• No results found

General design considerations for bottom founded structures

force model ? waves (u, u)

from 0.0007 to 900 cycles per hour; Journal of Meteorology, 14, 1957; pp 160-164.

D.7 Waves and current

5.3 Conceptual design 1 Historical overview

5.3.2 General design considerations for bottom founded structures

The design of an offshore platform is governed by: - the user or functional requirements

- the operating requirements - the environmental conditions

- the method of construction (including onshore fabrication, transportation to site, and offshore installation)

- the management of the platform during its service life (inspection, maintenance and repair)

General consideration will further need to be given to platform decommissioning at the end of its useful life, but this will rarely translate into specific design requirements. Considerations of abandonment will generally more relate to factors that should be kept in mind and factors that may lead to a preference for choosing between different concepts or options, rather than that they directly impact on the design of the platform as such.

Safety

Section 1.5.3 includes a general discussion on safety issues. These are of paramount importance. Considerations on safety offshore need to be incorporated into every aspect of the design from the very first moment. They need to encompass the entire system from the reservoir, via the drilling and production facilities and any oil or gas that may be imported to the platform, to the export by pipeline or through offshore loading. Supply of goods and transportation of personnel must also be included. It is often necessary that parts of the platform, or even the entire platform, can be isolated by valves in pipework, risers or (subsea) pipelines. Safety hazards should be systematically assessed and reduced, or even better eliminated, by such techniques as hazard and operability studies (HAZOPS). A modern development is that for each installation a so-called safety case is prepared, which carefully reviews all safety aspects, documents the safety precautions and the measures to be taken in case of an incident.

The superstructure is usually the most vulnerable part of a platform with respect to safety. It contains a chemical plant where several potentially dangerous activities may go on at the same time. The very beginning of safety is therefore a simple and logical layout of the various processes and the associated equipment. In shallow waterdepths safety is often pursued using separate platforms for different functions, together forming a platform complex where the platforms are often interconnected by bridges. Otherwise physical separation between areas where the various processes take place is desirable and an effective contributor to improving safety. For example, where possible we should arrange for a separate drilling area; production area (separators, pumps, treatment facilities); gas compression area; utilities area (power

Chapter 5 – Design 5-8

total deck

tide

foundation settlement

subsidence = reservoir compaction

underside of any structural steel or equipment under deck

elevation above LAT

LAT=Lowest Astronomical Tide

air gap

wave crest

storm surge

1/2 tide

1/2 (foundation settlement + subsidence)

LAT=Lowest Astronomical Tide MSL=Mean Sea Level

average height of MSL

above LAT

generation, drinking water) and accommodation. This allows the separation of hazardous from non-hazardous areas. Fire resistant walls and blast walls may provide protection against fire and explosions where necessary, but prevention will always be more effective and should be the first aim. If notwithstanding all precautions an accident occurs, containment and control is the first priority. If this is unsuccessful and an accident escalates after all, evacuation may become necessary. Escape routes should be straight, sufficiently wide, unobstructed, clearly lit by emergency lighting, clearly marked and must lead to (a) muster station(s) from where the platform may be abandoned by (free fall) life boats, helicopter or other means.

Deck elevation

The superstructure needs to be above the water at all times. Therefore, the elevation of the superstructure should be determined in such a way that it is above the highest crest of the waves expected to occur in the most severe sea state at the location for which the installation is designed. This should take into account water level increases due to tide, storm surge and wave crests, as well as a possible lowering of the sea floor due to settlement of the foundation and/or subsidence of the entire sea floor resulting from compaction of the reservoir deep down in the earth. In addition to these factors one usually includes an air gap of 1.5 m as a safety margin between the underside of any structural element under the deck and the top of any green water. The procedure is illustrated in figure 5.3-1. The 1.5 m is a general allowance for uncertainties in the various contributions for setting the elevation of the deck and rather common practice. However, this practice is not really rationally based. Instead of a fixed value the magnitude of the air gap should be related to the magnitude and degree of uncertainty of the individual contributions and be determined in a probabilistic manner. The consequences of elements of the deck becoming inadvertently inundated can be very serious, both with regard to damage done to the deck structure or the equipment it carries and with regard to overloading of the substructure and/or its foundation. The deck is usually made up of many flat surfaces (e.g. beams, walls of modules), as opposed to the circular members used in substructures. Therefore, horizontal wave loads on the deck quickly become very large, while these loads also act at a very high point resulting in huge additional overturning moments.

