11. COMMITMENTS AND CONTINGENCIES Operating Leases

We have long-term operating lease commitments for land, office facilities and equipment, transportation equipment, time charters for ocean-going tankers and coastal vessels, dock facilities, and various facilities and equipment used in the storage, transportation, production, and sale of refinery feedstock, refined product and corn inventories.

Certain leases for processing equipment and feedstock and refined product storage facilities provide for various contingent payments based on, among other things, throughput volumes in excess of a base amount. Certain leases for vessels contain renewal options and escalation clauses, which vary by charter, and provisions for the payment of chartering fees, which either vary based on usage or provide for payments, in addition to established minimums, that are contingent on usage. In most cases, we expect that in the normal course of business, our leases will be renewed or replaced by other leases.

As of December 31, 2015, our future minimum rentals for leases having initial or remaining noncancelable lease terms in excess of one year were as follows (in millions):

2016 $ 430 2017 283 2018 200 2019 143 2020 100 Thereafter 311

Total minimum rental payments $ 1,467 Rental expense was as follows (in millions):

Year Ended December 31,

2015 2014 2013

Minimum rental expense $ 732 $ 618 $ 588

Contingent rental expense 105 43 47

Total rental expense $ 837 $ 661 $ 635

Purchase Obligations

We have various purchase obligations under certain industrial gas and chemical supply arrangements (such as hydrogen supply arrangements), crude oil and other feedstock supply arrangements, and various throughput and terminalling agreements. We enter into these contracts to ensure an adequate supply of utilities and feedstock and adequate storage capacity to operate our refineries. Substantially all of our purchase obligations are based on market prices or adjustments based on market indices. Certain of these purchase obligations include fixed or minimum volume requirements, while others are based on our usage requirements. None of these obligations are associated with suppliers’ financing arrangements. These purchase obligations are not reflected as liabilities.

VALERO ENERGY CORPORATION

NOTES TO CONSOLIDATED FINANCIAL STATEMENTS (Continued)

Environmental Matters Hartford Matters

We are involved, together with several other companies, in an environmental cleanup in the Village of Hartford, Illinois (the Village) and recently, one of these companies assumed the ongoing remediation in the Village pursuant to a federal court order. We had previously conducted an initial response in the Village, along with other companies, pursuant to an administrative order issued by the U.S. Environmental Protection Agency (EPA). The parties involved in the initial response may have further claims between themselves for costs already incurred. We also continue to be engaged in site assessment and interim measures at the adjacent shutdown refinery site, which we acquired as part of an acquisition in 2005, and we are in litigation with the Illinois EPA and other potentially responsible parties relating to the remediation of the site. In each of these matters, we have various defenses and rights for contribution from the other responsible parties. We have recorded a liability for our own expected contribution obligations. However, because of the unpredictable nature of these cleanups, the methodology for allocation of liabilities and the state of Illinois’ failure to directly sue third parties responsible for historic contamination at the site, it is reasonably possible that we could incur a loss in a range of $0 to $200 million in excess of the amount of our accrual to ultimately resolve these matters. Factors underlying this estimated range are expected to change from time to time, and actual results may vary significantly from this estimate.

Litigation Matters

We are party to claims and legal proceedings arising in the ordinary course of business. We have not recorded a loss contingency liability with respect to some of these matters because we have determined that it is remote that a loss has been incurred. For other matters, we have recorded a loss contingency liability where we have determined that it is probable that a loss has been incurred and that the loss is reasonably estimable. These loss contingency liabilities are not material to our financial position. We re-evaluate and update our loss contingency liabilities as matters progress over time, and we believe that any changes to the recorded liabilities will not be material to our financial position, results of operations, or liquidity.

Tax Matters

We are subject to extensive tax liabilities imposed by multiple jurisdictions, including income taxes, indirect taxes (excise/duty, sales/use, gross receipts, and value-added taxes), payroll taxes, franchise taxes, withholding taxes, and ad valorem taxes. New tax laws and regulations and changes in existing tax laws and regulations are continuously being enacted or proposed that could result in increased expenditures for tax liabilities in the future. Many of these liabilities are subject to periodic audits by the respective taxing authority. Subsequent changes to our tax liabilities as a result of these audits may subject us to interest and penalties. Self-Insurance

We are self-insured for certain medical and dental, workers’ compensation, automobile liability, general liability, and property liability claims up to applicable retention limits. Liabilities are accrued for self-insured claims, or when estimated losses exceed coverage limits, and when sufficient information is available to reasonably estimate the amount of the loss. These liabilities are included in accrued expenses and other long- term liabilities.

VALERO ENERGY CORPORATION