ALL CUTTING AND PATCHING SHALL BE CONSIDERED PART OF THE BASE BID PRICE WHEN THE WORK IS REQUIRED AS PART OF THE

RFI RESPONSE

A. WORK REQUIRED TO BE PERFORMED UNDER THIS CONTRACT SHALL BE COMPLETED IN ACCORDANCE WITH THE FOLLOWING

I. ALL CUTTING AND PATCHING SHALL BE CONSIDERED PART OF THE BASE BID PRICE WHEN THE WORK IS REQUIRED AS PART OF THE

OVERALL PROJECT. NO ADDITIONAL PAYMENT WILL BE CONSIDERED FOR WORK OF THIS SECTION UNLESS ALL APPLICABLE PARTIES OBTAIN PRIOR AUTHORIZATION OR WRITTEN APPROVAL.

3.6 UNCOVERING AND CORRECTION OF WORK

A. Comply with requirements of the General Conditions of the Contract, and with additional requirements specified herein.

1. Subsequent Disclosure of Faulty Work: Failure of Owner or Architect/Engineer to exercise powers of rejection or condemnation against the work of the Contractor during construction shall not be construed as an acceptance on Owner's part or Architect/ Engineer's part that Contractor's work has been faithfully performed, if the fact be otherwise.

3.7 PROJECT CONDITIONS

B. Ventilate enclosed areas to assist cure of materials, to dissipate humidity, and to prevent accumulation of dust, fumes, vapors, or gases.

C. Pollution Control: Provide methods, means, and facilities to prevent contamination of soil, water, and air from discharge of noxious, toxic substances, and pollutants

produced by construction activities. Comply with all governmental and code requirements.

3.8 PREPERATION FOR CUTTING AND PATCHING AND/OR NEW WORK.

A. Prepare surfaces and remove surface finishes to provide for proper installation of work and finishes.

B. Clean substrate surfaces prior to applying next material or substance.

C. Seal cracks or openings of substrate prior to applying next material or substance.

D. Apply manufacturers required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond.

3.9 LAYING OUT THE WORK

A. Verify locations of survey control points prior to starting work.

B. Promptly notify Owner’s Representative and Architect of any discrepancies discovered.

C. Protect survey control points prior to starting site work; preserve permanent reference points during construction.

D. Promptly report to Architect/Engineer and Owner’s Representative the loss or

destruction of any reference point or relocation required because of changes in grades or other reasons.

E. Utilize recognized engineering survey practices.

F. Establish elevations, lines and levels. Locate and lay out by instrumentation and similar appropriate means:

1. Site improvements including but not limited to pavements; stakes for grading, fill and topsoil placement; utility locations, slopes, and invert elevations, etc.

2. Building foundation, column locations, all floor elevations, stairwells, elevator shafts, machine and mechanical rooms, etc.

G. Periodically verify layouts by same means.

H. Maintain a complete and accurate log of control and survey work as it progresses.

3.10 GENERAL INSTALLATION REQUIREMENTS

A. Install Products as specified in individual sections and in accordance with manufacturer’s recommendations.

B. Make neat transitions. Patch work to match adjacent work in texture and appearance.

Where new Work abuts or aligns with existing, perform a smooth and even transition.

C. When existing finished surfaces are cut so that a smooth transition with new Work is not possible, terminate existing surface along a straight line at a natural line of division and make recommendations to the Architect and Owner.

3.11 CLEANING AND PROTECTION

A. General: During handling and installation of work at project site, Contractor shall clean and protect work in progress and adjoining work on a basis of perpetual maintenance.

Apply suitable protective covering on newly installed work where reasonably required to ensure freedom from damage or deterioration at time of substantial completion;

otherwise, clean and perform maintenance on newly installed work as frequently as necessary through remainder of construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

B. Removal of all debris and rubbish resulting from or relating to the construction work;

rubbish shall not be thrown from building openings above the ground floor unless confined within chutes;

1. Progress Cleaning:

a. Maintain areas free of waste material, debris, and rubbish on a daily basis.