Well drilling

Many platforms have wells. These wells may have been drilled from the platform itself or by means of a mobile drilling unit that is positioned adjacent to the platform. In the first case the platform needs to be designed to carry the full weight of the drilling installation together with any additional loads associated with the drilling operation. If a mobile drilling unit is used adjacent to the platform and this unit is a jack-up, the substructure will often need to have one vertical side to enable the jack-up to come close enough to reach the drilling slots on the platform. For the same reason, the deck can normally not be cantilevered over the side of the substructure. Another point to pay attention to is the possible interaction of soil forces in the soil layers underneath the spud cans carrying the jack-up legs (which are usually very large) with the relatively small piles supporting the fixed structure. If the mobile drilling unit is a floating unit, e.g. a semi-submersible, we will need to arrange for an adequate anchoring system that will not interfere with the platform nor with any equipment on the sea floor (such as pipelines, manifolds, subsea wells). Furthermore, a floating unit will move due to wave action and we will thus need to take care that it will never be in contact with the platform.

Chapter 5 – Design 5-10

Conductors

Wells are drilled through a protective conduit between the drill floor and a certain depth below the seabed; this conduit is usually called the conductor or also the stove pipe. Through the water column the conductors are laterally supported by the substructure to prevent buckling under their own weight, the weight of fluids inside and any possible weight on top. Another reason for providing lateral supports is to avoid vortex induced vibrations. By reducing the length of free spans the natural frequencies of conductor vibration are increased and better separated from the vortex shedding frequencies that are the source of excitation. Conductors are laterally supported by guides, but axially free to move up and down (e.g. due to differential deformations or temperature effects).

Interfaces with petroleum engineering - platform location

- number and type of wells - requirement for curved conductors

- number of risers and J-tubes, including their orientation - reservoir compaction and seabed subsidence

Interfaces with metocean engineers - water depth

- environmental conditions - platform orientation Interface with geotechnical engineers

- seabed topography - soil conditions - foundation design

Interfaces with drilling (equipment) engineers - spacing between wells

- accessibility of wells by a platform mounted or a mobile drilling rig - space and weight for drilling rig and associated equipment

- design and setting depth of well conductors

- allowing relative movements between wells and structure

Interfaces with process -, facilities -, mechanical equipment - and piping engineers - lay-out of deck(s), horizontal as well as vertical

- routing of pipework, pipe supports

- expansion loops in pipework to allow relative movements or extensions e.g. due to temperature - foundations for vessels, storage tanks, other heavy equipment

- access for inspection and maintenance - level adjustment for sensitive equipment

- avoiding or coping with machinery vibrations, isolating vibrating machinery from the structure - support for deck cranes

- support for and design/construction of a flare boom or flare stack. Interfaces with electrical and instrumentation engineers

- foundations for generators - access for maintenance and repair

- routing of electrical cabling and support of cable trays - positioning and fixing of light fixtures

- positioning and fixing of instrument panels, together with accessibility in case of breakdown Interfaces with pipeline engineers

- riser supports to substructure and deck(s) (N.B. the riser itself is a pressure conduit and its design belongs to the pipeline discipline)

- J-tubes for riser pull-in

- expansion loops on deck and/or at the base of the structure - pigging facilities on board

Interfaces with safety engineers - fire, smoke and gas detection

- fire fighting systems (pumps, ring main, deluge, sprinklers) - explosion protection (pressure relief, blast walls)

- escape routes

- life saving equipment (rafts, life boats, etc.)

- safety during (onshore) fabrication and (offshore) installation Interfaces with materials and corrosion engineers

- determining type and quality of materials for structural design - welding procedures and weld testing

- (cathodic) corrosion protection below water - corrosion protection by painting above water Interfaces with drilling/production operations

- boat bumpers, boat landings, supply boat moorings - loading and unloading facilities (platform cranes, etc.) - helicopter landing areas

- access platforms, stairs, ladders

- structural inspection and maintenance above and below water

Chapter 5 – Design 5-12

Curved conductors

In many cases wells are drilled from one central location above water, but radiating out to a much wider circle at reservoir depth in order to drain a much larger area. This is called deviated drilling. The rate of deviation is typically some 4 degrees per 100 feet (30 m). More recently wells have become ever more deviated, up to being horizontal in the reservoir region. In these cases the rate of deviation may be greater. The deviation will often start in the ground, below the depth at which the straight conductors have been set. However, sometimes the deviation needs to start already above water. In this case the conductors must be curved and the framing pattern is consequently different at each plan level at which the conductors are supported, considerably complicating design. The complications do not only arise from geometrical factors, but are also due to vertical loads on the frames during conductor driving arising from friction between the conductor and the conductor guides in the frames.

Interfaces

Design of an offshore installation is a multi-functional activity, with structural design being only one of the many aspects involved. It should be recognised that satisfying functional and operating requirements can be more important than optimal structural design. There are numerous interfaces between structural design and the design activities of other disciplines. All parties must be aware of these interfaces and co-operate in a constructive manner to resolve any problems that may arise; however, there are no simple or firm rules to guide the process or the resolution of conflicts. Typical interfaces are listed in figure 5.3-2.