• No results found

20 00 EARTH MOVING

PANEL MDP BUS ASSEMBLIES

SECTION 31 20 00 EARTH MOVING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Preparing subgrades for pavements and turf and grasses.

2. Structural Fill: For backfill under structures, pavements, concrete pads, etc.

3. Granular Fill: Sub base for interior concrete slabs-on-grade, asphalt paving, concrete paving, etc.

4. Subsurface drainage fill for foundation drains, underdrains, etc. 5. Excavating and backfilling for buildings and structures.

6. Excavating and backfilling trenches for utilities and pits for buried utility structures. 1.3 UNIT PRICES

A. Work of this Section is affected by unit prices for earth moving specified in Division 01 Section "Unit Prices."

B. Rock Measurement: Volume of rock actually removed, measured in original position, but not to exceed the following. Unit prices for rock excavation include replacement with approved materials.

1. 24 inches outside of concrete forms other than at footings. 2. 12 inches outside of concrete forms at footings.

3. 6 inches outside of minimum required dimensions of concrete cast against grade.

4. Outside dimensions of concrete walls indicated to be cast against rock without forms or exterior waterproofing treatments.

5. 6 inches beneath bottom of concrete slabs-on-grade.

6. 6 inches beneath invert of pipe in trenches, and the greater of 24 inches wider than pipe or 42 inches wide.

1.4 DEFINITIONS

A. Backfill: Soil material or controlled low-strength material used to fill an excavation.

1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe.

2. Final Backfill: Backfill placed over initial backfill to fill a trench.

113

C. Bedding Course: Aggregate layer placed over the excavated subgrade in a trench before laying pipe.

D. Borrow Soil: Satisfactory soil imported from off-site for use as fill or backfill.

E. Drainage Course: Aggregate layer supporting the slab-on-grade that also minimizes upward capillary flow of pore water.

F. Subbase: Granular aggregate layer supporting the slab-on-grade and pavement that also minimizes upward capillary flow of pore water.

G. Excavation: Removal of material encountered above subgrade elevations and to lines and dimensions indicated.

1. Authorized Additional Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions as directed by Geotechnical Engineer. Authorized additional excavation and replacement material will be paid for according to Contract provisions for unit prices, if specified, or changes in the Work.

2. Bulk Excavation: Excavation more than 10 feet in width and more than 30 feet in length. 3. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated

lines and dimensions without direction by Geotechnical Engineer or Architect. Unauthorized excavation, as well as remedial work directed by Geotechnical Engineer or Architect shall be without additional compensation.

H. Fill: Soil materials used to raise existing grades.

I. Hazardous Soil Materials: Soils that are contaminated with petroleum product and/or hazardous chemicals, waste or industrial waste.

J. Rock: Rock material in beds, ledges, unstratified masses, conglomerate deposits, and boulders of rock material that exceed 1 cu. yd. for bulk excavation or for footing, trench, and pit excavation that cannot be removed by rock excavating equipment equivalent to the following in size and performance ratings, without systematic drilling, ram hammering, ripping, or blasting, when permitted:

1. Rock Excavation: Track-mounted excavator rated at not less than 222-hp flywheel power with weight of 70,000 lbs or greater and a 30” wide short-tip radius rock bucket. (Ratings are based on Caterpillar's "Model No. 330B”.)

K. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and electrical appurtenances, or other man-made stationary features constructed above or below the ground surface.

L. Subgrade: Uppermost surface of an excavation or the top surface of a fill or backfill immediately below aggregate base, structural fill, drainage fill, or topsoil materials.

M. Utilities: On-site underground pipes, conduits, ducts, and cables, as well as underground services within buildings.

N. Non-Granular Fill: Soil fill material used to raise existing grades in areas that do not require granular or structural fill.

114 1.5 SUBMITTALS

A. General: Submit all action submittals and informational submittals required by this Section concurrently.

B. Action Submittals:

1. Product Data: For each type of the following manufactured products required: a. Geotextiles.

b. Warning tapes.

2. Material Test Reports: For each on-site and borrow soil material proposed for fill and backfill as follows:

a. Classification according to ASTM D 2487.

b. Laboratory compaction curve according to ASTM D 1557.

3. Samples for Verification: For the following products, in sizes or quantities indicated below:

a. Fill: One-half gallon by volume of material in sturdy container of each type of fill, naming source for each material.

b. Geotextile: 12 by 12 inches.

c. Warning Tape: 12 inches long; of each color. C. Informational Submittals:

1. Qualification Data: For qualified testing agency.

2. Pre-excavation Photographs or Videotape: Show existing conditions of adjoining construction and site improvements, including finish surfaces, which might be misconstrued as damage caused by earth moving operations. Submit before earth moving begins.

1.6 QUALITY ASSURANCE

A. Installer Qualifications: Qualified Installers as defined below:

1. Earthwork Contractor Experience Requirements: Provide a list of at least four Earthwork projects of comparable size, scope, and quality completed successfully by the proposed Sub Contractor within the past two years that includes the date completed, project Owner’s name and current contact information, including telephone numbers and e-mail addresses. 1.7 PROJECT CONDITIONS

A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during earth moving operations.

1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction.

2. Provide alternate routes around closed or obstructed traffic ways if required by Owner or authorities having jurisdiction.

115

B. Improvements on Adjoining Property: If work includes improvements on adjoining property, written authorization for performing earth moving indicated on property adjoining Owner's property will be obtained by Owner before award of Contract.

1. Do not proceed with work on adjoining property until directed by Architect.

C. Utility Locator Service: Notify utility locator service for area where Project is located before beginning earth moving operations.

D. Do not commence earth moving operations until temporary and permanent erosion- and sedimentation-control measures, specified in Division 31 Section “Erosion and Sedimentation Control” are in place.

E. Do not commence earth moving operations until plant-protection measures specified in Division 31 Sections “Erosion and Sedimentation Control” and “Site Clearing” are in place.

F. The following practices are prohibited within tree- or plant-protection zones: 1. Storage of construction materials, debris, or excavated material. 2. Parking vehicles or equipment.

3. Foot traffic.

4. Erection of sheds or structures. 5. Impoundment of water.

6. Excavation or other digging unless otherwise indicated.

7. Attachment of signs to or wrapping materials around trees or plants unless otherwise indicated.

8. Directing vehicle or equipment exhaust towards protection zones.

9. Heat sources, flames, ignition sources, and smoking within or near protection zones. G. Existing Hazardous Materials:

1. If during the performance of the work suspected hazardous materials are encountered, do not disturb; immediately notify Architect and Owner. If present, hazardous materials will be removed by Owner under a separate contract.

PART 2 - PRODUCTS