RAPID - Zone 4B
9.0 FOUNDATIONS 9.1 Shallow Foundations
Shallow foundations can be used in
For preliminary design, shallow foundations can be designed for exceeding
• 100kPa in firm clays with SPT(N) values greater than 15
• 200kPa in medium dense sandy soils
• 500kPa on rock
The factor of safety against bearing capacity failure
For detailed design, site investigation should be carried out on a 50m to 150m grid after platform construction to confirm the above bearin
as part of confirmation testing.
Settlement analyses can be carried out when foundation loads are known.
expected to be less than 25mm for pad footing sizes up to 3m x 3m pressure not exceeding 100kPa.
detailed engineering phase.
All other plant and strictures (to be determined during FEED or detailed engineering phase) that can be supported on shallow foundations should be piled.
9.2 Piled Foundation
9.2.1 General
It is recommended that all major to refusal.
Piles driven to set are preferred to bored piles because they (i) Compact the ground during their installation;
(ii) have higher safe working loads;
(iii) are cost effective.
Pre-tensioned high strength spun concrete piles
(i) are robust (due to their construction process); and (ii) can sustain higher driving stresses without damage.
All piles should be driven to set with sufficient
not to overstress the piles. Stress wave testing should be carried out as part of test piling programme to determine suitable hammer sizes and drops
acceptable levels.
FOUNDATIONS
Shallow Foundations in Cut Areas
Shallow foundations can be used in Cut Areas.
foundations can be designed for allowable bearing pressures not in firm clays with SPT(N) values greater than 15
200kPa in medium dense sandy soils and in stiff clays 500kPa on rock
The factor of safety against bearing capacity failure must be greater than 3.
For detailed design, site investigation should be carried out on a 50m to 150m grid after platform construction to confirm the above bearing pressures. Plate load bearing test should be carried out
be carried out when foundation loads are known. Total s
expected to be less than 25mm for pad footing sizes up to 3m x 3m and designed for bearing pressure not exceeding 100kPa. Differential settlement analyses should be carried out in the
All other plant and strictures (to be determined during FEED or detailed engineering phase) that ed on shallow foundations should be piled.
Foundations in Filled Areas
major and settlement-sensitive structures are supported on piles driven
Piles driven to set are preferred to bored piles because they ground during their installation;
ve higher safe working loads; and are cost effective.
tensioned high strength spun concrete piles are preferred to precast RC piles becaus are robust (due to their construction process); and
can sustain higher driving stresses without damage.
All piles should be driven to set with sufficient energy to mobilise their full structural capacity but not to overstress the piles. Stress wave testing should be carried out as part of test piling programme to determine suitable hammer sizes and drops so to keep dynamic stresses to
allowable bearing pressures not
For detailed design, site investigation should be carried out on a 50m to 150m grid after platform g pressures. Plate load bearing test should be carried out
Total settlements are designed for bearing Differential settlement analyses should be carried out in the
All other plant and strictures (to be determined during FEED or detailed engineering phase) that
are supported on piles driven
are preferred to precast RC piles because they
to mobilise their full structural capacity but not to overstress the piles. Stress wave testing should be carried out as part of test piling so to keep dynamic stresses to within
9.2.2 DRIVEN Pile Sizes and Safe Working Loads Spun pile with Outside Diameters (
minimum effective prestress should be 5N/mm
Piles in Zones 3 and 4 will experience negative friction due to settling
the platform fill. This will mobilise drag loads on the piles that will reduce their effective safe working loads. The magnitude of drag loads can approach 30% of the maximum permissible structural loads and it is recommended tha
the maximum permissible structural load.
Design safe working loads are summarised below for spun pile from 300 to 600mm.
Table 27 Safe working loads for spun piles Minimum concrete strength = 78.5N/mm Minimum effective prestress = 5N/mm Spun
(4) calculated as 70% of max structural load with geotechnical rounding Safe working loads must be confirmed by pile load testing.
The following minimum factors of safety should be applied to the ultimate geotechnical capacity spun piles driven to set:
i. FOS = 2.0 applied to
ii. FOS = 2.5 applied to the ultimate shaft resistance (tension); and iii. FOS = 2.0 applied to
Pile Sizes and Safe Working Loads
with Outside Diameters (OD) ranging from 300mm to 600mm can be used. The prestress should be 5N/mm2.
will experience negative friction due to settling ground under the weight of . This will mobilise drag loads on the piles that will reduce their effective safe working loads. The magnitude of drag loads can approach 30% of the maximum permissible structural loads and it is recommended that their safe working loads be not greater than
the maximum permissible structural load.
Design safe working loads are summarised below for spun pile Outside Diameters
Safe working loads for spun piles DRIVEN to set Minimum concrete strength = 78.5N/mm2
Minimum effective prestress = 5N/mm2 Maximum Structural Safe Working Load
(kN)
as 70% of max structural load with geotechnical rounding.
Safe working loads must be confirmed by pile load testing.
factors of safety should be applied to the ultimate geotechnical capacity
FOS = 2.0 applied to the ultimate shaft resistance (compression);
FOS = 2.5 applied to the ultimate shaft resistance (tension); and FOS = 2.0 applied to the ultimate toe resistance.
00mm can be used. The
under the weight of . This will mobilise drag loads on the piles that will reduce their effective safe working loads. The magnitude of drag loads can approach 30% of the maximum permissible not greater than 70% of
iameters (OD) ranging
. A = cross section area of concrete.
factors of safety should be applied to the ultimate geotechnical capacity of
;
9.2.3 BORED Piles Sizes and Safe Working Loads
Design safe working loads are summarised below for BORED pile having diameters ranging from 500mm to 1000mm
Table 28 Safe working loads for BORED piles Minimum concrete strength = 40N/mm BORED
Pile Diameter
(mm) (1)
Maximum Structural Safe Working Load
(kN) (2)
500 1963
600 2827
700 3848
800 5027
900 6362
1000 1963
Key
(3) calculated as 0.25 x Fcu x A where A = cross section area. F
(4) calculated as 70% of max structural load with geotechnical rounding Safe working loads must be confirmed by pile load testing.
The following minimum factors of safety should be applied to the ultimate geotechnical capacity of B0RED piles:
i. FOS = 2.0 applied to the ultimate shaft resistance ii. FOS = 2.5 applied to the ultimate shaft resistance iii. FOS = 3.0 applied to the ultimate toe resistance.
Sizes and Safe Working Loads
loads are summarised below for BORED pile having diameters ranging from
Safe working loads for BORED piles Minimum concrete strength = 40N/mm2
imum Structural
Working Load
Recommended Geotechnical Safe Working Load
(kN) (3)
1350
2000
2700
3500
4500
1350
x A where A = cross section area. Fcu = 40N/mm2 as 70% of max structural load with geotechnical rounding.
Safe working loads must be confirmed by pile load testing.
The following minimum factors of safety should be applied to the ultimate geotechnical capacity of
2.0 applied to the ultimate shaft resistance (compression);
applied to the ultimate shaft resistance (tension); and FOS = 3.0 applied to the ultimate toe resistance.
loads are summarised below for BORED pile having diameters ranging from
The following minimum factors of safety should be applied to the ultimate geotechnical capacity of
;
9.2.4 DRIVEN Pile Toe Levels All piles should be driven to set which
into N>50 strata. Figure 50 presents levels of N>50 strata as determined from the existing boreholes.
9.2.5 BORED Pile Toe Levels Bored piles should be founded
into bedrock, whichever is encountered first,
9.2.6 Pile Testing
Allowance should be made for a
Stage I Design Verification Testing