Maintain site in a clean and orderly condition, as determined by the Owner.

b. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing the space.

c. Broom and vacuum clean interior areas prior to start of surface finishing, and continue cleaning to eliminate dust.

d. Collect and remove waste materials, debris, and rubbish from site periodically and dispose of off-site.

e. Protect installed work and provide special protection where specified in individual specification sections.

damage.

g. Protect finished floors and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials appropriate for the task involved.

B. Limiting Exposures of Work: To extent possible through reasonable control and protection methods, Contractor shall supervise performance of work in a manner and by means which will ensure that none of the work, whether completed or in progress, will be subjected to harmful, dangerous, damaging, or otherwise deleterious exposures during construction period. Such exposures include (where applicable, but not by way of limitation) static loading, dynamic loading, internal pressures, external pressures, high or low temperatures, thermal shock, high or low humidity, air contamination or pollution, water, ice, solvents, chemicals, light, radiation, puncture, abrasion, heavy traffic, soiling, bacteria, insect infestation, combustion, electrical current, high speed operation, improper lubrication, unusual wear, misuse, incompatible interface, destructive testing, misalignment, excessive weathering, unprotected storage, improper shipping/handling, theft and vandalism.

C. Construction Debris: The Contractor shall intermittently remove waste and rubble so that at no time shall there be undue accumulations. Upon completion, the Contractor shall dress up all areas affected by this work whether inside or outside the boundary of the Project. Loading, crating, hauling and dumping will be at the contractor's expense.

D. Rubbish: The Contractor shall provide covered metal trash cans in sufficient quantity to accept the accumulation of rubbish and garbage from lunch and the like of employees of all Contractors working on site.

1. The Contractor shall instruct his and his subcontractors’ employees to deposit their trash and garbage in these containers and not elsewhere about the site; and also not to use the containers for construction scraps, rubbish, trash and surplus materials.

2. The Contractor shall empty these containers daily and haul the rubbish to a legal disposal site off the property.

E. Roads and Pathways:

1. The Contractor is responsible for the removal of construction dirt and debris in public areas on the site and in the surrounding areas serving the site.

2. Dirt and mud tracked onto streets by the Contractor or its subcontractors is to be immediately cleaned up by the Contractor to the satisfaction of the Owner and the local municipal authorities.

F. Trucks: All trucks leaving the construction area are to be covered in accordance with NJDOT over the road requirements. Trucks leaving the site are to be clean and free of mud or other materials.

safe condition at all times. Under no circumstances shall the Contractor leave the site each day without inspecting and verifying that streets and paths to the construction site, access areas, lay down areas, and gates in the area of the site are clean of all

construction related materials and are clean and sage for use by the Rowan University population. The Contractor will immediately correct any violation of this provision upon notification by the Owner.

3.12 CONSERVATION AND SALVAGE

A. General: It is a general procedural requirement for Contractor's supervision and administration of the work that construction operations be carried out with maximum practical consideration for conservation of energy, water and materials; and with maximum practical consideration for salvaging materials and equipment involved in performance of the work but not incorporated therein.

END OF SECTION 012400

CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section. In the event of any conflicts between the requirements of these Sections, the more stringent requirement shall apply.

1.2 SUMMARY

A. This Section specifies administrative and procedural requirements for handling and processing Contract modifications.

B. Related Sections include the following:

1. Division 1 Section "Unit Prices" for administrative requirements for using unit prices.

2. Division 1 Section "Product Requirements" for administrative procedures for handling requests for substitutions made after Contract award.

1.3 MINOR CHANGES IN THE WORK

A. Architect may issue through Owners project manager supplemental instructions authorizing Changes in the Work, not involving adjustment to the Contract Time, as

“Architects Supplemental Instructions” (ASI). Architects Supplemental Instructions may or may not involve adjustments to the contract sum. THERE WILL BE NO ADJUSTMENTS TO THE CONTRACT TIME ALLOWED FOR THIS PROJECT.

