2013

Daly BB. Woods practical guide to fan engineering. Colchester, Woods of 2014

Colchester Ltd. Third impression, June 1985. Cambridge, Cambridge 2015

University Press. www.flaktwoods.com.

2016 2017

Working document QAS/15.639 page 76

2018

European Commission. The rules governing medicinal products in the 2019

European Community, Volume IV. Good manufacturing practice for 2020

medicinal products. European Commission, Brussels, 2005.

2021

http://www.cen.eu/cenorm/ sectors/sectors/healthcare/index.asp.

2022 2023

ISPE Baseline® pharmaceutical engineering guides, Volume 2. Oral solid 2024

dosage forms, Second Edition / November 2009, International Society for 2025

Pharmaceutical Engineering. http://www.ispe.org/.

2026 2027

ISPE Baseline® pharmaceutical engineering guides for new and 2028

renovated facilities, Volume 5. Commissioning and qualification, 1st ed.

2029

Tampa, Fl, International Society for Pharmaceutical Engineering, 2001.

2030

http://www.ispe.org/.

2031 2032

International Cleanroom Standards, ISO 14644. Geneva, International 2033

Organization for Standardization. http://www.iso.org/iso/standards_

2034

development.htm.

2035 2036

Luwa. Introduction to high efficiency filtration. Bulletin 50.10.10, Sheet 2037

020. Pharmaceutical Inspectorate Convention/Pharmaceutical Inspection 2038

Co-operation Scheme. Guide to Good Manufacturing Practice for 2039

Medicinal Products. PH 1/97 (Rev. 3), 15 January 2002.

2040 2041

PIC/s GMP Guide (PE 009) 2042

http://www.picscheme.org/publication.php?id=4.

2043 2044

ICH Q9: “Quality Risk Management”, November 2005 2045

http://www.ich.org.

2046 2047

World Health Organization. Guidelines on quality risk management, 2048

Geneva, World Health Organization, 2013 (WHO Technical Report Series, 2049

No. 981), Annex 2).

2050

***

2051

In document GMP guidelines for HVAC (Page 62-76)

Related documents