Project Title Bidder
PART 3 - EXECUTION - NOT USED
END OF SECTION
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.02 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing Contract modifications.
1.03 SUBMITTALS
A. The Contractor shall submit the following documentation to the Port:
1. List of Labor Rates
a. For the Contractor and each subcontractor, a list of labor rates for each trade applicable to the scope of work to be performed. These submitted rates shall be broken down to include the base wage, fringes, FICA, SUTA, FUTA, industrial insurance and medical aid premiums as stated in the General Conditions. The rates shall not contain any travel time, safety, loss efficiency factors, overhead or profit.
Rates shall be submitted for straight time, overtime and double time in a form acceptable to the Engineer. Contractor shall provide proof of all labor rate costs as required by the Engineer including the submission of a copy of the most current Workers Compensation Rate Notice from Labor & Industries and a copy of the
Unemployment Insurance Tax Rate notice from the Employment security department.
1) If labor rates change during the course of the project or additional labor rates become required to complete the work, the Contractor shall submit new rates for approval.
2. List of Equipment.
a. Submit for the Contractor and each subcontractor, a list of equipment and rates
applicable to the scope of work to be performed. The equipment rates shall conform to the rates shown on Equipment Watch. A separate page from equipment watch
detailing the hourly rate shall be submitted as backup documentation for each piece of equipment.
1) If the list of equipment and/or equipment rates changes during the course of the project or additional equipment becomes required to complete the work, the Contractor shall submit a new list and rates for approval.
3. No applications for payment or change orders will be processed for the Contractor until labor and equipment rates have been submitted and approved.
1.04 METHOD TO CALCULATE ADJUSTMENTS TO CONTRACT PRICE A. One of the following methods shall be used:
1. Unit Price Method;
2. Firm Fixed Price Method (Lump Sum); or, 3. Time and Materials Method (Force Account).
B. The Port preferred methods are firm fixed price or unit prices.
1.05 MINOR CHANGES IN THE WORK
A. Engineer will issue a written directive authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time.
1.06 PROPOSAL REQUESTS
A. Port-Initiated Proposal Requests: The Engineer will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Work Change Proposal Requests issued by Engineer are not instructions either to stop work in progress or to execute the proposed change.
2. Contractor shall submit a written proposal within the time specified in the General Conditions. The proposal shall represent the Contractor’s offer to perform the requested work, and the pricing set forth within the proposal shall represent full, complete, and final compensation for the proposed change and any impacts to any other Contract Work, including any adjustments in the Contract Time.
a. Include a breakdown of the changed work in sufficient detail that permits the Engineer to substantiate the costs.
1) Generally, the cost breakdown should be divided into the time and materials categories listed in the General Conditions under Article 8.02B for either Lump Sum Proposals or Force Account Proposals.
2) For Unit Price Proposals, include the quantity and description of all work involved in the unit pricing being proposed, along with a not to exceed total cost.
b. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
B. Contractor-Initiated Proposals: If latent or differing site conditions require modifications to the Contract, the Contractor may initiate a claim by submitting a request for a change to the Engineer.
1. Notify the Engineer immediately upon finding differing conditions prior to disturbing the site.
2. Provide follow-up written notification and differing site conditions proposal within the time frames set forth in the General Conditions.
3. Provide the differing site condition change proposal in the same or similar manner as described above under 1.04.A.
4. Comply with requirements in Section 01 25 00 Substitution Procedures During
Construction if the proposed change requires substitution of one product or system for product or system specified.
5. Proposal Request Form: Use form acceptable to Engineer.
1.07 PROCEEDING WITH CHANGED WORK
A. The Engineer may issue a directive instructing the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order per the General Conditions, Article 8.01.E.
1. The directive will contain a description of change in the Work and a not-to exceed amount.
It will designate the method to be followed to determine the change in the Contract Sum or the Contract Time.
1.08 CHANGE ORDER PROCEDURES A. Issuance of Change Order
1. On approval of the Contractor’s proposal, and following successful negotiations, the Engineer will issue a Change Order for signature by the Contractor and execution by the Engineer.
a. The Contractor shall sign and return the Change Order to the Engineer within four (4) days following receipt of the Change Order from the Engineer. If the Contractor fails to return the signed Change Order within the allotted time, the Engineer may issue a Unilateral Change Directive.
PART 2 - PRODUCTS - NOT USED PART 3 - EXECUTION - NOT USED
END OF SECTION