1. For ASI’s involving no adjustment to the contract sum or time, the contractor is authorized to execute the change or clarification immediately.

2. For ASI’s resulting in an adjustment to the contract sum, do not consider them instructions either to stop work in progress or to execute the proposed change without obtaining written authorization from the Owner. Written authorization can include the provisions of the general conditions, Article 14, paragraphs 14.5.3 and 14.7.1, an approved change order or a Construction Change Directive.

A. In the event the Contractor believes that any change directed by the Owner or Architect would entitle it to additional compensation to complete its work under this contract, the Contractor shall immediately notify the Owners project manager of this fact WITHIN 48 HOURS OF RECEIPT OF THE CHANGE REQUESTED. The contractor shall then prepare and submit an original of the Change Order Request (COR) with all supporting documentation to the Owners project manager and submit two (2) copies of the Change Order Request (COR) with all supporting documentation to the Architect and University within five (5) calendar days of its receipt of the directive by the Owner and/or Architect.

B. Owner-Initiated Proposal Requests: Owner may issue proposal requests or may have the Architect issue such requests. In any event a detailed description of proposed changes in the Work will be submitted to the contractor that may require adjustment to the Contract Sum. THERE WILL BE NO ADJUSTMENTS TO TIME FOR ANY GIVEN CHANGE ORDER REQUESTED. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Proposal Requests issued by Architect are for information only. For ASI’s resulting in adjustments to the contract sum, do not consider them instructions either to stop work in progress or to execute the proposed change without first obtaining written authorization from the Owner.

2. If the contractor feels the ASI or proposal request requires a change to the contract sum then the contractor shall notify the Owners project manager of this fact within 48 hours of receipt of the ASI or OIPR directive.

3. Within five (5) business days after receipt of directive, ASI or proposal request from the Owner, submit a Change Order Request estimating cost adjustments to the Contract Sum necessary to execute the change. The contractor shall then prepare and submit an original of the Change Order Request (COR) with all supporting documentation to the Owners project manager and submit two (2) copies of the COR with all supporting documentation to the architect.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor directly attributable to the change.

1. Labor shall be broken down by man-hours, hourly wages, fringe benefits per hour and any other benefits payable.

d. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity

extended.

C. In the event that the Contractor encounters a condition that it considers a change, the Contractor shall immediately notify the Owners Project Manager prior to disturbing the condition and shall then prepare and submit an original of the COR with all supporting documentation to the Owners project manager and two (2) copies of a Change Order Request with all required supporting documentation to the architect within five (5) calendar days of encountering the condition. The condition shall not be disturbed until the Project Manager has inspected the condition.

D. Contractor-Initiated Proposals: If latent or unforeseen conditions require modifications to the Contract, Contractor may propose changes by submitting a Change Order Request (COR) to Owners project manager. The contractor shall prepare and submit one (1) original of the COR with all supporting documentation to the Owners project manager and submit two (2) copies of the COR with all supporting documentation to the architect.

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float however the date of Substantial and Final Completion cannot be extended.

6. Comply with requirements in General Conditions Article 4.15 if the proposed change requires substitution of one product or system for product or system specified.

E. Proposal Request Form: Use AIA Document G709 for Proposal Requests.

1.5 CHANGE ORDER PROCEDURES

A. Upon the Owner’s approval of a Change Order Request (COR), the Owner will direct the Architect to issue a Change Order for signatures of the Contractor and Owner on AIA Document G701.

1. The Change Order breakdown shall be in sufficient detail to permit an analysis of all material, labor, equipment, sub-contract and overhead costs as well as profit.

B. Each Change Order must contain a detailed description of the change and the amount by which the Contract Price will be increased or decreased.